Base Period Recurring
| Attachment J-0200000-13 |
| Exhibit Line Item Numbers |
| Solicitation No.:N6945023R0020 |
| Line Item 0001 - Recurring Work - Base Recurring Period | | | | | | | | | | |
| Provide Prices for Recurring Work in accordance with Section C, Spec Item 3 | | | | | | | | | | |
| ELINs A001 through A003 | | | | | | | | | | |
| Customer | ELIN | Sub-ELIN | Annex/Sub-annex | Category | Spec Item | Description | Quantity | Unit of Measure | Unit Price | Total |
| NSA | A001 | A001AA | 1501000 | Facility Management | 3 | Recurring Work | 12 | MO | | |
| NSA | A001 | A001AB | 1502000 | E/U/R Work Orders | 3.1.1 | Emergency Work Orders | 10 | EA | | |
| NSA | A001 | A001AC | 1502000 | E/U/R Work Orders | 3.1.2 | Urgent Work Orders | 20 | EA | | |
| NSA | A001 | A001AD | 1502000 | E/U/R Work Orders | 3.1.3 | Routine Work Orders | 325 | EA | | |
| NSA | A001 | A001AE | 1502000 | Project Orders | 3.2 | Project Orders | 100 | EA | | |
| NSA | A001 | A001AF | 1502000 | Preventative Maintenance Program | 3.3.1 | HVAC and Refrigeration Systems | 12 | MO | | |
| NSA | A001 | A001AG | 1502000 | Preventative Maintenance Program | 3.3.2 | Interior and Exterior Lighting Systems | 12 | MO | | |
| NSA | A001 | A001AH | 1502000 | Preventative Maintenance Program | 3.3.3 | Boilers and UPVs | 12 | MO | | |
| NSA | A001 | A001AJ | 1502000 | Preventative Maintenance Program | 3.3.4 | Lightning Arrestors and Grounding Devices | 12 | MO | | |
| NSA | A001 | A001AK | 1502000 | Preventative Maintenance Program | 3.3.5 | Fire Protection Systems | 12 | MO | | |
| NSA | A001 | A001AL | 1502000 | Preventative Maintenance Program | 3.3.6 | Vertical Transportation Equipment (VTE) | 12 | MO | | |
| NSA | A001 | A001AM | 1502000 | Preventative Maintenance Program | 3.3.7 | Auxiliary Generators | 12 | MO | | |
| NSA | A001 | A001AN | 1502000 | Preventative Maintenance Program | 3.3.8 | Fuel and Oil Storage Tanks | 12 | MO | | |
| NSA | A001 | A001AP | 1502000 | Preventative Maintenance Program | 3.3.9 | Safety Equipment | 12 | MO | | |
| NSA | A001 | A001AQ | 1502000 | Preventative Maintenance Program | 3.3.10 | Roll-up, Overhead, Automatic, and Access Doors | 12 | MO | | |
| NSA | A001 | A001AR | 1502000 | Preventative Maintenance Program | 3.3.11 | Electrical Distribution | 12 | MO | | |
| NSA | A001 | A001AS | 1502000 | Preventative Maintenance Program | 3.3.12 | Renewable Energy System | 12 | MO | | |
| NSA | A001 | A001AT | 1502000 | Preventative Maintenance Program | 3.3.13 | Plumbing System | 12 | MO | | |
| NSA | A001 | A001AU | 1502000 | Preventative Maintenance Program | 3.3.14 | Galley Equipment | 12 | MO | | |
| NSA | A001 | A001AV | 1502000 | Preventative Maintenance Program | 3.3.15 | Electronic Security System | 12 | MO | | |
| NSA | A001 | A001AW | 1502000 | Preventative Maintenance Program | 3.3.16 | Intrusion Detection System | 12 | MO | | |
| NSA | A001 | A001AX | 1502000 | Inspection, Testing, and Certification Program | 3.4.1 | Boilers and UPVs | 12 | MO | | |
| NSA | A001 | A001AY | 1502000 | Inspection, Testing, and Certification Program | 3.4.2 | Backflow Prevention Devices | 12 | MO | | |
| NSA | A001 | A001AZ | 1502000 | Inspection, Testing, and Certification Program | 3.4.3 | Vertical Transportation Equipment (VTE) | 12 | MO | | |
| NSA | A001 | A001BA | 1502000 | Inspection, Testing, and Certification Program | 3.4.4 | Fuel/Oil Storage System Inspection | 12 | MO | | |
| NSA | A001 | A001BB | 1502000 | Other Recurring Services | 3.5.1 | Grease and Oil Interceptor | 12 | MO | | |
| NSA | A001 | A001BC | 1502000 | Other Recurring Services | 3.5.2 | Exhaust Hoods and Ducts | 12 | MO | | |
| NSA | A001 | A001BD | 1502000 | Other Recurring Services | 3.5.3 | HVAC Water Testing and Treatment Services | 12 | MO | | |
| NSA | A001 | A001BE | 1502000 | Other Recurring Services | 3.5.4 | Stormwater Retention Pond Maintenance | 12 | MO | | |
| NSA | A001 | A001BF | 1502000 | Other Recurring Services | 3.5.5 | Building Water Management Program | 12 | MO | | |
| NSA | A001 | A001BG | 1503020 | Pest Control | 3.1 | Scheduled Pest Control Services | 12 | MO | | |
| NSA | A001 | A001BH | 1503020 | Pest Control | 3.2 | Pest Control Work Orders | 12 | MO | | |
| NSA | A001 | A001BJ | 1503020 | Pest Control | 3.3 | Pest Management Reporting | 12 | MO | | |
| NSA | A001 | A001BK | 1503030 | Integrated Solid Waste Management | 3 | Recurring Work | 12 | MO | | |
| NSA | A001 | A001BL | 1503050 | Grounds Maintenance | 3.1 | Improved Grounds | 12 | MO | | |
| NSA | A001 | A001BM | 1503050 | Grounds Maintenance | 3.2 | Grounds Maintenance Work Orders | 12 | MO | | |
| NSA | A001 | A001BN | 1503050 | Grounds Maintenance | 3.3 | Storm Drainage Systems | 12 | MO | | |
| NUWC | A002 | A002AA | 1502000 | E/U/R Work Orders | 3.1.3 | Routine Work Orders | 25 | EA | | |
| NUWC | A002 | A002AB | 1502000 | Preventative Maintenance Program | 3.3.1 | HVAC and Refrigeration Systems | 12 | MO | | |
| NUWC | A002 | A002AC | 1502000 | Preventative Maintenance Program | 3.3.5 | Fire Protection Systems | 12 | MO | | |
| NUWC | A002 | A002AD | 1503020 | Pest Control | 3.2 | Pest Control Work Orders | 12 | MO | | |
| NUWC | A002 | A002AB | 1503030 | Integrated Solid Waste Management | 3 | Recurring Work | 12 | MO | | |
| NUWC | A002 | A002AC | 1503050 | Grounds Maintenance | 3.1 | Improved Grounds | 12 | MO | | |
| NUWC | A002 | A002AD | 1503050 | Grounds Maintenance | 3.2 | Grounds Maintenance Work Orders | 12 | MO | | |
| NEX | A003 | A003AA | 1502000 | Preventative Maintenance Program | 3.3.5 | Fire Protection Systems | 12 | MO | | |
| Total Recurring Work: | | | | | | | | | | $ - 0 |
Base Period Non-Recurring
| Attachment J-0200000-13 |
| Exhibit Line Item Numbers |
| Solicitation No.: N6945023R0020 |
| Line Item 0002 - Non-Recurring Work - Fourth Option Period | | | | | | |
| Provide Prices for Recurring Work in accordance with Section C, Spec Item 4 | | | | | | |
| ELINs A700 through A712 | | | | | | |
| ELIN | Product Name (120 Characters) | Description Extended | Estimated Quantity | Unit of Measure | Unit Price | Extended Price |
| A700 | Unit Priced Labor Hour Work - MUST BE NEGOTIATED BY KO | The Contractor shall perform all UPL work in accordance with the scope and delivery schedule negotiated per each task order. | | | | |
Refer to: Section C, Annex 0200000 Managmenent and Administration, Specification Item 2.15.2 Unit Priced Labor (UPL)Work (Negotiated) for description of UPL Work.
