BUILDING WATER
MANAGEMENT PLAN
Naval Support Activity
Orlando, Florida
Naval Facilities Engineering Systems Command Southeast Contract: N62470-19-D-4001 | Task Order: N6945020F0364
March 2021
Final
BUILDING WATER
MANAGEMENT PLAN
NAVAL SUPPORT ACTIVITY
ORLANDO, FLORIDA
Prepared For:
Naval Facilities Engineering Systems Command Southeast
Engineer in Charge: Jens Sapin, P.E.
Contract Number: N62470-19-D-4001 Task Order Number: N6945020F0364
March 2021
AH/BC Navy JV, LLC
11837 Rock Landing Drive Suite 300
Newport News, Virginia 23606-4493
(757) 873-4959
BUILDING WATER MANAGEMENT PLAN
NAVAL SUPPORT ACTIVITY ORLANDO, FLORIDA TABLE OF CONTENTS
AH/BC Navy JV, LLC i Final, March 2021 134-014
ACRONYMS AND ABBREVIATIONS ............................................................ iii
EXECUTIVE SUMMARY .................................................................................. v
INTRODUCTION ................................................................................... 1-1
1.1 LEGIONELLA CONTROL GOAL ....................................................................1-2
1.2 BUILDING WATER MANAGEMENT TEAM ......................................................1-4
1.3 PLAN ORGANIZATION ................................................................................1-5
WATER SYSTEM DESCRIPTION ........................................................ 2-1
2.1 WATER SUPPLIER ....................................................................................2-2
2.2 BUILDING SYSTEM DESCRIPTION ...............................................................2-3
2.3 COOLING TOWERS ...................................................................................2-9
2.4 WATER USE ........................................................................................... 2-10
2.5 OTHER WATER SYSTEMS ........................................................................ 2-10
ANALYSIS OF HAZARD CONDITIONS ............................................... 3-1
3.1 LEGIONELLA .............................................................................................3-2
3.2 TEMPERATURE .........................................................................................3-3
3.3 OPERATIONAL CONDITIONS .......................................................................3-3
CONTROL MEASURES AND MONITORING....................................... 4-1
4.1 AUTOMATED FLUSHING .............................................................................4-5
4.2 SHOWERHEAD FILTERS.............................................................................4-5
VERIFICATION AND VALIDATION ...................................................... 5-1
NAVAL SUPPORT ACTIVITY ORLANDO, FLORIDA TABLE OF CONTENTS
AH/BC Navy JV, LLC ii Final, March 2021 134-014
APPENDICES
A. Water System Monitoring Standard Operating Procedure
B. Water System Flushing Standard Operating Procedure
C. Dead Leg Management Standard Operating Procedure
D. Miscellaneous Standard Operating Procedures
E. Cooling Towers Standard Operating Procedures
F. Building Water Management Plan Validation (Including Sampling) Standard Operating Procedure
FIGURES
Figure 1-1 Water Management Program Process .................................................1-2 Figure 2-1 Naval Support Activity Orlando Installation Layout ...............................2-1 Figure 2-2 Central Florida Research Park Water Treatment Plant Layout.............2-3 Figure 2-3 Naval Support Activity Orlando Domestic Water System Layout ..........2-5 Figure 2-4 Naval Support Activity Orlando Domestic Water System Process
Flow Diagram ......................................................................................2-6 Figure 2-5 Naval Support Activity Orlando Hot-Water Booster Heaters ................2-8 Figure 2-6 Naval Support Activity Orlando Cooling Towers ..................................2-9 Figure 3-1 Faucet Aerators ...................................................................................3-4
TABLES
Table ES-1 Summary of Potential Areas of Water Quality Concern........................... v Table 1-1 Action Levels Following Legionella Sampling ......................................1-4 Table 3-1 Summary of Potential Areas of Water Quality Concern........................3-1 Table 4-1 Summary of Control Measures ............................................................4-3
NAVAL SUPPORT ACTIVITY ORLANDO, FLORIDA ACRONYMS AND ABBREVIATIONS
AH/BC Navy JV, LLC iii Final, March 2021
ACRONYMS AND ABBREVIATIONS
% percent
°C degrees Celsius
°F degrees Fahrenheit
AH/BC AH/BC Navy JV, LLC
ANSI American National Standards Institute
ASHRAE American Society of Heating, Refrigerating, and Air-Conditioning Engineers
AST aboveground storage tank
BFP backflow preventer
BOS Base Operating Services
CDC Centers for Disease Control and Prevention
CFRP Central Florida Research Park
CO commanding officer
COVID-19 coronavirus disease 2019
HVAC heating, ventilation, and air conditioning
L. pneumophila Legionella pneumophila
MG million-gallon mg/L milligrams per liter
N/A not applicable
NAVFAC SE Naval Facilities Engineering Systems Command Southeast
NMCPHC Navy and Marine Corps Public Health Center
No. number
NSA Naval Support Activity
POE point of entry
POU point of use
PWD Public Works Department
RPZ reduced pressure zone
SOP standard operating procedure
US United States
WMP water management plan
NAVAL SUPPORT ACTIVITY ORLANDO, FLORIDA ACRONYMS AND ABBREVIATIONS
AH/BC Navy JV, LLC iv Final, March 2021
WTP water treatment plant
NAVAL SUPPORT ACTIVITY ORLANDO, FLORIDA EXECUTIVE SUMMARY
AH/BC Navy JV, LLC v Final, March 2021 134-014
EXECUTIVE SUMMARY
Naval Facilities Engineering Systems Command Southeast contracted AH/BC Navy
JV, LLC (AH/BC) to provide a building water quality site assessment study and water management plan (WMP) at Naval Support Activity (NSA) Orlando, Florida, under Con-tract Number (No.) N62470-19-D-4001, Delivery Order No. N6945020F0364. This is in response to the detection of Legionella in the de Florez Complex (Building 1) and An-nex (Building 2) domestic water system during sampling events on 18 November 2019 and 12 February 2020. AH/BC published a water quality site assessment study report in December 2020 summarizing potential hazards identified and recommendations to consider when developing this WMP (summarized in Table ES-1).
