This document is an Industry Engagement Briefing for the P1062 Dry Dock 3 Modernization project at the Norfolk Naval Shipyard in Portsmouth, Virginia. The project involves reconstructing Dry Dock 3 infrastructure to support Los Angeles and Virginia Class submarines. The solicitation will be a Design-Bid-Build contract with an anticipated advertisement in January 2025 and award in February/March 2026. The construction schedule includes dry dock access for the contractor in June-August 2026, an interim milestone for the north crane rail by January 2029, and construction completion by December 2030. Key details include the project scope, environmental considerations, structural design, utilities, construction challenges, and the procurement strategy which will use a best value tradeoff source selection. One-on-one industry engagement meetings are planned, and the solicitation is expected to be posted on SAM.gov.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FY25 MCON P1062
Dry Dock 3 Modernization
Norfolk Naval Shipyard Portsmouth, Virginia
Industry Engagement Briefing 25 June 2024Admin notes for virtual attendees:
1. Rollcall: please type your name/organization within MS Teams chat feature if able.
2. Please mute yourself.
2 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Welcome and Introductions
3 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Andy Herr, Project Manager - NAVFAC LANT
Eric Speight, Design Manager - NAVFAC LANT
Brandi Upton, Contract Specialist - NAVFAC LANT
Keith Barbish, SIOP Program Director - NAVFAC LANT
Matt Morris, Deputy Director - NNSY SIOP Office
Hahns Copeland, Supervisory Construction Manager - NAVFAC LANT
Pete Crum, Natural Resource Specialist - NAVFAC PWD Portsmouth
Brad Perkl, SIOP Cultural Resources Program Manager - NAVFAC
PWD Portsmouth
Bill Wheaton, Project Manager - MN+BMcD Joint Venture
Mike Brengel, Project Manager - MN+BMcD Joint Venture
Speakers and Introductions
4 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
0830-0845 Introductions and Opening Remarks
0845-0915 Project Overview
0915-0930 Project Constraints & EV Considerations
0915-1015 Project Scope Details
1015-1030 Break
1030-1100 Existing Conditions – 3D Laser Scan
1100-1130 Proposed Conditions – BIM Overview
1130-1145 Acquisition Plan
1145-1200 Question and Answer Period
Agenda
5 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
These discussions (both in the group setting and during individual one-on-one conversations) are informational and for planning purposes only. This is not a request for proposal. Nothing discussed as part of this event will be evaluated in response to any future requests for proposals.
In this meeting, do not provide the government with any proprietary information, trade secrets, or any other information deemed source selection sensitive, or any information that you do not want disseminated to the public.
Registering for and joining this virtual meeting indicates your understanding and consent to the government making a summary of this meeting publicly available including the question and answer period.
*** All Questions and Comments should be addressed to the Contracting Officer, Rebecca Douglas, Rebecca.v.douglas.civ@us.navy.mil
Ground Rules
6 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Notify Industry of the upcoming solicitation for the P-1062 Dry Dock 3 Modernization at Norfolk Naval Shipyard.
Inform industry as to the scope, timeline, and possible construction challenges for the NNSY DD Project.
Conduct one-on-one discussions and seek responses to project questionnaire.
Foster industry partnering by soliciting innovative private sector input through KTR
RFIs, responses to project questionnaire, and one-on-one sessions to help shape the acquisition strategy, technical solution, and other aspects of the project procurement.
*** NOTE: Everything you see today is a DRAFT and is subject to change
Industry Engagement Goals
7 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Project Background and Scope:
DD3 construction was completed in 1911 and has been upgraded over many years, however DD3 has aged to a condition where it cannot function safely and satisfactorily.
FY25 MILCON for reconstruction of Dry Dock 3 infrastructure to support Los Angeles and Virginia Class Block I-V submarines.
