Q A__4.pdf

PDF 79 KB Posted

Attached to
Space Launch System (SLS) Universal Stage Adapter (USA)
Solicitation number
NNC16ZMX004R
Issued by

View the file

Other files

File Type Posted
SLS_USA_SSS.pdf PDF
Q A__6.pdf PDF
Q A__5.pdf PDF
Amendment__3.pdf PDF
14_of_19_RFP_Att_J.2-5_SLS_USA_Price_Summary_Template_-_Amended.xlsx XLSX spreadsheet
13_of_19_RFP_Att_J.2-4_SLS_USA_Cost_Summary_Template_-_Amended.xlsx XLSX spreadsheet
Amendment__2.pdf PDF
Q A__3.pdf PDF
Amendment__1.pdf PDF
Q A__2.pdf PDF
Q A__1.pdf PDF
SLS_USA_Final_RFP.zip ZIP file
3_RFP_files_to_post_to_FBO.zip ZIP file
list_of_reports_available.zip ZIP file
USA_Industry_Day_Master_Final.pdf PDF
Amendment_1_-_Additional_question.docx DOCX document
07_of_19_DRFP_Att_J.1-D_Deliverable_Items_List.docx DOCX document
14_of_19_DRFP_Att_J.2-5_SLS_USA_Price_Summary_Template.xlsx XLSX spreadsheet
19_of_19_DRFP_Att_J.2-10_USA_Industry_Day_Information.docx DOCX document
05_of_19_DRFP_Att_J.1-B_Data_Procurement_Document.docx DOCX document
03_of_19_DRFP_Sections_B__M.docx DOCX document
11_of_19_DRFP_Att_J.2-2_Master_Schedule.docx DOCX document
15_of_19_DRFP_Att_J.2-6_Cognizant_Audit_Office_Template.xlsx XLSX spreadsheet
18_of_19_DRFP_Att_J_2-9_Request_for_Technical_Data.docx DOCX document
13_of_19_DRFP_Att_J.2-4_SLS_USA_Cost_Summary_Template.xlsx XLSX spreadsheet
01_of_19_DRFP_Introduction.pdf PDF
16_of_19_DRFP_Att_J.2-7_Standard_Labor_Categories.docx DOCX document
04_of_19_DRFP_Att_J.1-A_Statement_of_Work.docx DOCX document
02_of_19_DRFP_Cover_Page.pdf PDF
09_of_19_DRFP_Att_J.1-F_Performance_Evaluation_Plan.docx DOCX document
12_of_19_DRFP_Att_J.2-3_Business_Systems_Reviews_and_Status_Info.xlsx XLSX spreadsheet
10_of_19_DRFP_Att_J.2-1_Past_Performance_Questionnaire.docx DOCX document
17_of_19_DRFP_Att_J.2-8_Government_Task_Agreement_Instructions.docx DOCX document
06_of_19_DRFP_Att_J.1-C_Applicable_Documents_List.docx DOCX document
08_of_19_DRFP_Att_J.1-E_Government_Furnished_Property _Information_and_Facilities_List.docx DOCX document
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Request for Proposals

Questions and Answers #4

NNC16ZMX004R

1) Question - A request for additional technical data has been submitted. SLS-SPEC-044-04, CROSS-PROGRAM VEHICLE DESIGN ENVIRONMENTS VOLUME 4: ACOUSTIC, has been requested. Will this document be made available?

Answer – No.

2) Question - Please clarify the performance period for Options 1-6 as it relates to

Year/Contract Year (CY). For example: Option 1, Year 5 (CY5) which is defined as August

1, 2021 through August 15, 2022 overlaps with the Option 1, Year 6 (CY6) performance period which begins August 1, 2022. This continues throughout the subsequent options.

Answer - Yes, there is meant to be overlap between the last year of the base and option 1;

there is an overlap between all option periods in the out-years.

3) Question - Att J.2-4, the Total WBS Elements tab provides a summary only through Year

12. Should this be modified by the offeror to include Years 13 through 16?

Answer – Offerors do not need to modify the attachment to include years 13 through 16. An amendment to this Solicitation will be posted modifying attachment “13 of 19 RFP Att J.2-4

SLS USA Cost Summary Template” to accomplish the following:

- Renaming the file to “13 of 19 RFP Att J.2-4 SLS USA Cost Summary Template –

Amended”.

- In Tab “1. Total WBS Elements”, the tab has been amended to include contract years 13-

16, not to be confused with Government Fiscal Years.

- In Tab “1. Total WBS Elements”, the tab has been amended to delete the Government estimated Indefinite Delivery-Indefinite Quantity (IDIQ) amounts and proposed award fee rates. These will now only be reflected in Attachment “14 of 19 RFP Att J.2-5 SLS

USA Price Summary Template - Amended”.

4) Question - Att J.2-5, the Price Summary by Fiscal Year tab: The TOTAL of WBS Elements section for identifying Estimated Cost plus Award Fee by Fiscal Year includes a formula that appears to reference an external link (e.g., ='C:\Users\hlinden\Desktop\[SLS_USA Pricing

Template.xlsx]2. WBS 4.1.1 Costs'!C63). Please clarify the expectation of traceability in this document to any other worksheets. Also, please define the fiscal year periods.

Answer – An amendment to this Solicitation will be posted modifying attachment “14 of 19

RFP Att J.2-5 SLS USA Price Summary Template” to accomplish the following:

- Renaming the file to “14 of 19 RFP Att J.2-5 SLS USA Price Summary Template –

Amended”.

- In Tab “Price Summary by Fiscal Year”, the tab has been amended to remove the links to external sources.

Request for Proposals

Questions and Answers #4

NNC16ZMX004R

- In Tab “Price Summary by Fiscal Year”, the tab has been amended to reflect that the

Government fiscal year begins October 1 and ends September 30, for example, October

1, 2017 – September 30, 2018 (FY 18), etc. The fiscal years have been included in row seven.

File details come from the government source that posted it. Updated .