Refer to: Section J, Annex 0200000 Managmenent and Administration, Attachment J-0200000-01 Definitions and Acronyms for description of Unit Priced Labor (UPL) Hour.
| Task order completion times will be specified on each task order. | 2,000 | LH | | $ - 0 |
| A701 | Material and Equipment - MUST BE NEGOTIATED BY KO. | Provide all materials and equipment to perform Unit Priced Labor work per the scope and delivery schedule specified in the order. Pre-expended bin supplies and materials will not be included in the list of materials since the cost for these items were included in the labor hour unit price bid. Material prices provided by the Contractor shall be the lowest price available considering the availability of materials and the time constraints of the job. The direct material price shall be adjusted by all discounts and rebates for core value or salvage value that accrue to the Contractor. | |
| Contractor owned equipment rental rates shall be based on calculations set forth in US Army Corp of Engineers “Construction Equipment Ownership and Operating Expense Schedule (EP 1110-1-8 (Vol. 11) July 03 or latest revision) Chapter 2. | $ 100,000.00 | DO | $ 1.00 | $ 100,000.00 |
| A702 | Cubicle Relocation (Inside NSA Complex) | | |
| AVAILABLE DOD FEDMALL | Relocate the entire Cubicle and its contents. Cubicle move from one location to another location within the NSA Complex. (The cubicles vary in size from 8.5' by 8.5' to 8.5' by 14.5'.) The Cubicle relocation includes relocation of all contents of the Cubicle to include books, files, folders, computer equipment, and all office supplies and equipment. It also includes the breakdown and re-assembly of the wall partitions, bookcases, desktops, chairs, lights, file drawers, shelves, drawers, pull outs etc. All minor material like fasteners or bolts are included. | 30 | EA | $ - 0 |
| A703 | Cubicle Relocation (Outside the NSA Complex) | | |
| AVAILABLE DOD FEDMALL | Relocate the entire Cubicle and its contents. Cubicle move from one location to another location outside the NSA Complex. (This will require a vehicle to transport the material approximately 8 miles. These moves may be from the NSA Complex to another facility or from another facility to the NSA Complex.)(The cubicles vary in size from 8.5' by 8.5' to 8.5' by 14.5'.) The Cubicle relocation includes relocation of all contents of the Cubicle to include books, files, folders, computer equipment, and all office supplies and equipment. It also includes the breakdown and re-assembly of the wall partitions, bookcases, desktops, chairs, lights, file drawers, shelves, drawers, pull outs etc. All minor material like fasteners or bolts are included. | 15 | EA | $ - 0 |
| A704 | Carpet Square removal and replacement | | |
| AVAILABLE DOD FEDMALL | Carpet Square removal and replacement shall match exising as close as possible in color, texture and manufacturer. This shall include moving or relocating furniture as required, and removing and replacing the adhesive in order to install in a first class manner. (The manufactor of the existing carpet is "Interface") | 600 | SY | $ - 0 |
| A705 | Canopy Cleaning | | |
| AVAILABLE DOD FEDMALL | Canopy Cleaning shall include complete cleaning of all visible residue in preparation for Command activities. This clean canopy shall present a uniform appearance with no stains form mildew, bird droppings, and dirt. All insect and bird nest shall be removed. | 2 | EA | $ - 0 |
| A706 | Subterranean Termite Control | | |
| AVAILABLE DOD FEDMALL | Provide labor and materials to control infestations of subterranean termites in accordance with J-1503020-09 (Termite Control Specifications). | | |
| Time Period to Respond: 3 calendar days after receipt of the task order. Complete work per time periods specified in J-1503020-09. | 2,500 | LF | $ - 0 |
| A707 | General Waste (20-34 Cubic Yard Container/Compactor) | |
| AVAILABLE DOD FEDMALL | The Contractor shall remove general waste from the designated 20 CY container or 34 CY compactor to ensure refuse is properly collected. Complete all work within 3 calendar days. | 25 | EA | $ - 0 |
| A708 | Recyclable Waste (20 CY Container) | | |
| AVAILABLE DOD FEDMALL | The Contractor shall remove recyclable waste from the designated 20 CY container to ensure it is properly collected. Complete all work within 3 calendar days. | 15 | EA | $ - 0 |
| A709 | Special Event Grass Cutting | | |
| AVAILABLE DOD FEDMALL | Grass shall be mowed and trimmed to a uniform height of 3 inches. Clippings and debris shall be removed. Complete all work within 3 calendar days. | 30 | AC | $ - 0 |
| A710 | Special Event Edging | | |
| AVAILABLE DOD FEDMALL | Edging to provide a uniform edged cut. All clippings shall be removed. Complete all work within 3 calendar days. | 10,000 | LF | $ - 0 |
| A711 | Plant Bed and Barrier Maintenance | | |
| AVAILABLE DOD FEDMALL | Dead, broken, damaged or diseased areas shall be removed and properly disposed. Plants and beds shall be fertilized, edged, weeded, and mulched as appropriate. Complete all work within 3 calendar days. | 5,000 | SF | $ - 0 |
| A712 | Debris Removal | | |
AVAILABLE DOD FEDMALL
Remove and properly dispose of natural debris (tree limbs, leaves, dry brush, rodent habitats, dead animals, etc.), and stray man-made trash/debris. Complete all work within 3 calendar days.
| 15 | AC | $ - 0 | |
| Total Non-Recurring Work | | | $ 100,000.00 |
1st Opt Period - Recurring
| Attachment J-0200000-13 |
| Exhibit Line Item Numbers |
| Solicitation No.:N6945023R0020 |
| Line Item 0003 - Recurring Work - Base Recurring Period | | | | | | | | | | |
| Provide Prices for Recurring Work in accordance with Section C, Spec Item 3 | | | | | | | | | | |
| ELINs B001 through B003 | | | | | | | | | | |
| Customer | ELIN | Sub-ELIN | Annex/Sub-annex | Category | Spec Item | Description | Quantity | Unit of Measure | Unit Price | Total |
| NSA | B001 | B001AA | 1501000 | Facility Management | 3 | Recurring Work | 12 | MO | | |
| NSA | B001 | B001AB | 1502000 | E/U/R Work Orders | 3.1.1 | Emergency Work Orders | 10 | EA | | |
| NSA | B001 | B001AC | 1502000 | E/U/R Work Orders | 3.1.2 | Urgent Work Orders | 20 | EA | | |
| NSA | B001 | B001AD | 1502000 | E/U/R Work Orders | 3.1.3 | Routine Work Orders | 325 | EA | | |
| NSA | B001 | B001AE | 1502000 | Project Orders | 3.2 | Project Orders | 100 | EA | | |
| NSA | B001 | B001AF | 1502000 | Preventative Maintenance Program | 3.3.1 | HVAC and Refrigeration Systems | 12 | MO | | |
| NSA | B001 | B001AG | 1502000 | Preventative Maintenance Program | 3.3.2 | Interior and Exterior Lighting Systems | 12 | MO | | |
| NSA | B001 | B001AH | 1502000 | Preventative Maintenance Program | 3.3.3 | Boilers and UPVs | 12 | MO | | |
| NSA | B001 | B001AJ | 1502000 | Preventative Maintenance Program | 3.3.4 | Lightning Arrestors and Grounding Devices | 12 | MO | | |
| NSA | B001 | B001AK | 1502000 | Preventative Maintenance Program | 3.3.5 | Fire Protection Systems | 12 | MO | | |
| NSA | B001 | B001AL | 1502000 | Preventative Maintenance Program | 3.3.6 | Vertical Transportation Equipment (VTE) | 12 | MO | | |
| NSA | B001 | B001AM | 1502000 | Preventative Maintenance Program | 3.3.7 | Auxiliary Generators | 12 | MO | | |