Solicitation:
Design-Bid-Build
Anticipated Advertisement – NLT January 2025
Anticipated Award – February/March 2026
Construction Schedule:
DD3 access provided to KTR in June-August 2026
Interim Milestone – North Crane Rail complete (head to interconnect) January 2029
Construction Complete December 2030
Project Overview
8 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Gate Access
Two gates access Shipyard
One contractor inspection area for clearance of contractor vehicles prior to entry
Security Badges
Two badges required for certain areas of the Shipyard, both require a background check
Dry Dock 3 project is located inside the Controlled Industrial Area (CIA)
DBIDS – Required for entry into NNSY
• Complete SECNAV Form 5512
• Requires 2 Forms of Acceptable Identification Documents - CNICINST 5530.14A
Green Contractor Badge – Required for entry into CIA
• Requires 2 Forms of Acceptable Identification Documents - CNICINST 5530.14A
• Employees must furnish proof of U.S. citizenship
Cameras, Video Equipment, etc.
Use of photographic and video equipment in the CIA requires prior approval from security.
All photographs and videos taken in the CIA requires approval from security prior to release.
Security/Access Requirements
9 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Laydown & Parking
Trailer parking area
Staging &
Stockpile area
Area around DD3 may be used for staging and laydown (including Berths 15, 16, & 17).
• Work area shaded on map with limits of disturbance
• Laydown area limited to the north portion of the crane rail separating the DD6/7 infill.
Maintain emergency response fire lanes within staging and work areas.
Maintain waterfront access to Berth 18
KTR employee parking is not allowed within the NNSY CIA.
• Parking only in designated KTR parking near NNSY
South Gate Annex area (not shown on map).
• Marked as Contractor Parking Long
Berth 18
10 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Primary Work & Laydown Area
11 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Construction
Design
8 FY19
RM17-1090 B261 & B1539 Facility Envelope Repair & SLD Demolition
10 FY22 P-256 Ships Maintenance Fac B510 Conversion
11 FY22 RM19-0182 DD8 Convert Caisson Flood Through
12 FY22 RM22-0455 Repair Berth 40 & 41
13 FY22 P-678 DD8 Saltwater System for CVN-78
14* FY22
RM22-1271 Replace Medium Voltage Circuits and Distribution Equipment
15 FY24 DD4 Refueling Complex (LOE 3)
16* FY24 RM17-1574 Repair Hatch & Prop Training B278
17 FY24
RM19-0364 DD8 Certification Maintenance Repairs
18 FY24 RM19-0173 B163 Repair Welding Shop
19 FY24
RM09-2338 B171 Ship Maintenance Shop Repairs
20 FY25 P-1062 DD3 Modernization
21 FY25
RM20-1531 Replace Drain Pump Systems & Provide Repairs, Pumpwell No. 2
22 FY26 P-732 Electrical Distribution Upgrades
Ongoing and Future Projects
8,15
11,13,1
12 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
National Environmental Policy Act (NEPA) documentation
Target is USACE NWPs 3 & 7, VMRC Habitat Division Permit under CWA 404/RHA10
Coordinating sediment sampling results with USACE/VDEQ
Validating availability of local disposal options for ~3,000CY dredged material
Assessing construction sequence, operational controls, best management practices
Assessing Water Quality Monitoring/Management
ESA and EFH Consultations
National Historic Preservation Act Section 106 Consultation
Memorandum of Agreement development and Historic American Engineering Record
(HAER) Level II Equivalent Documentation
VDEQ Stormwater Management: Water quantity requirements waiver approved
Mixing Zone Study and VPDES Permit Modification (diffuser, post KTR installation)
Air Quality Permit Modification (generators, post KTR installation)
Environmental Considerations (GOVT)
13 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Marine Mammal Monitoring - Mitigate to Zero
Protected Species Observers (PSO) under supervision of qualified Lead PSO that is independent of the project KTR during in-water construction activities
Dredged Material Management and Disposal
Material is not suitable for disposal at Craney Island Dredged Material Management Facility
Disposal at KTR-selected suitable upland facility
Treatment/disposal of decant water
Construction-phase BMPs to Comply with NWPs
Turbidity curtain and absorbent boom for sheens during dredging, cofferdam installation, and pile removal/replacement
Environmental bucket for dredging
Water quality monitoring at cofferdam/dredging
Soft start for in-water pile driving
Environmental Considerations (KTR)
14 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Cultural Resources Compliance
Develop Archaeological Monitoring and Discovery Plan (AMDP)
Employ full-time & part-time archaeological monitors during ground disturbing activities
Soil Management and Disposal
Dewatering Treatment and Management
PFAS, VOCs, Metals
Erosion & Sediment Control
Air Permit Documentation
VDEQ Construction General Permit
Environmental Considerations (KTR)
15 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Project Rendering
16 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Modernize Dry Dock 3 and improve flood resiliency:
Temporary entrance cofferdam & dewatering system
Install tension piles to anchor floor and entrance
Remove granite facing
Reconfigure dry dock cross section extending coping up to EL 106.0.