Table ES-1 Summary of Potential Areas of Water Quality Concern
Hazard Potential Area(s) of Concern
Legionella present throughout system
The installation population is exposed to potential illness, including Legionnaires’ disease, from use of the system.
High cold-water temperatures (cross-connection)
A heated cold-water system improves conditions for Legionella growth and spread within the system.
Significant Legionella levels detected at points of use (POU)s1 with carbon filters installed (i.e., ice machines, water fountains)
Carbon filters provide a favorable substrate for bacterial growth, including Legionella when the bacterium is present in the system.
Low population conditions (i.e., coronavirus disease 2019 pandemic personnel restrictions)
Low water use allows for longer periods of stagnant water within the system, which leads to the decay of free chlorine disinfectant residual and amplifies the potential for microbial growth.
Low hot-water temperatures (upstream and separate from booster heaters)
Hot-water systems unable to maintain system temperatures above 108 degrees Fahrenheit (42 degrees Celsius) present optimal conditions for Legionella growth and spread within the system.
Spray aerators installed on majority of hand wash sinks
Spray aerator devices disperse aerosols into the air, increasing the susceptibility of Legionella inhalation when the bacterium is present in the system.
1 POU refers to any plumbing fixture that supplies potable water.
NAVAL SUPPORT ACTIVITY ORLANDO, FLORIDA EXECUTIVE SUMMARY
AH/BC Navy JV, LLC vi Final, March 2021 134-014
Table ES-1 Summary of Potential Areas of Water Quality Concern (continued)
Hazard Potential Area(s) of Concern
Lack of cold-water line insulation in areas with no temperature control
A lack of insulation makes the supply line susceptible to increased temperatures during warm weather, improving conditions for Legionella growth and spread within the system.
This is especially applicable to the supply line in the Mechanical Building.
Convective heat transfer to cold-water supply from booster heaters
Heating of the cold-water system improves conditions for Legionella growth and spread within the system.
Dead legs2 from removed POUs The potential for microbial growth is amplified by stagnant water conditions.
Electronic faucets with thermostatic mixing valves
The tempered water can provide ideal conditions for microbial growth on surfaces within POU fixtures.
Showerhead membrane filters The tempered water can provide ideal conditions for microbial growth on the filters if not maintained properly.
Hazards associated with building water systems can be managed through effective system operation. To assist building owners and operators, the Centers for Disease
Control and Prevention (CDC) created a standardized process that complies with
American National Standards Institute (ANSI)/American Society of Heating, Refrigerat-ing, and Air-Conditioning Engineers (ASHRAE) Standard 188 to identify risks and man-agement strategies to mitigate the risk of building water quality threats. AH/BC used the CDC process and the latest version of ANSI/ASHRAE Standard 188 (188-2018), in conjunction with ASHRAE Guideline 12-2020, as the main resources in developing this
WMP.
Section 4 summarizes recommended control measures, monitoring strategies, and cor-rective actions for identified hazards. Supporting these recommendations are standard operating procedures (SOPs) that provide more details on implementation for the NSA
Orlando building water management team.
The building water management team must establish procedures to confirm that this building WMP is being implemented as designed (verification) and whether the recom-mended control measures are successfully controlling the hazardous conditions iden-tified (validation).
2 Dead legs refer to water pipes that are no longer used but still connected to the active premise plumbing.
BUILDING WATER MANAGEMENT PLAN SECTION 1
NAVAL SUPPORT ACTIVITY ORLANDO, FLORIDA INTRODUCTION
AH/BC Navy JV, LLC 1-1 Final, March 2021 134-014
INTRODUCTION
Hazards associated with building water systems are a leading cause of outbreaks and serious illnesses from exposure to potable drinking water. The most common microbial hazard associated with building water systems is Legionella pneumophila (L. pneu-mophila), the bacterium that causes Legionnaires’ disease.
Naval Facilities Engineering Systems Command Southeast (NAVFAC SE) contracted
AH/BC Navy JV, LLC (AH/BC) to provide a building water quality site assessment study and water management plan (WMP) at Naval Support Activity (NSA) Orlando, Florida, under Contract Number (No.) N62470-19-D-4001, Delivery Order No.
N6945020F0364. This is in response to the detection of Legionella in the de Florez
Complex (Building 1) and Annex (Building 2) domestic water system during sampling events on 18 November 2019 (two men’s restrooms) and 12 February 2020 (eighteen out of 40 locations after the application of shock chlorination). AH/BC personnel con-ducted two site visits. The initial site visit occurred from 31 August to 2 September 2020 and consisted of an assessment of the building plumbing system and water quality sampling. AH/BC published a water quality site assessment study report in December
2020 summarizing potential hazards identified and recommendations to consider when developing this WMP. The second site visit occurred from 5 to 7 January 2021 and consisted of meetings with key facility personnel to review the potential hazards iden-tified and determine which hazards require control or mitigation.
Hazards associated with building water systems can be managed through effective system operation. To assist building owners and operators, the Centers for Disease
Control and Prevention (CDC) created a standardized process3 that complies with
American National Standards Institute (ANSI)/American Society of Heating, Refrigerat-ing, and Air-Conditioning Engineers (ASHRAE) Standard 188 to identify risks and
3 CDC. Developing a Water Management Program to Reduce Legionella Growth & Spread in Buildings:
A Practical Guide to Implementing Industry Standards. Version 1.1. 5 June 2017. https://www.cdc.gov/le-gionella/downloads/toolkit.pdf. Accessed 19 January 2021.
https://www.cdc.gov/legionella/downloads/toolkit.pdf https://www.cdc.gov/legionella/downloads/toolkit.pdf
AH/BC Navy JV, LLC 1-2 Final, March 2021 134-014 management strategies to mitigate the risk of building water quality threats (Figure
1- 1). AH/BC used the CDC process and the latest version of ANSI/ASHRAE Standard
188 (188-20184), in conjunction with ASHRAE Guideline 12-2020,5 as the main re-sources in developing this WMP.
