Attachment C Financial Management Reporting

View the file

Other files

File Type Posted
Final_Amendment__2.pdf PDF
Final_Questions_and_Answers__3.pdf PDF
RFP_Amendment.pdf PDF
Final_Questions_and_Answers__2.pdf PDF
Questions_and_Answers.pdf PDF
Final_RFP_(B-M).pdf PDF
Enclosure_BB_2--SSCO_RTO_finalRFP.pdf PDF
Attachment_H _Small_Business_Subcontracting_Plan.pdf PDF
Attachment_M _DD_254.pdf PDF
Attachment_L _IT_Security_Management_Plan.pdf PDF
Attachment_A _Final_Draft_OMES-II_SOW.pdf PDF
Enclosure_AA _Government_QA_Plan.pdf PDF
ENCLOSURE_DD_-_Incumbent_Direct_Labor_Rates.pdf PDF
RFP_Cover_letter.pdf PDF
Attachment_G _Safety_and_Health_Plan.pdf PDF
Encosure_BB__1--JPSS_RTO_finalRFP.pdf PDF
Attachment_E _List_of_GFP.pdf PDF
Attachment_I _Contract_Historical_Data.pdf PDF
Attachment_B _IDIQ_Cost-Type_Rate_Matrix--All_IDIQ_Contract.pdf PDF
Attachment_N _Quality_Assurance_Plan.pdf PDF
Copy_of_Final_Review_of_Exh_GPM_Exhibits_2-12_All_IDIQ_by_CY-1.pdf PDF
Exhibit_13 _Past_Performance_Questionnaire.pdf PDF
Attachment_C _533_Attach_All_IDIQ--Both_Onsite_and_Offsite.pdf PDF
Attachment_K _IT_Security_Applicable_Documents_List.pdf PDF
Enclosure_CC _FINAL_GPM-Specified_Non-Mgmt_DL_Categories_DL_Hours_and_PDs_Enclosure.pdf PDF
SF_33.pdf PDF
Attachment_J _OCI_Avoidance_Plan.pdf PDF
Attachment_F _PIV_Attachment.pdf PDF
Attachment_D _List_of_IAGP.pdf PDF
Copy_of_Final_Review_Exh_GPM_Exhibits_1A-1C_All_IDIQ_with_GPM-Specified_ODCs_by_CY-1_(2).pdf PDF
ENCLOSURE_DD_-_Incumbent_Direct_Labor_Rates.pdf PDF
Attachment_J _OCI_Avoidance_Plan.pdf PDF
Attachment_G _Safety_and_Health_Plan.pdf PDF
Final_Review_of_Exh_GPM_Exhibits_2-12_All_IDIQ_by_CY-1.pdf PDF
Attachment_D _List_of_IAGP.pdf PDF
Attachment_K _IT_Security_Applicable_Documents_List.pdf PDF
Attachment_H _Small_Business_Subcontracting_Plan.pdf PDF
Attachment_E _List_of_GFP.pdf PDF
Attachment_M _DD_254.pdf PDF
Enclosure_BB--_1_SSCO_RTO.pdf PDF
Enclosure_DD _Incumbent_Direct_Labor_Rates.pdf PDF
SF_33.pdf PDF
Enclosure_CC _FINAL_GPM-Specified_Non-Mgmt_DL_Categories_DL_Hours_and_PDs_Enclosure.pdf PDF
Attachment_F _PIV_Attachment.pdf PDF
Enclosure_AA _Government_QA_Plan.pdf PDF
Attachment_N _Quality_Assurance_Plan.pdf PDF
Attachment_B _IDIQ_Cost-Type_Rate_Matrix--All_IDIQ_Contract.pdf PDF
Enclosure_BB--_2_JPSS_RTO.pdf PDF
Signed_RFP_letter.pdf PDF
Final_Draft_RFP.pdf PDF
Show 40 more

Latest 50 of 55 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT C

FINANCIAL MANAGEMENT REPORTING

REQUIREMENTS

DATED FEBRUARY 2016

RFP NNG16549116R

CONTRACT TBD

Contract TBD

Attachment C

(06/2014) 2

FINANCIAL MANAGEMENT REPORTING REQUIREMENTS

Financial Management Reports shall be submitted by the Contractor on the NASA 533 series reports, in accordance with the instructions on the reverse of the forms, NASA

Procedural Requirements NPR 9501.2E entitled "NASA Contractor Financial

Management Reporting,” dated May 27, 2011, and additional instructions issued by the

Contracting Officer.

a. Level of Detail

An individual 533 Report shall be provided for each Task Order in addition to a cumulative 533 Report summarizing all Task Orders issued. The reports shall contain a breakdown of hours and costs by the elements of cost categories listed in Section d below.

b. Variance Narrative Reporting

In accordance with Section 3.6 of NPR 9501.2, the Contractor shall include a narrative explanation for variances exceeding plus or minus 5 percent (+/- 5%) between the Total

Direct Labor Hours (prime and subcontractors) and/or Total Estimated Cost amount shown in the prior month and the Actual Total Direct Labor Hours and/or Actual Total

Cost amount shown in the current month for each individual task order. (For example, the Total Estimated Cost amount shown for June in column 8a in the May NF 533M and the Actual June Total Cost amount shown in column 7a in the June NF 533M.)

Each variance narrative shall explain the: (1) reason for the variance, (2) impact(s) on the individual task order, and (3) specific corrective action(s) being taken or to be taken.

c. Distribution

The Contractor shall distribute 533 reports to each addressee indicated in the contract clause entitled, "Financial Management Reporting." The Contractor shall submit an initial report in the NF 533Q format within 30 working days after contract award.

After the initial report, the NF 533M reports shall be distributed not later than the tenth

(10th) working day following the close of the contractors' monthly accounting period.

The 533Q reports shall be distributed not later than the fifteenth (15th) day of the month preceding the quarter being reported. The NF 533M need not be submitted in months in which an NF 533Q is submitted.

d. Reporting Requirements

Each individual report shall, at a minimum, provide cost data by the following elements of cost categories:

1. Prime Direct Labor Hours:

(06/2014) 3

Prime Direct Labor Hours - Onsite

(List applicable labor categories)

Prime Direct Labor Hours – Offsite

Total Prime Direct Labor Hours

2. Subcontractor Direct Labor Hours:

Subcontractor A Direct Labor Hours – Onsite

Subcontractor A Direct Labor Hours – Offsite

Subcontractor B Direct Labor Hours – Onsite

Subcontractor B Direct Labor Hours – Offsite

Subcontractor C Direct Labor Hours – Onsite

Subcontractor C Direct Labor Hours – Offsite

Total Subcontractors Direct Labor Hours

3. Total Prime and Subcontractors Direct Labor Hours:

Total Prime and Subcontractors Hours – Onsite

Total Prime and Subcontractors Hours – Offsite

Total Prime and Subcontractors Direct Labor Hours

4. Prime Direct Labor Costs:

Prime Direct Labor Costs - Onsite

Prime Direct Labor Costs – Offsite

Total Prime Direct Labor Costs

5. Prime Overhead Expenses:

(06/2014) 4

Onsite Overhead

Offsite Overhead

Total Prime Overhead

6. Other Direct Costs (ODCs):

a. Subcontracts (list separately, Subcontractor A, B, C, etc.)

b. Material

c. Travel

d. Other (specify)

Total ODCs

7. Subtotal (Direct Labor, Overhead & ODCs)

8. G&A Expense

9. Total Estimated Cost

10. Fixed Fee

11. Total Cost-Plus-Fixed-Fee (CPFF)