Construct perimeter utility trench
Replace existing Pumpwell 3 with a Wet Well system:
Deep excavation support system
Wet well and Pumphouse Structures
Includes all systems & controls; collect dirty water
Replace surrounding utility systems & deteriorated infrastructure
Mechanical, Electrical, Crane Rail/Foundations, Railroad, Mooring Hardware
Repair/extend Refueling Tunnel and DD2/3 Drainage Tunnel
Project Scope Summary
17 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Dredge alignment prior to pile installation
PP60x1.00 w/ pile connectors (ripped PS31), 145 VLF
Designed for up to 58.25 ft of hydrostatic head
9.5 ft min thick tremie slab
Concrete closure walls anchored to granite
Temporary floodwall to permanent floodwall up to EL106.0
Remove Berth 15 & Berth 16/17 fender piles
Cut off cofferdam piles at mudline at end of construction.
Entrance Cofferdam
18 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Overall Structural Demolition Site Plan
Sequence work such that grade beam demolition is spaced at least 50ft apart.
- Demolish crane rail, crane & tie beams
- Cut off crane rail timber piles
- Demolish existing bollards & capstans;
cut off timber piles.
50’+/-
Sheeting, as req’d
Substation
Pumpwell
Bldg.
19 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Dry Dock Demolition
Constructed circa 1903
554 ft long, unreinforced
Granite blocks, forming multiple altars
Timber pile supported
Lengthened in 1910
178 ft long extension, unreinforced
Soil supported
Existing Floor
13ft +/- thick
Longitudinally sloped to river (1.85 ft)
Demolition Depth
Min. 1ft below granite blocks
Min. 5.5 ft at entrance
Full wall depth at wet well interface
4’ dia. core drill blockouts for H-piles
20 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Demolition – Section
21 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Circa 1910 Photos
22 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Overall Structural Site Plan
Capstan & Bollard
(4.5ft drilled shafts)
Grade Beam
P/S Panel
25’
Trench Drain
Wet
Well
Intake
Sump In-haul Rail
Refueling Tunnel
Doghouse &
DD2/3 Suction
Tunnel
23 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Construction - Section
24 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Intake Sump & Culvert
25 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Structural & Miscellaneous Metals
Cofferdam Pile Piles: ASTM A252, Grade 3 Modified (fy = 60 ksi)
Steel Sheet Piles: ASTM A572, Grade 60
Crane Beam Pipe Piles: ASTM A572, Grade 50
Dry Dock Floor H-Piles: ASTM A252, Grade 3 Modified (fy = 50 ksi)
Duplex (Type 2205) Stainless Steel Selectively Used in Dry Dock Basin
Cast-in-Place Concrete
Marine Concrete:
• f’c = 4,500 psi (typical)
• f’c = 5,000 psi (immersed, river walls)
Self-Consolidating & Tremie Concrete: f’c = 3,000 psi
Precast Concrete Wall Panels : f’c = 5,000 psi
Prestressed Concrete Floor Panels : f’c = 6,000 psi
Structural Materials
26 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Provide entrance floor piling prior to wet well & sump excavation.
