Package 2 - WVA B125 Reno - Spec.pdf

PDF 6 MB Posted

Attached to
WVA Renovate Building 125 Federal contract opportunity
Solicitation number
W912DS23B0008
Issued by
Department of the Army Corps of Engineers Engineering District New York

About this file

This document outlines requirements for a construction contract solicitation to renovate Building 125 at the Watervliet Arsenal in New York. The solicitation is identified as number W912DS23B0008 and will be awarded by the Department of the Army Corps of Engineers Engineering District New York.

The renovation work includes architectural, electrical, mechanical, fire protection and incidental related work. Contractors must comply with numerous administrative requirements including progress reporting, invoicing, scheduling, safety plans, quality control procedures, and submitting qualifications for key management personnel on the project. Insurance, bonding, and veteran hiring goals are also addressed. The document specifies work restrictions, access policies and other installation rules that contractors must follow while performing the contract work at the Watervliet Arsenal.

View the file

Other files for this federal contract opportunity

Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Watervliet Arsenal Building 125 Renovations WVABLDG125

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 00 01 05/22 COVER SHEET

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 08/15, CHG 2: 08/21 SUMMARY OF WORK

01 14 00 11/11, CHG 14: 02/22 WORK RESTRICTIONS

01 20 00 11/20, CHG 2: 08/21 PRICE AND PAYMENT PROCEDURES

01 30 00 11/20, CHG 2: 05/22 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 02/15 PROJECT SCHEDULE

01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES

01 35 26 11/20, CHG 3: 02/22 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 11/16, CHG 2: 11/21 QUALITY CONTROL

01 45 00.15 10 11/16, CHG 2: 08/19 RESIDENT MANAGEMENT SYSTEM CONTRACTOR

MODE (RMS CM)

01 45 20.00 18 NY Dist. July 2018 TESTING FOR MECHANICAL AND ELECTRICAL

SYSTEMS

01 45 35 11/20 SPECIAL INSPECTIONS

01 50 00 11/20, CHG 2: 08/22 TEMPORARY CONSTRUCTION FACILITIES AND

CONTROLS

01 57 19 08/22 TEMPORARY ENVIRONMENTAL CONTROLS

01 58 00 08/19, CHG 5: 08/22 PROJECT IDENTIFICATION

01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND

DISPOSAL

01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS

01 78 23 08/15, CHG 2: 08/21 OPERATION AND MAINTENANCE DATA

01 78 24.00 10 05/18, CHG 1: 11/21 FACILITY DATA REQUIREMENTS

01 91 00.15 10 05/19, CHG 3: 05/22 TOTAL BUILDING COMMISSIONING

DIVISION 02 - EXISTING CONDITIONS

02 41 00 05/10, CHG 2: 02/19 DEMOLITION AND DECONSTRUCTION

02 42 51 11/19 CARPET REMOVAL AND RECLAMATION

DIVISION 03 - CONCRETE

03 01 00 02/18 REHABILITATION OF CONCRETE

03 30 00 02/19, CHG 3: 11/21 CAST-IN-PLACE CONCRETE

DIVISION 05 - METALS

05 12 00 08/18, CHG 2: 05/21 STRUCTURAL STEEL

05 40 00 05/15, CHG 1: 08/18 COLD-FORMED METAL FRAMING

05 50 13 05/17, CHG 1: 08/18 MISCELLANEOUS METAL FABRICATIONS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 08/16, CHG 2: 11/18 ROUGH CARPENTRY

06 41 16.00 10 08/10, CHG 1: 11/18 PLASTIC-LAMINATE-CLAD ARCHITECTURAL

CABINETS

06 61 16 08/20 SOLID SURFACING FABRICATIONS

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 16 11/11, CHG 4: 08/18 MINERAL FIBER BLANKET INSULATION

PROJECT TABLE OF CONTENTS Page 1

07 22 00 02/16, CHG 3: 11/18 ROOF AND DECK INSULATION

07 52 00 05/12, CHG 5: 11/19 MODIFIED BITUMINOUS MEMBRANE ROOFING

07 54 23 THERMOPLASTIC POLYOLEFIN (TPO) ROOFING

07 60 00 05/17, CHG 2: 11/18 FLASHING AND SHEET METAL

07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING

07 92 00 08/16, CHG 3: 11/18 JOINT SEALANTS

DIVISION 08 - OPENINGS

08 11 13 08/20 STEEL DOORS AND FRAMES

08 31 00 05/17, CHG 1: 08/18 ACCESS DOORS AND PANELS

08 34 16.20 08/21, CHG 1: 11/21 VERTICAL LIFT FABRIC DOORS

08 71 00 02/16, CHG 3: 08/20 DOOR HARDWARE

08 81 00 05/19 GLAZING

08 87 23.13 08/09 SAFETY FILMS

DIVISION 09 - FINISHES

09 06 00 05/09, CHG 1: 11/13 SCHEDULES FOR FINISHES

09 29 00 08/16, CHG 4: 02/20 GYPSUM BOARD

09 51 00 08/20 ACOUSTICAL CEILINGS

09 65 00 08/10, CHG 3: 08/18 RESILIENT FLOORING

09 67 23.14 08/16, CHG 1: 08/18 CHEMICAL RESISTANT RESINOUS FLOORING

09 90 00 02/21 PAINTS AND COATINGS

DIVISION 10 - SPECIALTIES

10 14 00.20 08/20 INTERIOR SIGNAGE

10 44 16 11/19 FIRE EXTINGUISHERS

DIVISION 12 - FURNISHINGS

12 48 13 08/17 ENTRANCE FLOOR MATS AND FRAMES

DIVISION 21 - FIRE SUPPRESSION

21 13 13 08/20 WET PIPE SPRINKLER SYSTEMS, FIRE

PROTECTION

DIVISION 22 - PLUMBING

22 00 00 11/15, CHG 4: 05/21 PLUMBING, GENERAL PURPOSE

22 07 19.00 40 08/16 PLUMBING PIPING INSULATION

22 15 09.00 40 11/16 GENERAL SERVICE COMPRESSED-AIR SYSTEMS

CLEANING PROCEDURES

22 15 14.00 40 11/17 GENERAL SERVICE COMPRESSED-AIR

SYSTEMS, LOW PRESSURE

22 15 19.19 20 05/11 NONLUBRICATED ROTARY SCREW AIR

COMPRESSORS (100 HP AND LARGER)

