15450.doc

DOC document 56 KB Posted

Attached to
RML Autoclave Replacement Project
Solicitation number
NIHOF2008061
Issued by

About this file

Specifications cont.

View the file

Other files

File Type Posted
Specification Index.doc DOC document
01310 Proj Mngmt Coor 3.doc DOC document
Disclosure of Lobbying Activities.pdf PDF
Standard Form 25.pdf PDF
SF 1413.pdf PDF
01140 Work Restrictions 3.doc DOC document
01320 Const Prog Doc 3.doc DOC document
01731 Cutting Patching 3.doc DOC document
15401.doc DOC document
15841.doc DOC document
15055.doc DOC document
09721 Stonhard.doc DOC document
16110.doc DOC document
01100 Summary 1.doc DOC document
01700 Execution Requirements 3.doc DOC document
16120.doc DOC document
MT7 Wage Determination.htm HTM file
Standard Form 25a.pdf PDF
07-734-Cover 1.xls XLS spreadsheet
A1-0.pdf PDF
16130.doc DOC document
NIH Form 2582.rtf RTF text file
15703.doc DOC document
16000.doc DOC document
15000.doc DOC document
15992.doc DOC document
A0-0.pdf PDF
01420 References 3.doc DOC document
01400 Quality Requirements 3.doc DOC document
15100.doc DOC document
A1-1.pdf PDF
07920 FULL ADG JOINT SEALANTS Aug 02 1.doc DOC document
01500 TEMP FACILITIES CONTROL 3 .doc DOC document
15250.doc DOC document
01230 Options.DOC DOC document
01330 SUBMTL PROCEDURES 3.doc DOC document
M2-0.pdf PDF
M1-1.pdf PDF
01600 ADG PROD REQUIREMENTS 3.doc DOC document
M1-0.pdf PDF
15090.doc DOC document
16140.doc DOC document
SF 1442 Autoclave Replacement Project.pdf PDF
15060.doc DOC document
NIS.dwg DWG drawing
M0-1.pdf PDF
E1-0.pdf PDF
11605 Equipment.doc DOC document
09960 High Performance Coatings 1.doc DOC document
01770 ADG CLOSE OUT PROCEDURES 3.doc DOC document
Show 40 more

Latest 50 of 51 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

96-620

00-32 07-733 07-743

SECTION 15450 - PLUMBING FIXTURES AND TRIM

PART 1 GENERAL

1.1

WORK INCLUDED

A.

Furnish and install all plumbing fixtures noted on the drawings or described herein.

B.

Provide and install all traps, stops, supply risers, etc., to laboratory equipment except where these accessories are furnished as part of the laboratory equipment.

1.2

SUBMITTAL DATA

A.

See SECTION 15000 for general submittal requirements.

B.

Provide submittal data for any materials or equipment specified in this Section as listed on the Submittal Schedule (see SECTION 15000) and any special or additional data as requested by the Contracting Officer.

C.

Submit complete manufacturer's literature for all fixtures, trim, stops, carriers and other accessories.

1.3

COORDINATION

A.

Cooperate in the installation of all fixtures with the General Contractor so that provisions can be made for required cutting and patching, solid backing for mounting fixtures, chair carriers, shower units, drains, etc., and proper elevation for setting roof and floor drains.

B.

Provide the necessary drawings, dimensions and instructions for proper installation of all fixtures and trim.

1.4

COMPLIANCE

A.

Fixtures and their installation shall comply with applicable plumbing codes, A.N.S.I. standards and A.D.A. requirements.

PART 2 PRODUCTS

2.1

MATERIALS

A.

Fixtures and their trim shall be complete in every respect, including such items as escutcheons, hanger plates, bolts, supplies, stops, traps, etc.

B.

See the "Plumbing Fixture Schedule" on the drawings or notes on the drawings for fixture types.

C.

Equivalent items of manufacturers listed herein may be used in lieu of items of the manufacturer specified if approved by the Contracting Officer. Contractor must list all variations and exceptions between specified items and substitute manufacturer's items on the shop drawings. Substitute items must be equal or superior in quality to that specified.

1.

Floor drains: Josam, J.R. Smith, Wade, Zurn.

PART 3 EXECUTION

3.1

INSTALLATION

A.

All fixtures shall be installed to meet manufacturer's recommendations and local codes.

B.

Set floor and roof drains in place, level and at proper elevation for drainage specified. Set grate flush with floor so water can drain to fixture.

C.

Indirect waste piping shall be securely mounted and supported.

END OF SECTION 15450

PACKAGE M OUTBUILDING RENOVATION NIH-NIAID RML HAMILTON, MT

PLUMBING FIXTURES AND TRIM 15450-2

RML AUTOCLAVE REPLACEMENT ( NIH-NIAID RML ( HAMILTON, MT

PLUMBING FIXTURES AND TRIM 15450-1