Figure 1-1 Water Management Program Process
1.1 LEGIONELLA CONTROL GOAL
Once this building WMP is in place and being implemented as designed, the validation process (see Section 5) will be used to determine when microbiological activity in the system is acceptable for no further remedial action.
4 ASHRAE. Legionellosis: Risk Management for Building Water Systems. ANSI/ASHRAE Standard 188- 2018. https://www.techstreet.com/ashrae/standards/ashrae-188-2018?product_id=2020895. Accessed 19 January 2021.
5 ASHRAE. Managing the Risk of Legionellosis Associated with Building Water Systems. ASHRAE Guideline 12-2020. https://www.techstreet.com/ashrae/standards/guideline-12-2020-managing-the-risk-of-legionellosis-associated-with-building-water-systems?product_id=2111422. Accessed 19 January 2021.
https://www.techstreet.com/ashrae/standards/ashrae-188-2018?product_id=2020895 https://www.techstreet.com/ashrae/standards/guideline-12-2020-managing-the-risk-of-legionellosis-associated-with-building-water-systems?product_id=2111422 https://www.techstreet.com/ashrae/standards/guideline-12-2020-managing-the-risk-of-legionellosis-associated-with-building-water-systems?product_id=2111422
AH/BC Navy JV, LLC 1-3 Final, March 2021 134-014
While no regulations exist in the United States (US) at the national level (or at state or local levels for NSA Orlando) for Legionella, other countries and some local US jurisdictions have developed guidance that recommend action levels when Legionella is detected in building plumbing.
The European Union has guidelines for acceptable levels of Legionella in building plumbing and bases remedial actions on detected levels. A modified version of these action levels was developed as part of the Navy and Marine Corps Public Health Center
(NMCPHC) Legionella Response Guidance for Navy Medicine.6 Table 1-1 summarizes these action levels, as presented in Table 4 of the NMCPHC guidance.
The action levels are based on analysis of sufficient samples to adequately represent the building water system. Section 2.4 of the NMCPHC guidance identifies representative sampling locations:
• Point of entry (POE)
• Storage tanks
• Hot-water supply (e.g., heat exchanger)
• Hot-water return
• At least 20 percent (%) of hot- and cold-water points of use (POUs)7
6 AH/BC; ESPRI, Inc.; and NMCPHC. Legionella Response Guidance for Navy Medicine. November 2020.
7 POU refers to any plumbing fixture that supplies potable water.
AH/BC Navy JV, LLC 1-4 Final, March 2021 134-014
Table 1-1 Action Levels Following Legionella Sampling
Legionella (colony-forming units per liter)
Sublevel Action Required
Not Detected
Not Applicable (N/A)
No action is required.
Less than 100 to 1,000
Refer to the responsible person and ensure that routine monitoring parameters are within target limits throughout the system.
Greater than 1,000 to <10,000
Less than 20% of samples are positive and not repeat positive
Resample the system. If a similar count is found again, conduct a review of the building WMP control measures and risk assessment to identify remedial actions.
Less than 20% of samples are positive and one or more are repeat positive
Resample the system.
For repeat positive sample locations, adjust the building WMP control strategy. For chronically positive locations, clean and disinfect to the origin of the branch.
For other sample locations, review the building WMP control measures, and conduct a hazard analysis to determine whether the building WMP control strategy must be changed.
20% or greater are positive
The system may be colonized, albeit at a low level.
Consider disinfection of the entire system; conduct an immediate review of the building WMP control measures and risk assessment to identify remedial actions.
Greater than or equal to 10,000
N/A
Resample the system. Conduct an immediate review of the building WMP control measures and risk assessment to identify remedial actions, including disinfection of the entire system or affected area(s).
1.2 BUILDING WATER MANAGEMENT TEAM
An imperative step in developing a building WMP is to establish an interdisciplinary team with expertise in building water management. Third-party team members with expertise on building water operations and quality management can add value in cre-ating the WMP. Implementation, however, incorporates steps and measures that fall upon staff to fully incorporate into their routine best practices.
The NSA Orlando WMP interdisciplinary development team included the team mem-bers listed below:
AH/BC Navy JV, LLC 1-5 Final, March 2021 134-014
• Jens Sapin, PE, NAVFAC SE Environmental Compliance Branch, Air and Wa-ter Section
• Lieutenant Brandon Roth, PE, Public Works Officer, NSA Orlando Public Works Department (PWD)
• Steven Wagner, Facilities Management Division Head/Energy Manager, NSA Orlando PWD
• Caleb Romero, PE, Facilities Management, NSA Orlando PWD
• William Holmgren, PE, NSA Orlando Project Management and Engineering Branch
The AH/BC team included the following:
• Peter Pommerenk, PhD, PE
• Richard Theiss, PE
• Robert Durso, PE
1.3 PLAN ORGANIZATION
This building WMP consists of the following sections:
• Section 1 (Introduction): Background and purpose of the project and WMP-development team
• Section 2 (Water System Description): Detailed description of the facility do-mestic water system and uses
• Section 3 (Analysis of Hazard Conditions): Summary of potential hazards identified during the building water quality site assessment study in August/Sep-tember 2020
• Section 4 (Control Measures and Monitoring): Recommendations for control measures, monitoring strategies, and corrective actions for each potential haz-ard identified and other recommendations per ANSI/ASHRAE Standard 188- 2018
• Section 5 (Validation Plan): Identification of validation efforts to ensure appli-cation of the recommended control measures
• Appendices: Standard operating procedures (SOPs) for water system moni-toring, water system flushing, dead leg8 management, cooling towers, building WMP validation, and other miscellaneous requirements per ANSI/ASHRAE Standard 188-2018
8 Dead legs refer to water pipes that are no longer used but still connected to the active premise plumbing.
AH/BC Navy JV, LLC 1-6 Final, March 2021
This page is left blank intentionally.