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 03 00.00 20 08/10, CHG 3: 08/18 BASIC MECHANICAL MATERIALS AND METHODS

23 05 15 05/22 COMMON PIPING FOR HVAC

23 05 93 11/15 TESTING, ADJUSTING, AND BALANCING FOR

HVAC

23 07 00 02/13, CHG 7: 05/20 THERMAL INSULATION FOR MECHANICAL

SYSTEMS

23 08 00.00 20 02/21, CHG 1: 05/21 COMMISSIONING OF MECHANICAL AND

PROJECT TABLE OF CONTENTS Page 2

PLUMBING SYSTEMS

23 21 13.00 20 04/06, CHG 2: 11/19 LOW TEMPERATURE WATER (LTW) HEATING

SYSTEM

23 30 00 05/20, CHG 1: 02/22 HVAC AIR DISTRIBUTION

23 31 13.00 40 05/16 METAL DUCTS

23 37 13.00 40 08/22 DIFFUSERS, REGISTERS, AND GRILLES

23 82 00.00 20 02/16, CHG 1: 08/18 TERMINAL HEATING UNITS

DIVISION 26 - ELECTRICAL

26 05 19.10 10 05/16 INSULATED WIRE AND CABLE

26 08 00 11/21 APPARATUS INSPECTION AND TESTING

26 20 00 08/19, CHG 3: 11/21 INTERIOR DISTRIBUTION SYSTEM

26 23 00 05/15, CHG 2: 11/19 LOW-VOLTAGE SWITCHGEAR

26 28 01.00 10 08/21 COORDINATED POWER SYSTEM PROTECTION

26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 10 05 05/16 ELECTRONIC SECURITY SYSTEMS (ESS)

28 31 76 08/20 INTERIOR FIRE ALARM AND MASS

NOTIFICATION SYSTEM, ADDRESSABLE

DIVISION 31 - EARTHWORK

31 23 00.00 20 02/11, CHG 2: 08/15 EXCAVATION AND FILL

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 11 20 05/22 AGGREGATE BASE COURSE

32 12 13 05/17 BITUMINOUS TACK AND PRIME COATS

32 12 16.16 11/20 ROAD-MIX ASPHALT PAVING

32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS

32 17 23 08/16, CHG 5: 11/18 PAVEMENT MARKINGS

32 92 19 08/17, CHG 1: 08/21 SEEDING

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 3

SECTION 00 00 01

COVER SHEET

05/22

PART 1 GENERAL

NEW YORK DISTRICT

CORPS OF ENGINEERS

NEW YORK, NEW YORK 10278-0090

INVITATION FOR BIDS

FOR

WVA MORTAR FACILITY

BUILDING 125 RENOVATION

WATERVLIET ARSENAL, NEW YORK

1. Attached is INVITATION FOR BIDS (IFB) NO. W912DS-20-D-0006 -

W912DS-21-F-0089.

2. BIDS MUST BE SET FORTH full, accurate, and complete information as required by this Invitation for Bids, including attachments. The penalty for making false statements in bids is prescribed under Title 18, United States Code, Section 1001.

3. SUBMISSION OF BIDS: Complete details concerning proper submission of bids are contained in the INSTRUCTIONS TO BIDDERS (Section 00 21 13).

4. Note the REQUIREMENT FOR AFFIRMATIVE ACTION of the EQUAL OPPORTUNITY clause as it applies to the contract resulting from this solicitation. (See paragraph NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY in Section 00 72 00 of this IFB).

5. REPRESENTATIONS AND CERTIFICATIONS - SECTION 00 45 00 Bidders and Offerors are required to complete the REPRESENTATIONS AND CERTIFICATIONS and submit them with their bids.

6. GENERAL CONDITIONS - SECTION 00 72 00, note in particular the PROHIBITION SEGREGATED FACILITIES. Failure of a bidder or offeror to agree to the certification will render his bid or offer non-responsive to the terms of solicitations involving awards of contracts exceeding $10,000 which are not exempt from the provisions of the Equal Opportunity Clause.

7. Please review all bonds and accompanying documents required to be submitted. Bonds, Powers of Attorney, statements of authenticity and continuing validity, and all related documents MUST NOT bear computer printer-generated signatures and/or seals. Documents bearing signatures and/or seals generated as part of a document, as opposed to being affixed to the document after its generation, will not be accepted. Submission of such documents may render the bid or offer non-responsive and ineligible for award.