| NSA | B001 | B001AN | 1502000 | Preventative Maintenance Program | 3.3.8 | Fuel and Oil Storage Tanks | 12 | MO | | |
| NSA | B001 | B001AP | 1502000 | Preventative Maintenance Program | 3.3.9 | Safety Equipment | 12 | MO | | |
| NSA | B001 | B001AQ | 1502000 | Preventative Maintenance Program | 3.3.10 | Roll-up, Overhead, Automatic, and Access Doors | 12 | MO | | |
| NSA | B001 | B001AR | 1502000 | Preventative Maintenance Program | 3.3.11 | Electrical Distribution | 12 | MO | | |
| NSA | B001 | B001AS | 1502000 | Preventative Maintenance Program | 3.3.12 | Renewable Engergy System | 12 | MO | | |
| NSA | B001 | B001AT | 1502000 | Preventative Maintenance Program | 3.3.13 | Plumbing System | 12 | MO | | |
| NSA | B001 | B001AU | 1502000 | Preventative Maintenance Program | 3.3.14 | Galley Equipment | 12 | MO | | |
| NSA | B001 | B001AV | 1502000 | Preventative Maintenance Program | 3.3.15 | Electronic Security System | 12 | MO | | |
| NSA | B001 | B001AW | 1502000 | Preventative Maintenance Program | 3.3.16 | Intrusion Detection System | 12 | MO | | |
| NSA | B001 | B001AX | 1502000 | Inspection, Testing, and Certification Program | 3.4.1 | Boilers and UPVs | 12 | MO | | |
| NSA | B001 | B001AY | 1502000 | Inspection, Testing, and Certification Program | 3.4.2 | Backflow Prevention Devices | 12 | MO | | |
| NSA | B001 | B001AZ | 1502000 | Inspection, Testing, and Certification Program | 3.4.3 | Vertical Transportation Equipment (VTE) | 12 | MO | | |
| NSA | B001 | B001BA | 1502000 | Inspection, Testing, and Certification Program | 3.4.4 | Fuel/Oil Storage System Inspection | 12 | MO | | |
| NSA | B001 | B001BB | 1502000 | Other Recurring Services | 3.5.1 | Grease and Oil Interceptor | 12 | MO | | |
| NSA | B001 | B001BC | 1502000 | Other Recurring Services | 3.5.2 | Exhaust Hoods and Ducts | 12 | MO | | |
| NSA | B001 | B001BD | 1502000 | Other Recurring Services | 3.5.3 | HVAC Water Testing and Treatment Services | 12 | MO | | |
| NSA | B001 | B001BE | 1502000 | Other Recurring Services | 3.5.4 | Stormwater Retention Pond Maintenance | 12 | MO | | |
| NSA | B001 | B001BF | 1502000 | Other Recurring Services | 3.5.5 | Building Water Management Program | 12 | MO | | |
| NSA | B001 | B001BG | 1503020 | Pest Control | 3.1 | Scheduled Pest Control Services | 12 | MO | | |
| NSA | B001 | B001BH | 1503020 | Pest Control | 3.2 | Pest Control Work Orders | 12 | MO | | |
| NSA | B001 | B001BJ | 1503020 | Pest Control | 3.3 | Pest Management Reporting | 12 | MO | | |
| NSA | B001 | B001BK | 1503030 | Integrated Solid Waste Management | 3 | Recurring Work | 12 | MO | | |
| NSA | B001 | B001BL | 1503050 | Grounds Maintenance | 3.1 | Improved Grounds | 12 | MO | | |
| NSA | B001 | B001BM | 1503050 | Grounds Maintenance | 3.2 | Grounds Maintenance Work Orders | 12 | MO | | |
| NSA | B001 | B001BN | 1503050 | Grounds Maintenance | 3.3 | Storm Drainage Systems | 12 | MO | | |
| NUWC | B002 | B002AA | 1502000 | E/U/R Work Orders | 3.1.3 | Routine Work Orders | 25 | EA | | |
| NUWC | B002 | B002AB | 1502000 | Preventative Maintenance Program | 3.3.1 | HVAC and Refrigeration Systems | 12 | MO | | |
| NUWC | B002 | B002AC | 1502000 | Preventative Maintenance Program | 3.3.5 | Fire Protection Systems | 12 | MO | | |
| NUWC | B002 | B002AD | 1503020 | Pest Control | 3.2 | Pest Control Work Orders | 12 | MO | | |
| NUWC | B002 | B002AB | 1503030 | Integrated Solid Waste Management | 3 | Recurring Work | 12 | MO | | |
| NUWC | B002 | B002AC | 1503050 | Grounds Maintenance | 3.1 | Improved Grounds | 12 | MO | | |
| NUWC | B002 | B002AD | 1503050 | Grounds Maintenance | 3.2 | Grounds Maintenance Work Orders | 12 | MO | | |
| NEX | B003 | B003AA | 1502000 | Preventative Maintenance Program | 3.3.5 | Fire Protection Systems | 12 | MO | | |
| Total Recurring Work: | | | | | | | | | | $ - 0 |
1st Opt Period - Non-Recurring
| Attachment J-0200000-13 |
| Exhibit Line Item Numbers |
| Solicitation No.: N6945023R0020 |
| Line Item 0004 - Non-Recurring Work - Fourth Option Period | | | | | | |
| Provide Prices for Recurring Work in accordance with Section C, Spec Item 4 | | | | | | |
| ELINs B700 through B712 | | | | | | |
| ELIN | Product Name (120 Characters) | Description Extended | Estimated Quantity | Unit of Measure | Unit Price | Extended Price |
| B700 | Unit Priced Labor Hour Work - MUST BE NEGOTIATED BY KO | The Contractor shall perform all UPL work in accordance with the scope and delivery schedule negotiated per each task order. | | | | |
Refer to: Section C, Annex 0200000 Managmenent and Administration, Specification Item 2.15.2 Unit Priced Labor (UPL)Work (Negotiated) for description of UPL Work.
Refer to: Section J, Annex 0200000 Managmenent and Administration, Attachment J-0200000-01 Definitions and Acronyms for description of Unit Priced Labor (UPL) Hour.
| Task order completion times will be specified on each task order. | 2,000 | LH | | $ - 0 |
| B701 | Material and Equipment - MUST BE NEGOTIATED BY KO. | Provide all materials and equipment to perform Unit Priced Labor work per the scope and delivery schedule specified in the order. Pre-expended bin supplies and materials will not be included in the list of materials since the cost for these items were included in the labor hour unit price bid. Material prices provided by the Contractor shall be the lowest price available considering the availability of materials and the time constraints of the job. The direct material price shall be adjusted by all discounts and rebates for core value or salvage value that accrue to the Contractor. | |
| Contractor owned equipment rental rates shall be based on calculations set forth in US Army Corp of Engineers “Construction Equipment Ownership and Operating Expense Schedule (EP 1110-1-8 (Vol. 11) July 03 or latest revision) Chapter 2. | $ 100,000.00 | DO | $ 1.00 | $ 100,000.00 |
| B702 | Cubicle Relocation (Inside NSA Complex) | | |
| AVAILABLE DOD FEDMALL | Relocate the entire Cubicle and its contents. Cubicle move from one location to another location within the NSA Complex. (The cubicles vary in size from 8.5' by 8.5' to 8.5' by 14.5'.) The Cubicle relocation includes relocation of all contents of the Cubicle to include books, files, folders, computer equipment, and all office supplies and equipment. It also includes the breakdown and re-assembly of the wall partitions, bookcases, desktops, chairs, lights, file drawers, shelves, drawers, pull outs etc. All minor material like fasteners or bolts are included. | 30 | EA | $ - 0 |
| B703 | Cubicle Relocation (Outside the NSA Complex) | | |
| AVAILABLE DOD FEDMALL | Relocate the entire Cubicle and its contents. Cubicle move from one location to another location outside the NSA Complex. (This will require a vehicle to transport the material approximately 8 miles. These moves may be from the NSA Complex to another facility or from another facility to the NSA Complex.)(The cubicles vary in size from 8.5' by 8.5' to 8.5' by 14.5'.) The Cubicle relocation includes relocation of all contents of the Cubicle to include books, files, folders, computer equipment, and all office supplies and equipment. It also includes the breakdown and re-assembly of the wall partitions, bookcases, desktops, chairs, lights, file drawers, shelves, drawers, pull outs etc. All minor material like fasteners or bolts are included. | 15 | EA | $ - 0 |
