04_of_19_DRFP_Att_J.1-A_Statement_of_Work.docx

DOCX document 86 KB Posted

Attached to
Space Launch System (SLS) Universal Stage Adapter (USA)
Solicitation number
NNC16ZMX004R
Issued by

About this file

Statement of Work

View the file

Other files

File Type Posted
SLS_USA_SSS.pdf PDF
Q A__6.pdf PDF
Q A__5.pdf PDF
Amendment__3.pdf PDF
14_of_19_RFP_Att_J.2-5_SLS_USA_Price_Summary_Template_-_Amended.xlsx XLSX spreadsheet
13_of_19_RFP_Att_J.2-4_SLS_USA_Cost_Summary_Template_-_Amended.xlsx XLSX spreadsheet
Q A__4.pdf PDF
Amendment__2.pdf PDF
Q A__3.pdf PDF
Amendment__1.pdf PDF
Q A__2.pdf PDF
Q A__1.pdf PDF
SLS_USA_Final_RFP.zip ZIP file
3_RFP_files_to_post_to_FBO.zip ZIP file
list_of_reports_available.zip ZIP file
USA_Industry_Day_Master_Final.pdf PDF
Amendment_1_-_Additional_question.docx DOCX document
07_of_19_DRFP_Att_J.1-D_Deliverable_Items_List.docx DOCX document
14_of_19_DRFP_Att_J.2-5_SLS_USA_Price_Summary_Template.xlsx XLSX spreadsheet
19_of_19_DRFP_Att_J.2-10_USA_Industry_Day_Information.docx DOCX document
05_of_19_DRFP_Att_J.1-B_Data_Procurement_Document.docx DOCX document
03_of_19_DRFP_Sections_B__M.docx DOCX document
11_of_19_DRFP_Att_J.2-2_Master_Schedule.docx DOCX document
15_of_19_DRFP_Att_J.2-6_Cognizant_Audit_Office_Template.xlsx XLSX spreadsheet
18_of_19_DRFP_Att_J_2-9_Request_for_Technical_Data.docx DOCX document
13_of_19_DRFP_Att_J.2-4_SLS_USA_Cost_Summary_Template.xlsx XLSX spreadsheet
01_of_19_DRFP_Introduction.pdf PDF
16_of_19_DRFP_Att_J.2-7_Standard_Labor_Categories.docx DOCX document
02_of_19_DRFP_Cover_Page.pdf PDF
09_of_19_DRFP_Att_J.1-F_Performance_Evaluation_Plan.docx DOCX document
12_of_19_DRFP_Att_J.2-3_Business_Systems_Reviews_and_Status_Info.xlsx XLSX spreadsheet
10_of_19_DRFP_Att_J.2-1_Past_Performance_Questionnaire.docx DOCX document
17_of_19_DRFP_Att_J.2-8_Government_Task_Agreement_Instructions.docx DOCX document
06_of_19_DRFP_Att_J.1-C_Applicable_Documents_List.docx DOCX document
08_of_19_DRFP_Att_J.1-E_Government_Furnished_Property _Information_and_Facilities_List.docx DOCX document
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DRAFT Request for Proposals 04 of 19 – DRFP Att J.1-A Statement of Work

NNC16ZMX004R

DRAFT Request for Proposals 04 of 19 – DRFP Att J.1-A Statement of Work

NNC16ZMX004R

ATTACHMENT J.1-A

STATEMENT OF WORK

SCOPE OF THE UNIVERSAL STAGE ADAPTER

STATEMENT OF WORK

The Space Launch System (SLS) is being developed to explore the solar system and extend the human presence throughout it. SLS will meet these objectives through a block upgrade strategy. Block 1 is being developed to launch the Exploration Mission (EM)-1 mission while the Block 1B configuration is being developed to launch the crewed EM-2 mission and future crewed missions. The Block 1B configuration features the Exploration Upper Stage (EUS) and requires an adapter to carry Orion crew vehicle. This adapter is known as the Universal Stage Adapter (USA). Additional volume inside of the adapter, below the Orion spacecraft, will be available to transport additional cargo to augment Exploration Missions. This additional cargo is designated as the co-manifested payload. This contract is for the acquisition of the USA and consists of definition and design activities culminating in the delivery of the flight article and support of SLS and Ground Systems Development and Operations (GSDO) through vehicle integration and flight.

This Statement of Work (SOW) for the USA summarizes the work required for the design, development, production, assembly, qualification, and acceptance for flight consistent with NASA design, construction, workmanship, qualification standards, and other technical and programmatic requirements associated with human rating considerations including configuration management, reliability analysis, safety, and quality assurance. This contract established a base contract period for the development and delivery of the EM-2 USA with six options for delivery of additional flight units. The entirety of the SOW defines the effort required for the contract base. For the 6 options, the SOW will be tailored for mission unique requirements. The SOW supports the following established USA project objectives:

Ensure crew safety within the limitations of meeting system performance requirements and achieving mission objectives.

Deliver a quality design that ensures simplicity and addresses all aspects of human spacecraft development, qualification, and operations.

Perform to an established schedule, cost (affordable and sustainable), and technical baseline.

Implement innovative designs for the USA to achieve efficient and effective operations.

Conduct a human flight in 2021 utilizing an USA.

The full-set of USA technical requirements are found in SLS-SPIE-RQMT-027, Spacecraft/ Payload Integration & Evolution Office (SPIE) Universal Stage Adapter (USA) Requirements Document (Attachment J.1-C). Those requirements fully define the USA technical objectives. The following objectives and initial Key Performance Parameters are used to emphasize items of particular importance.