BUILDING WATER MANAGEMENT PLAN SECTION 2
NAVAL SUPPORT ACTIVITY ORLANDO, FLORIDA WATER SYSTEM DESCRIPTION
AH/BC Navy JV, LLC 2-1 Final, March 2021 134-014
WATER SYSTEM DESCRIPTION
NSA Orlando consists of two administrative buildings, the de Florez Complex and An-nex, and a Mechanical Building (Building 3). Figure 2-1 shows an overall layout of the facility, including the domestic water POE and cooling towers.
The de Florez Complex has subareas designated as Zones A through D, running north to south in the building. The Annex is sometimes referred to as Zone E based on con-struction drawings provided to AH/BC.
Figure 2-1 Naval Support Activity Orlando Installation Layout
AH/BC Navy JV, LLC 2-2 Final, March 2021 134-014
2.1 WATER SUPPLIER
NSA Orlando receives finished water from Central Florida Research Park (CFRP) wa-ter treatment plant (WTP), located southwest of the facility at the southern dead end of
Technology Parkway. Figure 2-2 provides a layout of the facility. The WTP is sourced by groundwater from two on-site wells drawing from the Upper Floridan aquifer. The water is initially treated via aeration through cascade trays before entering a 2-mil-lion- gallon (MG) aboveground storage tank (AST). Inside the tank, the water is treated with sodium hypochlorite (tank contains a mixer) for disinfection.
The treated water is distributed to tenants of the business park, including NSA Orlando, via four high service pumps with variable frequency drives. According to the CFRP drinking water quality report for 2019 to 2020, the finished water is used by tenants for drinking water, irrigation, and fire protection purposes.9 There are no downstream stor-age tanks or booster pumps.
The WMP development team met with Thomas King, Director of Utilities and Infrastruc-ture for the CFRP WTP, on 6 January 2021 for a tour of the facility. According to Mr.
King, the free chlorine residual leaving the WTP is typically 2 to 3 milligrams per liter
(mg/L). Automatic flushing devices with timers are installed on the distribution network.
During the initial Legionella sampling events at NSA Orlando in November 2019 and
February 2020, free chlorine residual levels leaving the WTP ranged from 0.7 to
1.4 mg/L, and the automatic flushing devices were not yet installed.
There is one backup diesel pump on-site at the WTP. Polyphosphate addition was a previous component of the WTP treatment process but has since been discontinued.
Lead and copper monitoring is conducted every three years.
In case of an interruption of water supply to the CFRP WTP system, the distribution system has an emergency interconnection with the University of Central Florida water system, which has an emergency interconnection with the Orlando Utilities Commis-sion water system. During the January 2021 WTP tour, the team discovered that this
9 CFRP. Drinking Water Quality Information for CENTRAL FLORIDA RESEARCH PARK, Orlando, Flor-ida 32826, 2019 - 2020.
AH/BC Navy JV, LLC 2-3 Final, March 2021 134-014 interconnection was in use (due to rehabilitation work on the AST) during the building water quality site assessment conducted in August and September 2020.
Figure 2-2 Central Florida Research Park Water Treatment Plant Layout
2.2 BUILDING SYSTEM DESCRIPTION
Drinking water is supplied to NSA Orlando by a 6-inch pipe with a reduced pressure zone (RPZ) backflow preventer (BFP) at the Loop Road West entrance, located at the west corner of the Annex. From the BFP, the service line reduces to a 5-inch diameter and enters the south corner of the Mechanical Building. Figure 2-3 presents a layout of the system (based on 17 January 1990 revisions to the 30 May 1985 as-built drawings provided by NSA Orlando personnel), and Figure 2-4 presents a process flow diagram of the system.
AH/BC Navy JV, LLC 2-4 Final, March 2021
AH/BC Navy JV, LLC 2-5 Final, March 2021
Figure 2-3 Naval Support Activity Orlando Domestic Water System Layout
DE FLOREZ COMPLEX
(BUILDING 1)
ANNEX
(BUILDING 2)
MECHANICAL BUILDING
(BUILDING 3)
ZONE A
ZONE B
ZONE C
ZONE D
ZONE E
POE
Legend
Cold Water
Hot Water
Hot-Water Return *Based on 17 January 1990 revisions to as-built drawings (subsequent modifications noted)
*Drawing not to scale
First-Floor
Restrooms Relocated
(Two Booster Heaters Installed, One Out of Service)
Booster Heater Installed at First-Floor Restrooms
Booster Heater Installed in
Food Preparation/Serving Area
Booster Heater Installed at First-Floor Restrooms
Hot-Water Storage
Tank Offline
AH/BC Navy JV, LLC 2-6 Final, March 2021
Figure 2-4 Naval Support Activity Orlando Domestic Water System Process Flow Diagram
AH/BC Navy JV, LLC 2-7 Final, March 2021 134-014
Once inside the building, the service line splits into a 2½-inch line and a 4-inch line.
The 2½-inch line delivers to two hose bibbs at the south corner of the building and a dual stacked pump/RPZ BFP setup that supplies the cooling towers. The 4-inch line splits to supply a heat exchanger and the cold-water service line entering the de Florez
Complex. Heated water from the heat exchanger supplies a 3-inch service line entering the de Florez Complex. The heat exchanger transfers heat from a closed-circuit, two- chiller system used for heating, ventilation, and air conditioning (HVAC) dehumidification. An electric boiler supplements heat whenever the chillers are off or the hot-water temperature is below 110 degrees Fahrenheit (°F) (43 degrees
Celsius [°C]).
The 4-inch cold- and 3-inch hot-water supply lines enter the de Florez Complex above the dropped ceiling for the food preparation/cooking (Room 1086) and serving (Room
1085) areas on the first floor in Zone C. The supply lines split upon entering the main corridor of the building and run along the corridor above the dropped ceiling to the ends of the building (hot-water line stops at the restrooms at the north end of Zone B).