Prior to filling existing pumpwell:
Demolish and reconstruct river walls.
Route wet well discharge and intake pipes to river.
Sequence work such at that grade beam demolition is at least 50 ft apart.
Provide floor piling and grade beams prior to dock wall demolition.
Sequence SCC wall placement to enable uniform load along length of dock.
Altar #1 is closure between floor panels and Altar #2.
Dry Dock Structural Sequencing
27 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Portion of crane rail along north side of DD3 and at the DD2/3 crane rail interconnect must be complete by January 2029.
Portal crane rail access required in this area required by NNSY from:
January - August 2029
February - September 2030
KTR will continue to have access to this area during these periods.
Interim Milestone
28 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Entrance cofferdam, pipe & HP pile driving.
Dewatering well system, lowering of ground water
Material handling – granite, soils, concrete
Deep excavation for wet well & intake sumps
Caisson seat concrete and armor plate tolerances
P/C wall & P/S floor panel erection
Concrete quality program during project
Long Lead Items
Entrance cofferdam piling (rolling, fabrication & shipping)
Wet Well excavation support piling (rolling, fabrication, & shipping)
Structural Construction Challenges
29 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Cannot interfere with Shipyard operations
Ongoing operations in adjacent buildings and dry docks
Coordination of utility, rail, and road outages and cutovers
Maintenance of fire lanes (emergency access)
Maintenance of building/facility access
Aged infrastructure
Limited ingress due to security (Controlled Industrial Area)
Access controls for personnel, vehicles, and waterborne equipment
Limited laydown area
Environmental / Permitting
Soil/sediment contaminants
Groundwater contaminants
Protection of historic/cultural resources
Challenges of Working in a Shipyard
30 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Instrumentation & Survey Monitoring
Temporary Dewatering System
Piezometers through floor and surroundings
Dewatering well system around dock perimeter (and through dock floor as required)
• EL 60.0 surrounding dock
• EL 35.0 surrounding wet well
Magnetic settlement gauges
Place around critical buildings
Spider magnets
Datum magnet at bottom of hole
Benchmarks
Crack monitoring
Monitor existing coping of dock to ensure there is minimal moment.
Vibration monitoring at adjacent facilities
31 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Dockside Utilities
Site Utilities to be Replaced or Added:
Fresh Water
Salt Water
Submarine Firefighting (FW)
Dry Dock Firefighting (SW)
Dry Hydrant at River
Steam
Compressed Air (Low Pressure)
Compressed Air (High Pressure; from
Refueling Tunnel)
Compressed Air (Temporary Reactor Air;
from Refueling Tunnel)
Sanitary Sewer (CHT)
Nitrogen (from Refueling Tunnel)
Oily Waste/Waste Oil (OWWO)
Ship Saltwater Drainage (ASW)
Emergency Mobile Pump Piping System
(EMP)
Clean Water Header and Trench Drainage
32 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
North Side Trench Example
South Side Trench Example
33 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
CA Floor Riser Example
Dockside Utilities
South Side Floor
(EMP and ASW Riser)
34 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Wharf Wall (ASW and EMP Discharge into River)
35 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Install major electrical components (see next slide)
Underground distribution construction
Sequence feeder reconstruction to maintain power to existing adjacent facilities
Electrical systems supporting equipment installation along coping wall / dry dock
Underground telecommunications construction
Telephone
Fiber optic data, AMI, and SCADA
Fire Alarm System
Salvage, store and reinstall existing radio fire alarm transmitters around Dry Dock – replace antennas
Mounting plates in Dry Dock for Government portable systems
Refueling Tunnel Alarm System
Removal and installation of heat sensing cable for tunnel extension
Addition of notification and fire alarm pull boxes – connect back to existing Building 1475 systems.