The Contractor shall meet the following non-tradable objectives:

0. Ensure crew safety through all mission phases within the limitations of meeting system performance requirements and achieving mission objectives.

0. Integrate with required elements of the SLS, MPCV, and Ground Operations systems.

Consistent with the technical requirements found in SLS-SPIE-RQMT-027 a set of initial Key Performance Parameters (KPPs) has been defined for the USA. Industry is expected to provide a USA that shall:

0. Optimize total liftoff mass within the required mass targets

0. Reliably separate without damaging or re-contacting the EUS, Co-Manifested Payload, or MPCV

0. Be space-flight qualified through the life of the design, including the ability to reconfigure access doors and other intrusions to mission specific requirements

0. Provide environmental protection, including thermal and acoustic, to the co-manifested payload

0. Provide electrical and communication paths between the EUS and MPCV This Statement of Work (SOW) is organized using the WBS structure below. In this SOW, the following naming conventions apply:

Universal Stage Adapter (USA) – The adapter that connects Orion to the Exploration Upper Stage (EUS) and accommodates a co-manifested payload.

Space Launch System (SLS) – The launch vehicle consisting of Core Stage, Solid Rocket Boosters (SRB’s), Exploration Upper Stage (EUS), and the USA.

Ground Systems Development and Operations (GSDO) – The elements of the ground support system including the Vehicle Assembly Building (VAB), integration and payload encapsulation offline processing facilities, SRB processing facilities, the Mobile Launch (ML) tower, the Launch Pad, and all facility support systems.

Universal Stage Adapter

0. Project Management

0. Systems Engineering and Integration

0. Safety and Mission Assurance

0. Structural Systems

0. Payload Environmental Control

0. Mechanical Systems

0. Instrumentation and Electrical

0. Assembly, Integration and Testing

0. Operations and Ground Support

Table of Contents

SCOPE OF THE UNIVERSAL STAGE ADAPTER STATEMENT OF WORK3
1.PROJECT MANAGEMENT7
1.1Project Management and Administration7
1.1.1Project Management, Systems, Planning and Reporting7
1.1.2Contractor Integrated Performance Measurement7
1.1.3Integrated Baseline Review (IBR)8
1.1.4Project Management Reviews8
1.1.5Integrated Collaborative Environment9
1.1.6Configuration and Data Management9
1.1.7Risk Management10
1.1.8Export Controls11
1.1.9Internal/External Project Reviews11
1.2Associate Contracts11
1.3Technical and Integration Reviews12
1.3.1Technical Milestone Reviews12
1.3.2Integration Reviews12
1.4Information Technology Management13
1.5Indefinite Delivery Indefinite Quantity (IDIQ) Special Studies13
1.6Education and Public Outreach13
1.7Subcontractor and Geographic Data Collection13
2.SYSTEMS ENGINEERING AND INTEGRATION14
2.1Systems Engineering Management14
2.2Requirements Definition and Management14
2.2.1Derived Requirement and Specification Definition14
2.2.2Interface Control Document (ICD) Data15
2.2.3Requirements Tracking15
2.2.4Test and Verification15
2.3Engineering Review Board and Engineering Panels17
2.4Document and Drawing Trees18
2.5Mass Properties Data18
2.6Hardware Handling, Transportation, and Storage Plan18
2.7Specialty Engineering – Materials and Processes (M&P)18
3.SAFETY AND MISSION ASSURANCE21
3.1System Safety21
3.2Industrial and Environmental Safety22
3.3Reliability23
3.4Quality Assurance24
4.STRUCTURAL SYSTEM25
4.1Primary Structures26
4.2Secondary Structures26
5.PAYLOAD ENVIRONMENTAL CONTROL28
5.1Acoustic Attenuation28
5.2Purge and Vent System29
6.MECHANICAL SYSTEMS30
6.1Separation System30
6.2Umbilicals and Disconnects31
7.INSTRUMENTATION AND ELECTRICAL32
7.1Instrumentation Subsystem32
7.2Electrical Wiring, Harnesses, and Cables33
8.ASSEMBLY, INTEGRATION, AND TESTING34
8.1Structural and Dynamic Qualification35
8.2Separation Qualification35
8.3Acoustic Qualification36
9.OPERATIONS AND GROUND SUPPORT37
9.1Ground Support Equipment37
9.2Operations, Maintenance, and Sustaining Engineering38
9.3Storage and Disposal38
APPENDIX A: ACRONYMS39

PROJECT MANAGEMENT

Project Management and Administration The Contractor shall perform the management functions to assure accomplishment of all outcomes and deliverable products required by this contract. The manufacture and delivery of a Universal Stage Adapter for the SLS Program is the principal objective of this contract. Document details are provided in the Data Requirements Descriptions (DRD’s) provided in each section (Attachment J.1-B).

Project Management, Systems, Planning and Reporting

1. The Contractor shall effectively manage all work to be performed under this contract including that performed by all subcontractors and team members. The Contractor shall manage the work performed to ensure that progress is tracked against plans and any variances are discovered and addressed in an effective manner. The Contractor shall provide the systems and processes required for the planning, organization, control, surveillance and reporting of contract activities to ensure disciplined performance of work and timely application of resources necessary for completion of all tasks in this Contract. These systems and processes shall be adequate to assure completion of all program safety, technical, schedule, and cost objectives. The Project Management Plan (PMP) and Integrated Project Management Report (IPMR) shall be used as critical tools to manage this contract.

The Contractor shall develop and maintain a Project Management Plan (PMP).

The Contractor shall manage the execution of the USA project using the PMP. The Contractor shall report on contract progress in accordance with the PMP at each Project Management Review.