| B704 | Carpet Square removal and replacement | | |
| AVAILABLE DOD FEDMALL | Carpet Square removal and replacement shall match exising as close as possible in color, texture and manufacturer. This shall include moving or relocating furniture as required, and removing and replacing the adhesive in order to install in a first class manner. (The manufactor of the existing carpet is "Interface") | 600 | SY | $ - 0 |
| B705 | Canopy Cleaning | | |
| AVAILABLE DOD FEDMALL | Canopy Cleaning shall include complete cleaning of all visible residue in preparation for Command activities. This clean canopy shall present a uniform appearance with no stains form mildew, bird droppings, and dirt. All insect and bird nest shall be removed. | 2 | EA | $ - 0 |
| B706 | Subterranean Termite Control | | |
| AVAILABLE DOD FEDMALL | Provide labor and materials to control infestations of subterranean termites in accordance with J-1503020-09 (Termite Control Specifications). | | |
| Time Period to Respond: 3 calendar days after receipt of the task order. Complete work per time periods specified in J-1503020-09. | 2,500 | LF | $ - 0 |
| B707 | General Waste (20-34 Cubic Yard Container/Compactor) | |
| AVAILABLE DOD FEDMALL | The Contractor shall remove general waste from the designated 20 CY container or 34 CY compactor to ensure refuse is properly collected. Complete all work within 3 calendar days. | 25 | EA | $ - 0 |
| B708 | Recyclable Waste (20 CY Container) | | |
| AVAILABLE DOD FEDMALL | The Contractor shall remove recyclable waste from the designated 20 CY container to ensure it is properly collected. Complete all work within 3 calendar days. | 15 | EA | $ - 0 |
| B709 | Special Event Grass Cutting | | |
| AVAILABLE DOD FEDMALL | Grass shall be mowed and trimmed to a uniform height of 3 inches. Clippings and debris shall be removed. Complete all work within 3 calendar days. | 30 | AC | $ - 0 |
| B710 | Special Event Edging | | |
| AVAILABLE DOD FEDMALL | Edging to provide a uniform edged cut. All clippings shall be removed. Complete all work within 3 calendar days. | 10,000 | LF | $ - 0 |
| B711 | Plant Bed and Barrier Maintenance | | |
| AVAILABLE DOD FEDMALL | Dead, broken, damaged or diseased areas shall be removed and properly disposed. Plants and beds shall be fertilized, edged, weeded, and mulched as appropriate. Complete all work within 3 calendar days. | 5,000 | SF | $ - 0 |
| B712 | Debris Removal | | |
AVAILABLE DOD FEDMALL
Remove and properly dispose of natural debris (tree limbs, leaves, dry brush, rodent habitats, dead animals, etc.), and stray man-made trash/debris. Complete all work within 3 calendar days.
| 15 | AC | $ - 0 | |
| Total Non-Recurring Work | | | $ - 0 |
2nd Opt Period - Recurring
| Attachment J-0200000-13 |
| Exhibit Line Item Numbers |
| Solicitation No.:N6945023R0020 |
| Line Item 0005 - Recurring Work - Base Recurring Period | | | | | | | | | | |
| Provide Prices for Recurring Work in accordance with Section C, Spec Item 3 | | | | | | | | | | |
| ELINs C001 through C003 | | | | | | | | | | |
| Customer | ELIN | Sub-ELIN | Annex/Sub-annex | Category | Spec Item | Description | Quantity | Unit of Measure | Unit Price | Total |
| NSA | C001 | C001AA | 1501000 | Facility Management | 3 | Recurring Work | 12 | MO | | |
| NSA | C001 | C001AB | 1502000 | E/U/R Work Orders | 3.1.1 | Emergency Work Orders | 10 | EA | | |
| NSA | C001 | C001AC | 1502000 | E/U/R Work Orders | 3.1.2 | Urgent Work Orders | 20 | EA | | |
| NSA | C001 | C001AD | 1502000 | E/U/R Work Orders | 3.1.3 | Routine Work Orders | 325 | EA | | |
| NSA | C001 | C001AE | 1502000 | Project Orders | 3.2 | Project Orders | 100 | EA | | |
| NSA | C001 | C001AF | 1502000 | Preventative Maintenance Program | 3.3.1 | HVAC and Refrigeration Systems | 12 | MO | | |
| NSA | C001 | C001AG | 1502000 | Preventative Maintenance Program | 3.3.2 | Interior and Exterior Lighting Systems | 12 | MO | | |
| NSA | C001 | C001AH | 1502000 | Preventative Maintenance Program | 3.3.3 | Boilers and UPVs | 12 | MO | | |
| NSA | C001 | C001AJ | 1502000 | Preventative Maintenance Program | 3.3.4 | Lightning Arrestors and Grounding Devices | 12 | MO | | |
| NSA | C001 | C001AK | 1502000 | Preventative Maintenance Program | 3.3.5 | Fire Protection Systems | 12 | MO | | |
| NSA | C001 | C001AL | 1502000 | Preventative Maintenance Program | 3.3.6 | Vertical Transportation Equipment (VTE) | 12 | MO | | |
| NSA | C001 | C001AM | 1502000 | Preventative Maintenance Program | 3.3.7 | Auxiliary Generators | 12 | MO | | |
| NSA | C001 | C001AN | 1502000 | Preventative Maintenance Program | 3.3.8 | Fuel and Oil Storage Tanks | 12 | MO | | |
| NSA | C001 | C001AP | 1502000 | Preventative Maintenance Program | 3.3.9 | Safety Equipment | 12 | MO | | |
| NSA | C001 | C001AQ | 1502000 | Preventative Maintenance Program | 3.3.10 | Roll-up, Overhead, Automatic, and Access Doors | 12 | MO | | |
| NSA | C001 | C001AR | 1502000 | Preventative Maintenance Program | 3.3.11 | Electrical Distribution | 12 | MO | | |
| NSA | C001 | C001AS | 1502000 | Preventative Maintenance Program | 3.3.12 | Renewable Engergy System | 12 | MO | | |
| NSA | C001 | C001AT | 1502000 | Preventative Maintenance Program | 3.3.13 | Plumbing System | 12 | MO | | |
| NSA | C001 | C001AU | 1502000 | Preventative Maintenance Program | 3.3.14 | Galley Equipment | 12 | MO | | |
| NSA | C001 | C001AV | 1502000 | Preventative Maintenance Program | 3.3.15 | Electronic Security System | 12 | MO | | |
| NSA | C001 | C001AW | 1502000 | Preventative Maintenance Program | 3.3.16 | Intrusion Detection System | 12 | MO | | |
| NSA | C001 | C001AX | 1502000 | Inspection, Testing, and Certification Program | 3.4.1 | Boilers and UPVs | 12 | MO | | |
| NSA | C001 | C001AY | 1502000 | Inspection, Testing, and Certification Program | 3.4.2 | Backflow Prevention Devices | 12 | MO | | |
| NSA | C001 | C001AZ | 1502000 | Inspection, Testing, and Certification Program | 3.4.3 | Vertical Transportation Equipment (VTE) | 12 | MO | | |
| NSA | C001 | C001BA | 1502000 | Inspection, Testing, and Certification Program | 3.4.4 | Fuel/Oil Storage System Inspection | 12 | MO | | |
| NSA | C001 | C001BB | 1502000 | Other Recurring Services | 3.5.1 | Grease and Oil Interceptor | 12 | MO | | |
| NSA | C001 | C001BC | 1502000 | Other Recurring Services | 3.5.2 | Exhaust Hoods and Ducts | 12 | MO | | |
| NSA | C001 | C001BD | 1502000 | Other Recurring Services | 3.5.3 | HVAC Water Testing and Treatment Services | 12 | MO | | |
| NSA | C001 | C001BE | 1502000 | Other Recurring Services | 3.5.4 | Stormwater Retention Pond Maintenance | 12 | MO | | |
| NSA | C001 | C001BF | 1502000 | Other Recurring Services | 3.5.5 | Building Water Management Program | 12 | MO | | |
| NSA | C001 | C001BG | 1503020 | Pest Control | 3.1 | Scheduled Pest Control Services | 12 | MO | | |
| NSA | C001 | C001BH | 1503020 | Pest Control | 3.2 | Pest Control Work Orders | 12 | MO | | |
| NSA | C001 | C001BJ | 1503020 | Pest Control | 3.3 | Pest Management Reporting | 12 | MO | | |
| NSA | C001 | C001BK | 1503030 | Integrated Solid Waste Management | 3 | Recurring Work | 12 | MO | | |
| NSA | C001 | C001BL | 1503050 | Grounds Maintenance | 3.1 | Improved Grounds | 12 | MO | | |