DOCUMENT 00 00 01 Page 1

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

DOCUMENT 00 00 01 Page 2

SECTION 01 11 00

SUMMARY OF WORK

08/15, CHG 2: 08/21

PART 1 GENERAL

1.1 FAR 52.211-10, COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK

a. The Contractor shall be required to (i) commence work under this contract within five (5) calendar days after the date the Contractor receives the Notice to Proceed, (ii) prosecute the work diligently, and

(iii) complete the entire work ready for use, not later than 420 calendar days after the date the Contractor receives the notice to proceed, except in case the Contracting Officer determines that seeding is not feasible during the construction period, the Contractor shall accomplish such seeding in the first planting period following the contract completion date. This action will not operate to extend the performance time for the balance of the work. The time stated for completion shall include final cleanup of the premises. (FAR 52.212-3)

b. The Contractor shall furnish all labor, materials, equipment, and services for the following work: shown in the plans and specifications.

c. All work shall be in accordance with the drawings and specifications or instructions attached hereto and made a part thereof, or to be furnished hereafter by the Contracting Officer and subject, in every detail, to his supervision, direction, and instructions.

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Salvage Plan; G

1.3 WORK COVERED BY CONTRACT DOCUMENTS

1.3.1 Project Description

The work includes building renovation including but not limited to architectural, electrical, mechanical, fire protection and incidental related work.

1.3.2 Location

The work is located at the Watervliet Arsenal, New York approximately as indicated. The exact location will be shown by the Contracting Officer.

1.4 DFARS 236.204, DISCLOSURE OF THE MAGNITUDE OF CONSTRUCTION PROJECTS

This project is estimated between $10,000,000 and $25,000,000.

SECTION 01 11 00 Page 1

1.5 OCCUPANCY OF PREMISES

Building(s) will be occupied during performance of work under this Contract. Occupancy notifications will be posted in a prominent location in the work area.

Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.6 EXISTING WORK

In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

c. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmenship to the existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone). Contractor shall provide immediate notification of the Contracting Officer and verbal procedures to restore. The Contractor must immediately assemble personnel, equipment and material necessary to restore. Compliance with Contract Documents for quality installation must be included. The work must proceed at 24-hours per day until satisfactorily restored service is achieved.

Fixing loose ends requires Contracting Officer approval to perform during normal working hours. The request to perform repairs during normal working hours requires Contractor's written approval. The write up of procedures to repair must be submitted ASAP.

d. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

1.7 LOCATION OF UNDERGROUND UTILITIES

Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.

No excavation whether minor or major including trenching, sidewalk replacement, etc. will be permitted without an approved digging permit.

Contractor shall apply for renewal of work permits as required if the work continues beyond the original permit expiration date. Verify existing utility locations indicated on contract drawings, within area of work.Dig safes are to be submitted to the Contracting Officer 's Representative a

SECTION 01 11 00 Page 2 minimum of 30 days prior to commencement of that item of work.

Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities,and any type of underground or encased obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

1.7.1 Notification Prior to Excavation

Notify the Contracting Officer at least 30 days prior to starting excavation work.

1.8 AUTHORIZED CONSTRUCTION AREA AND TRESPASSING

Do not inflict damage upon land and properties outside the authorized construction area by unwarranted entry upon, passage through, damage to, or disposal of, material on such land or property. The Contractor may make a separate agreement with any other party, regarding the use of, or right to, land or facilities outside the contract area. If such an agreement is made, it must be in writing and a copy shall be provided to the Contracting Officer. The Contractor must hold and save the Government, its officers, and agents free from liability arising from trespassing or damage occasioned by his operations.

1.9 SALVAGE MATERIAL AND EQUIPMENT

Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area at no additional cost to the U.S. Government.

Provide a salvage plan, listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Provide a system for property control in the salvage plan. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

SECTION 01 11 00 Page 3

WATERVLIET ARSENAL (WVA)

INFORMATION FOR CONTRACTORS

23 Nov 2015

This Information is intended to provide general guidelines and instructions to contractors who will be providing various services on the Watervliet Arsenal Installation. These guidelines include general as well as specific information dealing with Security, Fire, Facilities, Environmental, Industrial Hygiene and Safety issues. These should not be considered as all-inclusive but as a guide as to what is expected when performing work at the arsenal. Questions should be directed to the Contracting Officer, the Contracting Officer’s Representative (COR), or the WVA Project Manager.

1. The Watervliet Arsenal personnel from Safety, Industrial Hygiene, Security, Fire Department, and Facilities Engineering will perform periodic inspections at the work site. WATERVLIET ARSENAL

RESERVES THE RIGHT TO STOP WORK OR THE USE OF EQUIPMENT NOT IN

COMPLIANCE WITH APPLICABLE LAWS, STANDARDS, OR REGULATIONS.

2. EMERGENCIES: All emergencies must be reported. All fires must be reported regardless of size.

All spills (oils, chemicals, fuels, coolants, etc.) must be reported regardless of size. Discovery of all pre-existing spills must also be reported regardless of size. First aid is available at the Arsenal Fire House 24 hours/day. Emergency phone numbers at the arsenal (prefix 266) are:

Fire - Ext 5222 Ambulance - Ext 5333 Security - Ext 5444 Safety Office- Ext- HOTLINE (4537)/Safety Manager (5677) Industrial Hygiene - Ext 4517/4516 To Report a Spill - Ext 5888 / dial 911 from a mobile phone (Albany County)

3. WORK HOURS: Visitors and Contractors will only be allowed access to Watervliet Arsenal during normal duty hours, which are 7:00 AM through 4:00 PM, Monday through Thursday, and 7:00 AM through 3:00 PM on select Fridays (the arsenal is closed every other Friday). Work may be performed on shutdown Fridays, after normal duty hours, Saturdays, Sundays or holidays only after the contractor has submitted their request two working days in advance through the project COR or technical point of contact for request evaluation and approval by the Contracting Officer. (Note:

request approval is not guaranteed). If a federal holiday falls on a Saturday or Sunday, the preceding Friday or following Monday is a work holiday. The COR or Arsenal Point of Contact will submit a request to the Security Office and arrange for a responsible arsenal POC to be on post at all times when the visitor is on post.