The Contractor shall develop and maintain an organization chart identifying their management reporting structure and all personnel including subcontractors by location.

Deliverables The Contractor shall deliver and maintain the following document(s):

DRD USA-001: Project Management Plan DRD USA-002: Contract WBS and WBS Dictionary Contractor Integrated Performance Measurement

1. The Contractor shall establish, maintain, and use in the performance of this contract, an Earned Value Management System (EVMS). The correlation and integration of these systems and processes shall provide for early indication of cost and schedule problems, and their relation to technical achievement.

The Contractor shall develop and maintain an Integrated Master Schedule (IMS) that contains the logically networked tasks and milestones by WBS from contract award to the completion of the contract. The IMS shall be delivered in accordance with DRD USA-005, Integrated Project Management Report.

The Contractor shall develop, deliver, and implement financial management reporting. Financial management reporting shall include data required to support the EVMS including, but not limited to: actual cost at the total contract level, cost projections at the total contract level, and cumulative total contract cost since inception.

The Contractor shall provide data, when required or requested by NASA, to be used in the Government's budget planning process. This data will be used for the purposes of gathering budget impacts. NASA will, in accordance with the budget or special request guidelines and reporting requirements, specify the format and content of the Contractor's inputs and rationale.

Deliverables The Contractor shall deliver and maintain the following document(s):

DRD USA-003: Earned Value Management System Description DRD USA-004: Financial Management Report (533M and 533Q) DRD USA-005: Integrated Project Management Report (IPMR) Integrated Baseline Review (IBR) The Contractor shall present its performance measurement baseline plan to the Government within ninety (90) days after contract award, and subsequently, when required, following major changes to the baseline. The IBR will be conducted following the guidance in NASA/SP—2010-3406, Integrated Baseline Review (IBR) Handbook. The Government will verify during the IBR, and follow-on IBRs when required, that the Contractor has established and maintains a reliable performance measurement baseline. The Contractor will ensure that the baseline includes the entire contract technical scope of work consistent with contract schedule requirements, and has adequate resources assigned. The Contractor will assure the Government that effective earned value methods are used to accurately status contract cost, schedule, and technical performance. The Contractor will perform a self-assessment of the cost and schedule risk for the IBR. The IBR will be used to achieve a mutual understanding of the baseline plan, cost and schedule risk, and the underlying management processes used for planning and controlling the project.

Project Management Reviews The Contractor shall conduct Project Management Review (PMR) meetings monthly at mutually agreed upon locations (virtual meetings may be acceptable). During the reviews, the Contractor shall present integrated cost, schedule, and technical performance status. Team leads or functional managers shall include cost information in discussions of schedule status, technical performance, and risk using earned value management as an integrating tool. The following shall be addressed: Cost/schedule trends, significant cost/schedule technical variances, projected impacts, qualitative risk assessments, and corrective action plans.

Deliverables The Contractor shall deliver and maintain the following document(s):

DRD USA-006: Contract Status Reports and Management Review Packages Integrated Collaborative Environment The Integrated Collaborative Environment (ICE) is the primary means of sharing, reporting, collecting, recording and accessing program information between NASA, USA Contractor, major/critical subcontractors and authorized U.S. Government personnel connected with the USA Project. ICE provides real-time collaborative access to a single source of management information, product information and technical data. ICE is the principal mechanism for integrating a “program” digital information management environment.

1. The Contractor shall use ICE for delivery of all data.

The Contractor shall use the interactive collaborative configuration management and document management environment of ICE for configuration management of USA Project Directives and change control.

The Contractor shall comply with guidelines of Appendix 2, ICE Operating Environment The Contractor shall implement ICE using one of the three options described in Appendix 2, ICE Operating Environment, Section II, Data Access Requirements.

Configuration and Data Management

1. The Contractor shall develop and implement Configuration Management (CM) and Data Management (DM) systems responsive to the guidelines and requirements in MSFC-STD-3394, Standard for Contractor Configuration Management for MSFC Programs/Projects, and SLS-SPIE-PLAN-032, SPIE Configuration Management Plan to ensure that configuration documentation is accurate and complete, design solutions are traceable to requirements, configuration changes are documented, controlled, and properly implemented, critical interfaces are defined and understood, and that there is consistency between the products and their associated documentation.

The Contractor Configuration Management program shall incorporate Configuration Management Planning; Configuration Identification, which includes Interface Management; Configuration Change Control; Configuration Status Accounting, which includes Traceability; Configuration Verification and Audits; and Technical Data Management.

The Contractor shall integrate the CM and DM systems across all pertinent project elements such as modeling and simulation, manufacturing, operations, quality, as well as acquisition organizations including customer and vendor Configuration and Data Management (CDM) systems.

The Contractor shall configuration manage all engineering models, drawings, and lists in accordance with DRD USA-008, Engineering Drawings and Associated Lists.

The Contractor shall periodically verify and validate their CDM system by an internal audit process.

The Contractor shall develop and implement a Configuration and Data Management Plan (CDMP) defining the Contractor's CM and DM program and method for implementation of the contract CM and DM requirements.

The Contractor shall implement and maintain a configuration status accounting system that provides information defining the as-designed and as-built configuration of the system hardware and the status of changes to this configuration, traceability of changes to controlled products, serve as the basis for communicating accurate and timely status of all Configuration Items, and ensuring the delivered documentation accurately describes and represents the associated Configuration Items.

The Contractor’s CM and DM systems shall provide the following: (1) configuration and data identification, (2) configuration and data control, (3) configuration and data status accounting, and (4) configuration and data management verification and audits.

The Contractor shall maintain Configuration Control of each deliverable item through mission use.

