Non-Competitive_Oversight_Committee_Justification_Form.docx

DOCX document 22 KB Posted

Attached to
Palm Harbor Recreation Center Addition State and local contract opportunity
Solicitation number
26-0011-ITB-C
Issued by
Pinellas County, Clewiston City, Florida

About this file

This document is a Non-Competitive Oversight Committee Justification Form associated with the Pinellas County Board of County Commissioners' Construction Services Department project for the Palm Harbor Recreation Center Addition. The project involves constructing a 28,000 square foot recreation center to replace an existing building next to the Senior Centre on the 16th Street campus, with the facility designed to serve as an at-risk hurricane evacuation shelter. The General Contractor will be required to provide a schedule of values and tentative schedule based on provided construction documents and specifications.

The justification form appears incomplete, with sections left blank regarding budget estimates, project duration, project manager, and requisitioning department. The form includes a section for Non-Competitive Oversight Committee approval with spaces for four committee members (Merry Celeste, Don Crowell, Chris Rose, and Department ACA), but no clear indication of their final approval status. The document is dated 05/05/2023 and seems to be a template for documenting non-competitive procurement justifications, though the specific details of the procurement are not fully elaborated in this document.

View the file

Other files for this state and local contract opportunity

Other files attached to Palm Harbor Recreation Center Addition, newest first.
File Type Posted
Site_visit_sign_in_sheet.pdf PDF
unlocked_Arch_and_Structural-Palm_Harbor.pdf PDF
Palm_Harbor_Recreation_Center_Addition_(Addendum_#5_Revision).pdf PDF
Palm_Harbor_Recreation_Center_Addition_(Addendum_#2_Revision).pdf PDF
Pricing_Proposal26-0011(reference_only).pdf PDF
Pricing_Proposal26-0011(reference_only).pdf PDF
250070-AS_Palm_Harbor_Parks_Rec_Building_2_Asbestos_Survey_Report.pdf PDF
250070-AS_Palm_Harbor_Parks_Rec_Building_2_Asbestos_Survey_Report.pdf PDF
26-0011_-_Insurance_Requirements_-_Palm_Harbor_Recreation_Center_Addition_VE.docx DOCX document
Palm_Harbor_Rec_Center_-_Mechanical_-_Rev_1.pdf PDF
PH_REC_CENTER_SPECIFICATIONS_-_VOL_2.pdf PDF
Palm_Harbor_Rec_Center_-_Mechanical_-_Rev_1.pdf PDF
Palm_Harbor_Rec_Center_-_Mechanical_-_Combined.pdf PDF
QUALIFICATION_SUBMITTAL_FORM_Non_FDOT.pdf PDF
SBE_Compliance_Form.pdf PDF
APPENDIX_7_-_SBE_COMPLIANCE_FORM.pdf PDF
APPENDIX_7_-_SBE_COMPLIANCE_FORM.pdf PDF
Agreement-26-0011.pdf PDF
Palm_Harbor_Rec_Center_-_Technology_-_Combined.pdf PDF
Palm_Harbor_Rec_Center_-_Technology_-_Combined.pdf PDF
250915_PERMIT_SET_-_PH_REC_CENTER_-_ARCHITECTURAL_ESS.pdf PDF
Palm_Harbor_Eng_Design_Rpt.pdf PDF
Palm_Harbor_Eng_Design_Rpt.pdf PDF
PH_REC_CENTER_SPECIFICATIONS_-_VOL_1.pdf PDF
250915_PERMIT_SET_-_PH_REC_CENTER_-_STRUCTURAL_S&S.pdf PDF
250915_PERMIT_SET_-_PH_REC_CENTER_-_STRUCTURAL_S&S.pdf PDF
250915_PERMIT_SET_-_PH_REC_CENTER_-_FOOD_SERVICE.pdf PDF
250915_PERMIT_SET_-_PH_REC_CENTER_-_LANDSCAPE.pdf PDF
250915_PERMIT_SET_-_PH_REC_CENTER_-_LANDSCAPE.pdf PDF
Palm_Harbor_Rec_Center_-_Electrical_-_Signed_and_Sealed.pdf PDF
Palm_Harbor_Rec_Center_-_Electrical_-_Signed_and_Sealed.pdf PDF
Palm_Harbor_Rec_Center_-_Plumbing_-_Combined.pdf PDF
Civil_Site_Permit_Set_S&S_09-15-25.pdf PDF
Palm_Harbor_Rec_Center_-_Fire_Protection_-_Signed_and_Sealed.pdf PDF
Palm_Harbor_Rec_Center_-_Fire_Protection_-_Signed_and_Sealed.pdf PDF
Bid_Submittal_Form-JOC.pdf PDF
Notice_of_Intent_to_Sole_Source_07-25-2023.pdf PDF
Sample_Application_for_Payment.pdf PDF
Notice_of_Intent_to_Sole_Source_07-25-2023.pdf PDF
Sample_Change_Order.pdf PDF
Affdavit_of_Release_and_Guarantee.pdf PDF
E-Verify_Affidavit.pdf PDF
OpenGov_Fillable-_Final.pdf PDF
Airport_Security_Program.pdf PDF
OpenGov_Fillable-_Final.pdf PDF
Sample_Application_for_Payment.pdf PDF
Airport_Security_Program.pdf PDF
Affdavit_of_Release_and_Guarantee.pdf PDF
E-Verify_Affidavit.pdf PDF
Florida_Trench_Safety_Form.pdf PDF
Show all 50

Palm Harbor Recreation Center Addition has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NON-COMPETITIVE OVERSIGHT COMMITTEE JUSTIFICATION FORM

Project/Purchase Name:

Total Budget Estimate:

Duration of engagement:

Project Manager:

Requisitioning Department:

Justification for non-compete purchase:

Was this vendor utilized on prior contracts? Please explain background:

Non-Competitive Oversight Committee
Approved at meeting
1) Merry Celeste
Yes: No:
2) Don Crowell
Yes: No:
3) Chris Rose
Yes: No:
4) Department ACA
Yes: No:

Rev. 05/05/2023