| NSA | C001 | C001BM | 1503050 | Grounds Maintenance | 3.2 | Grounds Maintenance Work Orders | 12 | MO | | |
| NSA | C001 | C001BN | 1503050 | Grounds Maintenance | 3.3 | Storm Drainage Systems | 12 | MO | | |
| NUWC | C002 | C002AA | 1502000 | E/U/R Work Orders | 3.1.3 | Routine Work Orders | 25 | EA | | |
| NUWC | C002 | C002AB | 1502000 | Preventative Maintenance Program | 3.3.1 | HVAC and Refrigeration Systems | 12 | MO | | |
| NUWC | C002 | C002AC | 1502000 | Preventative Maintenance Program | 3.3.5 | Fire Protection Systems | 12 | MO | | |
| NUWC | C002 | C002AD | 1503020 | Pest Control | 3.2 | Pest Control Work Orders | 12 | MO | | |
| NUWC | C002 | C002AB | 1503030 | Integrated Solid Waste Management | 3 | Recurring Work | 12 | MO | | |
| NUWC | C002 | C002AC | 1503050 | Grounds Maintenance | 3.1 | Improved Grounds | 12 | MO | | |
| NUWC | C002 | C002AD | 1503050 | Grounds Maintenance | 3.2 | Grounds Maintenance Work Orders | 12 | MO | | |
| NEX | C003 | C003AA | 1502000 | Preventative Maintenance Program | 3.3.5 | Fire Protection Systems | 12 | MO | | |
| Total Recurring Work: | | | | | | | | | | $ - 0 |
2nd Opt Period - Non-Recurring
| Attachment J-0200000-13 |
| Exhibit Line Item Numbers |
| Solicitation No.: N6945023R0020 |
| Line Item 0006 - Non-Recurring Work - Fourth Option Period | | | | | | |
| Provide Prices for Recurring Work in accordance with Section C, Spec Item 4 | | | | | | |
| ELINs C700 through C712 | | | | | | |
| ELIN | Product Name (120 Characters) | Description Extended | Estimated Quantity | Unit of Measure | Unit Price | Extended Price |
| C700 | Unit Priced Labor Hour Work - MUST BE NEGOTIATED BY KO | The Contractor shall perform all UPL work in accordance with the scope and delivery schedule negotiated per each task order. | | | | |
Refer to: Section C, Annex 0200000 Managmenent and Administration, Specification Item 2.15.2 Unit Priced Labor (UPL)Work (Negotiated) for description of UPL Work.
Refer to: Section J, Annex 0200000 Managmenent and Administration, Attachment J-0200000-01 Definitions and Acronyms for description of Unit Priced Labor (UPL) Hour.
| Task order completion times will be specified on each task order. | 2,000 | LH | | $ - 0 |
| C701 | Material and Equipment - MUST BE NEGOTIATED BY KO. | Provide all materials and equipment to perform Unit Priced Labor work per the scope and delivery schedule specified in the order. Pre-expended bin supplies and materials will not be included in the list of materials since the cost for these items were included in the labor hour unit price bid. Material prices provided by the Contractor shall be the lowest price available considering the availability of materials and the time constraints of the job. The direct material price shall be adjusted by all discounts and rebates for core value or salvage value that accrue to the Contractor. | |
| Contractor owned equipment rental rates shall be based on calculations set forth in US Army Corp of Engineers “Construction Equipment Ownership and Operating Expense Schedule (EP 1110-1-8 (Vol. 11) July 03 or latest revision) Chapter 2. | $ 100,000.00 | DO | $ 1.00 | $ 100,000.00 |
| C702 | Cubicle Relocation (Inside NSA Complex) | | |
| AVAILABLE DOD FEDMALL | Relocate the entire Cubicle and its contents. Cubicle move from one location to another location within the NSA Complex. (The cubicles vary in size from 8.5' by 8.5' to 8.5' by 14.5'.) The Cubicle relocation includes relocation of all contents of the Cubicle to include books, files, folders, computer equipment, and all office supplies and equipment. It also includes the breakdown and re-assembly of the wall partitions, bookcases, desktops, chairs, lights, file drawers, shelves, drawers, pull outs etc. All minor material like fasteners or bolts are included. | 30 | EA | $ - 0 |
| C703 | Cubicle Relocation (Outside the NSA Complex) | | |
| AVAILABLE DOD FEDMALL | Relocate the entire Cubicle and its contents. Cubicle move from one location to another location outside the NSA Complex. (This will require a vehicle to transport the material approximately 8 miles. These moves may be from the NSA Complex to another facility or from another facility to the NSA Complex.)(The cubicles vary in size from 8.5' by 8.5' to 8.5' by 14.5'.) The Cubicle relocation includes relocation of all contents of the Cubicle to include books, files, folders, computer equipment, and all office supplies and equipment. It also includes the breakdown and re-assembly of the wall partitions, bookcases, desktops, chairs, lights, file drawers, shelves, drawers, pull outs etc. All minor material like fasteners or bolts are included. | 15 | EA | $ - 0 |
| C704 | Carpet Square removal and replacement | | |
| AVAILABLE DOD FEDMALL | Carpet Square removal and replacement shall match exising as close as possible in color, texture and manufacturer. This shall include moving or relocating furniture as required, and removing and replacing the adhesive in order to install in a first class manner. (The manufactor of the existing carpet is "Interface") | 600 | SY | $ - 0 |
| C705 | Canopy Cleaning | | |
| AVAILABLE DOD FEDMALL | Canopy Cleaning shall include complete cleaning of all visible residue in preparation for Command activities. This clean canopy shall present a uniform appearance with no stains form mildew, bird droppings, and dirt. All insect and bird nest shall be removed. | 2 | EA | $ - 0 |
| C706 | Subterranean Termite Control | | |
| AVAILABLE DOD FEDMALL | Provide labor and materials to control infestations of subterranean termites in accordance with J-1503020-09 (Termite Control Specifications). | | |
| Time Period to Respond: 3 calendar days after receipt of the task order. Complete work per time periods specified in J-1503020-09. | 2,500 | LF | $ - 0 |
| C707 | General Waste (20-34 Cubic Yard Container/Compactor) | |
| AVAILABLE DOD FEDMALL | The Contractor shall remove general waste from the designated 20 CY container or 34 CY compactor to ensure refuse is properly collected. Complete all work within 3 calendar days. | 25 | EA | $ - 0 |
| C708 | Recyclable Waste (20 CY Container) | | |
| AVAILABLE DOD FEDMALL | The Contractor shall remove recyclable waste from the designated 20 CY container to ensure it is properly collected. Complete all work within 3 calendar days. | 15 | EA | $ - 0 |
| C709 | Special Event Grass Cutting | | |
| AVAILABLE DOD FEDMALL | Grass shall be mowed and trimmed to a uniform height of 3 inches. Clippings and debris shall be removed. Complete all work within 3 calendar days. | 30 | AC | $ - 0 |
| C710 | Special Event Edging | | |
| AVAILABLE DOD FEDMALL | Edging to provide a uniform edged cut. All clippings shall be removed. Complete all work within 3 calendar days. | 10,000 | LF | $ - 0 |
| C711 | Plant Bed and Barrier Maintenance | | |
| AVAILABLE DOD FEDMALL | Dead, broken, damaged or diseased areas shall be removed and properly disposed. Plants and beds shall be fertilized, edged, weeded, and mulched as appropriate. Complete all work within 3 calendar days. | 5,000 | SF | $ - 0 |
| C712 | Debris Removal | | |
AVAILABLE DOD FEDMALL
Remove and properly dispose of natural debris (tree limbs, leaves, dry brush, rodent habitats, dead animals, etc.), and stray man-made trash/debris. Complete all work within 3 calendar days.