The Contractor shall participate in biannual (once every two years) NASA Configuration Management Audits.

The Contractor shall plan for records retention, using NPR 1441.1 as a guide, and shall coordinate with NASA in the development of this plan.

Deliverables The Contractor shall deliver and maintain the following document(s):

DRD USA-007: Configuration and Data Management Plan DRD USA-008: Engineering Drawings and Associated Lists Risk Management Risk Management will be applied to all phases of the USA Project as an integral part of project management.

1. The Contractor shall identify, evaluate, manage, and control the safety, technical, cost, and schedule related risks associated with all aspects of the USA Project in accordance with the SLS-PLAN-180, SLS Risk Management Plan.

The Contractor shall implement a risk management process for the USA Project that is consistent with the SLS-PLAN-180, SLS Risk Management Plan. Risk management provides for a proactive decision-making process to continuously assess USA Project risks, prioritize risks, and implement strategies to mitigate and control those risks.

The Contractor shall provide substantiating data for each safety, technical, cost, and schedule risk identified and mitigated in accordance with DRD USA-009, Risk Management Plan.

The Contractor shall perform integrated risk analysis, mitigation, and tracking/control, communication of external interface and multi-element risks in support of the SLS/SPIE level risk management process.

The Contractor shall present issues as part of the risk reporting process. For an undesirable risk or event that has occurred, or an occurrence cannot be stopped or directly controlled, the risk will be converted into an issue.

Deliverables The Contractor shall deliver and maintain the following document(s):

DRD USA-009: Risk Management Plan and Risk Management Reports Export Controls

1. The Contractor is responsible for compliance with all the International Traffic in Arms Regulation (ITAR) and Export Administration Regulation (EAR). Violations of these export laws are subject to severe criminal and civil penalties consistent with NFS 1852.225-70, Export Licenses.

The Contractor shall plan and apply for Export Control licenses not included in the NASA licenses.

Internal/External Project Reviews

1. The Contractor shall develop briefing materials and analyses for USA/SLS meetings with various internal and external review groups.

The Contractor shall prepare and present various topics, such as USA Project technical, cost, and schedule status, specific safety r risks, or issues, design and development issues, and responses to external inquiries.

The Contractor shall participate in weekly technical meetings to facilitate technical exchange with the government via telecom or in attendance when feasible.

The Contractor shall support various SPIE and Integrated Vehicle Level (SLS) Working Groups, as needed, including, but not limited to the following areas: Integrated Structures, Shared Compartment Purge/Vent, Instrumentation Program & Command, Integrated Thermal, Vibroacoustics, Separation, Ground Operations, Flight Operations, and Design Environments.

Associate Contracts

1. The Contractor shall establish relationships with other SLS, Orion, and GSDO Contractors, defined as Associate Contractor relationships. Associate relationships are required for expeditious exchange of data among SLS, Orion, and GSDO Contractors. Associate Contractor relationships shall adhere to the 'Associate Contractor Agreements' clause in section H of the contract.

To achieve efficient and effective implementation of the SLS Program, the Contractor shall establish the means for the coordination and exchange of information with Associate Contractors.

The Contractor shall exchange information required by the Associate Contractors in the execution of their respective contract.

The Contractor shall engage in cooperative relationships that facilitate effective management of the development of the overall SLS effort.

The Contractor shall establish formal guidelines to address coordination, cooperation and communication with Associate Contractors, including intra-company relationships.

The Contractor shall provide NASA with a copy of each signed Associate Contractor Agreement.

Technical and Integration Reviews Technical Milestone Reviews

1. The Contractor shall provide engineering, management, documentation, and planning support for design reviews required by NASA to certify product maturity. NASA design reviews shall be based on NPR 7120.5E and NPR 7123.1B.

The Contractor shall participate and submit documentation in support of Government-led reviews, conducted at the SLS SPIE Element. The formal SPIE design reviews include Preliminary Design Review (PDR), Critical Design Review (CDR), and Design Certification Review (DCR). The Government will lead a System Acceptance Review (SAR) of hardware condition and Acceptance Data Packages prior to government acceptance of the USA flight unit.

The Contractor shall implement requirements defined in this SOW and the Data Procurement Document (DPD) for Government-led reviews. At all reviews, the Contractor shall submit and present documentation and data. The Contractor shall respond to Review Item Discrepancies (RIDs) and comments generated by NASA authorized reviewers.

The Contractor shall make available to NASA the associated documentation by the official review data drop date.

The Contractor shall support the SLS/SPIE Flight Readiness Review (FRR) and post flight analysis.

The Government has the expectation to attend internal reviews (e.g., PDR, CDR, Manufacturing Readiness Review (MRR)) held by the Contractor in support of and preparation for the Government design reviews. Reference NPR 7123.1B Deliverables The Contractor shall deliver and maintain the following document(s):

DRD USA-010: Major Review Plans and Documentation Integration Reviews The Contractor shall support the planning and execution of integrated system reviews conducted by the Government at the Element, Vehicle, and GSDO Levels. The Contractor shall support integrated analysis and assessment efforts in support of the integration reviews to identify and resolve integration issues with other SLS elements as required.

Information Technology Management The Contractor shall develop, implement, and maintain an Information Technology System Security Plan that covers all aspects of IT for the Contractor performed tasks in accordance with DRD USA-011, Information Technology System Security Plan.

Deliverables The Contractor shall deliver and maintain the following document(s):

DRD USA-011: Information Technology System Security Plan Indefinite Delivery Indefinite Quantity (IDIQ) Special Studies In accordance with the task ordering procedures in this contract, the Contractor shall perform special studies in support of this contract as initiated by written direction from the Contracting Office. Content of these studies may include, but are not limited to: mission specific requirements, integration, evolvability, interface definition, trade studies, and capability assessments.

