This document provides details for a draft request for proposal for operation of the Naval Shipbuilding and Advanced Manufacturing Center of Excellence III. The Department of the Navy, Secretary of the Navy Office of Naval Research intends to issue a full and open competitive solicitation as a cost plus fixed fee indefinite delivery/indefinite quantity contract for a base period of two years and three optional one-year periods, with an additional optional six month extension. The solicitation number will be N0001424R0002 and is anticipated for release on or around March 29, 2024. The contractor will operate and manage the NSAM Center of Excellence to identify, develop, and facilitate advanced manufacturing technologies to reduce cost and time for building and sustaining key naval platforms such as submarines, carriers, surface combatants and the F-35 Joint Strike Fighter. The contractor shall also manage, operate, sustain and enhance the center's ability to function as an ONR Manufacturing Technology Center of Excellence.

View the file

Other files

File Type Posted
NSAM3 RFP Sec J Attachment 10 Expenditure Estimate Spreadsheet and Monthly Expenditure Report Guidance REV K Feb 2024.docx DOCX document
NSAM3 RFP Sec J Attachment 18 Project Book Guidance REV L MAY22.docx DOCX document
NSAM3 RFP Sec J Attachment 16 Affordability Assessment Guidance REV L AUG22.docx DOCX document
NSAM3 RFP CDRL ENCLOSURE NUMBER 1.docx DOCX document
NSAM3 RFP Sec J Attachment 13 Project Quad Chart Guidance REV I OCT22.docx DOCX document
NSAM3 RFP Sec J Attachment 8 Data Call Chart REV O APR22.xlsx XLSX spreadsheet
NSAM3 RFP Sec J Attachment 26 Annual_Review_Project_Briefing_Template_REV_D_JAN23.pptx PPTX presentation
NSAM3 RFP Sec J Attachment 23 Proposal Pipeline and ONR Contracts Actions Spreadsheet Guidance REV C OCT21.docx DOCX document
NSAM3 RFP Exhibit A COE CDRLS 02.27.2024.docx DOCX document
NSAM3 RFP Sec J Attachment 5 Price Information.docx DOCX document
NSAM3 RFP Sec J Attachment 25 Navy ManTech Code 33 Monthly Report Guidance REV E OCT22.docx DOCX document
NSAM3 RFP Sec J Attachment 9 Funding Allocation Spreadsheet Guidance REV J OCT22.docx DOCX document
NSAM3 RFP Sec J Attachment 21 Rapid Response and Special Projects Guidance REV E OCT22.docx DOCX document
NSAM3 RFP Sec J Attachment 22 Return on Investment Calculation Guidance REV E OCT21.docx DOCX document
NSAM3 RFP Sec J Attachment 14 Technology Transition Plan Guidance REV N OCT22.docx DOCX document
NSAM3 RFP Sec J Attachment 4 Q and A Template.xlsx XLSX spreadsheet
NSAM3 RFP Sec J Attachment 10 Expenditure Estimate Spreadsheet and Monthly Expenditure Report Guidance REV K Feb 2024.docx DOCX document
NSAM3 RFP Sec J Attachment 24 Public Release Request Tool Guidance REV G OCT22 draft.docx DOCX document
NSAM3 RFP Sec J Attachment 12 Final Report Guidance REV J OCT22.docx DOCX document
NSAM3 RFP Sec J Attachment 1 SOW Feb 28 2024.docx DOCX document
NSAM3 RFP Sec J Attachment 17 COE Transition Implementation Guidance - REV F OCT22.docx DOCX document
NSAM3 RFP Sec J Attachment 11 Quarterly Report Guidance REV J OCT22.docx DOCX document
NSAM3 RFP Sec J Attachment 28 Review Form Instructions - Portfolio Review.pptx PPTX presentation
NSAM3 RFP Sec J Attachment 7 Annual Data Call REV L OCT22.docx DOCX document
NSAM3 RFP Sec J Attachment 2 Key Personnel.docx DOCX document
NSAM3 RFP Sec J Attachment 20 Implementation Risk Assessment Guidance REV H OCT22.docx DOCX document
N0001424R0002 2.29.2024 DRAFT RFP.pdf PDF
NSAM3 RFP Sec J Attachment 19 Project Briefing Guidance REV I OCT22.docx DOCX document
NSAM3 RFP Sec J Attachment 27 Annual Portfolio Review Form REV B JAN23.xlsx XLSX spreadsheet
NSAM3 RFP Exhibit B Project CDRLS 02.27.2024.docx DOCX document
NSAM3 RFP Sec J Attachment 15 Success Story Guidance REV M OCT22.docx DOCX document
NSAM3 RFP Sec K ONR Reps Certs Feb 2024.docx DOCX document
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