4. CONTRACTOR’S PROJECT WORK ATTENDANCE: The contractor is responsible to inform the COR and/or Project Inspector of their presence on post at all times. At the beginning and end of each workday, the Contractor is required to notify the COR and/or Project Inspector of location(s) on post where work is being performed or has been completed for the day.

5. SUB-CONTRACTORS: It is the responsibility of the Contractor to inform all their sub-contractors of all the instructions contained in this information sheet. Subcontractors are responsible to report project work attendance through the prime contractor to the COR whenever they are on post.

6. OIL AND CHEMICALS: The contractor shall furnish and utilize secondary containment measures for all storage activities. The contractor shall protect oils and chemicals from rainwater at all times.

Containers shall be appropriately closed and labeled; the load shall be adequately secured during all transportation on post. The contractor shall not abandon any oil and/or chemicals on post at WVA.

e3endres Text Box This document Watervliet Arsenal (WVA) INFORMATION FOR CONTRACTORS are requirements for Contractors and cannot be modified except in writing from the Commanding Officer of WVA. Compliance is required without exception except 3 shifts as specified by Project documents. Any conflict is resolved such that this document takes precedent over all other requirements other than Laws, Rules & Regulations.

e3endres Text Box NYS Spill 1-800-457-7362 or 1-518-...

7. ELEVATED THREAT LEVEL FORCE PROTECTION CONDITION (FPCON) AT

WATERVLIET ARSENAL: Impact on contractor performance during increased FPCON during periods of increased threat. During FPCONs Charlie and Delta, services may be discontinued/postponed due to higher threat. Services will resume when FPCON level is reduced to level Bravo or lower.

8. RAMDOM ANTITERRRORISM MEASURESS PROGRAM (RAMP) AT THE WATERVLIET

ARSENAL: In accordance with AR 525-13, contractor personnel working on an installation are subject to participation in installation RAMP security program (e.g. vehicles, wearing of ID badges, etc) and installation security program.

9. BADGES: All personnel will report to the Visitors Center daily to be issued a pass. They must return the pass when they leave for the day by dropping it off in the drop box by the Visitors Center attached to the barrier to the left prior to entering the exit lane of the south gate. All personnel must show a driver’s license or state identification card (picture ID) to the security guard in order to get the pass. If the personnel will be working on the arsenal for over 90 days, they may be authorized a WVA picture badge, which will allow them access during normal work hours without getting a daily pass.

PICTURE BADGES: The contractor may request through the Contracting Officer a picture badge if the term of the contract warrants. Requests must be made in writing on company letterhead to the Contracting Officer listing the following:

a. Contract Number

b. Indicate that the individual(s) work for said company

c. Project name and location of worksite (i.e. Bldg. #)

d. Duration of performance (start and stop dates)

e. All personnel being issued a picture badge shall present a passport or original birth certificate

(with a raised seal) and drivers license. (A social security card is not an acceptable form of identification).

f. During performance of the contract, the contractor is responsible for prompt return of badges for any employee who no longer requires access to the work site.

g. Upon completion or termination of the contract or expiration of badge(s), the contractor shall ensure that they are returned to the issuing office.

h. Final payment on the contract will be held until all badges are properly returned.

i. Possession of a picture badge does not relieve the badge holder from the responsibility to notify the COR of project work attendance.

10. ACCESS POLICY: a. All contractor personnel entering the installation and requiring unescorted access must have a valid purpose to enter and be sponsored by a US government organization or a contractor providing support on the installation. They must have their identity proofed and vetted through the National Crime Information Center (NCIC) database, and be issued, or in possession of an authorized and valid access credential from the Watervliet Arsenal installation.

b. At the discretion of the Commander, US Army Watervliet Arsenal, any individual known to have a criminal background involving violence or meets the disqualifying standards in the Final Credentialing Standards for Issuing Personal Identity Verification Cards under HSPD-12 (31 JUL 2008) and local command guidance, may be denied access to the Watervliet Arsenal. Fingerprinting of employees and any other security procedures deemed necessary for the security of Watervliet Arsenal (vehicle searches or x-raying packages, bags, briefcases) may be required based on the Force Protection Condition level at the time of access and whether the installation or building location is identified as a restricted area or Mission Essential Vulnerable Area (MEVA).

11. NON-CITIZENS: Non-citizens of the U.S. may not be approved for access.

e3endres Text Box

RANDOM

e3endres Pencil

12. CAMERAS:

a. The Security Office and Public Affairs Officer must approve all cameras use prior to any pictures being taken, to include using a photographic-capable cell phone as a photographic device. Requests must be submitted to the WVA COR then routed to Security and then to the Public Affairs Officer.

Violations may result in the camera and film being confiscated and a citation being issued for an appearance before the U.S. Magistrate in Albany, NY.

b. For any photos that have been approved by the Security Office and Public Affairs Officer be advised that the photos contain military imagery that is owned by the US Government: US Army Watervliet Arsenal. It is not to be used for any purpose other than the purpose for which it is furnished nor distributed or reproduced for any purpose to persons other than the individuals specified to receive it, or their employees, without written consent of the US Army Watervliet Arsenal.

c. All photos must be reviewed by the security office before the photo capture system (i.e., camera, cell phone, etc) has left the arsenal.