Site Electrical / Telecom / Fire Alarm
36 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Existing Unit Substations
SF6 Pad Mounted Switches *
MV Pad Mounted Transformer *
Low Voltage Industrial and Shore Power Connection Boxes *
Low voltage connection boxes (industrial, shore, caisson power)*
Crane Hotel Power
Capstan Power
Communications Shore Tie Stations (e.g. dockside telecommunications connections)
Underground Distribution System (e.g. conductors, duct bank, and vaults)
* Denotes long lead items *
Major Site Electrical Components
37 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Coordination with existing and new utilities
Coordination of underground installation with structural construction
Medium voltage phasing
Circuit identification
Protecting temporary above ground conductors
Building access
Site Electrical Challenges
38 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Demolish existing steel structure within PW3
Core through thick existing PW3 concrete wall for new discharge and intake pipes
Fill PW3 with Self-Consolidating Concrete
Existing Pumpwell Demolition
View of PW3 and Existing Modeled Steel View of Distribution Piping from Wet Well through PW3
39 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Mechanical demolition to include all existing piping, valves, pumps, motors, actuators, and associated appurtenances
Notable equipment includes pumps, motors, and control centers
Existing Pumpwell Demolition
40 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Excavation Support System:
W44x335 Wide Flanges and NZ19
Sheet Pile Wall
Jet Grouting
• Jet Grouting 20 feet thick (EL 35 to EL
15) at bottom of Wet Well footprint
• Jet Grouting on the south side between the Wet Well and existing DD6 substructure (EL 93 to EL 15)
Dewater Wet Well area to EL 35
Sequenced Excavation / Support
30" Diameter, 1" Thick Steel Pipe
Struts
3 Rows of 12" Diameter Grouted
Tiebacks (45 Deg Angle)
• Ranging 215-273 Kips of Capacity
• 20-30 Feet of Unbonded Length
• 34-44 Feet of Bonded Length
Wet Well Construction
41 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Shell Only: Wet Well Walls
6' Thick Concrete Exterior Walls
3' Thick Concrete Baffle Wall
Laying Rebar for later construction of beams, slabs, and concrete corbels
Adding in Floors:
Pump Level – Below Grade
• 18” Thick Concrete Slab
• Concrete Beams
Control Level and Roof – Above Grade
• Concrete on Non-Composite Deck
• Steel Beams
• Overhead Coiling Doors
• 8’ x 8’ Roof Hatches for Equipment Access
Elevated Generator Equipment Platform
(9) 12” Diameter Steel Pipe Piles
24” Thick Concrete Flat Slab
34' X 34' Equipment Platform Plan
42 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
(6) 350hp Vertical Pumps
(4) 60hp Sump Pumps
(2) Sluice Gates
30” - 48” Check and Gate Valves
30” - 48” Ductile Iron Piping
6” - 10” HDPE Piping
Dock Control Panel
43 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
(2) 96” x 72” Sluice Gates
Above-grade actuators
Watertight thimble plates (uplift)
Several other watertight penetrations
Large diameter pipes
Environmental Process Pump removal plates
44 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Custom Dock Control Panel
Control and monitoring of pumps
Control of valves and gates
Water level monitoring, etc.
Notable Control/Monitoring Equipment
Valve/Gate Actuators
Level Monitoring Systems
Pump Motors
Flow Meters
45 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Long Lead Equipment Includes:
Vertical Drainage Pumps and Motors
Dry Dock Control Panel
Large Valves
• Check and gate valves
• Many valves are required to be duplex stainless steel construction
Sluice Gates/Weirs
46 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Telecommunications
Infrastructure for DoD and shipyard data networks & cabling
Separate infrastructure for SCADA network equipment & cabling
Passive Distributed Antenna System (DAS) for distributing VHF/UHF signals into the Wet Well
47 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Fire Alarm
Addressable system
• FACU, Fire Alarm Transmitter, Remote Annunciator
• Control and pump levels
Initiating Devices: smoke detectors, waterflow switch, manual pull stations, etc.