General

Prime Contractor:Prime 1 (Fill-in)COST PROPOSAL
Subcontractor:Sub 1 (Fill-in)
GENERAL INFORMATION
The purpose of the requested information in the attached worksheets is to assist government personnel in the review and evaluation of cost proposals submitted by offerors. Offerors are reminded that the responsibility for providing adequate supporting data and attachments lies solely with them. Further, the offeror must also bear the burden of proof in establishing reasonableness of proposed costs; therefore, it is in the offeror’s best interest to submit a fully supportable and well-prepared cost proposal. The basis and rationale for all proposed costs should be provided as part of the proposal so that Government personnel can place reliance on the information as current, complete and accurate. Further, FAR 15.403-4 sets forth those circumstances in which offerors are required to submit certified cost or pricing data. (Updated Nov. 19, 2013)

Cost by Task: In addition to providing summary by period of performance (Base and any Options), the contractor is also responsible for providing a breakdown of cost for each task indentified in the statement of work. The sum of all cost by task worksheets MUST equal the total cost summary.

Options: Upriced Options will not be accepted. Any Option that is not fully priced, will not be included in any resulting award.

Enter the proposed cost detail for the Base and each Option period (as needed) on the tabs entitled,, "Base", "O-I". "O-II", O-III", "O-IV", and "O-V". The tab entitled, "Total Amount" will automatically calculate from the Base and Option tabs.

• Do not change formulas.
• Ensure all costs from other worksheets are correct.
Below is a summary of the proposed cost. This chart will automatically fill in from the "Total Amount" tab.Below is a summary of Documentation/Documents Required
Prior to Negotiations
Total Direct Labor Costs$0
Total Fringe Benefit Costs$0Consulting Agreement for each Consultant
Total Labor Overhead Costs$0Supporting documentation for Materials/Supplies
Total Subcontract Costs$0Supporting documentation for Equipment
Total Consultant Costs$0Supporting documentation for Other ODC
Total Other Direct Costs$0
Total Material Handling Costs$0
Subtotal Costs$0
Total G&A Costs$0
Subtotal Costs$0
Total Cost of Money$0
Total Estimated Costs$0
Fixed Fee (If proposing a CPFF contract)$0
Total Estimated Costs Plus Fixed Fee$0

Total Amount

Cost Proposal - Total Amount
Prime Offeror:Prime 1 (Fill-in)
Subcontractor:Sub 1 (Fill-in)
(Note 2)(Note 2)(Note 2)(Note 2)(Note 2)(Note 2)
BASEOPTION 1OPTION 2

Wade Wargo: Note:

Offeror to insert whether it's accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

OPTION 3OPTION 4OPTION 5Total
Direct Labor (DL)MM/YR to MM/YR

Wade Wargo: Note:

The months during the Base period of performance that these rates apply

MM/YR to MM/YR Wade Wargo: Note:

The months during the Option period of performance that these rates apply

MM/YR to MM/YR Wade Wargo: Note:

The months during the Option period of performance that these rates apply

MM/YR to MM/YR Wade Wargo: Note:

The months during the Option period of performance that these rates apply

MM/YR to MM/YR Wade Wargo: Note:

The months during the Option period of performance that these rates apply

MM/YR to MM/YR Wade Wargo: Note:

The months during the Option period of performance that these rates apply

(Note 3) X-Months wade.wargo: Indicate the actual number of total months for the Base and Options.