There are three sets of restrooms (men’s room, women’s room, and janitor’s closet) on the first floor of the de Florez Complex: one at the north end of Zone B, one at the borders of Zones B and C, and one at the south end of Zone D. The supply line branches for these restrooms also supply similar restroom setups on the second and third floors above these restrooms via riser pipes. The first-floor restrooms in Zone D were relocated to the southeast corner of Zone D sometime in the mid- to late 1990s according to NSA Orlando personnel (no as-builts were provided to AH/BC), but the restrooms on the second and third floors in Zone D did not change. In addition to faucets and toilets, the first-floor restrooms in Zone D and at the Zone B/C border have showers.
Cold- and hot-water supply lines branch off from the main corridor supply line in Zone
C to transport water to the Annex. The lines travel above a covered exterior walkway connecting the buildings. The supply lines enter the southeast corner of the building above the dropped ceiling of the first floor and travel along the main corridor and split to support stacked restrooms (men’s room, women’s room, and janitor’s closet) on the
AH/BC Navy JV, LLC 2-8 Final, March 2021 134-014 first and second floors at the center of the building and the private restroom for the
Senior Executive Service Director (Room 2025) on the second floor at the northeast corner of the building.
Five in-line electric hot-water booster heaters have been installed (no as-builts were provided) throughout the facility. One was installed to support the food preparation/serving area, while the other four were installed to support shower areas
(plus some janitor’s closet mop sinks) throughout the installation. Two heaters were installed to support the showers at the first-floor restrooms in Zone D; however, one is inactive and tagged out due to insufficient demand. Figure 2-5 shows photos of two of the heaters. During the January 2021 site visit, it was determined that the hot-water booster pumps pushed heated water into the cold-water plumbing at various cross- connections, including at these heaters and potentially elsewhere (e.g., defective mixing valves) (see Section 3.2).
Annex, First Floor de Florez Complex, First Floor, Zone D
Figure 2-5 Naval Support Activity Orlando Hot-Water Booster Heaters
AH/BC Navy JV, LLC 2-9 Final, March 2021 134-014
Hot-water return lines start above the dropped ceiling on the first floor at the stacked restrooms in Zones B and D of the de Florez Complex and the Annex, retrace back to the food preparation/serving area, and enter the Mechanical Building via a 1-inch return line. These lines do not go above the first floor in either building. The return water passes through a RPZ BFP before rejoining the cold-water feed.
2.3 COOLING TOWERS
Three cooling towers are located southwest of the Mechanical Building (see Figure
2- 6) and are supplied by a 2½-inch line as mentioned above. They are used to remove heat from the installation HVAC system.
The water used in these towers is treated with Spectrus® NX1106 (5-chloro-2-methyl-
4-isothiazolin-3-one and 2-methyl-4-isothiazolin-3-one solution) as a biocide and
OX103 (bromo-chloro-dimethylhydantoin tablets) as a disinfectant.
Figure 2-6 Naval Support Activity Orlando Cooling Towers
AH/BC Navy JV, LLC 2-10 Final, March 2021 134-014
2.4 WATER USE
POUs at NSA Orlando include the following:
• Computer room air handling units (cold only)
• Hand wash sinks
− Breakrooms
− Food preparation/cooking
− Restrooms
• Hose bibbs (cold only, mainly external plus roof penthouses)
• Ice machines (cold only)
• Cafetorium
• Food preparation/cooking
• Janitor’s closet mop sinks
• Kitchen equipment (food preparation/cooking and serving)
− Bain-marie (cold only)
− Carbonator (cold only)
− Coffee and hot-water urn (cold only)
− Drink dispensers (cold only)
− Steam cabinet
− Trash can washer
− Water wash hoods (hot only)
• Showers
− First-floor restrooms in Zone D and at the Zone B/C border
− Private restrooms (e.g., commanding officer [CO])
• Toilets (cold only)
• Water fountains (cold only)
2.5 OTHER WATER SYSTEMS
The NSA Orlando fire suppression system consists of an internal suppression system
(sprinklers) and a fire loop (hydrants), which are both supplied with water by the CFRP
AH/BC Navy JV, LLC 2-11 Final, March 2021 134-014
WTP. Water enters the installation via an 8-inch pipe interconnection at the Loop Road
North entrance, located north of the de Florez Complex and exits the installation at the
Loop Road West entrance adjacent to the domestic water system interconnection. The system is connected to a fire pump on the east side of the Mechanical Building and is not part of the NSA Orlando domestic water system.
The installation also has an irrigation system that is supplied by an on-site well. NSA
Orlando has a consumptive use permit with the St. Johns River Water Management
District for use of the well for this system.
A cooling tower system is supplied via connection to the domestic water system (see
Section 2.2). There are no whirlpools, spas, ornamental fountains, misters, atomizers, air washes, humidifiers, or other non-potable water systems or devices that release water aerosols at the installation.
AH/BC Navy JV, LLC 2-12 Final, March 2021
BUILDING WATER MANAGEMENT PLAN SECTION 3
NAVAL SUPPORT ACTIVITY ORLANDO, FLORIDA ANALYSIS OF HAZARD CONDITIONS
AH/BC Navy JV, LLC 3-1 Final, March 2021 134-014
ANALYSIS OF HAZARD CONDITIONS
Table 3-1 summarizes key hazardous conditions identified for the NSA Orlando do-mestic water system. For further details, please refer to the following sections and the building water quality site assessment study report developed by AH/BC.10
Table 3-1 Summary of Potential Areas of Water Quality Concern
Hazard Potential Area(s) of Concern
Legionella present throughout system The installation population is exposed to potential illness, including Legionnaires’ disease, from use of the system.
High cold-water temperatures (cross-connection)
A heated cold-water system improves conditions for Legionella growth and spread within the system.