| 15 | AC | $ - 0 | |
| Total Non-Recurring Work | | | $ - 0 |
3rd Opt Period - Recurring
| Attachment J-0200000-13 |
| Exhibit Line Item Numbers |
| Solicitation No.:N6945023R0020 |
| Line Item 0007 - Recurring Work - Base Recurring Period | | | | | | | | | | |
| Provide Prices for Recurring Work in accordance with Section C, Spec Item 3 | | | | | | | | | | |
| ELINs D001 through D003 | | | | | | | | | | |
| Customer | ELIN | Sub-ELIN | Annex/Sub-annex | Category | Spec Item | Description | Quantity | Unit of Measure | Unit Price | Total |
| NSA | D001 | D001AA | 1501000 | Facility Management | 3 | Recurring Work | 12 | MO | | |
| NSA | D001 | D001AB | 1502000 | E/U/R Work Orders | 3.1.1 | Emergency Work Orders | 10 | EA | | |
| NSA | D001 | D001AC | 1502000 | E/U/R Work Orders | 3.1.2 | Urgent Work Orders | 20 | EA | | |
| NSA | D001 | D001AD | 1502000 | E/U/R Work Orders | 3.1.3 | Routine Work Orders | 325 | EA | | |
| NSA | D001 | D001AE | 1502000 | Project Orders | 3.2 | Project Orders | 100 | EA | | |
| NSA | D001 | D001AF | 1502000 | Preventative Maintenance Program | 3.3.1 | HVAC and Refrigeration Systems | 12 | MO | | |
| NSA | D001 | D001AG | 1502000 | Preventative Maintenance Program | 3.3.2 | Interior and Exterior Lighting Systems | 12 | MO | | |
| NSA | D001 | D001AH | 1502000 | Preventative Maintenance Program | 3.3.3 | Boilers and UPVs | 12 | MO | | |
| NSA | D001 | D001AJ | 1502000 | Preventative Maintenance Program | 3.3.4 | Lightning Arrestors and Grounding Devices | 12 | MO | | |
| NSA | D001 | D001AK | 1502000 | Preventative Maintenance Program | 3.3.5 | Fire Protection Systems | 12 | MO | | |
| NSA | D001 | D001AL | 1502000 | Preventative Maintenance Program | 3.3.6 | Vertical Transportation Equipment (VTE) | 12 | MO | | |
| NSA | D001 | D001AM | 1502000 | Preventative Maintenance Program | 3.3.7 | Auxiliary Generators | 12 | MO | | |
| NSA | D001 | D001AN | 1502000 | Preventative Maintenance Program | 3.3.8 | Fuel and Oil Storage Tanks | 12 | MO | | |
| NSA | D001 | D001AP | 1502000 | Preventative Maintenance Program | 3.3.9 | Safety Equipment | 12 | MO | | |
| NSA | D001 | D001AQ | 1502000 | Preventative Maintenance Program | 3.3.10 | Roll-up, Overhead, Automatic, and Access Doors | 12 | MO | | |
| NSA | D001 | D001AR | 1502000 | Preventative Maintenance Program | 3.3.11 | Electrical Distribution | 12 | MO | | |
| NSA | D001 | D001AS | 1502000 | Preventative Maintenance Program | 3.3.12 | Renewable Engergy System | 12 | MO | | |
| NSA | D001 | D001AT | 1502000 | Preventative Maintenance Program | 3.3.13 | Plumbing System | 12 | MO | | |
| NSA | D001 | D001AU | 1502000 | Preventative Maintenance Program | 3.3.14 | Galley Equipment | 12 | MO | | |
| NSA | D001 | D001AV | 1502000 | Preventative Maintenance Program | 3.3.15 | Electronic Security System | 12 | MO | | |
| NSA | D001 | D001AW | 1502000 | Preventative Maintenance Program | 3.3.16 | Intrusion Detection System | 12 | MO | | |
| NSA | D001 | D001AX | 1502000 | Inspection, Testing, and Certification Program | 3.4.1 | Boilers and UPVs | 12 | MO | | |
| NSA | D001 | D001AY | 1502000 | Inspection, Testing, and Certification Program | 3.4.2 | Backflow Prevention Devices | 12 | MO | | |
| NSA | D001 | D001AZ | 1502000 | Inspection, Testing, and Certification Program | 3.4.3 | Vertical Transportation Equipment (VTE) | 12 | MO | | |
| NSA | D001 | D001BA | 1502000 | Inspection, Testing, and Certification Program | 3.4.4 | Fuel/Oil Storage System Inspection | 12 | MO | | |
| NSA | D001 | D001BB | 1502000 | Other Recurring Services | 3.5.1 | Grease and Oil Interceptor | 12 | MO | | |
| NSA | D001 | D001BC | 1502000 | Other Recurring Services | 3.5.2 | Exhaust Hoods and Ducts | 12 | MO | | |
| NSA | D001 | D001BD | 1502000 | Other Recurring Services | 3.5.3 | HVAC Water Testing and Treatment Services | 12 | MO | | |
| NSA | D001 | D001BE | 1502000 | Other Recurring Services | 3.5.4 | Stormwater Retention Pond Maintenance | 12 | MO | | |
| NSA | D001 | D001BF | 1502000 | Other Recurring Services | 3.5.5 | Building Water Management Program | 12 | MO | | |
| NSA | D001 | D001BG | 1503020 | Pest Control | 3.1 | Scheduled Pest Control Services | 12 | MO | | |
| NSA | D001 | D001BH | 1503020 | Pest Control | 3.2 | Pest Control Work Orders | 12 | MO | | |
| NSA | D001 | D001BJ | 1503020 | Pest Control | 3.3 | Pest Management Reporting | 12 | MO | | |
| NSA | D001 | D001BK | 1503030 | Integrated Solid Waste Management | 3 | Recurring Work | 12 | MO | | |
| NSA | D001 | D001BL | 1503050 | Grounds Maintenance | 3.1 | Improved Grounds | 12 | MO | | |
| NSA | D001 | D001BM | 1503050 | Grounds Maintenance | 3.2 | Grounds Maintenance Work Orders | 12 | MO | | |
| NSA | D001 | D001BN | 1503050 | Grounds Maintenance | 3.3 | Storm Drainage Systems | 12 | MO | | |
| NUWC | D002 | D002AA | 1502000 | E/U/R Work Orders | 3.1.3 | Routine Work Orders | 25 | EA | | |
| NUWC | D002 | D002AB | 1502000 | Preventative Maintenance Program | 3.3.1 | HVAC and Refrigeration Systems | 12 | MO | | |
| NUWC | D002 | D002AC | 1502000 | Preventative Maintenance Program | 3.3.5 | Fire Protection Systems | 12 | MO | | |
| NUWC | D002 | D002AD | 1503020 | Pest Control | 3.2 | Pest Control Work Orders | 12 | MO | | |
| NUWC | D002 | D002AB | 1503030 | Integrated Solid Waste Management | 3 | Recurring Work | 12 | MO | | |
| NUWC | D002 | D002AC | 1503050 | Grounds Maintenance | 3.1 | Improved Grounds | 12 | MO | | |
| NUWC | D002 | D002AD | 1503050 | Grounds Maintenance | 3.2 | Grounds Maintenance Work Orders | 12 | MO | | |
| NEX | D003 | D003AA | 1502000 | Preventative Maintenance Program | 3.3.5 | Fire Protection Systems | 12 | MO | | |
| Total Recurring Work: | | | | | | | | | | $ - 0 |
3rd Opt Period - Non-Recurring
| Attachment J-0200000-13 |
| Exhibit Line Item Numbers |
| Solicitation No.: N6945023R0020 |
| Line Item 0008 - Non-Recurring Work - Fourth Option Period | | | | | | |
| Provide Prices for Recurring Work in accordance with Section C, Spec Item 4 | | | | | | |
| ELINs D700 through D712 | | | | | | |
| ELIN | Product Name (120 Characters) | Description Extended | Estimated Quantity | Unit of Measure | Unit Price | Extended Price |
| D700 | Unit Priced Labor Hour Work - MUST BE NEGOTIATED BY KO | The Contractor shall perform all UPL work in accordance with the scope and delivery schedule negotiated per each task order. | | | | |
Refer to: Section C, Annex 0200000 Managmenent and Administration, Specification Item 2.15.2 Unit Priced Labor (UPL)Work (Negotiated) for description of UPL Work.