Offeror's Labor Category (Note 1)Name (Last, First)Base/HoursRateExtended $Base/HoursRateExtended $Base/HoursRateExtended $Base/HoursRateExtended $Base/HoursRateExtended $Base/HoursRateExtended $Base/HoursExtended $
0$0.000$0.000$0.000$0.000$0.000$0.000$0.00
0$0.000$0.000$0.000$0.000$0.000$0.000$0.00
0$0.000$0.000$0.000$0.000$0.000$0.000$0.00
0$0.000$0.000$0.000$0.000$0.000$0.000$0.00
0$0.000$0.000$0.000$0.000$0.000$0.000$0.00
0$0.000$0.000$0.000$0.000$0.000$0.000$0.00
0$0.000$0.000$0.000$0.000$0.000$0.000$0.00
0$0.000$0.000$0.000$0.000$0.000$0.000$0.00
0$0.000$0.000$0.000$0.000$0.000$0.000$0.00
0$0.000$0.000$0.000$0.000$0.000$0.000$0.00
0$0.000$0.000$0.000$0.000$0.000$0.000$0.00
0$0.000$0.000$0.000$0.000$0.000$0.000$0.00
0$0.000$0.000$0.000$0.000$0.000$0.000$0.00
0$0.000$0.000$0.000$0.000$0.000$0.000$0.00
0$0.000$0.000$0.000$0.000$0.000$0.000$0.00
0$0.000$0.000$0.000$0.000$0.000$0.000$0.00
0$0.000$0.000$0.000$0.000$0.000$0.000$0.00
0$0.000$0.000$0.000$0.000$0.000$0.000$0.00
0$0.000$0.000$0.000$0.000$0.000$0.000$0.00
0$0.000$0.000$0.000$0.000$0.000$0.000$0.00
Total Direct Labor Costs0$0.000$0.000$0.000$0.000$0.000$0.000$0.00
Fringe Benefits (F/B) (See Escalation and Indirect Rate Worksheet)
Insert F/B rate title$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0.00$0.00
Insert line(s) & title(s) for any other F/B rates$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Fringe Benefit Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Labor Overhead (O/H) (See Escalation and Indirect Rate Worksheet)
Insert O/H rate title$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0.00$0.00
Insert line(s) & title(s) for any other O/H rates$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Labor Overhead Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Subcontracts/Interorganizational TransferFile/Tab Name or Link
Subcontract/Interorganizational Name - #01

Sutherland, Susan M CIV ONR, 22: Sutherland, Susan M CIV ONR, 22:

Include the Subcontractor Name

Wade Wargo: Note:

The months during the Option period of performance that these rates apply

The months during the Base period of performance that these rates apply wade.wargo: Indicate the actual number of total months for the Base and Options.

The months during the Option period of performance that these rates apply

Offeror to insert whether it's accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

Wade Wargo: Note:

The months during the Option period of performance that these rates apply

Provide details in Subcontractor Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Subcontract/Interorganizational Name - #02Provide details in Subcontractor Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Subcontract/Interorganizational Name - #03Provide details in Subcontractor Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Insert line(s) for any additional Subcontractors/InterorganizationalProvide details in Subcontractor Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Subcontract Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Consultants
Consultant Name - #01Provide details in Consultant Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Consultant Name - #02Provide details in Consultant Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Consultant Name - #03Provide details in Consultant Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Insert line(s) for any additional ConsultantsProvide details in Consultant Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Consultant Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Other Direct Costs
Materials/SuppliesProvide details in Materials Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
EquipmentProvide details in Equip. Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
TravelProvide details in Travel Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Insert line(s) for any other types of ODCsProvide details in ODC Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Other Direct Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Material Handling (M/H O/H) (See Escalation and Indirect Rate Worksheet)
Insert M/H O/H rate title$00.000%$0.00$00.000%$0.00$00.000%$0.00$00.000%$0.00$00.000%$0.00$00.000%$0.00$0.00$0.00
Insert line(s) & title(s) for any other M/H O/H rates$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Material Handling Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Subtotal Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
General and Administrative (G&A) (See Escalation and Indirect Rate Worksheet)
Insert G&A rate title$00.000%$0.00$00.000%$0.00$00.000%$0.00$00.000%$0.00$00.000%$0.00$00.000%$0.00$0.00$0.00
Insert line(s) & title(s) for any other G&A rates$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total G&A Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Subtotal Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Facilities Cost of Money (COM) (See Escalation and Indirect Rate Worksheet)
Insert COM rate title$00.000%$0.00$00.000%$0.00$00.000%$0.00$00.000%$0.00$00.000%$0.00$00.000%$0.00$0.00$0.00
Insert line(s) & title(s) for any other COM rates$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Cost of Money$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Estimated Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Fixed Fee (If proposing a CPFF contract)(Note 4)$00.000%$0.00$00.000%$0.00$00.000%$0.00$00.000%$0.00$00.000%$0.00$00.000%$0.00$0.00$0.00
Total Estimated Costs Plus Fixed Fee$0.00$0.00$0.00$0.00$0.00$0.00$0.00

Instructions: • For PRIME submission - Subcontractor Name: If there are subcontracts, list all subcontractor names.

• In upper right last column, replace the X in X-Months with actual number of months for the Base and Options.