Significant Legionella levels detected at POUs with carbon filters installed (i.e., ice machines, water fountains)
Carbon filters provide a favorable substrate for bacterial growth, including Legionella when the bacterium is present in the system.
Low population conditions (i.e., coronavirus disease 2019 [COVID-
19] pandemic personnel restrictions)
Low water use allows for longer periods of stagnant water within the system, which leads to the decay of free chlorine disinfectant residual and amplifies the potential for microbial growth.
Low hot-water temperatures (upstream and separate from booster heaters)
Hot-water systems unable to maintain system temperatures above 108 °F (42 °C) present optimal conditions for Legionella growth and spread within the system.
Spray aerators installed on majority of hand wash sinks
Spray aerator devices disperse aerosols into the air, increasing the susceptibility of Legionella inhalation when the bacterium is present in the system.
Lack of cold-water line insulation in areas with no temperature control
A lack of insulation makes the supply line in the Mechanical Building susceptible to increased temperatures during warm weather, improving conditions for Legionella growth and spread within the system.
Heat transfer to cold-water supply from booster heaters11
Heating of the cold-water system improves conditions for Legionella growth and spread within the system.
Dead legs from removed POUs The potential for microbial growth is amplified by stagnant water conditions.
10 AH/BC. Building Water Quality Site Assessment Study. NSA Orlando, Florida. December 2020. Pre-pared for NAVFAC SE under contract No. N62470-19-D-4001.
11 During the January 2021 site visit, it was determined that the hot-water booster pumps pushed heated water into the cold-water system through various cross-connections.
AH/BC Navy JV, LLC 3-2 Final, March 2021 134-014
Table 3-1 Summary of Potential Areas of Water Quality Concern (continued)
Hazard Potential Area(s) of Concern
Electronic faucets with thermostatic mixing valves
The tempered water can provide ideal conditions for microbial growth on surfaces within POU fixtures.
Showerhead membrane filters The tempered water can provide ideal conditions for microbial growth on the filters if not maintained properly.
3.1 LEGIONELLA
Legionella has been regularly detected within the NSA Orlando domestic water system since it was detected in November 2019. During the most recent sampling event on 1 and 2 September 2020 by AH/BC, L. pneumophila was detected in fourteen of the 40 samples collected, with the highest levels detected at the cooling towers and POUs with carbon filters (ice machine and water fountain). Two of those samples (both from the janitor’s closet mop sink at the first-floor restrooms in Zone D of the de Florez Com-plex) tested positive for L. pneumophila serogroup 1, which is responsible for most cases of Legionnaires’ disease.
During the September 2020 sampling, the system was observed to be continuously flushing from four POU fixtures:
• Cold-Water System
− Hose Bibb, de Florez Complex, Penthouse, Zone D, Room 4004
− Janitor’s Closet Mop Sink, Annex, Second Floor, Room 2045
• Hot-Water System
− Janitor’s Closet Mop Sink, de Florez Complex, Second Floor, Zone C, Room 2075
− Janitor’s Closet Mop Sink, de Florez Complex, Second Floor, Zone D, Room 2125
Although significant Legionella levels were detected throughout the water system, the rates were generally lower than those initially detected in November 2019, indicating that initial responses (i.e., shock chlorination, continuous flushing) were improving the situation (although further remedial action is still required).
AH/BC Navy JV, LLC 3-3 Final, March 2021 134-014
3.2 TEMPERATURE
According to ASHRAE Guideline 12-2020, the optimum temperature range for Le-gionella growth is between 85 and 108 °F (30 to 42 °C). Approximately half of the sam-ples collected in September 2020 (23 out of 40) had temperatures within this range.
Additionally, ASHRAE Guideline 12-2020 recommends maintaining hot-water temper-atures at or above 140 °F (60 °C) from water heaters and 120 °F (49 °C) throughout the entire system to control Legionella growth.
Several conditions are likely contributing to these inadequate temperature levels:
• There is a cross-connection between the cold- and hot-water systems at the Mechanical Building. During the January 2021 site visit, it was confirmed that the cold-water system heats up when hot-water booster pumps are in operation.
The pumps push heated water into the cold-water system at various cross-con-nections, which include the electric water heaters that are fed from the cold-water system without check valves. Other potential cross-connections may in-clude defective mixing valves.
• The heat exchanger in the Mechanical Building does not adequately increase the temperature of the hot-water system. While a supplemental electric boiler is installed to ensure that water temperature does not fall below 110 °F (43 °C), the system’s ability to reach sufficient hot-water temperatures is inadequate.
• The cold-water supply line entering and running through the Mechanical Build-ing is not insulated. The building does not have any air temperature controls (i.e., air conditioning). There may be other similar situations within the distribu-tion network (i.e., above the first-floor dropped ceiling).
• The in-line electric hot-water booster heaters with mixing valves are potentially causing convective heat transfer to the cold-water system during periods of low demand (i.e., COVID-19 population restrictions) and/or due to defective mixing valves.
3.3 OPERATIONAL CONDITIONS
There are several aspects of the current NSA Orlando domestic water system opera-tion that contribute to hazardous conditions:
• Significantly high levels of Legionella were detected downstream of carbon fil-ters (installed in ice machines, water fountains, and the CO lounge hand wash sink). The filters, which remove free chlorine residuals and serve primarily to improve water taste and odor, provide a favorable substrate for bacterial growth if not replaced frequently or removed altogether.
AH/BC Navy JV, LLC 3-4 Final, March 2021 134-014
• Significant periods of low water usage (i.e., COVID-19 population restrictions) increase the potential for stagnant water to be present throughout the system.
Under stagnant conditions, water temperatures adjust to ambient conditions (if not insulated) and free chlorine disinfectant residual begins to decay. This cre-ates favorable conditions for microbial growth and spread within the system.