Notification Devices: horn/strobes
Class B circuits
Fire Suppression
Domestic water supply from Dry Dock
Automatic wet-pipe system
• Light and Ordinary Hazards
• One riser serving control and pump levels
Riser and wall-mounted PIV at control level
FDC on plan west side
Wet Well Fire Protection
48 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Wet Well Electrical Power Distribution
49 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
5-Way, SF6 Switch powered from two 11.5kV feeders from Distributions IV and XII
4.16kv MCC2 powers drainage pumps DP-1 thru DP-6
480V MCC1 powers the remaining Wet Well Mechanical loads
480V SWBD1 powers the main Wet Well distribution system
800KW 480V Diesel Generator with 400KW resistive load bank for backup power of drainage pumps and critical systems
Wet Well Electrical Power Distribution
50 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Long Lead Times
800KW 480V Generator and Enclosure
• 400KW Resistive Load Bank
4160V, 800A Switchgear
480V, 600A Switchgear
800A Automatic Transfer Switch
2500KVA 11.5KV – 4.16KV Transformer
750KVA 480V – 4.16KV Transformer
500KVA 11.5KV – 480Y/277V Transformer
Generator Service Agreements
Short lead time parts within 24 hours.
Long lead time parts within 72 hours.
Authorized service support within 50-mile radius or 1-hour response time.
Wet Well Electrical Considerations
51 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Transition to Videos
52 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Procurement Strategy
Brandi Upton
Contract Specialist, SIOP
Naval Facilities Engineering Systems Command Atlantic
Construction Acquisition
53 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Procurement Strategy
Project Budget
- DFARS 236.204 Magnitude of Construction: Over $500,000,000
- Project is incrementally funded from FY25 through FY29
Overall Contract Duration
Approximately 4.5 years
Construction Contract
FY25 MCON P-1062 Dry Dock 3 Modernization
Request for Proposals (Single Solicitation Package)
- Best Value Source Selection (BVSS) – Trade-off
54 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
FAR 15.1 Competitive acquisitions – proposals will be evaluated in an impartial and comprehensive manner, ultimately leading to the selection of the proposal that represents the best value to the Government.
Best value - the expected outcome of an acquisition that, in the Government's estimation, provides the greatest overall benefit in response to the requirement.
FAR 15.101-1 – Tradeoff process
Used when it may be in the best interest of the Government to consider award to other than the lowest priced offeror or other than the highest technically rated offeror.
All evaluation factors that will affect contract award and their relative importance shall be clearly stated in the solicitation.
The solicitation shall state whether all evaluation factors other than cost or price, when combined, are significantly more important than, approximately equal to, or significantly less important than cost or price.
Past performance will be evaluated in accordance with FAR 15.305.
Best Value – Tradeoffs
55 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
FAR 15.101-1 – Tradeoff process
Evaluation Factors:
• Price
• Technical Factors (not inclusive):
– Past Performance (shall be equal to technical factors
– Small Business Utilization (if procurement is unrestricted)
– Safety
Evaluation Factors
56 Dry Dock 3 Modernization, Norfolk Naval Shipyard, Portsmouth, Virginia
Industry Engagement Part 2:
One-on-One Meetings by request TBD
• Review of GOV provided questions
• Information in discussions will not be shared publicly
Expected Project Schedule:
November 2024-January 2025: RFP Release
Proposals Due: 90 days after RFP Release
Proposal Evaluation: Q3-FY25 to Q2-FY26
Award: Q2-FY26
Construction Start: Q4-FY26
Construction Completion: Q1-FY31
Solicitation and Award Venue: https://sam.gov
Note: Dates and acquisition strategy are still in refinement, and subject to change. Source selection evaluation factors will be specifically defined in the solicitation.