ESSCA_RFP_Amendment_2.docx

DOCX document 496 KB Posted

Attached to
Engineering Services and Science Capability Augmentation (ESSCA) Federal contract opportunity
Solicitation number
NNM16568754R
Issued by
National Aeronautics and Space Administration Marshall Space Flight Center

About this file

ESSCA RFP Amendment 2

View the file

Other files for this federal contract opportunity

Other files attached to Engineering Services and Science Capability Augmentation (ESSCA), newest first.
File Type Posted
ESSCA_RFP_Amendment_3_Attachment_L-3A_Cost_Forms_IDIQ.xlsx XLSX spreadsheet
Amendment_1_ESSCA_RFP_Attachment_L-3B_Cost_Forms_Offeror_Only.xlsx XLSX spreadsheet
Amendment_1_ESSCA_RFP_Attachment_L-3A_Cost_Forms_IDIQ.xlsx XLSX spreadsheet
ESSCA_RFP_Amendment_1_Section_G.docx DOCX document
ESSCA_RFP_Amendment_1_Attachment_J-5_Installation_Provided_Property_and_Services.docx DOCX document
ESSCA_RFP_Amendment_1_Section_L.docx DOCX document
ESSCA_RFP_Complete.docx DOCX document
ESSCA_RFP_Attachment_J-15_Acronym_Initialism_List.docx DOCX document
ESSCA_RFP_Attachment_J-12_Wage_Determination.docx DOCX document
ESSCA_RFP_Attachment_J-10_Safety_Health_and_Environmental_(SHE)_Plan.docx DOCX document
ESSCA_RFP_Attachment_B.docx DOCX document
ESSCA_RFP_Attachment_J-7_Rates_Schedule_and_Labor_Categories.docx DOCX document
ESSCA_RFP_Attachment_J-1_Performance_Work_Statement.docx DOCX document
ESSCA_RFP_Attachment_L-3B_Cost_Forms_Offeror_Only.xlsx XLSX spreadsheet
ESSCA_RFP_Section_C.docx DOCX document
ESSCA_RFP_Attachment_L-2_Sample_Task_2.docx DOCX document
ESSCA_RFP_Attachment_J-6_List_of_Government_Property_Furnished.docx DOCX document
ESSCA_RFP_Attachment_J-5_Installation-Provided_Property_and_Services.docx DOCX document
ESSCA_RFP_Section_L.docx DOCX document
ESSCA_RFP_Attachment_A.docx DOCX document
ESSCA_RFP_Attachment_J-13_Indefinite_Delivery_Indefinite_Quantity_(IDIQ)_Task_Orders.docx DOCX document
ESSCA_RFP_Phase-In_Purchase_Order.docx DOCX document
ESSCA_RFP_Section_D.docx DOCX document
ESSCA_RFP_Section_M.docx DOCX document
ESSCA_RFP_Attachment_L-5_Past_Performance_Interview_Questionnaire_Form.docx DOCX document
Industry_Day_Attendees.xlsx XLSX spreadsheet
ESSCA__Industry_Briefing_FINAL.pptx PPTX presentation
ESSCA_DRFP_Attachment_L-9_Industry_Day_Resgistration_Form.docx DOCX document
ESSCA_DRFP_Section_M.docx DOCX document
ESSCA_DRFP_Phase-In_Purchase_Order.docx DOCX document
ESSCA_DRFP_Attachment_J-3_Award_Fee_Evaluation_Plan.docx DOCX document
ESSCA_DRFP_Section_L.docx DOCX document
ESSCA_DRFP_Attachment_J-4_Small_Business_Subcontracting_Plan.docx DOCX document
ESSCA_DRFP_Attachment_J-1_Performance_Work_Statement.docx DOCX document
ESSCA_DRFP_Attachment_J-11_Organizational_Conflict_of_Interest_(OCI)_Plan.docx DOCX document
ESSCA_DRFP_Attachment_J-9_Contract_Work_Breakdown_Structure_(CWBS).docx DOCX document
ESSCA_DRFP_Attachment_J-13_Indefinite_Delivery_Indefinite_Quantity_(IDIQ)_Task_Orders.docx DOCX document
ESSCA_DRFP_Attachment_L-1_Sample_Task_1.docx DOCX document
ESSCA_DRFP_Attachment_J-6_List_of_Government_Property_Furnished.docx DOCX document
ESSCA_DRFP_Attachment_J-5_Installation-Provided_Property_and_Services.docx DOCX document
ESSCA_DRFP_Section_B.docx DOCX document
ESSCA_DRFP_Attachment_L-3B_Cost_Forms_Offeror_Only.xlsx XLSX spreadsheet
ESSCA_DRFP_Attachment_J-8_Automated_Task_Order_Management_System_(ATOMS)_Requirements_and_Processes.docx DOCX document
ESSCA_DRFP_Attachment_L-6_Days_Away_From_Work_Injury_Illness_(DAWFII)_and_Total_Case_Rate_(TCR)_Matrix.docx DOCX document
ESSCA_DRFP_Attachment_J-10_Safety _Health _and_Environmental_(SHE)_Plan.docx DOCX document
ESSCA_DRFP_Section_H.docx DOCX document
ESSCA_DRFP_Attachment_J-14_Applicable_Regulations_and_Procedures.docx DOCX document
ESSCA_DRFP_Section_C.docx DOCX document
ESSCA_DRFP_Section_A.docx DOCX document
ESSCA_DRFP_Attachment_L-5_Past_Performance_Interview_Questionnaire_Form.docx DOCX document
Show all 50