• List Principal Investigator and Key Personnel working on the project even if they receive no salary support.

• Subcontracts/Interorganizational Transfers: If appropriate, place Subcontractor name(s) or Interorganizational Name/Code in Column B.

• Consultants: If appropriate, place Consultant name(s) in Column B.

• Remember that the total of all Base and Option worksheets should equal the total of the Total Amount worksheet.

• Add descriptions in Column B if costs are entered in the following areas: Fringe Benefits, Labor Overhead, Other Direct Costs/other types, Material Handling, General and Administrative, and Facilities Cost of Money.

Note 1:Any proposed personnel in the technical proposal should be identified with their labor category.
Note 2:Indicate the period of performance that these rates apply. Ensure that the length of the periods proposed match those stated in the technical proposal.
Note 3:The values under Total Direct Labor "hours/base" column indicate the total level of effort for the project for each labor category. The Offeror must define the split of hours between initial and subsequent rate years based on its FY or CY in the prior columns.
Note 4:Profit or fee is not allowed on direct costs for equipment, Government entities or cost share contracts. In addition, a DD Fom 1547 (DFARS 215.404-70) will be utilized in calculating the Government objective for fee.

Base

Cost Proposal - Base
Prime Offeror:Prime 1 (Fill-in)
Subcontractor:Sub 1 (Fill-in)
(Note 2)(Note 2)(Note 2)(Note 2)(Note 2)(Note 2)
CY/FY

Wade Wargo: Note:

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year CY/FY Wade Wargo: Note:

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

CY/FY

Wade Wargo: Note:

Offeror to insert whether it's accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

CY/FY

Wade Wargo: Note:

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

CY/FY

Wade Wargo: Note:

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year CY/FY Wade Wargo: Note:

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current yearTotal
Direct Labor (DL)MM/YR to MM/YR

Wade Wargo: Note:

The months during the base period of performance that these rates apply

MM/YR to MM/YR Wade Wargo: Note:

The months during the base period of performance that these rates apply

MM/YR to MM/YR Wade Wargo: Note:

The months during the base period of performance that these rates apply

MM/YR to MM/YR Wade Wargo: Note:

The months during the base period of performance that these rates apply

MM/YR to MM/YR Wade Wargo: Note:

The months during the base period of performance that these rates apply

MM/YR to MM/YR Wade Wargo: Note:

The months during the base period of performance that these rates apply

(Note 3) X-Months wade.wargo: Indicate total months of Base period

Offeror's Labor Category (Note 1)Name (Last, First)Base/HoursRateExtended $Base/HoursRateExtended $Base/HoursRateExtended $Base/HoursRateExtended $Base/HoursRateExtended $Base/HoursRateExtended $Base/HoursExtended $
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
Total Direct Labor Costs0$0.000$0.000$0.000$0.000$0.000$0.000$0.00
Fringe Benefits (F/B) (See Escalation and Indirect Rate Worksheet)
Insert F/B rate title$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0.00
Insert line(s) & title(s) for any other F/B rates$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Fringe Benefit Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Labor Overhead (O/H) (See Escalation and Indirect Rate Worksheet)
Insert O/H rate title$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0.00
Insert line(s) & title(s) for any other O/H rates$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Labor Overhead Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Subcontracts/Interorganizational TransferFile/Tab Name or Link
Subcontract/Interorganizational Name - #01

Sutherland, Susan M CIV ONR, 22: Sutherland, Susan M CIV ONR, 22:

Include the Subcontractor Name

Wade Wargo: Note:

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

The months during the base period of performance that these rates apply

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

Offeror to insert whether it's accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

wade.wargo: Indicate total months of Base periodProvide details in Subcontractor Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Subcontract/Interorganizational Name - #02Provide details in Subcontractor Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Subcontract/Interorganizational Name - #03Provide details in Subcontractor Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Insert line(s) for any additional Subcontractors/InterorganizationalProvide details in Subcontractor Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Subcontract Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Consultants
Consultant Name - #01Provide details in Consultant Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Consultant Name - #02Provide details in Consultant Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Consultant Name - #03Provide details in Consultant Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Insert line(s) for any additional ConsultantsProvide details in Consultant Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Consultant Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Other Direct Costs
Materials/SuppliesProvide details in Materials Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
EquipmentProvide details in Equip. Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
TravelProvide details in Travel Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Insert line(s) for any other types of ODCsProvide details in ODC Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Other Direct Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Material Handling (M/H O/H) (See Escalation and Indirect Rate Worksheet)
Insert M/H O/H rate title$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0.00
Insert line(s) & title(s) for any other M/H O/H rates$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Material Handling Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Subtotal Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
General and Administrative (G&A) (See Escalation and Indirect Rate Worksheet)
Insert G&A rate title$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0.00
Insert line(s) & title(s) for any other G&A rates$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total G&A Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Subtotal Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Facilities Cost of Money (COM) (See Escalation and Indirect Rate Worksheet)
Insert COM rate title$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0.00
Insert line(s) & title(s) for any other COM rates$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Cost of Money$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Estimated Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Fixed Fee (If proposing a CPFF contract)(Note 4)$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0.00
Total Estimated Costs Plus Fixed Fee$0.00$0.00$0.00$0.00$0.00$0.00$0.00