Refer to: Section J, Annex 0200000 Managmenent and Administration, Attachment J-0200000-01 Definitions and Acronyms for description of Unit Priced Labor (UPL) Hour.
| Task order completion times will be specified on each task order. | 2,000 | LH | | $ - 0 |
| D701 | Material and Equipment - MUST BE NEGOTIATED BY KO. | Provide all materials and equipment to perform Unit Priced Labor work per the scope and delivery schedule specified in the order. Pre-expended bin supplies and materials will not be included in the list of materials since the cost for these items were included in the labor hour unit price bid. Material prices provided by the Contractor shall be the lowest price available considering the availability of materials and the time constraints of the job. The direct material price shall be adjusted by all discounts and rebates for core value or salvage value that accrue to the Contractor. | |
| Contractor owned equipment rental rates shall be based on calculations set forth in US Army Corp of Engineers “Construction Equipment Ownership and Operating Expense Schedule (EP 1110-1-8 (Vol. 11) July 03 or latest revision) Chapter 2. | $ 100,000.00 | DO | $ 1.00 | $ 100,000.00 |
| D702 | Cubicle Relocation (Inside NSA Complex) | | |
| AVAILABLE DOD FEDMALL | Relocate the entire Cubicle and its contents. Cubicle move from one location to another location within the NSA Complex. (The cubicles vary in size from 8.5' by 8.5' to 8.5' by 14.5'.) The Cubicle relocation includes relocation of all contents of the Cubicle to include books, files, folders, computer equipment, and all office supplies and equipment. It also includes the breakdown and re-assembly of the wall partitions, bookcases, desktops, chairs, lights, file drawers, shelves, drawers, pull outs etc. All minor material like fasteners or bolts are included. | 30 | EA | $ - 0 |
| D703 | Cubicle Relocation (Outside the NSA Complex) | | |
| AVAILABLE DOD FEDMALL | Relocate the entire Cubicle and its contents. Cubicle move from one location to another location outside the NSA Complex. (This will require a vehicle to transport the material approximately 8 miles. These moves may be from the NSA Complex to another facility or from another facility to the NSA Complex.)(The cubicles vary in size from 8.5' by 8.5' to 8.5' by 14.5'.) The Cubicle relocation includes relocation of all contents of the Cubicle to include books, files, folders, computer equipment, and all office supplies and equipment. It also includes the breakdown and re-assembly of the wall partitions, bookcases, desktops, chairs, lights, file drawers, shelves, drawers, pull outs etc. All minor material like fasteners or bolts are included. | 15 | EA | $ - 0 |
| D704 | Carpet Square removal and replacement | | |
| AVAILABLE DOD FEDMALL | Carpet Square removal and replacement shall match exising as close as possible in color, texture and manufacturer. This shall include moving or relocating furniture as required, and removing and replacing the adhesive in order to install in a first class manner. (The manufactor of the existing carpet is "Interface") | 600 | SY | $ - 0 |
| D705 | Canopy Cleaning | | |
| AVAILABLE DOD FEDMALL | Canopy Cleaning shall include complete cleaning of all visible residue in preparation for Command activities. This clean canopy shall present a uniform appearance with no stains form mildew, bird droppings, and dirt. All insect and bird nest shall be removed. | 2 | EA | $ - 0 |
| D706 | Subterranean Termite Control | | |
| AVAILABLE DOD FEDMALL | Provide labor and materials to control infestations of subterranean termites in accordance with J-1503020-09 (Termite Control Specifications). | | |
| Time Period to Respond: 3 calendar days after receipt of the task order. Complete work per time periods specified in J-1503020-09. | 2,500 | LF | $ - 0 |
| D707 | General Waste (20-34 Cubic Yard Container/Compactor) | |
| AVAILABLE DOD FEDMALL | The Contractor shall remove general waste from the designated 20 CY container or 34 CY compactor to ensure refuse is properly collected. Complete all work within 3 calendar days. | 25 | EA | $ - 0 |
| D708 | Recyclable Waste (20 CY Container) | | |
| AVAILABLE DOD FEDMALL | The Contractor shall remove recyclable waste from the designated 20 CY container to ensure it is properly collected. Complete all work within 3 calendar days. | 15 | EA | $ - 0 |
| D709 | Special Event Grass Cutting | | |
| AVAILABLE DOD FEDMALL | Grass shall be mowed and trimmed to a uniform height of 3 inches. Clippings and debris shall be removed. Complete all work within 3 calendar days. | 30 | AC | $ - 0 |
| D710 | Special Event Edging | | |
| AVAILABLE DOD FEDMALL | Edging to provide a uniform edged cut. All clippings shall be removed. Complete all work within 3 calendar days. | 10,000 | LF | $ - 0 |
| D711 | Plant Bed and Barrier Maintenance | | |
| AVAILABLE DOD FEDMALL | Dead, broken, damaged or diseased areas shall be removed and properly disposed. Plants and beds shall be fertilized, edged, weeded, and mulched as appropriate. Complete all work within 3 calendar days. | 5,000 | SF | $ - 0 |
| D712 | Debris Removal | | |
AVAILABLE DOD FEDMALL
Remove and properly dispose of natural debris (tree limbs, leaves, dry brush, rodent habitats, dead animals, etc.), and stray man-made trash/debris. Complete all work within 3 calendar days.
| 15 | AC | $ - 0 | |
| Total Non-Recurring Work | | | $ - 0 |
4th Opt Period - Recurring
| Attachment J-0200000-13 |
| Exhibit Line Item Numbers |
| Solicitation No.:N6945023R0020 |
| Line Item 0009 - Recurring Work - Base Recurring Period | | | | | | | | | | |
| Provide Prices for Recurring Work in accordance with Section C, Spec Item 3 | | | | | | | | | | |
| ELINs E001 through E003 | | | | | | | | | | |
| Customer | ELIN | Sub-ELIN | Annex/Sub-annex | Category | Spec Item | Description | Quantity | Unit of Measure | Unit Price | Total |
| NSA | E001 | E001AA | 1501000 | Facility Management | 3 | Recurring Work | 12 | MO | | |
| NSA | E001 | E001AB | 1502000 | E/U/R Work Orders | 3.1.1 | Emergency Work Orders | 10 | EA | | |
| NSA | E001 | E001AC | 1502000 | E/U/R Work Orders | 3.1.2 | Urgent Work Orders | 20 | EA | | |
| NSA | E001 | E001AD | 1502000 | E/U/R Work Orders | 3.1.3 | Routine Work Orders | 325 | EA | | |
| NSA | E001 | E001AE | 1502000 | Project Orders | 3.2 | Project Orders | 100 | EA | | |
| NSA | E001 | E001AF | 1502000 | Preventative Maintenance Program | 3.3.1 | HVAC and Refrigeration Systems | 12 | MO | | |
| NSA | E001 | E001AG | 1502000 | Preventative Maintenance Program | 3.3.2 | Interior and Exterior Lighting Systems | 12 | MO | | |
| NSA | E001 | E001AH | 1502000 | Preventative Maintenance Program | 3.3.3 | Boilers and UPVs | 12 | MO | | |
| NSA | E001 | E001AJ | 1502000 | Preventative Maintenance Program | 3.3.4 | Lightning Arrestors and Grounding Devices | 12 | MO | | |
| NSA | E001 | E001AK | 1502000 | Preventative Maintenance Program | 3.3.5 | Fire Protection Systems | 12 | MO | | |
| NSA | E001 | E001AL | 1502000 | Preventative Maintenance Program | 3.3.6 | Vertical Transportation Equipment (VTE) | 12 | MO | | |
| NSA | E001 | E001AM | 1502000 | Preventative Maintenance Program | 3.3.7 | Auxiliary Generators | 12 | MO | | |
| NSA | E001 | E001AN | 1502000 | Preventative Maintenance Program | 3.3.8 | Fuel and Oil Storage Tanks | 12 | MO | | |