13. TRAFFIC CONTROL: Post Speed Limit is 15 mph. Parking is allowed in valid spaces only. All valid spaces are clearly marked with white lines on both sides of the space. Vehicles parked in other than valid spaces are subject to being issued traffic citations requiring a monetary fine and/or an appearance before the U.S. Magistrate in Albany, N.Y. Motorists within the confines of WVA are subject to all New York State Vehicle and Traffic Laws. Any moving or nonmoving violation may result in a traffic citation being issued. Loading and unloading of vehicles will be allowed only for the amount of time required to perform the function. Vehicles cannot be left unattended in other than valid parking spaces. If a patrol officer can approach a vehicle, write a traffic citation, affix that citation to the vehicle, and depart the area with no one present at the vehicle, that vehicle is considered to be unattended. Both the Fire Department and Security Department must be notified prior to blocking of streets. The contractor must coordinate through the COR for approval to block or close streets.

14. DELIVERIES: Deliveries to contractors shall enter the post through the South Gate. Contractors expecting deliveries should notify the South Gate (266-5821) prior to the arrival of the delivery. The contractor’s representative must accept deliveries. Materials, which are delivered to the site, are the responsibility of the contractor. Storage and special conditions must be coordinated with the COR.

15. EXPLOSIVE MATERIALS: The use of explosive materials is prohibited.

16. CONTRABAND: Alcohol, illegal drugs, and any firearms are prohibited. Violations may result in the items being confiscated and a citation being issued for an appearance before the U.S. Magistrate in Albany, NY.

17. RESTRICTION OF WVA PROVIDED DOCUMENTS: Documents provided by WVA contain proprietary information and are to be used only in support of their current authorized release. Other requests for documents must be referred to the Contracting Officer, Army Contracting Command – Warren (ACC-WRN) (WVA), 1 Buffington Street, Watervliet, NY 12189. Documents shall be destroyed to prevent disclosure and reconstruction of the contents upon completion of contracted work.

18. SECURITY OF EQUIPMENT: Contractors are responsible for securing all of their equipment.

WVA is not responsible for stolen or lost items.

19. VEHICLES IN BUILDINGS: Contractors' vehicles and equipment using fuel shall receive clearance from the Fire Chief before entering the building. Refueling of vehicles in a building requires Fire Department standby.

20. STORAGE SHED/TRAILERS/TEMPORARY OFFICES: The placement of all storage shed/trailers/temporary offices are subject to the approval of the Public Works Division, the Watervliet Arsenal Fire department, and the Watervliet Arsenal Security Department. The contractor shall submit their placement request in writing 10 business days in advance to the project COR or technical POC for request evaluation and approval. (Note: request approval is not guaranteed.)

All temporary sheds, trailers or offices within thirty feet of any Arsenal structure must be equipped with a temporary sprinkler system as required by NFPA 13. The Fire Inspection Staff will assist contractors in determining sprinkler requirements on site, upon request. Call extension 5990 for fire inspector assistance.

21. EQUIPMENT, DUMPSTER, STORAGE CONTAINER/SHED, TRAILER, and OFFICE IDENTIFICATION: Contractor shall prominently display the following information on all contractor and subcontractor, owned, leased or rented motorized and wheeled equipment, dumpsters, storage containers/sheds, trailers, and offices:

a. Contractor Company Name

b. Project Number/Contract Number or Equivalent (information will be provided to contractor by the Watervliet Arsenal, the Arsenal Partnership (AP), or the AP’s Construction Manager)

c. Contractor Project Point of Contact (POC) with phone number or Arsenal/AP Project POC with phone number (information will be provided to contractor by the Watervliet Arsenal, the AP, or the AP’s Construction Manager)

22. FLAME PERMITS: A flame permit is required daily for the use of any open flame device (blowtorches, portable furnaces, tar kettles, welding, cutting devices, etc.). Call extension 5990 for request of a flame permit to be issued; give exact location of the job site, and the name of the contractor that will use the permit.

23. FIRE EXTINGUISHERS: Whenever open flame devices are used, the contractor will provide an approved fire extinguisher. Minimum size will be a 10-pound chemical (A-B-C) powder or CO2.

24. FIRE WATCH PERSONNEL (OVERHEAD WELDING OR CUTTING): The contractor will retain a worker at floor level at all times during cutting/welding operations with proper extinguishers to assure that sparks are properly controlled. Fire Watch personnel must also be provided for hot tar kettles while in operation, with approved fire extinguisher and sandbag (dike) around tar kettle.

Contractor must have a fire blanket to cover flammable material that cannot be moved.

25. GASOLINE CONTAINERS AND FLAMMABLES: Gasoline will be stored in safety containers equipped with self closing lids and other features as certified by the Underwriters' Laboratories.

Flammable liquids will be kept in National Fire Protection Association or UL approved containers;

Fire Department (extension 5990) will be called in event of a question. If gasoline or any other type fuel is kept in a portable tank it must have secondary containment or the tank be double walled and the product labeled on the side of the tank (i.e. flammable).

26. FIRE HYDRANTS: Fire hydrants shall not be used without the permission of Facilities Engineering and notification of the Fire Department (extension 5990). If permission is granted to use hydrants, the contractor will provide adapters, valves and hoses. A backflow preventer will also be required of the contractor. It is the responsibility of the contractor to insure the hydrants are shut off and have drained properly. The Fire Department must be notified when finished.

27. WATER: Backflow prevention is required for any connections to the arsenal water system throughout construction work.

28. DISCHARGES: Unless granted prior written approval, there shall be no discharge to the sanitary sewer, the storm sewer, the industrial sewer system, or the Industrial Waste Treatment Plant (IWTP).

Except when WVA has established with the contractor a prior written agreement regarding discharge of "purge water" originating from groundwater monitoring wells and/or "decontamination water" originating from activities associated with groundwater monitoring wells, there shall be no dumping of oil or chemicals or fluids to the ground.