Instructions: • For PRIME submission - Subcontractor Name: If there are subcontracts, list all subcontractor names.

• In upper right last column, replace the “X” in X-Months with actual number of months.

• Add descriptions in Column B if costs are entered in the following areas: Fringe Benefits, Labor Overhead, Other Direct Costs (other types), Material Handling, General and Administrative, and Facilities Cost of Money.

• Subcontracts/Interorganizational Transfers: If appropriate, place Subcontractor name(s) or Interorganizational Name/Code in Column B.

• Consultants: If appropriate, place Consultant name(s) in Column B. Running title will indicate when submission is from a prime, subcontractor or consultant.

Note 1:Any proposed personnel in the technical proposal should be identified with their labor category.
Note 2:Indicate whether the Offeror's accounting system is based on a calendar year or fiscal year (Row 5). Indicate the months during the period of performance that these rates apply (Rox 6).
Note 3:The values under Total Direct Labor "hours/base" column indicate the total level of effort for the project for each labor category. The Offeror must define the split of hours between initial and subsequent rate years based on its FY or CY in the prior columns.
Note 4:Profit or fee is not allowed on direct costs for equipment, Government entities or cost share contracts. In addition, a DD Fom 1547 (DFARS 215.404-70) will be utilized in calculating the Government objective for fee.

&"Arial,Bold"&12&A

Offeror: Page &P of &N Pages &F

O-I

Cost Proposal - Option I
Prime Offeror:Prime 1 (Fill-in)
Subcontractor:Sub 1 (Fill-in)
(Note 2)(Note 2)(Note 2)(Note 2)(Note 2)(Note 2)
CY/FY

Wade Wargo: Note:

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

CY/FY

Wade Wargo: Note:

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

CY/FY

Wade Wargo: Note:

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

CY/FY

Wade Wargo: Note:

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

CY/FY

Wade Wargo: Note:

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year CY/FY Wade Wargo: Note:

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current yearTotal
Direct Labor (DL)MM/YR to MM/YR

Wade Wargo: Note:

The months during the base period of performance that these rates apply

MM/YR to MM/YR Wade Wargo: Note:

The months during the base period of performance that these rates apply

MM/YR to MM/YR Wade Wargo: Note:

The months during the base period of performance that these rates apply

MM/YR to MM/YR Wade Wargo: Note:

The months during the base period of performance that these rates apply

MM/YR to MM/YR Wade Wargo: Note:

The months during the base period of performance that these rates apply

MM/YR to MM/YR Wade Wargo: Note:

The months during the base period of performance that these rates apply

(Note 3) X-Months wade.wargo: Indicate total months of Option period

Offeror's Labor Category (Note 1)Name (Last, First)Base/HoursRateExtended $Base/HoursRateExtended $Base/HoursRateExtended $Base/HoursRateExtended $Base/HoursRateExtended $Base/HoursRateExtended $Base/HoursExtended $
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
Total Direct Labor Costs0$0.000$0.000$0.000$0.000$0.000$0.000$0.00
Fringe Benefits (F/B) (See Escalation and Indirect Rate Worksheet)
Insert F/B rate title$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0.00
Insert line(s) & title(s) for any other F/B rates$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Fringe Benefit Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Labor Overhead (O/H) (See Escalation and Indirect Rate Worksheet)
Insert O/H rate title$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0.00
Insert line(s) & title(s) for any other O/H rates$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Labor Overhead Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Subcontracts/Interorganizational TransferFile/Tab Name or Link
Subcontract/Interorganizational Name - #01

Sutherland, Susan M CIV ONR, 22: Sutherland, Susan M CIV ONR, 22:

Include the Subcontractor Name

Wade Wargo: Note:

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

wade.wargo: Indicate total months of Option periodProvide details in Subcontractor Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Subcontract/Interorganizational Name - #02Provide details in Subcontractor Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Subcontract/Interorganizational Name - #03Provide details in Subcontractor Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Insert line(s) for any additional Subcontractors/InterorganizationalProvide details in Subcontractor Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Subcontract Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Consultants
Consultant Name - #01Provide details in Consultant Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Consultant Name - #02Provide details in Consultant Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Consultant Name - #03Provide details in Consultant Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Insert line(s) for any additional ConsultantsProvide details in Consultant Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Consultant Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Other Direct Costs
Materials/SuppliesProvide details in Materials Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
EquipmentProvide details in Equip. Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
TravelProvide details in Travel Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Insert line(s) for any other types of ODCsProvide details in ODC Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Other Direct Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Material Handling (M/H O/H) (See Escalation and Indirect Rate Worksheet)
Insert M/H O/H rate title$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0.00
Insert line(s) & title(s) for any other M/H O/H rates$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Material Handling Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Subtotal Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
General and Administrative (G&A) (See Escalation and Indirect Rate Worksheet)
Insert G&A rate title$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0.00
Insert line(s) & title(s) for any other G&A rates$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total G&A Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Subtotal Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Facilities Cost of Money (COM) (See Escalation and Indirect Rate Worksheet)
Insert COM rate title$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0.00
Insert line(s) & title(s) for any other COM rates$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Cost of Money$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Estimated Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Fixed Fee (If proposing a CPFF contract)(Note 4)$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0.00
Total Estimated Costs Plus Fixed Fee$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Instructions:• Indicate “Not Applicable” in cell D1 if there is no information to include on a tab. There is no need to add further information.
If proposing Option I:

• For PRIME submission - Subcontractor Name: If there are subcontracts, then list all subcontractor names.

• For Subcontractor submission - Subcontractor Name: Replace “Sub-1 (Fill-in)” with name of the Subcontractor.

• On upper right, replace the X in X-Months with actual number of months.

• Add descriptions in Column B if costs are entered in the following areas: Fringe Benefits, Labor Overhead, Other Direct Costs/other types, General and Administrative, and Facilities Cost of Money.

• Subcontracts/Interorganizational Transfers: If appropriate, place Subcontractor name(s) or Interorganizational Name/Code in Column B.

• Consultants: If appropriate, place Consultant name(s) in Column B.

Note 1:Any proposed personnel in the technical proposal should be identified with their labor category.
Note 2:Indicate whether the Offeror's accounting system is based on a calendar year or fiscal year (Row 5). Indicate the months during the period of performance that these rates apply (Rox 6).
Note 3:The values under Total Direct Labor "hours/base" column indicate the total level of effort for the project for each labor category. The Offeror must define the split of hours between initial and subsequent rate years based on its FY or CY in the prior columns.
Note 4:Profit or fee is not allowed on direct costs for equipment, Government entities or cost share contracts. In addition, a DD Fom 1547 (DFARS 215.404-70) will be utilized in calculating the Government objective for fee.

O-II

Cost Proposal - Option II
Prime Offeror:Prime 1 (Fill-in)
Subcontractor:Sub 1 (Fill-in)
(Note 2)(Note 2)(Note 2)(Note 2)(Note 2)(Note 2)
CY/FY

Wade Wargo: Note:

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year CY/FY Wade Wargo: Note:

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

CY/FY

Wade Wargo: Note:

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

CY/FY

Wade Wargo: Note:

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

CY/FY

Wade Wargo: Note:

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year CY/FY Wade Wargo: Note:

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current yearTotal
Direct Labor (DL)MM/YR to MM/YR

Wade Wargo: Note:

The months during the base period of performance that these rates apply

MM/YR to MM/YR Wade Wargo: Note:

The months during the base period of performance that these rates apply

MM/YR to MM/YR Wade Wargo: Note:

The months during the base period of performance that these rates apply

MM/YR to MM/YR Wade Wargo: Note:

The months during the base period of performance that these rates apply

MM/YR to MM/YR Wade Wargo: Note:

The months during the base period of performance that these rates apply

MM/YR to MM/YR Wade Wargo: Note:

