This document is a flyer for a virtual industry engagement event and one-on-one meetings regarding the Military Construction Project (MILCON) P1062 Design-Bid-Build, Dry Dock 3 Modernization at the Norfolk Naval Shipyard in Portsmouth, Virginia.

The project scope includes rebuilding the caisson seats with deep foundations, refurbishing the dock floor and walls, constructing a wet well and pump house, rerouting utilities, and replacing the dry dock's surrounding rail systems. The project cost is estimated to be over $500,000,000, with an anticipated award in Q2/Q3 FY26.

Contractors are invited to register for the virtual industry event on June 25, 2024 and request one-on-one meetings with the NAVFAC LANT team. Contractors are also requested to submit questions, comments, and feedback on the draft drawings and specifications by July 9, 2024. The government reserves the right to cancel the event and will not be responsible for any costs incurred by participants.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

P1062 Industry Day Event Dry Dock 3 Modernization

Norfolk Naval Shipyard, Portsmouth Virginia

When: June 25, One-on-One meeting date TBD

Virtual Industry Engagement, Project Introduction and Overview – Tuesday, June 25, 2024 (0830-1200)

One on One Meetings with NAVFAC LANT – TBD (0830-1600) (Location To be Determined)

What: Naval Facilities Engineering Systems Command, Atlantic (NAVFAC LANT) invites contractors to receive updates, learn, ask questions, and provide feedback in a general meeting (virtual) as well as breakout sessions (in person) regarding the proposed Military Construction Project (MILCON) P1062 Design-Bid-Build, Dry Dock 3 Modernization, Norfolk Naval Shipyard (NNSY), Portsmouth, Virginia.

Who: Construction contractors (general and specialty) with appropriate experience with Waterfront construction.

Where: Virtual Meeting

Registration is required to participate and access the meeting. Please follow the instructions provided below under Registration Information.

A web link to access the virtual industry event will be emailed to contractors whose registration information is received no later than 14 June 2024. The invitation for the virtual industry engagement event will be provided to those whose registration was received no later than 20 June 2024.

Project Scope: The Dry Dock 3 modernization project includes the following major components: rebuilding the caisson seats with deep foundations, refurbishing the dock floor and walls, pinning the concrete floor, constructing a wet well and pump house to replace the existing pumpwell, rerouting all utilities into a new utility trench around the dock perimeter, and replacing the dry dock’s surrounding rail systems.

1. Cofferdam A temporary cofferdam at the entrance to Dry Dock 3 will be constructed to allow the contractor to perform demolition and construction under dry working conditions. The cofferdam consists of a continuous steel pipe pile wall (SPP Wall) driven side-by-side to form a continuous wall. The wall will support approximately 40 feet of water on the riverside. The cofferdam will be constructed approximately 8 feet east of the dry dock entrance (in the river), beyond the existing timber pile supported apron. In the space between the dry dock entrance and the cofferdam, riverbed soils will be dredged and replaced with a tremie concrete slab to seal off upward water flow.

In addition, composite sheet pile/concrete closure walls will be constructed on either side of the dock entrance, connecting the SPP Wall to the dock proper and therefore closing off the entrance.

2. Dry Dock The floors and walls of the dry dock will be reconstructed by initially removing all the dry dock’s existing granite blocks (ranging from 15 inches thick along the floor and up to 50 inches thick along the altars) and a minimum of 12 inches of existing concrete beneath the granite. The coping/floodwall elevation will be the entrance, will have a tie-down system to resist increased uplift demands due to higher flood events. The dry dock’s walls and floor will be reconstructed with reinforced concrete to provide improved capacity accommodating the increased “superflood” load condition and reestablishing the 2009 FCR design blocking loads.

3. Wet Well Selective demolition of the existing below grade Pumpwell is required to accommodate the discharge piping for the Wet Well and Pump House. This includes the removal of the existing ladders, catwalks, platforms, stairs, concrete walls/slabs and fiberglass grating as required by structural work.

Project Cost Range: Over $500,000,000

Anticipated Project Award: Q2/Q3 FY26

Agenda:

June 25: General Presentation, to include but not limited to:

Project Overview Dry Dock 3 Site Overview and Project Scope of Work Acquisition Overview Existing Conditions and Proposed Conditions

TBD: One-on-one Breakout Sessions from– Please specify with your registration if a oneon-one session is requested and if you can attend in person. Provisions may be made for those who are unable to attend in person.

30-60 -minute one-on-one conference call sessions with the NAVFAC team to provide feedback on the project.

Discussions held during one-on-one meetings will be private ➢ Priority for one-on-one meetings will be given to prime contractors.

Contractors will be notified of their designated time slot, if selected. This notice will be updated to specify a date/time that each contractor will be notified by.

Meetings are preferred to be in person in Hampton Roads Area. Exact times and location TBD.

Registration Information:

Registration for the general meeting and the breakout sessions is required. Provide company name, physical address, email address(es), POC, and telephone number(s) to Brandi Upton (brandi.j.upton.civ@us.navy.mil), Contract Specialist and Rebecca Douglas (rebecca.v.douglas.civ@us.navy.mil), Contracting Officer, no later than 14 June 2024. Please identify whether your firm is a prime contractor. Please indicate within your registration if you are requesting a one-on-one session.

Comment Submission:

Contractors are invited to submit questions and/or comments via email to Brandi Upton, Contract Specialist, at brandi.j.upton.civ@us.navy.mil. Please submit your questions no later than 09 July 2024.

General questions and answers will be posted as an addendum to this announcement no later than 15 July 2024.

Please review the attached industry day questions and provide general answers via email to Brandi Upton, Contract Specialist, at brandi.j.upton.civ@us.navy.mil no later than 09 July 2024. These answers will provide the Government an initial agenda for the one-on one meetings.

Draft drawings and specifications are attached to this notice. In addition to the draft drawings and specs, a drawings and specs feedback sheet is included as an attachment to this notice. Please review drawings and specifications and provide feedback utilizing the attached excel spreadsheet no later than 09 July 2024.

The One-on-one meeting date is still TBD at this time.

Individuals who submit a response to this notice will not be contacted directly with event details. Any updates or modifications to this notice will be posted to https://sam.gov. It is your firm’s sole responsibility to obtain the information from the SAM website.

NOTE: THE GOVERNMENT RESERVES THE RIGHT TO CANCEL THIS P1062 INDUSTRY DAY EVENT AT

ANY TIME. THE GOVERNMENT IS NOT RESPONSIBLE FOR ANY COSTS INCURRED IN ORDER TO

PARTICIPATE IN THIS PROCESS. THIS P1062 INDUSTRY DAY EVENT IS IN SUPPORT OF ON-GOING

MARKET RESEARCH AND ALL INFORMATION, RECOMMENDATIONS OR SUGGESTIONS PROVIDED BY

ATTENDEES MAY BE UTILIZED WITHOUT ANY RESTRICTIONS WHATSOEVER OR COST TO THE

GOVERNMENT AND MAY BE INCLUDED IN FUTURE STATEMENTS OF WORK. NOTE: NAVFAC intends to post the project briefing as an addendum to this announcement no later than 15 July 2024. Please https://sam.gov/ monitor https://sam.gov.

NOTE: Revision 2 - If you have already registered for industry engagement day, you do not have to re-register. You will be included on the invitation for the virtual industry engagement on 25 June 2024 in lieu of the originally scheduled date

Revision 3- Registration is closed for industry engagement day.

https://sam.gov/

File details come from the government source that posted it. Updated .