Engineering Services and Science Capability Augmentation (ESSCA) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NNM16568754R Amendment 2

Attachment A, Responses to Industry RFP Questions, provides responses to questions provided by industry. Attachment B, Change Log, provides a From-To Matrix of the change made to the RFP.

1. Based upon the change delineated in Attachment B, the following pages are hereby deleted/added in their entirety. A vertical line in the right margin indicates the specific area(s) of change.

Section/Pages Deleted
Section/Pages Substituted
L-16
L-16
Attachment L-3A (Tab D)
Attachment L-3A (Tab D)

2. Due date of proposals changed from October 24, 2016 to November 2, 2016.

3. All other terms and conditions of RFP NNM16568754R remain unchanged.

NNM16568754R Amendment 2

Amendment 2-2 Amendment 2-2

ATTACHMENT A – RESPONSES TO INDUSTRY RFP QUESTIONS

Index
Industry-Provided RFP Reference
Question
Response
Change Index
1
ESSCA RFP ATTACHMENT-L-3A Cost Forms IDIQ.xlsx; Tab D, Contractor Overhead, G&A and Other Indirect Rates Calculation Real Year Dollars
Cells D60 to K60 reference years 2016 – 2023. Please clarify the years that should be included in the yellow shading on row 60 (we think the years that should be in the yellow shading on row 60 should be 2017 – 2025).
Fiscal Year Titles were updates to reflect the correct dates: 2017-2025.

See Amendment_2_ESSCA_RFP_Attachment_L-3A_Cost_Forms_IDIQ_Tab_D_Replacement.xlsx, Tab D

2
ESSCA RFP ATTACHMENT-L-3A Cost Forms IDIQ.xlsx; Tab D, Contractor Overhead, G&A and Other Indirect Rates Calculation Real Year Dollars
Cells D86 and D87 calculate the Contract Year 1 portions of Offerors Fiscal Year rates to determine the Conversion to Proposed Contract Year Rate. Cell D86 references Offeror Fiscal Year Prior Yr 1 (cell C83) while cell D87 references the first year of the contract currently shown as 2016 (cell D60). The references are one year behind (we think the reference for Contract Yr 1 Portion of Offerors Fiscal Year 1 should be should be to cell D83; the reference for Contract Yr 2 Portion of Offerors Fiscal Year 2 should be to cell E83). This pattern continues Contract Yr 2 through Contract Yr 8 (columns E through K).
The correction to the Fiscal Year Title dates made in response to Question 1 also corrects the cell reference formula error.

Offeror’s fiscal year prior to Contract Year 1 (Prior Year 1 as shown in Column C) may include months of Contract Year 1.

NNM16568754R Amendment 2

Attachment A-1

ATTACHMENT B – CHANGE LOG

Index
RFP Reference
From
To
1
L.16

Description of Change:

Due date of proposals changed from October 24, 2016 to November 2, 2016.

2
Attachment L-3A, Tab D

Description of Change:

Fiscal Year Titles in Tab D changed from 2016-2023 to 2017-2024 and added column L to include 2025.

3
Attachment L-3A, Tab D

Description of Change:

Corrected formula error in cells H86, I86, J86, K86, H130, I130, J130, K130, H167, I167, J167, and K167.

4
Attachment L-3A, Tab D

Description of Change:

Sentence “Offeror’s fiscal year prior to Contract Year 1 (Prior Year 1 as shown in Column C) may include months of Contract Year 1” added to Instruction 1 for G&A Rate, Overhead/Service Center Pool Rate, and Other Indirect Rate Development tables.

5
Attachment L-3A, Tab D

Description of Change:

Formula removed from B81-K81.

NNM16568754R Amendment 2

Attachment B-1 NNM16568754R Amendment 2

Attachment C-1

Attachment C-6 image1.png image2.png image3.png image4.png image5.png image6.png image7.png