• The majority of hand wash sinks in restrooms and lounges, as well as the food preparation/cooking area, have spray aerators installed. These devices dis-perse aerosols into the air, increasing the susceptibility of Legionella inhalation when present in the system. Figure 3-1 shows examples of faucet aerator de-vices and their impact on aerosol formation (from Figure 4-4 in Management of Legionella in Water Systems by the National Academy of Sciences, Engineer-ing and Medicine).12
− Most of these faucets are also electronic faucets with thermostatic mixing valves that provide water temperatures within the optimum growth range for Legionella. Additionally, they receive limited use and are difficult to flush.
• NSA Orlando personnel confirmed that there are dead legs throughout the sys-tem. This is due to capping of service lines during the removal of inactive POU fixtures instead of removing the service lines up to their connection with a main system line. These dead legs allow for stagnant water conditions.
Figure 3-1 Faucet Aerators
12 National Academy of Sciences, Engineering, and Medicine. Management of Legionella in Water Sys-tems. 2020. https://www.nap.edu/catalog/25474/management-of-legionella-in-water-systems. Accessed 3 February 2021.
https://www.nap.edu/catalog/25474/management-of-legionella-in-water-systems
BUILDING WATER MANAGEMENT PLAN SECTION 4
NAVAL SUPPORT ACTIVITY ORLANDO, FLORIDA CONTROL MEASURES AND MONITORING
AH/BC Navy JV, LLC 4-1 Final, March 2021 134-014
CONTROL MEASURES AND MONITORING
Table 4-1 summarizes recommended control measures, monitoring strategies, and corrective actions for identified hazards. Supporting these recommendations are SOPs in Appendices A through C that provide more details on implementation for the NSA
Orlando building water management team. These SOPs cover the following:
• Cold- and hot-water system monitoring (Appendix A)
• Cold- and hot-water system flushing (Appendix B)
• Dead leg management (Appendix C)
Additional applicable SOPs are listed in Appendices D and E to cover all applicable preventive measures required per Section 7 of ANSI/ASHRAE Standard 188-2018, broken down into the following categories:
• System start-up and shutdown (Appendix D, Section 4)
• System maintenance (Appendix D, Section 5)
• Water treatment (Appendix D, Section 6)
• Contingency response plan (Appendix D, Section 7)
• Cooling towers (Appendix E)
Note that all of these measures must be considered where appropriate, even if they are not directly linked to the hazards identified in Table 4-1 and the appendices of this
WMP. Unless stated otherwise in Table 4-1 and/or the SOPs in the appendices, the responsible party for activities in this section will be the NSA Orlando PWD.
Some preliminary steps may be appropriate to facilitate the execution of this WMP:
• Ensure that hot-water source temperatures are at least 140 °F (60 °C)
• Eliminate cross-connections between the cold- and hot-water systems
• Install automated flushing equipment at cold- and hot-water system locations representative of both systems (see Appendix B)
− The setups shall consist of a water timer, flow meter, and dechlorination (cold only)
AH/BC Navy JV, LLC 4-2 Final, March 2021 134-014
− Discharges for the cold-water system setups in the roof penthouses shall be directed to stormwater drainage (i.e., roof drainage)
• Install temperature gauges at the booster heaters and hot-water return RPZ
BFP
• Remove and/or maintain (per manufacturers’ recommendations) carbon filters installed at ice machines and water fountains
• Insulate cold-water lines in areas with no temperature control
• Remove hand wash sink spray aerator devices and/or replace with laminar flow devices
• Replace electronic faucets with thermostatic mixing valves at hand wash sinks (preferably one per restroom at minimum)
• Ensure free chlorine residual levels at the POE are at least 0.5 mg/L
AH/BC Navy JV, LLC 4-3 Final, March 2021 134-014
Table 4-1 Summary of Control Measures
Hazard Control Measure(s) Control Location(s) Control Limit(s) Responsible
Party Monitoring Verification Frequency
Corrective Action(s)
SOP(s)
Legionella present throughout system
System flush (including installation of automated flushing equipment) and disinfection; review of temperature conditions throughout system
Throughout
Decreased Legionella conditions until no further action required per Table 1-1
NSA Orlando
PWD
Daily free chlorine measurements at the POE; weekly free chlorine measurements at the hot-water return RPZ BFP and cold-water POUs (janitor’s closet mop sinks) in Rooms 3012 and 3060 of the de Florez Complex and Room 2045 in the
Annex; daily temperature readings at the hot-water return RPZ BFP with newly installed gauge; weekly temperature readings at third-floor janitor’s closet mop sink at the north end of Zone B (Room 3012)
Log review by supervisor
Weekly reviews Flushing and disinfection; CFRP correspondence
Appendices A (monitoring) and B (flushing)
High cold-water temperatures (cross-connection)
Identify and remove cross-connections
Throughout No cross-connections NSA Orlando
PWD
Weekly readings at third-floor janitor’s closet mop sink at the north end of Zone B (Room 3012) Log review by supervisor Quarterly reviews
Removal of cross-connection
Appendix A (monitoring)
Flush all cold-water POU fixtures for 5 minutes
All cold-water POU fixtures
Cold-water temperature less than 25 °C (77 °F) at distal POU fixtures
Janitorial staff Weekly readings at third-floor janitor’s closet mop sink at the north end of Zone B (Room 3012) Log review by supervisor Quarterly reviews Flushing
Appendices A (monitoring) and B (flushing)
Significant Legionella levels detected at POUs with carbon filters installed (i.e., ice machines, water fountains)
Remove or replace carbon filters
All POU fixtures with carbon filters installed
No carbon filters or adherence to filter replacement schedule
Base Operating Services
(BOS)
contractor
Microbiological analysis at affected POUs Log review by supervisor Semiannual reviews
Removal or replacement of filters
Appendix F
(WMP
validation)
Low population conditions (i.e., COVID- 19 pandemic personnel restricitons)
Flush all POU fixtures for 5 minutes weekly (single flush for toilets) All POU fixtures