29. DOCUMENTATION OF DISPOSITION OF MATERIALS AND ITEMS REMOVED FROM

WATERVLIET ARSENAL: The contractor shall furnish documentation of the final disposition of all materials and items leaving Watervliet Arsenal. If an item is resold intact, indicate such action for the item and the name and address of purchaser. If oil is drained from an item, provide documentation for both the oil and the item by identifying final disposition location and management method for each (e.g., recycled, incinerated, land filled). All materials and items leaving Watervliet Arsenal shall be managed strictly in accordance with all applicable environmental regulations. The contractor shall indicate intentions for all such materials and items at the pre-construction meeting, for approval by Watervliet Arsenal.

30. WASTE DISPOSAL: All hazardous waste shall be relinquished to WVA at a location on post as designated by the COR, thereafter WVA will be responsible for management of such hazardous waste. Hazardous waste shall be relinquished to WVA in accordance with the RCRA "three day" rule. Drums of hazardous waste shall not remain outdoors overnight. Other wastes include any spent material such as garbage, packaging, residues, construction and demolition debris, excavated soils and earthen materials not designated for immediate reuse, etc., which is known by WVA and/or demonstrated by the contractor via appropriate sampling and analysis to not be hazardous waste (such demonstration shall be to the satisfaction of WVA). The contractor is responsible for disposal of other wastes. Disposal of wastes at private sites such as sites advertising clean fill wanted, etc. is prohibited. The contractor shall comply with 6 NYCRR Part 364 for all waste hauling activities. The contractor shall furnish copies of documents for each waste shipment, such as Bills of Lading, etc. (Including "light weight" upon entering WVA, and "heavy weight" upon exiting WVA), through the COR to Facilities Engineering. Contractor shall furnish and properly label new, unused, appropriate drums and/or containers (including, but not limited to, compliance with DOT's Performance Oriented Packaging Standards [POPS]) for containerizing waste.

Contractor supplied dumpsters shall be covered with water proof covers to prevent precipitation from entering the dumpster. Covers shall be secured in place whenever the contractor leaves the job site, and whenever precipitation is possible or occurring.

31. INDUSTRIAL WASTE TREATMENT: Remediation work and/or hazardous waste work shall be performed in accordance with the requirements of the Resource Conservation and Recovery Act (RCRA) and OSHA's Hazardous Waste Operations and Emergency Response (HAZWOPER), including, but not limited to:

a. Documentation of appropriate training.

b. Submittal for approval of a Site Specific Work Plan.

c. Submittal for approval of a Health & Safety Plan.

d. Except when WVA has established with the contractor a prior written agreement whereby

WVA agrees to furnish drums and/or containers, contractor shall furnish and properly label new, unused, appropriate drums and/or containers (including, but not limited to, compliance with DOT's Performance Oriented Packaging Standards (POPS) for containerizing hazardous waste.

e. Contractor shall appropriately containerize all hazardous waste, consolidating the waste to minimize the number of containers as appropriate. Contractor shall not overload containers.

Each container which has some hazardous waste shall be appropriately labeled, and shall be closed at all times except when waste is actually being added to the container ("closed" means sealed in a manner appropriate for shipment).

f. All hazardous waste generated shall be relinquished to WVA.

32. INDUSTRIAL WASTE TREATMENT PLANT (IWTP): Due to OSHA Process Safety Management rule requirements, the contractor shall coordinate with the IWTP Leader regarding IWTP- specific requirements when work is to be performed in and/or around the IWTP. Requirements will include:

-hazard awareness of chemicals used at the - to include sulfur dioxide (so2).

-hazmin system- access by IWTP leader for all chemicals/msds upon request.

-proper PPE to be used when working with chemicals.

-building evacuation procedures when so2 alarm activates.

-must sign in/out of IWTP roster as acknowledgment this procedure.

33. ASBESTOS: Both OSHA Regulation 29CFR1910 and NY State Industrial Code Rule 56, (12NYCRR56) will be followed with regard to asbestos removal. If asbestos material is unexpectedly encountered during work, the contractor must contact the COR immediately. The contractor shall sign and submit the "Contractor Asbestos Notification Record" prior to starting work on any facility project.

All asbestos waste, except where WVA provides written authorization to do otherwise, shall be Properly containerized, labeled, manifested and disposed of by Contractor, at their expense, according to all Local, State and Federal laws. All manifests for such waste, including weights, shall be presented to WVA Environmental staff for signature at least 24 hours prior to removal from WVA for disposal.

The Generator copy of each Manifest shall be left with Environmental at the time of signing, for WVA records. All asbestos personnel shall provide their training certificates to the safety office prior to beginning work on the job site. Also all personnel shall have their training credentials with them at all times on the job site 34.

34. UTILITIES: Active utility services to the area of work, which are to remain, or services through the area feeding other areas, shall be rerouted, redirected or otherwise maintained. Required utility shutdowns shall be performed at such times as coordinated with Arsenal personnel and shall provide a minimum of shutdown time. Requests for shutdown shall be made at least 7 days prior to desired shutdown and be approved by the Contracting Officer prior to Contractor’s work. Arsenal personnel shall perform actual shutdown of utilities. The contractor’s work schedule shall be well planned and accomplished as expeditiously as possible. Service no longer required shall be removed.

35. ENVIRONMENTAL MANAGEMENT SYSTEM (EMS) - Watervliet Arsenal (WVA) has implemented an Environmental Management System (EMS) to proactively deal the environmental impacts of its processes, activities and services. Watervliet Arsenal uses the ISO 14001:2004 as the standard for its Environmental Management System (EMS). All personnel performing work for or on behalf of Watervliet Arsenal must be aware and understand Watervliet Arsenal’s Environmental Policy. The contractor, to include any subcontract that a contractor uses, is responsible to ensure that all goods and services do not deviate from installation environmental policy. Watervliet Arsenal’s Environmental Policy can be viewed by going to https://www.wva.army.mil/

36. UTILITY CLEARANCE PERMIT (UCP): All contracted work is subject to the WVA Regulation on utility clearance permits, WVAR 420-02. The contractor will assist the COR in preparing the UCP.