The months during the base period of performance that these rates apply

(Note 3) X-Months wade.wargo: Indicate total months of Option period

Offeror's Labor Category (Note 1)Name (Last, First)Base/HoursRateExtended $Base/HoursRateExtended $Base/HoursRateExtended $Base/HoursRateExtended $Base/HoursRateExtended $Base/HoursRateExtended $Base/HoursExtended $
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
Total Direct Labor Costs0$0.000$0.000$0.000$0.000$0.000$0.000$0.00
Fringe Benefits (F/B) (See Escalation and Indirect Rate Worksheet)
Insert F/B rate title$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0.00
Insert line(s) & title(s) for any other F/B rates$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Fringe Benefit Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Labor Overhead (O/H) (See Escalation and Indirect Rate Worksheet)
Insert O/H rate title$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0.00
Insert line(s) & title(s) for any other O/H rates$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Labor Overhead Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Subcontracts/Interorganizational TransferFile/Tab Name or Link
Subcontract/Interorganizational Name - #01

Sutherland, Susan M CIV ONR, 22: Sutherland, Susan M CIV ONR, 22:

Include the Subcontractor Name

Wade Wargo: Note:

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

wade.wargo: Indicate total months of Option periodProvide details in Subcontractor Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Subcontract/Interorganizational Name - #02Provide details in Subcontractor Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Subcontract/Interorganizational Name - #03Provide details in Subcontractor Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Insert line(s) for any additional Subcontractors/InterorganizationalProvide details in Subcontractor Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Subcontract Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Consultants
Consultant Name - #01Provide details in Consultant Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Consultant Name - #02Provide details in Consultant Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Consultant Name - #03Provide details in Consultant Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Insert line(s) for any additional ConsultantsProvide details in Consultant Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Consultant Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Other Direct Costs
Materials/SuppliesProvide details in Materials Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
EquipmentProvide details in Equip. Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
TravelProvide details in Travel Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Insert line(s) for any other types of ODCsProvide details in ODC Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Other Direct Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Material Handling (M/H O/H) (See Escalation and Indirect Rate Worksheet)
Insert M/H O/H rate title$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0.00
Insert line(s) & title(s) for any other M/H O/H rates$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Material Handling Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Subtotal Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
General and Administrative (G&A) (See Escalation and Indirect Rate Worksheet)
Insert G&A rate title$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0.00
Insert line(s) & title(s) for any other G&A rates$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total G&A Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Subtotal Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Facilities Cost of Money (COM) (See Escalation and Indirect Rate Worksheet)
Insert COM rate title$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0.00
Insert line(s) & title(s) for any other COM rates$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Cost of Money$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Estimated Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Fixed Fee (If proposing a CPFF contract)(Note 4)$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0.00
Total Estimated Costs Plus Fixed Fee$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Instructions:• Indicate “Not Applicable” in cell D1 if there is no information to include on a tab. There is no need to add further information.
If proposing Option I:

• For PRIME submission - Subcontractor Name: If there are subcontracts, then list all subcontractor names.

• For Subcontractor submission - Subcontractor Name: Replace “Sub-1 (Fill-in)” with name of the Subcontractor.

• On upper right, replace the X in X-Months with actual number of months.

• Add descriptions in Column B if costs are entered in the following areas: Fringe Benefits, Labor Overhead, Other Direct Costs/other types, General and Administrative, and Facilities Cost of Money.

• Subcontracts/Interorganizational Transfers: If appropriate, place Subcontractor name(s) or Interorganizational Name/Code in Column B.

• Consultants: If appropriate, place Consultant name(s) in Column B.

Note 1:Any proposed personnel in the technical proposal should be identified with their labor category.
Note 2:Indicate whether the Offeror's accounting system is based on a calendar year or fiscal year (Row 5). Indicate the months during the period of performance that these rates apply (Rox 6).
Note 3:The values under Total Direct Labor "hours/base" column indicate the total level of effort for the project for each labor category. The Offeror must define the split of hours between initial and subsequent rate years based on its FY or CY in the prior columns.
Note 4:Profit or fee is not allowed on direct costs for equipment, Government entities or cost share contracts. In addition, a DD Fom 1547 (DFARS 215.404-70) will be utilized in calculating the Government objective for fee.