Free chlorine residual greater than 0.2 mg/L at distal POU fixtures
Janitorial staff
Daily free chlorine measurements at the POE; weekly free chlorine measurements at the hot-water return RPZ BFP and cold-water POUs (janitor’s closet mop sinks) in Rooms 3012 and 3060 of the de Florez Complex and Room 2045 in the
Annex
Log review by supervisor
Monthly reviews Flushing Appendices A (monitoring) and B (flushing)
Low hot-water temperatures (upstream and separate from booster heaters)
Raise hot-water source temperature at heat exchanger and booster heaters to 140 °F (60 °C)
Heat exchanger and booster heaters
Heat exchanger effluent water greater than 140 °C (60 °C)
BOS
contractor
Weekly temperature readings with existing and newly installed gauges
Log review by supervisor
Quarterly reviews Adjust heat exchanger temperature
Appendices A (monitoring) and B (flushing)
Flush the hot-water return line until it reaches 125 °F (52 °C) at the RPZ BFP
Hot-water return RPZ BFP at the
Mechanical Building
Hot-water temperature greater than 125 °F (52 °C) at the hot-water return RPZ
BOS
contractor
Daily temperature readings with newly installed gauge Log review by supervisor Quarterly reviews Flushing
Flush all hot-water POU fixtures for 5 minutes at least weekly during periods of low building occupancy
All hot-water POU fixtures
Hot-water temperature greater than 120 °F (49 °C) at distal POU fixtures
Janitorial staff Weekly temperature readings at third-floor janitor’s closet mop sink at the north end of Zone B (Room 3012) Log review by supervisor Quarterly reviews Flushing
Spray aerators installed on majority of hand wash sinks
Remove spray aerator devices and/or replace with laminar flow devices
All POU fixtures with device installed
No spray aerators
BOS
contractor Observe changes during removal/replacement
Work order review
Project initiation and completion
Removal or replacement of spray aerators
N/A
Lack of cold-water line insulation in areas with no temperature control
Install pipe insulation around cold-water lines
Mechanical Building and other areas with no temperature control
Insulated cold-water lines
NSA Orlando
PWD
Observe changes during installation Work order review Project initiation and completion
Installation of insulation
N/A
AH/BC Navy JV, LLC 4-4 Final, March 2021 134-014
Table 4-1 Summary of Control Measures (continued)
Hazard Control Measure(s) Control Location(s) Control Limit(s) Responsible
Party Monitoring Verification Frequency
Corrective Action(s)
SOP(s)
Heat transfer to cold-water supply from booster heaters
Install check valves on cold-water intake lines
Each booster heater
Check valves installed
BOS
contractor
Observe changes during installation Work order review Project initiation and completion
Installation of check valves
N/A
Flush all hot-water POU fixtures served by heaters for
5 minutes at least weekly during periods of low building occupancy
Cold-water supply temperature less than 25 °C (77 °F) Janitorial staff Weekly temperature readings at booster heater supply lines
Log review by supervisor
Quarterly reviews (monthly during extended low-population events)
Flushing N/A
Dead legs from removed POUs
Establish plan for decommissioning of dead legs and inactive POU fixtures
Areas with removed/inactive
POU fixtures No dead legs
NSA Orlando
PWD
Observe changes during removal Work order review Project initiation and completion
Removal of dead legs
Appendix C (dead leg management)
Electronic faucets with thermostatic mixing valves at hand wash sinks
Replace electronic faucets with two-handled faucets
All electronic faucet POU fixtures
No electronic faucets with mixing valves
BOS
contractor
Observe changes during replacement Work order review Project initiation and completion
Replacement of electronic faucets with mixing valves
N/A
Showerhead membrane filters
Replace filters regularly All showerhead POU fixtures Manufacturer’s recommendations
BOS
contractor Observe changes during replacement
Log review by supervisor
Quarterly reviews Replacement of filters Appendix D (Section 5.3)
AH/BC Navy JV, LLC 4-5 Final, March 2021 134-014
4.1 AUTOMATED FLUSHING
For the cold-water system automated flushing SOP listed in Appendix B, note that automated flushing equipment are to be installed and monitored to reduce sanitary service charges incurred by flushing activities. The equipment shall consist of a water timer, flow meter, and dechlorination. The CFRP sanitary sewer charges are based on metered water consumption.13 Flushed water from the penthouse hose bibbs
(cold- water system) will be discharged, after dechlorination, into the stormwater collection system. The recorded water consumption for flushing can then be deducted from the CFRP metered water use and would not incur sanitary service charges.
The automated flushing equipment setup for the hot-water system shall consist of a flow meter and solenoid valve connected to a timer. Flushed water from these setups will be discharged into the sanitary collected system (i.e., sink/floor drains).
4.2 SHOWERHEAD FILTERS
All showerhead POU fixtures that are part of the NSA Orlando domestic water system have membrane filters installed for removal of microorganisms such as Legionella. As discussed in the miscellaneous SOPs in Appendix D, these membranes should be replaced per manufacturers’ recommendations. These filters shall remain until the building WMP has been implemented, verified, and validated (see Section 5 and subsequent appendices).
13 $4.20 and $6.80 per 1,000 gallons for water and sewer, respectively
AH/BC Navy JV, LLC 4-6 Final, March 2021
BUILDING WATER MANAGEMENT PLAN SECTION 5
NAVAL SUPPORT ACTIVITY ORLANDO, FLORIDA VERIFICATION AND VALIDATION
AH/BC Navy JV, LLC 5-1 Final, March 2021 134-014
VERIFICATION AND VALIDATION
Per Section 6.2.8 of ANSI/ASHRAE Standard 188-2018, the building water manage-ment team must establish procedures to confirm that this building WMP is being imple-mented as designed (verification) and whether the recommended control measures listed in Section 4 are successfully controlling the hazardous conditions identified (val-idation).
Verification activities are detailed in Table 4-1 and the monitoring SOP in Appendix A.
Validation activities are detailed in…