Education and Public Outreach The Contractor shall provide Education and Public Outreach support to NASA to disseminate information regarding the USA, SLS, and NASA Human Space Exploration.

Subcontractor and Geographic Data Collection The Contractor shall provide subcontractor and geographical economic impact data in accordance with DRD USA-012, Subcontractor and Geographic Data Collection.

Deliverables The Contractor shall deliver and maintain the following document(s):

DRD USA-012: Subcontractor and Geographic Data Collection

SYSTEMS ENGINEERING AND INTEGRATION

1. Systems Engineering and Integration consists of the technical and management efforts of directing and controlling the integrated engineering effort for the System to achieve a solution that satisfies all USA Project requirements and otherwise balances performance, cost, schedule, and risk.

The SLS, including all subelement components, will be human rated per NPR 8705.2, Human Rating Requirements for Space Systems, for EM-2 and beyond. This certification is being performed as a program-to-program task through the ESD Cross-Program Integration Human Rating Task Team. This Task Team, being led by the MPCV Program through ESD delegation, will address the human rating certification of the SLS, Orion and GSDO collectively. For their part, the SLS Program will supply products to Orion for inclusion in the overall human rating certification package that will be developed. These products are identified in SLS-PLAN-001, SLS Program Plan, along with the milestone reviews requiring product delivery. As of August 2016, no individual SPIE products have been identified by the SLS Program to support the certification effort. However, in the event that SPIE products are identified in the future, SPIE will compile and deliver said products upon request from the SLS Program. In support of the above, the Contractor shall deliver any products required by the SPIE in support of Human Rating per NPR 8705.2 Systems Engineering Management

1. The Contractor shall integrate and manage the total engineering and operations disciplines required to perform the technical tasks defined in this SOW. Total engineering includes subcontractors, Space Act Agreements, and negotiations to develop External Interface Requirements Documents with other SLS/SPIE Systems and other external interfaces as defined by the Contractor.

The Contractor shall develop, implement, and maintain a System Engineering Management Plan (SEMP) that covers how the project will be technically managed and all activities throughout the lifecycle of the system engineering effort for the Contractor performed tasks in accordance with DRD USA-001, Project Management Plan. Note: It is not intended that this plan be duplicated in addition to the requirements in DRD USA-001. If the Contractor desires, the SEMP may be developed as a document separate from the Project Management Plan and referenced accordingly.

Requirements Definition and Management Derived Requirement and Specification Definition The Contractor shall perform all system engineering and analysis to develop specifications for the contract end-item (CEI) deliverables based upon the requirements documented in SLS-SPIE-RQMT-027, SPIE Block 1B Universal Stage Adapter (USA) Requirements Document, (Attachment J.1-C).

Deliverables The Contractor shall deliver and maintain the following document(s):

DRD USA-013: Contract End-Item (CEI) Specification Interface Control Document (ICD) Data The Contractor shall perform all system engineering and analysis to develop specifications and drawings defining external interfaces. These interfaces shall be maintained in Interface Control Documents, controlled by the Government, defining the interfaces with SPIE/SLS, MPCV, and GSDO. These documents will require input from the Contractor. Interface requirements shall be captured in DRD USA-013, Contract End-Item (CEI) Specification.

The Contractor shall use the following applicable documents for the interface requirements:

SLS-SPIE-RQMT-028, SPIE Block 1B Payload Attached Fitting Technical Requirements Document SLS-ICD-052-07, Space Launch System (SLSP)-to-Ground Systems Development and Operations Program (GSDOP) Interface Control Document (ICD), Volume 7: Functional Interface Definition & SLSP Block 1B Integrated Vehicle to-GSDOP Detailed Design SLS-ICD-052-08, Space Launch System (SLSP)-to-Ground Systems Development and Operations Program (GSDOP) Interface Control Document (ICD), Volume 8: SLS Block 1B Integrated Spacecraft & Payload Element (ISPE) to GSDOP Detailed Design MPCV 70026, Multi-Purpose Crew Vehicle (MPCV) Program Orion-to-Space Launch System (SLS) Program Interface Requirements Document (IRD) SLS-ICD-029, Space Launch System (SLSP) -Stages to Integrated Spacecraft and Payload Element Interface Control Document Deliverables The Contractor shall deliver and maintain the following document(s):

DRD USA-013: Contract End-Item (CEI) Specification Requirements Tracking

1. The Contractor shall implement a requirements management and closeout system to:

Trace the origin of and changes to the contract end-item requirements Track requirements verification activities Document that all design and performance requirements are verified and all verification requirements are closed out.

The closeout system shall link to and maintain the Verification Closure Notices.

Test and Verification Systems Test and Verification covers the work to verify the USA hardware meets requirements by inspection, demonstration, simulation, analysis and/or test.

Verification Planning

1. The Contractor shall develop a plan for the verification of the USA and associated subsystems and components including the following characteristics:

The verification method for each USA System level requirement and each allocated requirement shall be clearly documented in a verification matrix in the corresponding specification or requirements document and interface document or requirement.

The Contractor shall support the SLS/SPIE Verification Working Group meetings.

Qualification of the USA System shall be accomplished through rigorous testing to confirm that the System can deliver the planned performance over its expected service life when exposed to levels of stress with margin above that defined in the predicted non-operating and operating environments and conditions. Qualification by other than test must be approved by the Government.

Acceptance testing shall be planned and conducted to verify the USA assembly has been completed successfully and that hardware functional performance meets requirements.