O-III

Cost Proposal - Option III
Prime Offeror:Prime 1 (Fill-in)
Subcontractor:Sub 1 (Fill-in)
(Note 2)(Note 2)(Note 2)(Note 2)(Note 2)(Note 2)
CY/FY

Wade Wargo: Note:

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year CY/FY Wade Wargo: Note:

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

CY/FY

Wade Wargo: Note:

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

CY/FY

Wade Wargo: Note:

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

CY/FY

Wade Wargo: Note:

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year CY/FY Wade Wargo: Note:

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current yearTotal
Direct Labor (DL)MM/YR to MM/YR

Wade Wargo: Note:

The months during the base period of performance that these rates apply

MM/YR to MM/YR Wade Wargo: Note:

The months during the base period of performance that these rates apply

MM/YR to MM/YR Wade Wargo: Note:

The months during the base period of performance that these rates apply

MM/YR to MM/YR Wade Wargo: Note:

The months during the base period of performance that these rates apply

MM/YR to MM/YR Wade Wargo: Note:

The months during the base period of performance that these rates apply

MM/YR to MM/YR Wade Wargo: Note:

The months during the base period of performance that these rates apply

(Note 3) X-Months wade.wargo: Indicate total months of Option period

Offeror's Labor Category (Note 1)Name (Last, First)Base/HoursRateExtended $Base/HoursRateExtended $Base/HoursRateExtended $Base/HoursRateExtended $Base/HoursRateExtended $Base/HoursRateExtended $Base/HoursExtended $
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
Total Direct Labor Costs0$0.000$0.000$0.000$0.000$0.000$0.000$0.00
Fringe Benefits (F/B) (See Escalation and Indirect Rate Worksheet)
Insert F/B rate title$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0.00
Insert line(s) & title(s) for any other F/B rates$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Fringe Benefit Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Labor Overhead (O/H) (See Escalation and Indirect Rate Worksheet)
Insert O/H rate title$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0.00
Insert line(s) & title(s) for any other O/H rates$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Labor Overhead Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Subcontracts/Interorganizational TransferFile/Tab Name or Link
Subcontract/Interorganizational Name - #01

Sutherland, Susan M CIV ONR, 22: Sutherland, Susan M CIV ONR, 22:

Include the Subcontractor Name

Wade Wargo: Note:

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

Offeror to insert whether its accounting system uses the Calendar Year (CY) or Fiscal Year (FY) and the current year

wade.wargo: Indicate total months of Option periodProvide details in Subcontractor Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Subcontract/Interorganizational Name - #02Provide details in Subcontractor Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Subcontract/Interorganizational Name - #03Provide details in Subcontractor Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Insert line(s) for any additional Subcontractors/InterorganizationalProvide details in Subcontractor Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Subcontract Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Consultants
Consultant Name - #01Provide details in Consultant Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Consultant Name - #02Provide details in Consultant Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Consultant Name - #03Provide details in Consultant Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Insert line(s) for any additional ConsultantsProvide details in Consultant Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Consultant Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Other Direct Costs
Materials/SuppliesProvide details in Materials Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
EquipmentProvide details in Equip. Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
TravelProvide details in Travel Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Insert line(s) for any other types of ODCsProvide details in ODC Tab$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Other Direct Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Material Handling (M/H O/H) (See Escalation and Indirect Rate Worksheet)
Insert M/H O/H rate title$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0.00
Insert line(s) & title(s) for any other M/H O/H rates$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Material Handling Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Subtotal Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
General and Administrative (G&A) (See Escalation and Indirect Rate Worksheet)
Insert G&A rate title$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0.00
Insert line(s) & title(s) for any other G&A rates$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total G&A Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Subtotal Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Facilities Cost of Money (COM) (See Escalation and Indirect Rate Worksheet)
Insert COM rate title$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0.00
Insert line(s) & title(s) for any other COM rates$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Cost of Money$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Estimated Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Fixed Fee (If proposing a CPFF contract)(Note 4)$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0$0.00$0.00
Total Estimated Costs Plus Fixed Fee$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Instructions:• Indicate “Not Applicable” in cell D1 if there is no information to include on a tab. There is no need to add further information.
If proposing Option I:

• For PRIME submission - Subcontractor Name: If there are subcontracts, then list all subcontractor names.

• For Subcontractor submission - Subcontractor Name: Replace “Sub-1 (Fill-in)” with name of the Subcontractor.

• On upper right, replace the X in X-Months with actual number of months.

• Add descriptions in Column B if costs are entered in the following areas: Fringe Benefits, Labor Overhead, Other Direct Costs/other types, General and Administrative, and Facilities Cost of Money.

• Subcontracts/Interorganizational Transfers: If appropriate, place Subcontractor name(s) or Interorganizational Name/Code in Column B.

• Consultants: If appropriate, place Consultant name(s) in Column B.

Note 1:Any proposed personnel in the technical proposal should be identified with their labor category.
Note 2:Indicate whether the Offeror's accounting system is based on a calendar year or fiscal year (Row 5). Indicate the months during the period of performance that these rates apply (Rox 6).