The contractor shall review the project site, project documents and utility record plans to determine the presence of concealed utilities within the area(s) of the project work. The contractor is required to sign the UCP and concur / non-concur with the project UCP.

37. MARKING UNDER GROUND UTILITIES: All contract work, which involves the installation or unearthing of underground utilities, shall include the marking of these utilities as part of the required project work. The tape shall be detectable by a metal detector when buried up to 3 feet deep. The tape shall be of a type specifically manufactured for marking and locating underground utilities. The metallic core of the tape shall be encased in a protective jacket or provided with other means to protect it from corrosion. Tape color shall be as specified below and shall bear a continuous printed inscription describing the specific utility.

RED: ELECTRIC

BLUE: WATER SYSTEM

GREEN: SEWER SYSTEM

YELLOW: GAS LINE OR PIPELINE (FOR NATURAL GAS, OIL,

STEAM/CONDENSATE OR OTHER DANGEROUS MATERIALS)

ORANGE: FIBER OPTIC (TELEPHONE, TELEVISION, SECURITY OR FIRE ALARM)

38. HISTORICAL ITEMS: The Contracting Officer or the COR reserves the right to declare any item or items resulting from removals, excavation, demolition, cleanup, or any other contract operation, as historically significant items. Included in this category are items of weaponry, ammunition, uniforms, equipment, relics, architectural features, archeological features or any other item that represents a part of the past history of the Arsenal. It is incumbent upon the contractor to report the finding of any item that may have historical significance. If the contractor discovers any item, which could be from the above category, all work will cease and the Contracting Officer or the COR will be contacted. These items shall remain in the property of the Arsenal and be delivered by the contractor to an area designated by the Contracting Officer or the COR. Historical items shall be carefully removed and carefully handled to prevent damage.

39. ASBESTOS AND MERCURY FREE: All materials utilized in the contract work shall be asbestos and mercury free. An asbestos material is any material containing more than one percent by weight of asbestos.

40. LEAD-FREE/CHROMIUM-FREE PAINT: All paints applied shall be lead-free and chromium free. Lead based paint is paint that contains more than six one hundredths of one percent, 0.06%, lead in weight.

41. PCB’s: To the extent that the project introduces fluids or equipment, such fluids and equipment shall not contain any polychlorinated biphenyls (PCBs). PCB-Free is a level of contamination less than 2 PPM using EPA approved methodologies.

42. CONFINED SPACE ENTRY: All contracted work is subject to WVA Regulation 385-1 Confined space entry procedure. Contractors shall provide proof of training in confined space entry procedures.

Contractor shall provide the COR a completed WVA Form 385-17-E, confined space entry permit or equivalent company form prior to starting any work within a confined space. Contractors shall provide their own calibrated confined space Monitors when entering all confined spaces. Contractors will have their own retrieval tripods and harnesses. Contractor will notify COR and Fire Dept contact prior to entering confined space each day.

43. ACCIDENT PREVENTION PLAN: Prior to commencement of contract work, the Contractor shall submit for approval to the COR, an Accident Prevention Plan if required per Federal Acquisition Regulation construction clause 52.236-13(f).

44. MATERIAL SAFETY DATA SHEETS (MSDS): When material safety data sheets (MSDS’s) or labels are required, failure to submit them prior to award, or when requested to do so, may result in the contractor being considered non-responsive. When providing MSDS’s at any time, provide 7 copies to the Contracting Officer. Material Safety Data Sheets for all chemicals/paints are to be made available at the work site and all containers of chemicals will be labeled for identification.

45. LASER OPERATIONS: All laser operations must be in accordance with ANSI Z13.6.1. The Radiation Safety Officer must be notified when a laser will be used on a worksite.

46. SOUND LEVELS: Sound levels in the vicinity of equipment installed under any project shall not exceed 85 BA following construction when the equipment is in use (measured by a sound level meter set for A scale, slow response). The vicinity of installed equipment is defined as a distance not to exceed 1 meter from the equipment. Techniques such as sound level averaging or exposure time weighting shall not be used to meet this requirement. If an 85-dBA limit is beyond the state of art for the equipment, documentation verifying the minimum level achievable shall be submitted to WVA for review and acceptance at time of equipment submittals. This documentation shall be provided and reviewed/approved prior to ordering any materials.

47. SAFETY REGULATIONS: The contractor shall comply with all provisions of U.S. Department of Labor and Occupational Safety and Health (OSHA) standards.

48. PROJECT DESIGN AND DOCUMENTATION: The Contractor shall be responsible to maintain a current copy of the project Statement of Work (SOW), or Performance Work Statement (PWS), or Statement of Objectives (SOO), whichever is applicable to the project and appears in the Contract, at the worksite(s) available to all Contractor and Subcontractor employees for reference. The Contractor shall promote the distribution of the SOW, PWS, or SOO to all Contractor and Subcontractor foremen, site supervisors, and employees providing construction services at the Watervliet Arsenal. Where the SOW, PWS, or SOO call out specific drawings and/or specifications for the proper performance and execution of project work, the Contractor shall also be responsible to provide copies of the drawings and specifications to the Contractor and Subcontractor employees, foremen, site supervisors, and workers.