| NSA | E001 | E001AP | 1502000 | Preventative Maintenance Program | 3.3.9 | Safety Equipment | 12 | MO | | |
| NSA | E001 | E001AQ | 1502000 | Preventative Maintenance Program | 3.3.10 | Roll-up, Overhead, Automatic, and Access Doors | 12 | MO | | |
| NSA | E001 | E001AR | 1502000 | Preventative Maintenance Program | 3.3.11 | Electrical Distribution | 12 | MO | | |
| NSA | E001 | E001AS | 1502000 | Preventative Maintenance Program | 3.3.12 | Renewable Engergy System | 12 | MO | | |
| NSA | E001 | E001AT | 1502000 | Preventative Maintenance Program | 3.3.13 | Plumbing System | 12 | MO | | |
| NSA | E001 | E001AU | 1502000 | Preventative Maintenance Program | 3.3.14 | Galley Equipment | 12 | MO | | |
| NSA | E001 | E001AV | 1502000 | Preventative Maintenance Program | 3.3.15 | Electronic Security System | 12 | MO | | |
| NSA | E001 | E001AW | 1502000 | Preventative Maintenance Program | 3.3.16 | Intrusion Detection System | 12 | MO | | |
| NSA | E001 | E001AX | 1502000 | Inspection, Testing, and Certification Program | 3.4.1 | Boilers and UPVs | 12 | MO | | |
| NSA | E001 | E001AY | 1502000 | Inspection, Testing, and Certification Program | 3.4.2 | Backflow Prevention Devices | 12 | MO | | |
| NSA | E001 | E001AZ | 1502000 | Inspection, Testing, and Certification Program | 3.4.3 | Vertical Transportation Equipment (VTE) | 12 | MO | | |
| NSA | E001 | E001BA | 1502000 | Inspection, Testing, and Certification Program | 3.4.4 | Fuel/Oil Storage System Inspection | 12 | MO | | |
| NSA | E001 | E001BB | 1502000 | Other Recurring Services | 3.5.1 | Grease and Oil Interceptor | 12 | MO | | |
| NSA | E001 | E001BC | 1502000 | Other Recurring Services | 3.5.2 | Exhaust Hoods and Ducts | 12 | MO | | |
| NSA | E001 | E001BD | 1502000 | Other Recurring Services | 3.5.3 | HVAC Water Testing and Treatment Services | 12 | MO | | |
| NSA | E001 | E001BE | 1502000 | Other Recurring Services | 3.5.4 | Stormwater Retention Pond Maintenance | 12 | MO | | |
| NSA | E001 | E001BF | 1502000 | Other Recurring Services | 3.5.5 | Building Water Management Program | 12 | MO | | |
| NSA | E001 | E001BG | 1503020 | Pest Control | 3.1 | Scheduled Pest Control Services | 12 | MO | | |
| NSA | E001 | E001BH | 1503020 | Pest Control | 3.2 | Pest Control Work Orders | 12 | MO | | |
| NSA | E001 | E001BJ | 1503020 | Pest Control | 3.3 | Pest Management Reporting | 12 | MO | | |
| NSA | E001 | E001BK | 1503030 | Integrated Solid Waste Management | 3 | Recurring Work | 12 | MO | | |
| NSA | E001 | E001BL | 1503050 | Grounds Maintenance | 3.1 | Improved Grounds | 12 | MO | | |
| NSA | E001 | E001BM | 1503050 | Grounds Maintenance | 3.2 | Grounds Maintenance Work Orders | 12 | MO | | |
| NSA | E001 | E001BN | 1503050 | Grounds Maintenance | 3.3 | Storm Drainage Systems | 12 | MO | | |
| NUWC | E002 | E002AA | 1502000 | E/U/R Work Orders | 3.1.3 | Routine Work Orders | 25 | EA | | |
| NUWC | E002 | E002AB | 1502000 | Preventative Maintenance Program | 3.3.1 | HVAC and Refrigeration Systems | 12 | MO | | |
| NUWC | E002 | E002AC | 1502000 | Preventative Maintenance Program | 3.3.5 | Fire Protection Systems | 12 | MO | | |
| NUWC | E002 | E002AD | 1503020 | Pest Control | 3.2 | Pest Control Work Orders | 12 | MO | | |
| NUWC | E002 | E002AB | 1503030 | Integrated Solid Waste Management | 3 | Recurring Work | 12 | MO | | |
| NUWC | E002 | E002AC | 1503050 | Grounds Maintenance | 3.1 | Improved Grounds | 12 | MO | | |
| NUWC | E002 | E002AD | 1503050 | Grounds Maintenance | 3.2 | Grounds Maintenance Work Orders | 12 | MO | | |
| NEX | E003 | E003AA | 1502000 | Preventative Maintenance Program | 3.3.5 | Fire Protection Systems | 12 | MO | | |
| Total Recurring Work: | | | | | | | | | | $ - 0 |
4th Opt Period - Non-Recurring
| Attachment J-0200000-13 |
| Exhibit Line Item Numbers |
| Solicitation No.: N6945023R0020 |
| Line Item 0010 - Non-Recurring Work - Fourth Option Period | | | | | | |
| Provide Prices for Recurring Work in accordance with Section C, Spec Item 4 | | | | | | |
| ELINs E700 through E712 | | | | | | |
| ELIN | Product Name (120 Characters) | Description Extended | Estimated Quantity | Unit of Measure | Unit Price | Extended Price |
| E700 | Unit Priced Labor Hour Work - MUST BE NEGOTIATED BY KO | The Contractor shall perform all UPL work in accordance with the scope and delivery schedule negotiated per each task order. | | | | |
Refer to: Section C, Annex 0200000 Managmenent and Administration, Specification Item 2.15.2 Unit Priced Labor (UPL)Work (Negotiated) for description of UPL Work.
Refer to: Section J, Annex 0200000 Managmenent and Administration, Attachment J-0200000-01 Definitions and Acronyms for description of Unit Priced Labor (UPL) Hour.
| Task order completion times will be specified on each task order. | 2,000 | LH | | $ - 0 |
| E701 | Material and Equipment - MUST BE NEGOTIATED BY KO. | Provide all materials and equipment to perform Unit Priced Labor work per the scope and delivery schedule specified in the order. Pre-expended bin supplies and materials will not be included in the list of materials since the cost for these items were included in the labor hour unit price bid. Material prices provided by the Contractor shall be the lowest price available considering the availability of materials and the time constraints of the job. The direct material price shall be adjusted by all discounts and rebates for core value or salvage value that accrue to the Contractor. | |
| Contractor owned equipment rental rates shall be based on calculations set forth in US Army Corp of Engineers “Construction Equipment Ownership and Operating Expense Schedule (EP 1110-1-8 (Vol. 11) July 03 or latest revision) Chapter 2. | $ 100,000.00 | DO | $ 1.00 | $ 100,000.00 |
| E702 | Cubicle Relocation (Inside NSA Complex) | | |
| AVAILABLE DOD FEDMALL | Relocate the entire Cubicle and its contents. Cubicle move from one location to another location within the NSA Complex. (The cubicles vary in size from 8.5' by 8.5' to 8.5' by 14.5'.) The Cubicle relocation includes relocation of all contents of the Cubicle to include books, files, folders, computer equipment, and all office supplies and equipment. It also includes the breakdown and re-assembly of the wall partitions, bookcases, desktops, chairs, lights, file drawers, shelves, drawers, pull outs etc. All minor material like fasteners or bolts are included. | 30 | EA | $ - 0 |
| E703 | Cubicle Relocation (Outside the NSA Complex) | | |
| AVAILABLE DOD FEDMALL | Relocate the entire Cubicle and its contents. Cubicle move from one location to another location outside the NSA Complex. (This will require a vehicle to transport the material approximately 8 miles. These moves may be from the NSA Complex to another facility or from another facility to the NSA Complex.)(The cubicles vary in size from 8.5' by 8.5' to 8.5' by 14.5'.) The Cubicle relocation includes relocation of all contents of the Cubicle to include books, files, folders, computer equipment, and all office supplies and equipment. It also includes the breakdown and re-assembly of the wall partitions, bookcases, desktops, chairs, lights, file drawers, shelves, drawers, pull outs etc. All minor material like fasteners or bolts are included. | 15 | EA | $ - 0 |
| E704 | Carpet Square removal and replacement | | |
This is the start of the file's text. The full file is on GovTribe.