01320 Const Prog Doc 3.doc

DOC document 34 KB Posted

Attached to
RML Autoclave Replacement Project
Solicitation number
NIHOF2008061
Issued by

About this file

Specifications cont.

View the file

Other files

File Type Posted
Specification Index.doc DOC document
01310 Proj Mngmt Coor 3.doc DOC document
Disclosure of Lobbying Activities.pdf PDF
Standard Form 25.pdf PDF
SF 1413.pdf PDF
01140 Work Restrictions 3.doc DOC document
01731 Cutting Patching 3.doc DOC document
15401.doc DOC document
15841.doc DOC document
15055.doc DOC document
09721 Stonhard.doc DOC document
16110.doc DOC document
01100 Summary 1.doc DOC document
01700 Execution Requirements 3.doc DOC document
16120.doc DOC document
MT7 Wage Determination.htm HTM file
15450.doc DOC document
Standard Form 25a.pdf PDF
07-734-Cover 1.xls XLS spreadsheet
A1-0.pdf PDF
16130.doc DOC document
NIH Form 2582.rtf RTF text file
15703.doc DOC document
16000.doc DOC document
15000.doc DOC document
15992.doc DOC document
A0-0.pdf PDF
01420 References 3.doc DOC document
01400 Quality Requirements 3.doc DOC document
15100.doc DOC document
A1-1.pdf PDF
07920 FULL ADG JOINT SEALANTS Aug 02 1.doc DOC document
01500 TEMP FACILITIES CONTROL 3 .doc DOC document
15250.doc DOC document
01230 Options.DOC DOC document
01330 SUBMTL PROCEDURES 3.doc DOC document
M2-0.pdf PDF
M1-1.pdf PDF
01600 ADG PROD REQUIREMENTS 3.doc DOC document
M1-0.pdf PDF
15090.doc DOC document
16140.doc DOC document
SF 1442 Autoclave Replacement Project.pdf PDF
15060.doc DOC document
NIS.dwg DWG drawing
M0-1.pdf PDF
E1-0.pdf PDF
11605 Equipment.doc DOC document
09960 High Performance Coatings 1.doc DOC document
01770 ADG CLOSE OUT PROCEDURES 3.doc DOC document
Show 40 more

Latest 50 of 51 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

07-726

07-743

SECTION 01320 - CONSTRUCTION PROGRESS DOCUMENTATION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including Sections A through M of the Contract and other Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:

1. Contractor's Construction Schedule.

B. Related Sections include the following:

1. Division 1 Section "Project Management and Coordination" for submitting and distributing meeting and conference minutes.

2. Division 1 Section "Submittal Procedures" for submitting schedules and reports.

1.3 DEFINITIONS

A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.

1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.

2. Predecessor activity is an activity that must be completed before a given activity can be started.

B. Event: The starting or ending point of an activity.

C. Float: The measure of leeway in starting and completing an activity.

1. Float time belongs to Government.

2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the following activity.

3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.

D. Milestone: A key or critical point in time for reference or measurement.

1.4 SUBMITTALS

A. Preliminary Construction Schedule: Submit two printed copies; one a single sheet of reproducible media, and one a print.

B. Contractor's Construction Schedule: Submit two printed copies of initial schedule, one a reproducible print and one a blue- or black-line print, large enough to show entire schedule for entire construction period.

1.5 COORDINATION

A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate contractors.

B. Coordinate Contractor's Construction Schedule with the Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.

1. Secure time commitments for performing critical elements of the Work from parties involved.

2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.

C. Auxiliary Services: Cooperate with photographer and provide auxiliary services requested, including access to Project site and use of temporary facilities including temporary lighting.

PART 2 - PRODUCTS

2.1 CONSTRUCTION SCHEDULE

A. Bar-Chart Schedule: Submit preliminary horizontal bar-chart-type construction schedule within seven days of date established for the Notice to Proceed.

B. Preparation: Indicate each significant construction activity separately. Identify first workday of each week with a continuous vertical line. Outline significant construction activities for first 60 days of construction. Include skeleton diagram for the remainder of the Work and a cash requirement prediction based on indicated activities.

PART 3 - EXECUTION (Not Used)

END OF SECTION 01320

AUTOCLAVE REPLACEMENT ( NIH-NIAID RML ( HAMILTON, MT

CONSTRUCTION PROGRESS DOCUMENTATION 01320 - 1