Deliverables The Contractor shall deliver and maintain the following document(s):

DRD USA-015: USA Verification Plan Verification Reporting and Compliance

1. The Contractor shall prepare and submit Verification Closure Notices to document the verification activity results associated with verification closure.

1. The Contractor shall prepare and submit a Verification compliance summary.

1. The Contractor shall prepare and submit acceptance information including status of open waivers/deviations, summary of hardware changes, summary of non-conformances, summary of technical issues, and readiness assessment in accordance with DRD USA-018, Acceptance Data Package (ADP).

Deliverables The Contractor shall deliver and maintain the following document(s):

DRD USA-016: Verification Closure Notices DRD USA-017: Verification Compliance Summary DRD USA-018: Acceptance Data Package (ADP).

Test Planning and Documentation

1. The Contractor shall prepare and submit Test Plans to document the testing approach, methodology, and strategy used to verify that a system or subsystem meets its requirement(s).

The Contractor shall conduct Test Readiness Reviews (TRR) as proposed and approved in the SLS-SPIO-PLAN-003, SLS SPIO Technical Management Plan in accordance with NPR 7123.1B, or equivalent Contractor processes, with Government participation. The TRRs shall be conducted not later than fifteen (15) days prior to the subject test. A TRR specific Data Package, in a Contractor-defined format, shall include approved test plans and shall be provided to the Government no later than seven (7) days before the TRR.

The Contractor shall prepare and submit Test Reports to document test results for all tests conducted.

Deliverables The Contractor shall deliver and maintain the following document(s):

DRD USA-019: Test Plans DRD USA-021: Test Reports Waivers and Deviations

1. The Contractor shall submit waiver or deviation requests in accordance with DRD USA-022, Request for Waiver or Deviation.

The Contractor shall provide waiver request to allow the use of hardware that does not meet performance specifications, exceeds certification limits, or surpasses time, age, or cycle life limits, after due diligence is done in a review and processed through a NASA Element Engineering Review Board Deliverables The Contractor shall deliver and maintain the following document(s):

DRD USA-022: Request for Waiver or Deviation Engineering Review Board and Engineering Panels

1. The Contractor shall utilize the SPIE Engineering Review Boards (ERB) for changes to flight hardware, GSE, and all associated controlled documents in accordance with the accepted Configuration and Data Management Plan. Engineering changes that impact requirement compliance, cost, schedule, or risk exceeding thresholds defined in the approved Contractor Project Management Plan shall be presented to the NASA ERB and the recommendations brought to the SPIE Element Control Board for decision.

The Contractor should convene joint Contractor/NASA Engineering Panels to support the NASA ERB and other technical processes.

The Contractor shall submit Class I change requests to the NASA Project for approval before implementation of the change. Class I changes are changes to the design, specification, configuration, material, part, manufacturing process or test flow, method or requirement that affect safety, verification status, performance, reliability, or interface characteristics as defined in the Configuration and Data Management Plan (DRD USA-007). Class II changes are any changes that do not meet the definition of Class I, and the Contractor ERB will be the approval authority for such changes. The Contractor shall provide NASA Configuration Management Office a listing of Class II changes approved by the Contractor on a Monthly basis.

Document and Drawing Trees

1. The Contractor shall develop, deliver, and maintain a document tree.

The Contractor shall develop, deliver, and maintain a drawing tree.

Deliverables The Contractor shall deliver and maintain the following document(s):

DRD USA-023: Document Tree DRD USA-024: Drawing Tree Mass Properties Data The definition, control, and verification of mass properties and growth allocation and depletion at the vehicle, subsystem, and component levels are essential for the effective management of the USA design. Mass properties data must be tracked throughout the life cycle of the USA and is needed for critical performance analyses in the areas of aerodynamics, aerothermal, trajectory design, propulsion, and attitude control. Mass properties must also be coordinated in a consistent manner across the SLS Program to ensure an integrated assessment interface loads, propulsive performance, and control authority during all mission phases.

Deliverables The Contractor shall deliver and maintain the following document(s) monthly:

DRD USA-025: Mass Properties Data Hardware Handling, Transportation, and Storage Plan The Contractor shall develop and implement plans for the handling, protection, transportation, and storage of all contract end-item hardware deliverables per NPR 6000.1: Requirements for Packaging, Handling, and Transportation for Aeronautical and Space Systems, Equipment, and Associated Components and NASA FAR1852,211-70: Packaging, Handling, and Transportation Deliverables The Contractor shall deliver and maintain the following document(s):

DRD USA-026: Hardware Handling, Transportation, and Storage Plan Specialty Engineering – Materials and Processes (M&P)

1. The Contractor shall provide methodology, agreements, lists, and plans needed to assure that materials and processes used in their fabrication conform to requirements, standards, and procedures per NASA-STD-6016, Standard Materials and Processes Requirements for Space and NASA-STD-6008, NASA Fastener Procurement, Receiving Inspection, and Storage Practices for Spaceflight Hardware.

The Contractor shall apply structured assessments to diverse and complex materials usage to aid in successful hardware development, early in the lifecycle to assure proper materials selection.

The Contractor shall develop a materials and processes selection, and implementation plan that puts forethought into how they will achieve the Materials and Processes requirements.

On drawings, M&P shall have drawing signature to assure correct material selection and control materials through proper specification of processes/handling/cleanliness, and approve ongoing design changes.

The Contractor shall use Materials and Processes Technical Information System (MAPTIS), a NASA database to obtain unique information on flammability, toxicity, corrosion, and materials properties. The Contractor shall submit any unique materials properties not found in the NASA database, to MAPTIS for incorporation.

The Contractor shall create a list of materials used and appropriate processes in the manufacture of the USA. The Contractor shall generate Materials Usage Agreements (MUAs) for materials-specific waivers used for applications that do not meet the materials requirements but can be rationalized as acceptable.

The Contractor shall maintain a closed loop system to receive, investigate, report, and exchange information involving problems related to the safety, reliability, or quality of parts and materials. The system will provide objective evidence to demonstrate that Acute Launch Emergency Restraint Tips (ALERTs) have been received and assessed for impact to the deliverables. The Contractor shall submit information relative to unexpected failures or discrepant conditions of parts and materials used in equipment which may be of significant application in other equipment and to safety problems of general concern to the MSFC ALERT System.

Contractor shall submit information and document Contractor-initiated ALERTs and provide response to MSFC-disseminated ALERTs for unexpected failures or discrepant conditions of parts and materials used in equipment which may be of significant application in other equipment and to safety problems of general concern to the MSFC ALERT System.

The Contractor shall develop a NDE plan that addresses the selection and the order of precedence of applicable government, industry, and prime Contractor NDE specifications and standards and how the requirements contained therein are implemented through internal procedures and processes. NDE shall also support the damage tolerance assessment.

The Contractor shall prepare and implement a Contamination Control Plan that describes methods for controlling contaminants and verifying that they have been prevented or abated such that the hardware will meet performance and cleanliness requirements.

Deliverables:

DRD USA-027: Mechanical and Physical Property Data DRD USA-028: Material Usage Agreements (MUA) DRD USA-029: Materials Identification and Usage List (MIUL) DRD USA-030: Materials and Processes Selection, Implementation, and Control Plan DRD USA-031: MSFC ALERT System Documentation DRD USA-032: Non-Destructive Evaluation Plan DRD USA-033: Contamination Control Plan

SAFETY AND MISSION ASSURANCE

The Contractor shall fully integrate Safety and Mission Assurance (S&MA) into the USA design, development, test, ground, assembly, integration, ground processing activities, and risk identification and mitigation processes. The S&MA deliverables, such as the hazards analyses, FMEAs, CILs, reliability predictions, etc. will be developed during the design concept phase and continuously matured throughout the Program life cycle as designs evolve and operations begin.

1. The Contractor shall implement safety, reliability, maintainability, and quality assurance requirements for all aspects of USA life cycle in accordance with SLS–RQMT-014, SLS Program Safety and Mission Assurance (S&MA) Requirements.

1. The Contractor shall provide an S&MA Plan that includes subcontractors, and defines their organization, processes, schedules, required skills, tasks and products for System Safety, Industrial Safety, Reliability and Maintainability, and Quality Assurance activities performed in support of the USA Project.

1. The Contractor shall provide S&MA representation and actively support program technical and management meetings, milestones, and reviews (e.g., Technical Interchange Meetings, Integration Meetings, Review Boards, Safety Review Panels, and Change Control Boards).

1. The Contractor shall address damage control including damage threat assessment from debris source transport analysis, damage during all handling operations and damage during transportation, assembly, and integration.

Deliverables The Contractor shall deliver and maintain the following document(s):

DRD USA-034: Safety and Mission Assurance (S&MA) Plan Reference Documents The Contractor may use the following document(s) as reference:

NPR 8705.2A, Human-Rating Requirements for Space Systems as tailored by SLS-RQMT-014, SLS Program Safety and Mission Assurance (S&MA) Requirements.

System Safety The Contractor shall provide the technical and management effort necessary to ensure the overall safety and protection of flight and ground personnel, general public, flight/ground hardware and facilities through all phases of the project, including oversight of contracted efforts.

1. The Contractor shall verify safety requirements throughout the life cycle of the USA.

The Contractor shall perform and document safety analyses to identify, mitigate and control the hazards of the USA throughout the USA life cycle, DRD USA-035, System Safety Analysis Report.

The Contractor shall perform and document an overall risk assessment including the identification of residual hazards/risks and provide rationale for acceptance in accordance with SLS-RQMT-014, SLS Program Safety and Mission Assurance (S&MA) Requirements.

The Contractor shall deliver review data packages in conjunction with and provide support to all safety reviews in accordance with the program schedule and the S&MA Plan.

The Contractor shall use SLS-SPIO-PLAN-008, Space Launch System (SLS) Program Spacecraft and Payload Integration Office (SPIO) Safety & Mission Assurance (S&MA) Plan.

Deliverables The Contractor shall deliver and maintain the following document(s):

DRD USA-034: Safety and Mission Assurance Plan DRD USA-035: System Safety Analysis Report Industrial and Environmental Safety The Contractor shall ensure that occupational (industrial) safety and health and environmental assurance activities for all aspects of the USA Project are accomplished

1. The Contractor shall perform the functions for all industrial activities in compliance with all applicable, federal, state and local, NASA and Center safety guidance and laws (NPR 8715.3, NASA General Safety Program Requirements and NPR 8715.1, NASA Occupational Safety and Health Programs), environmental and fire protection legislation, the Occupational Safety and Health Act (OSHA), Environmental Protection Agency (EPA) standards, and National Fire Protection Act (NFPA) standards, or the applicable Government-industrial safety law. The following NASA standards shall be used:

NASA STD-8719.9, Standard for Lifting Devices and Equipment NASA-STD-8719.12, NASA Safety Standard for Explosives, Propellants, and Pyrotechnics.

The Contractor shall report and provide all mishap close calls and safety statistics including trend items in accordance with NPR 8621.1A, NASA Procedures and Guidelines for Mishap Reporting, Investigating, and Record Keeping, and NFS 1852.223-70, Safety and Health Measures and Mishap Reporting.

The Contractor shall develop a Mishap Preparedness and Contingency Plan in accordance with USA DRD-036, Mishap Preparedness and Contingency Plan. The Contractor shall document how they will notify the appropriate NASA Points of Contacts, and provide investigation reports and corrective action plans (CAP) following any mishap involving NASA personnel injury and or property damage at a Contractor facility.

The Contractor shall furnish to NASA or its agent sufficient information and technical data to enable NASA or its agent to complete its National Environmental Policy Act (NEPA) analysis in accordance with NPR 8580.1, Implementing the National Environmental Policy Act, and Executive Order 12114.

The Contractor shall provide a Safety and Health Plan in accordance with clause H.1 52.236-13, Accident Prevention (November 1991) Alternate I (November 1991).

Deliverables The Contractor shall deliver and maintain the following document(s):

DRD USA-036: Mishap Preparedness and Contingency Plan Reliability

1. The Contractor shall identify, plan, and document all Reliability and Maintainability (R&M) tasks and activities to be performed in the overall Safety and Mission Assurance Plan per DRD USA-034, Safety and Mission Assurance Plan. The Contractor shall define, develop, and implement a Reliability program in accordance with SLS-RQMT-014, SLS Program Safety and Mission Assurance (S&MA) Requirements.

The Contractor shall define, develop, implement and provide a Reliability Analysis Report of the Reliability tasks as an integral part of the design, development, test, evaluation, and operations processes in accordance with NPD 8720.1C, NASA Reliability and Maintainability (R&M) Program Policy and SLS-RQMT-014: SLS Program Safety and Mission Assurance (S&MA) Requirements.

The Contractor shall develop a Failure Modes Effects Analyses (FMEA) and a Critical Items Lists (CIL) for all SLS flight hardware and critical ground support equipment associated with this contract in accordance with SLS-RQMT-016, SLS Program FMEA/CIL Requirements Document.

The Contractor shall identify limited life items and assure they are tracked and controlled such that their operating characteristics will not be degraded beyond acceptable limits, including consideration for total mission time/cycles and safety factor margins, accumulated time and/or cycles at time of shipment, and required time and/or cycles that must be remaining prior to conducting each major milestone test and launch. A limited life item is any item designated as having a limited useful life, regardless of whether it is a limited operating life, limited shelf life, operating life sensitivity, or combinations of these.

Deliverables The Contractor shall deliver and maintain the following document(s):

DRD USA-034: Safety and Mission Assurance Plan DRD USA-037: Failure Modes Effects Analysis & Critical Items List (FMEA/CIL) DRD USA-038: Reliability Analysis Report DRD USA-039: Limited Life Items Quality Assurance

1. The Contractor shall define, develop, and implement Quality Assurance requirements and processes in accordance with SLS-RQMT-014, SLS Program Safety and Mission Assurance (S&MA) Requirements, as an integral part of the USA life cycle.

The Contractor shall define, develop, and implement an effective quality assurance program that establishes quality requirements for hardware and EEE parts, contributes to the logistics processes, assembly, integration, and verification compliance, maintains effective configuration management, reviews test plans/procedures/drawings, observes testing, and establishes a sound Problem Assessment system.

The Contractor and its subcontractors shall be certified to or compliant with SAE AS 9100, Quality Management System - Aerospace Requirements, and shall develop, implement, and maintain quality management systems for all activities performed under the USA contract.

The Contractor shall provide notification to NASA of major non-conformances as soon as they are determined in accordance with SAE AS9100, Quality Systems – Aerospace – Model for Quality Assurance in Design, Development, Production, Installation and Servicing. The Contractor shall notify the government per the government provided contact list and disposition the nonconformance in a Material Review Board.

The Contractor shall document activities and operations performed on selected deliverable hardware delivery when specified by drawing or contract in a log book.

The Contractor shall issue a statement that all requirements are met or waived for each major component of the USA for design qualification and certification.

The Contractor shall develop and implement a Manufacturing, Assembly, Production, and Repair Plan and maintain the associated process and inspection records and reports.

The Contractor shall develop and implement a Non-Destructive Evaluation Plan and maintain the associated process and inspection records and reports.

The Contractor shall develop and implement a Contamination Control Plan (CCP) and maintain the associated cleanliness during transport from Contractor’s facility to the encapsulation facility and from encapsulation facility to the VAB, including inspection records and reports.

Deliverables The Contractor shall deliver and maintain the following document(s):

DRD USA-034: Safety and Mission Assurance Plan DRD USA-040: Certificate of Qualification (COQ) DRD USA-041: Log Books DRD USA-042: Manufacturing, Assembly, Production, and Repair Plan DRD USA-043: Manufacturing Process Records and Inspection Reports DRD USA-032: Non-Destructive Evaluation Plan DRD USA-033: Contamination Control Plan (CCP)

STRUCTURAL SYSTEM

The Contractor shall provide the design, development, production, assembly, test, qualification, and acceptance efforts required to deliver the completed USA structural system for payload encapsulation and integration with the launch vehicle. This includes the primary structure, secondary structure, joints, and Thermal Protection System.

1. The Contractor shall tailor NASA-STD-5001B, Structural Design and Test Factors of Safety for Space Flight Hardware, NASA-STD-5019A, Fracture Control Requirements for Spaceflight Hardware, and NASA-STD-6016, Standard Materials and Processes Requirements for Spacecraft to provide a project specific Structural Design Requirements document for the USA in DRD USA-047, Structural Strength, Buckling, and Fatigue Analysis Reports and Models, and DRD USA-045, Fracture Control Plan.

The Contractor shall develop, maintain and deliver models and drawings of systems,…