49. SAFETY PRECAUTIONS: The contractor shall be responsible for instructing his workers and sub-contractors in appropriate safety measures and shall not permit them to place tools, machines and other equipment in traffic lanes or other locations in such a manner as to create safety hazards.

50. SAFETY RULES: Contractors must adhere to the following:

a. Work area will be barricaded and appropriately marked.

b. The work area will be kept clean and orderly. Waste materials are to be located so as not to create a hazard.

c. Dust and noise are to be kept to a minimum and within allowable limits (OSHA AND ACGIH TLV’s and PEL’s). (To be determined by the contracting representatives with the assistance of Industrial Hygiene and Safety).

d. Existing means of egress will be adequately maintained during construction.

e. Compressed gas cylinders shall be secured in an upright position.

f. Flashback protection is required for oxygen and acetylene welding.

g. Hand and portable power tools shall be maintained and used in a safe manner.

h. Ground fault circuit interrupters are to be used with portable electric powered tools.

i. Proper protective clothing & equipment (PPE) must be provided and worn where necessary.

j. Safety glasses must be worn in designated areas in the arsenal and within any designated construction work area.

k. Hard hats must be worn when overhead work is being performed.

l. Ladders are to be free of defects and secured from movement.

m. Scaffolds or elevated work platforms are to be properly erected and adequately guarded.

(Guardrails, toe boards, etc.).

n. Fall protection will be used whenever work is elevated above 6 feet.

o. Sides of all excavations in which employees are exposed to danger from moving ground shall be guarded by sloping, shoring, or other equivalent means.

p. Wheeled equipment (trailers, carts, etc.) must be free of defects and secured from movements.

q. Internal combustion engine exhausts are to be vented to the outside.

r. Bi-directional vehicles (fork trucks, dump trucks, shop carts, etc.) will be equipped with backup alarms.

s. Vehicular traffic flow in and out of building (work site) will be such so as to not endanger safety of personnel.

t. Material Safety Data Sheets for all chemicals/paints are to be made available at the work site and all containers of chemicals will be labeled for identification.

u. Lock-out/tag-out procedures per OSHA will be used as required.

51. SULFUR DIOXIDE (SO2) AWARENESS: Due to the presence of highly hazardous chemicals located in the Industrial Waste Treatment Plant, always follow the instructions of WVA officials quickly and completely in the event of any emergency. This is especially important when working in or near the Industrial Waste Treatment Plant (IWTP).

Because of the requirements of OSHA's Process Safety Management (PSM) standard (For specific requirements see Title 29 of the Code of Federal Regulations, Part 1910.119 on the OSHA website) safe work practices have been developed that provide for the control of hazards during operations such as lockout/tag out; confined space entry; line breaking of process associated piping; control over IWTP facility entry. These safe work practices apply to all employees and contractors equally. Contractors must follow all safe work practices while working on the installation and provide training to employees on PSM before working within the IWTP.

For contractors performing maintenance or repair, turnaround, major renovation, or specialty work on or adjacent to a covered process, contact the Contracting Officer's Representative (COR) for more instructions on special provisions of the PSM standard that applies to this work.

52. SUBMISSION OF RECORDABLE INJURIES AND ILLNESS CASES: Watervliet Arsenal is pursuing OSHA Voluntary Protection Program (VPP) recognition. In VPP, management, labor, and OSHA work cooperatively and proactively to prevent fatalities, injuries, and illnesses through a system focused on: hazard prevention and control; worksite analysis; training; and management commitment and worker involvement.

The VPP impacts all contractors whose employees cumulatively work more than 1000 hours per quarter within a calendar year at Watervliet Arsenal (herein referred to as “applicable contractors”). It is the contractor’s responsibility to ensure its employees and managers are in full compliance with OSHA requirements and have a general understanding of VPP. Detailed information on VPP is available on the OSHA website at https://www.osha.gov/dcsp/vpp/index.html . All contractors, whether regularly involved in routine site operations or engaged in temporary projects such as construction or repair, must follow the safety and health rules of Watervliet Arsenal.

Applicable contractors are required to annually submit to Watervliet Arsenal, ATTN: TAWV-XO S/Safety Office, 1 Buffington Street, Watervliet, NY 12189-4000 or email:

usarmy.watervliet.tacom.list.water-safety@mail.mil the following documents (covering the previous calendar year quarters) by 15 January:

- Total Case Incidence Rate (TCIR) - the number of recordable injuries and illness cases per 100 full-time employees that a site has experienced in a given time frame.

- Days Away, Restricted, and/or Transfer Case Incident Rate (DART) - Number of recordable injuries and illness cases per 100 full-time employees resulting in days away from work, restricted work activity, and/or job transfer that a site has experienced in a given time frame.

- OSHA Form 300A

Applicable contractors may submit the above immediately following the completion of a quarter, if desired.

53. RADIOACTIVE SOURCES: Contractor must comply with U.S. Army requirements for Radioactive Sources well as Nuclear Regulatory Commission and local WVA requirements Watervliet Arsenal's Radiation Safety Officer (RSO), in the Safety Office phone: 518-266-5635, must be notified when any radioactive sources are to be brought into WVA and must be given a copy of required licenses. The Watervliet Arsenal RSO must also be provided a POC before materials are to be brought on post for any potential follow-up questions or required information. No one will be allowed to bring any radioactive source on post until an Army Radiation Permit is issued by the Commanding Officer through the WVA RSO.

54. MEDIA: The Arsenal public affairs officer must approve any media announcement or press release that mentions the Watervliet Arsenal in either the headline or in the text of the release. Additionally, no media activity may occur on the Arsenal without prior coordination with the public affairs officer.

Coordination or requests for approval must be submitted to the public affairs officer at least two…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .