N6945022R0002_JL11_ GPI Responses.pdf

PDF 757 KB Posted

Attached to
Base Operations Support (BOS) Services at Naval Construction Battalion Center (NCBC) Gulfport, MS and Outlying Areas
Solicitation number
N6945022R0002
Issued by

About this file

This request for proposal solicits base operations support services at Naval Construction Battalion Center Gulfport, Mississippi and various outlying areas. Services required include facility management, facility investment, custodial services, grounds maintenance and landscaping, and wastewater management. Proposals are due by January 6, 2022 with an anticipated award date in March 2022. The contract will have one base year and four option years and utilize both fixed-price and cost-reimbursement contract line item numbers. The solicitation is set aside for small businesses and involves the Department of the Navy and Naval Facilities Engineering Command. The incumbent contractor is referenced but not named. Questions from potential offerors are included as an appendix.

View the file

Other files

File Type Posted
N6945022R0002_SectionC_Amend0006.pdf PDF
N6945022R0002_J-0200000-14_ELINs_Amend0006.xlsx XLSX spreadsheet
N6945022R0002_Ament0006.pdf PDF
N6945022R0002_Ament0005.pdf PDF
N6945022R0002_J-0200000-14_ELINs_Amend0004.xlsx XLSX spreadsheet
N6945022R0002_SectionC_Amend0004.pdf PDF
N6945022R0002_JL11_ GPI Responses_Amend0004.pdf PDF
N6945022R0002_SectionJ_Amend0004.pdf PDF
N6945022R0002_J-0200000-16-03_DBA MS20210049 Modification 5.pdf PDF
N6945022R0002_Ament0004.pdf PDF
N6945022R0002_J-0200000-16-03_DBA MS20210050 Modification 4.pdf PDF
N6945022R0002_J-0200000-16-03_DBA MS20210052 Modification 5.pdf PDF
N6945022R0002_J_150100_04_Locksmith PM Job Plan.pdf PDF
N6945022R0002_J_1502000_11_05_STI Inspection Report.pdf PDF
N6945022R0002_J_150100_07_Locksmith Tickets.xlsx XLSX spreadsheet
N6945022R0002_J_150100_05_High Security Locks.xlsx XLSX spreadsheet
N6945022R0002_JL3__AMAG Form_Amend0003.xls XLS spreadsheet
N6945022R0002_Ament0003.pdf PDF
N6945022R0002_Section J Inventories Amend0003.xlsx XLSX spreadsheet
N6945022R0002_J-1503050-04-02_Stennis Site Map Amend0003.pdf PDF
N6945022R0002_J-0200000-17-02 Amend0003.xlsx XLSX spreadsheet
N6945022R0002_J_1502000_11_04_STI Inspection Recommendations.pdf PDF
N6945022R0002_J_150100_06_Lock PM Bldg List.xlsx XLSX spreadsheet
N6945022R0002_J-1503050-04-01_NCBC Gulfport Site Map Amend0003.pdf PDF
N6945022R0002_JL1_Labor Hours_Amend0003.xlsx XLSX spreadsheet
N6945022R0002_J_150100_08_Locksmith_Shop_Inventory.xlsx XLSX spreadsheet
N6945022R0002_SectionJ_Amend0003.pdf PDF
N6945022R0002_J-0200000-14_ELINs_Amend0003.xlsx XLSX spreadsheet
N6945022R0002_SectionC_Amend0003.pdf PDF
N6945022R0002_Ament0002.pdf PDF
N6945022R0002_J-0200000-16-03_DBA MS20210049 Modification 4.pdf PDF
N6945022R0002_SectionJ_Amend0001.pdf PDF
N6945022R0002_JL9_SiteVisitTourMaps.pdf PDF
N6945022R0002_J-0200000-16-03_DBA MS20210050 Modification 3.pdf PDF
N6945022R0002_J-0200000-16-03_DBA MS20210052 Modification 4.pdf PDF
N6945022R0002_SectionF_Amend0001.pdf PDF
N6945022R0002_JL10_SiteVisitAttendees.pdf PDF
N6945022R0002_JL4_Site Visit Itinerary_Amend0001.pdf PDF
N6945022R0002_SectionC_Amend0001.pdf PDF
N695022R00002_JL8_SiteVisitBrief.pdf PDF
N6945022R0002_Ament0001.pdf PDF
N6945022R0002_JL6_CNRSE 5200-1.pdf PDF
N6945022R0002_JL3__AMAG Form.xls XLS spreadsheet
N6945022R0002_J-0200000-06-02_NAVFAC Asset Reference Value List.xlsx XLSX spreadsheet
N6945022R0002_J-0200000-03-05_Equipment Changeover Spec Sheet.pdf PDF
N6945022R0002_SectionF.pdf PDF
N6945022R0002_J-0200000-16-02_SCA 1968-0005 Rev 67.pdf PDF
N6945022R0002_J-0200000-05-02_NAVFAC Service Provider Reference Value List.xlsx XLSX spreadsheet
N6945022R0002_SectionC.pdf PDF
N6945022R0002_SectionJ.pdf PDF
Show 40 more

Latest 50 of 77 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N6945022R0002 Gulfport BOS

GOVERNMENT PRE AWARD INQUIRY FORM

Page Section Para.

11/5/2021

ELINs

Ref. Attachment J-0200000-14 ELINS for N-RW CLINs. Line X700- 702 references "Composite Labor Hours" - please define what the Government means in reference to these line items.

11/5/2021

ElLINs

Ref. Attachment J-0200000-14 ELINS, N-RW CLINs. Lines X700- 703 referencs "Controls Specialist". There is no labor category in the CBA, SCA WDs or DBA WDs incorporated into the solicitation.

Please clarify this labor category.

11/5/2021

ELINs

Ref. Attachment J-0200000-14 ELINS, N-RW CLINs. Is the offeror to insert unit prices based on their cost to provide the line item services, which will then be uploaded to FedMall for future ordering? Yes. Refer to Section H.2 of the RFP.

11/5/2021

ELINs

Ref. Attachment J-0200000-14 ELINS, N-RW CLINS. Are the prices for the listed services currently available in FedMall and are offerors expected to input those unit prices in the line items? If so, how are offerors without access to FedMall expected to obtain those prices?

No. The offeror is to propose their price for the work identified in the applicable ELIN.

11/5/2021

ELINs

Ref. Attachment J-0200000-14 ELINS, N-RW CLINS. If offerors are to input unit prices based on the offeror's cost to provide the line item services, will there be an opportunity to update the pricing annually to conform to Wage Determination or CBA increases in wages?

11/5/2021

ELINs

Ref. J-0200000-14 ELINS, N-RW CLINS. Line items x721 and 722 reference "DoDeMal". Please confirm that the reference should be FedMall.

Yes they should reference FedMall. This will be corrected in an amendmendment. 0003

Amend No.

REFERENCEQuestion No.

QUESTION GOVERNMENT RESPONSEDate Received

SOURCE SELECTION INFORMATION - SEE FAR 2.101 AND 3.104

GOVERNMENT PRE AWARD INQUIRY FORM

Page Section Para.

Amend

No.

REFERENCEQuestion

No.

QUESTION GOVERNMENT RESPONSEDate Received

11/15/2021

2 100000 1.1

Under the Annexes listed in this paragraph, 1503020 Pest Control is listed as part of the requirement however, there is no reference to 1503020 in Section C, Section F, or Section J. Is 1503020 a part of this contract?

Sub-annex 1503020 Pest control is not included in this contract; this will be corrected in a forthcoming admendment. Herbicide requirements previously specified under pest control are now contained in Sub-annex 1503050 Grounds Maintenance and Landscaping. 0003

11/15/2021

ELINs A018

Under ELIN018 Sub-ELIN A018AG, A018AH, and A018AK there is no inventory listed in Attachment J-1502000-06 for Funding Activity EXWC. Please provide the inventory so offerors can determine manpower/costing for these sub-ELINs.

The NGIS boiler in B314 listed on Attachment J- 1502000-06-01 has been removed and is now provided in Attachment J-1502000-06-05. The EXWC boiler in B400 listed on Attachment J-1502000-06-01 has been removed and is now provided in Attachment J-1502000- 06-06. The table in Attachment J-1502000-06 has been updated accordingly. These changes will be provided in a forthcoming amendment. 0003

11/15/2021

J-1502000-04-05

In the inventory for Stennis Space Center, Kitchen Exhaust Hoods are included. Are there also grease traps associated with the kitchen facility? If so, is it the responsibility of the contractor to clean the grease traps? If so, What are the sizes of the grease traps and how often do they require pumping? Grease traps are not part of this contract.

GOVERNMENT PRE AWARD INQUIRY FORM

Page Section Para.

Amend

No.

REFERENCEQuestion

No.

QUESTION GOVERNMENT RESPONSEDate Received

11/16/2021

18 C-020000 2.7.1.3

This paragraph states that the contractor must "Provide a Safety oversight team that includes a minimum of one Competent Person at each project site to function as the Site Safety and Health Officer (SSHO).

The paragraph goes on to state that the SSHO "shall have completed five years of satisfactory experience in preparing and enforcing safety programs ..."

Please clarify what is meant as "project site" in the context of this paragarph.

Also, please clarify what is meant as "Competent Person".

11/18/2021 1 RFP 1

To support the small business's proposing on this opportunity and in light of ongoing events as a result of COVID and the holiday season, will the Government extend the due date of this opportunity to January 15th or after?

The proposal due date has been extended to Thursday, January 6th. 0003

11/18/2021 66 & 70 L.2 & L.14 2

Will the Government allow for softcopy/digital submittals, in lieu of hardcopy proposal files, reducing the need for additional travel or shipping, and reducing any risk associated with COVID and multiple parties handling these documents?

The requirement remains unchanged. Hard copy proposals are required.

11/18/2021 N/A N/A N/A

Given the secure nature of the various work locations and in an effort to ensure the Government receives the highest overall value, will the Government provide a listing of current and approved vendors and/or subcontractors supporting this program with base access?

All current vendors and/or subcontractors supporting this program are managed by the BOS Contractor. This information will not be provided by the Government.

11/18/2021

40 C

2.14.1 - Recurring Work Preparation of

Proposals

Please verify that contractors shall price additions or deletions to the Recurring Work requirements post award using the unit prices bid for Non-Recurring Work Unit Priced Tasks (UPTs).

GOVERNMENT PRE AWARD INQUIRY FORM

Page Section Para.

Amend

No.

REFERENCEQuestion

No.

QUESTION GOVERNMENT RESPONSEDate Received

11/18/2021

40 C

2.14.1 - Recurring Work Preparation of

Proposals

We recommend adding separate ELINs for contractors to provide unit prices for pricing additions and deletions to the recurring work requirements post award. For example, if a building is added to the contract that requires recurring custodial services, it would be easier for contractors to provide a unit price for the various COLs related to custodial services.

11/18/2021

Mississippi sales tax levies a 3.5% contractor's tax on all construction, renovation or repair of non-residential, real property when the total contract price or compensation received exceeds $10,000. If the contract exceeds $75,000 in scope or if the contractor is from another state, the contractors tax must be paid before work begins. Please confirm this applies to all Recurring and Non-recurring work for this contract.

11/18/2021

I - Contract

Clauses Is 52.223-99, Ensuring Adequate COVID-19 Protocols for Federal Contractors applicable to this RFP?

11/18/2021

65 C

3.2.8 - Micro-grid Power Generation

Please verify that the micro-grid system is currently maintained under a separate contract from the BOS contract.

11/18/2021

64 C

3.2.7 - Facility Related Control Systems (FRCS) Is this a new requirement to the existing contract?

11/18/2021

J-0200000-

14_ELINS

Sub-Annex 1503050- Grounds Maintenance and Landscaping

Will the Government provide an ELIN/Sub-ELIN for Grounds Maintenance Service Orders unit price per Spec Item 3.4 in Section C?

There are no Grounds Maintenance Service Orders under this contract. Section C will be amended to delete this spec item. These services are covered under the non-recurring work ELINS. 0003

GOVERNMENT PRE AWARD INQUIRY FORM

Page Section Para.

Amend

No.

REFERENCEQuestion

No.

QUESTION GOVERNMENT RESPONSEDate Received

11/18/2021

J-1503010-07 Custodial Inventory

Work Areas column What is considered "All Admin Areas"?

11/18/2021

J-1503010-07 Custodial Inventory

Work Areas column

What is the difference between "Entire Bldg" and "All Admin Areas"?

11/18/2021 ELINs A001 -

A018

Please provide total square feet as well as cleanable square feet for each building associated with this solicitation which either require facility investment or custodial services.

11/18/2021

Section J-503050-

The maps provided in J-1503050-04 only identify mowing requirements by acreage. We respectfully request that the Government provide more detailed grounds and landscaping workload data to include items that mirror the actions found in the referenced attachment to include but not limited to linear footage for edging, quantity and size of xeriscape areas, quantity and size of plant beds, quantity of shrubs and hedges and quantity of ornamental trees.

GOVERNMENT PRE AWARD INQUIRY FORM

Page Section Para.

Amend

No.

REFERENCEQuestion

No.

QUESTION GOVERNMENT RESPONSEDate Received

11/18/2021

Section C- 0100000 1.7

The paragraph states that "all facilities, systems and assets identified in this contract shall be accepted by the contractor in “AS-IS” condition. The contractor is fully responsible for all work up to and including the limits of liabilities specified”. How can any offeror other than the incumbent prepare an equitable proposal without know what the condition of systems are? Non-recurring work has a limit of liability of $2500 in direct material cost. Not knowing the status of systems puts offerors at a decided disadvantage while at the same time potentially allows the incumbent the ability to withhold repairs in order to save money. Respectfully request that repairs determined during a change on contractor allows for the incoming contractor to bill for work performed.

11/18/2021

Section C- 0200000 2.3.2

How much new equipment is anticipated that may result in the training of contractor personnel? Should contractor personnel be taken off-line to train, there will be a required replacement necessary to keep up with work requirements.

11/18/2021

Section C- 0200000 2.3.3.2

Please identify what “The Charter” partnership agreement includes.

11/18/2021

Section C- 0200000 2.4.2

The third paragraph states that Janitorial and refuse collection services for the facilities shall be provided by the contractor.

Does the contractor have to establish their own refuse collection agreement with a trash company to accommodate their offices?

GOVERNMENT PRE AWARD INQUIRY FORM

Page Section Para.

Amend

No.

REFERENCEQuestion

No.

QUESTION GOVERNMENT RESPONSEDate Received

11/18/2021

Section C- 0200000 2.4.4

Please clarify what exactly the contractor needs to provide to accommodate the statement that says" Provide and maintain backflow prevention devices on connections to domestic water lines and electrical transformer provisions on connections to electrical lines"

11/18/2021

Section C- 0200000 2.6.11

The paragraph references placing new bar codes on newly installed or replaced equipment. Is there Government furnished bar code equipment as we do not see any listed?

11/18/2021

Section C- 0200000 2.9.5

The second paragraph states that “written documentation of the last weight test of the crane and all related weight handling equipment shall be maintained on site.” This reads as if the contractor is responsible for owning a crane. If this was a rental unit, there is no guarantee that the same machine would be provided each time one was sent thereby not allowing for any continuity regarding the weight test paperwork. Please clarify.

11/18/2021

Section C- 1502000 1.1

The building systems (including FRCS) section of this paragraph includes fire protection however, we do not see any fire protection equipment listed in the Section J Inventories Listings.

Are the fire alarm systems a part of this contract?

Fire Protection systems are not a part of this contract.

This will be corrected in a forthcoming admendment. 0003

11/18/2021

Section C- 1502000 2.3.2

Are there any Buildings and/or facilities that are designated as historical sites?

There are no historical facilities or sites on NCBC Gulfport or its Special Areas that are the responsibility of the Navy or in this contract.

11/18/2021

Section C- 1502000 3.2

Please clarify the difference between recurring work and preventative maintenance as they have different levels of liabilities.

GOVERNMENT PRE AWARD INQUIRY FORM

Page Section Para.

Amend

No.

REFERENCEQuestion

No.

QUESTION GOVERNMENT RESPONSEDate Received

11/18/2021

Section C- 1502000 3.1

This paragraph states that both recurring and non-recurring work have a liability limit of 32 direct hours or $2500. The examples that follow read as if the liability limit should be “32 direct hours and $2500” as both numbers come into play regarding a possible task order. Please clarify.

11/18/2021

Section C- 1502000 3.2.1

The paragraph states: “Once per year the Contract shall clean diffusers, grills, registers and other associated equipment as part of the PM program.” We do not see a listing that provide the associated quantities. Please clarify.

11/18/2021

Section C- 1502000 3.2.3

The paragraph states “Inspection dates listed on Attachment J- 1502000-07 Inventory are the latest annual inspection dates.”

However, the last inspection dates listed in the document for all VTE show 6/20/2019 virtually 2.5 years ago. Please clarify either an error in the reported dates and/or a failure to comply with the PWS requirements.

The most recent certification of all elevators is June 2021, except the one at the BOB which is under repair.

The inspection dates have been updated in the attachment. 0003

11/18/2021

Section C- 1502000 3.2.3

The information provided in Attachment J-1502000-07 is insufficient to accurately price the required work. Please provide whether these systems are electric or hydraulic.

11/18/2021

Section C- 1502000 3.2.8

As this is a new requirement we respectfully request that the Government provide a copy of the PWS that Mississippi Power is working with in order to allow offerors a better understanding of what is involved with this type of system.

GOVERNMENT PRE AWARD INQUIRY FORM

Page Section Para.

Amend

No.

REFERENCEQuestion

No.

QUESTION GOVERNMENT RESPONSEDate Received

11/18/2021

Section C- 1502000 3.3.2

This paragraph is somewhat confusing as it states that "the Contractor shall perform all inspections and tests for certification in the presence of a Government provided inspector." Are we correct that this does not prevent the contractor from having to have a certified/licensed elevator technician in place to perform the work. The second paragraph also makes it appear that the Government determines when this work is done. Please clarify.

11/18/2021

Section C- 1502000 3.3.2

This section does not appear as detailed as paragraph 3.2.3.

Which section prevails?

11/18/2021

Section C- 1503050

Request that the Government provide topographical maps that show the contours of the areas to be mowed around drainage easements and/or ponds and lakes as these areas may require specialized equipment.

11/18/2021

Section C- 1503050 2.3.4

This paragraph states that “Use of powered equipment is prohibited in operational areas listed on Site Maps provided in J- 1503050-04.” We do not see on the referenced maps where these areas are identified. Please clarify.

11/18/2021

Section C- 1503050 3.2.2

The paragraph states that “The Contractor shall maintain a 30 feet clear zone on the inside of the fencing and where existing maintain a 20 feet clear zone on the outside of the fencing.” Can growth inhibitors be used to control the rate of growth within these areas?

45 11/18/2021 1 1 1

Will the Government provide a 30 day extension to allow bidders appropriate time to develop their solutions and provide accurate pricing to the high level of dtail required by this solicitation? Refer to GPI #11.

GOVERNMENT PRE AWARD INQUIRY FORM

Page Section Para.

Amend

No.

REFERENCEQuestion

No.

QUESTION GOVERNMENT RESPONSEDate Received

11/19/2021 N/A N/A N/A

Can additional time or another opportunity be provided to submit questions? Since the site visit concluded on 11/17/21 and the questions are due on 11/19/21, the government has not provided enough time to properly go over the mutliple files, site visit notes to develop questions that will clarify issues concerning the bid.

An extenstion was granted in Amendment 0002.

11/19/2021 N/A N/A N/A

Can the contractor store equipment (lawnmowers, blowers, supplies, etc) at the large storage shed (Bldg Z) located at the Lakeside property.?

There are no Government furnished facilities at Lakeside.

11/19/2021 N/A 3.2.8 150200-C N/A Is the contractor's limit of liability, per battery, or does the government intend to apply a single limit of liability for instances where multiple batteries require replacement?

The limit of liability appies individually to each PM action.

11/19/2021 N/A N/A N/A

What is the average occupancy rate at Lakeside on a monthly basis?

11/19/2021 N/A N/A N/A

What are the current COL standard per location for grounds on the current contract?

11/19/2021 N/A Sec C- 1503010 3.1.1.2 Please clarify that the contractor is responsible for having a third party service provider pick-up and remove recycling from exterior collection sites and moved to an offsite recycling center.

11/19/2021 N/A ELIN Sheet and J-

1503050-04 Stennis Site Map

N/A

On Row 80 of the ELIN worksheet, grounds maintenance and landscaping for improved grounds is required at the WARCOM Range (Stennis Space Center). When you look at the Stennis Site Map, there in no reference made to theWARCOM Range. In addition, I beleive the WARCOM range is not even shown on the map.

The small arms range is not part of the grounds maintenance requirement in this contract. The ELINS have been revised from WARCOM Range to NSWC to align with the Stennis Site Map. 0003

GOVERNMENT PRE AWARD INQUIRY FORM

Page Section Para.

Amend

No.

REFERENCEQuestion

No.

QUESTION GOVERNMENT RESPONSEDate Received

11/19/2021 N/A J-1503050-04 Stennis Map

On the Stennis Site Map Legend, it show a light green color titled Lawn Care (COL 2) - 2 acres. But if you look at the map, the light green color is a lot more than 2 acres. Does the map and legend need to be corrected and reissued?

The Stennis Site Map Legend Acreage has been revised from 2 to 8.56 acrees and will be included in a forthcoming amendment. 0003

11/19/2021 10 Section C - 0200000

2.7.1.3

Per this section it states, "Provide a Safety oversight team that includes a minimum of one Competent Person at each project site to function as the Site Safety and Health Officer (SSHO). The SSHO or an equally-qualified Designated Representative/alternate shall be on-site at all times when work is being performed to implement and administer the Contractor's safety program and government-accepted Accident Prevention Plan ". Is there a requirment to provide a on-site SSHO at every outlying location associated with this contract? Or is having one (1) on-site SSHO on this contract sufficient?

11/19/2021 48 Section C - 1501000

3.1 Does the current FRCS system(s) have dedicated laptop computers for monitoring and troubleshooting? If so, are they government owned or provided by the current contractor?

The contractor shall provide the required laptops.

11/19/2021 48 Section C - 1501000

3.1

If the current contractor is providing laptops to monitor the FRCS systems, will they remain in place if the contract is awarded to someone else? Leaving the current laptops in place makes sense since they have already meet all American Act and government cybersecurity requirements.

The contractor shall provide the required laptops.

11/19/2021

Attch J-200000-

17-2 FRCS

Cybersecurity R&R

Within this document colums C & D have the letters "S" and "L" in them. What do those letters mean? No legend was provided.

The letter "L" denotes Lead responsibility and "S" denotes supporting role. Attachment J-0200000-17-2 has been revised to include a key and will be provided in a forthcoming amendment. 0003

GOVERNMENT PRE AWARD INQUIRY FORM

Page Section Para.

Amend

No.

REFERENCEQuestion

No.

QUESTION GOVERNMENT RESPONSEDate Received

11/19/2021 79 of 83 RFQ M.3

Can the government please provide more guidance than what is provided in the RFQ for what is required in the BOE? Besides Attachment JL-1 Labor Hours worksheet, we are unclear what is to be provided in the BOE narrative. The JL-1 worksheet lays out all labor hours by ELIN and tech specification. We are unclear what further information is required. On past NAVFAC bids, only the JL-1 Labor Hours worksheet was required.

11/19/2021

J-1502000-06-03

Statement: The title of the attachment is BOILER AND UPV INVENTORY AND CERTIFICATION DATES (STENNIS & BOB). There is no ELIN for boilers and unfired Pressure vessels for Stennis Space Center, Stennis, MS (NAVO BOB).

Question: Are we to cost the work for this equipment in ALIN A007AE and A007AH?

There are no Boiler and UPV requirements at NAVO BOB. The Boiler Inventory Title has been revised to reflect this correction and will be provided in a forthcoming amendment. 0003

11/19/2021

J-1502000-06-04

Statement: The title of the attachment is BOILER AND UPV INVENTORY AND CERTIFICATION DATES (BUMED). There is no ELIN identified at specifically for BUMED.

Question: Under which ELIN(s) should this equipment be priced?

Navy BUMED requirements are now listed as Defense Health Agency (DHA). The invetory Title has been revised to reflect this change and will be provided in a forthcoming amendment. 0003

GOVERNMENT PRE AWARD INQUIRY FORM

Page Section Para.

Amend

No.

REFERENCEQuestion

No.

QUESTION GOVERNMENT RESPONSEDate Received

11/19/2021

J-1502000-04

Statement: Note 1 at the bottom of the sheet states, “Note 1:

The assets highlighted in green are shown for inventory purposes and/or are dummy assets that control the PM schedules on other assets, but do not require PM's of their own.” There is also a cell to the left of the note that is highlighted in green. There are two equipment lines that are highlighted in the same color green and several other lines highlighted in a different shade of green. In addition, there are several lines highlighted in yellow.

Questions: Are we to exclude all equipment highlighted in any color green from the pricing according to the note? Does the yellow highlight have some significance that could affect pricing?

All equipment highlighted in green is to be excluded.

The inventory has been revised to make the shading consistent. Yellow denotes changes from previous versions and has been removed. These changes will be provided in a forthcoming amendment. 0003

11/19/2021

48 C 3.1

How many existing devices are in alarms are programmed into the BAS?

63 11/19/2021 48 C 3.1 How many devices are in manual or forced override?

64 11/19/2021 48 C 3.1 How many devices have communication loss?

11/19/2021

C-1503050 and J-

020000-14 ELINS

3.4 Section C -1503050 Grounds Maintenance and Landscaping refers to Spec Item 3.4 Grounds Maintenance Service Orders.

There does not appear to be a place to price grounds maintenance service Orders

There are no Grounds Maintenance Service Orders under this contract. Section C will be amended to delete this spec item. These services are covered under the non-recurring work ELINS. 0003

11/19/2021

97 of

J-1503010 Custodial Inventory, Stennis Space Center and

Building 2608 Will the government please provide the estimated days when beds are to be made when classes are being held?

GOVERNMENT PRE AWARD INQUIRY FORM

Page Section Para.

Amend

No.

REFERENCEQuestion

No.

QUESTION GOVERNMENT RESPONSEDate Received

11/19/2021

57 3.1

Section C, 1502000: The requirement lists a liability limit of 32 labor hours OR $2,500 material, but the 3 examples use 32 labor hours AND $2,500 material. Does the liability limit apply to 32 labor hours OR $2,500 material, or does the liability limit apply to 32 labor hours AND $2,500 material?

11/19/2021

General Is there a laydown/storage area area for equipment? If so, where is it located?

11/19/2021

General Has the current Solicitation changed signifigntly from the current contract? If so, please describe the differences.

11/19/2021

70 L.14 b.1.d Does the FAR/DFAR report need to be submitted with the proposal?

No. Only clauses that are applicable to this solicition that deviate or are not included in your SAM FAR/DFAR report need to be submitted.

11/19/2021 51 1.1

PWS states KTR perform maintenance, repair, alteration, demolition & minor construction for the following: Roofing: does this include inspections of roofs & davits? If so, please provide last annual & 5-year roof inspection reports. Please provide annual third-party inspection for davits? Please provide number of davits [anchors] for each building; type & whether they are attached to roof or to a wall? What are the existing warranties?

11/19/2021 63 3.2.6 Please provide the date of the last 5-year inspection for each above ground storage tank? Please provide the last 5-year inspection reports for each above ground storage tank?

Last tank inspection was March 22 -25 2021. Refer to J- 150211-05 and 04 for the latesed inspection report.

See new attachments J-1502000-06-05 (NGIS) and J-

1502000-06-06 (EXWC). 0003

GOVERNMENT PRE AWARD INQUIRY FORM

Page Section Para.

Amend

No.

REFERENCEQuestion

No.

QUESTION GOVERNMENT RESPONSEDate Received

11/19/2021 65 3.2.8

The PWS states Contractor shall develop a preventive maintenance schedule and perform preventive maintenance on the Micro-Grid System. However, it then states the micro-grid system is presently maintained by Mississippi Power under a separate contract.

For clarification, what are the responsibilities of the Contractor to maintain the Micro-Grid System under this contract. The RFP states Mississippi Power has the responsibility to maintain the Micro-Grid system. What responsibilities does Mississippi Power have under this separate contract? Is the Contractor responsible for cleaning the Micro-Grid system. If so, how offten?

11/19/2021 103 1.1

Is the Contractor responsible for disposal of waste offsite after cleaning of sewer lift stations? Or does the Contractor drop off waste at collection points onsite for Government disposal? If the contractor is responsible for disposal offsite, what is the monthly and/or yearly amount of estimated disposal (lbs or tons)?

11/19/2021 76 3.1.1.2

Please provide attachment J-1503010-08 that lists the collection sites? Also, please provide the average monthly weight of each?

11/19/2021 95 3.1.1.4

Is the irrigation system hooked directly to the city/county water?

Or is it a secondary storage tank? Is irrigation maintenance a part of this contract?

11/19/2021 81 3.1.3

PWS states the Contractor shall inform the KO when dispensers, fixtures, and drinking fountains are damaged or missing. Will the Government replace or reimburse the Contractor for these identified damaged items?

GOVERNMENT PRE AWARD INQUIRY FORM

Page Section Para.

Amend

No.

REFERENCEQuestion

No.

QUESTION GOVERNMENT RESPONSEDate Received

11/19/2021 93 3.1

Grounds:

1) Are parking lots included in the Common Output Levels at each site?

2) For clarification, berms are not included in the COLs at Woolmarket. Correct?

11/19/2021 22 2.8.7

Are locksmiths required to have or obtain a DoD security clearance? If so, what level?

Yes, the security requirements will be added in the next amendment. 0003

11/19/2021 65 3.2.8

Referring to Micro Grid Power Generation System: Please clarify if the cleaning of Solar Panels is a part of Contractors resonsibility? If so, please provide quantities and current frequency per 12 months

The Solar Panels are not owned or maintained by the Government and are not a part of this contract.

11/19/2021 65 3.2.8

“The micro-grid system is presently maintained by Mississippi Power under a separate contract.” Please provide the contract number and contract value.

11/19/2021 N/A N/A

We respectfully request a 30-day extension to the proposal due date to permit all Contractors to enhance our solutions from a very well designed Gulfport Site Visit. This extension will give the USG more time to research and respond to industry questions and allow Contractors to integrate your responses into our proposals. Considering that we are all basically working remote due to the pandemic, it has been also a challenge getting the proposal team and teammates all in concert. The extension will also allow both the USG and all Contractors to have some precious time with families over the upcoming Holidays.

Refer to GPI #11.

11/19/2021 3.1

Facility Related Control Systems (FRCS). How many laptop computers is the contractor required to provide? Please provide laptop specifications.

The contractor is required to provide laptops per the

PWS.

GOVERNMENT PRE AWARD INQUIRY FORM

Page Section Para.

Amend

No.

REFERENCEQuestion

No.

QUESTION GOVERNMENT RESPONSEDate Received

11/19/2021 3.1

Facility Related Control Systems (FRCS). Does the Government pay for software licenses associated with the FRCS systems?

11/19/2021

N6945022R0002 _J-1502000-03-

01_Service+Orde r+Detail

Please provide hours per call. This should be available as a simple add to the report in Maximo.

11/19/2021

N6945022R0002 _J-1502000-03-

01_Service+Orde r+Detail

Please provide material cost per call. This should be available as a simple add to the report in Maximo.

GOVERNMENT PRE AWARD INQUIRY FORM

Page Section Para.

Amend

No.

REFERENCEQuestion

No.

QUESTION GOVERNMENT RESPONSEDate Received

11/19/2021 J-1503050- 04-01 & 02 N/A N/A

Do areas classified as "Bunkers" on each of these two site maps require grounds maintenance to be performed? If so, what Common Output Level Standard should be applied at each area?

Bunkers are listed as operational areas at the COL levels provided on the corresponding map and J-tables.

11/19/2021 106 of

J - 1503050-01 Definitions and Acronyms Irrigation System

Are there any existing automatic irrigation systems in place at each location included in this bid? If so, please provide a list of total irrigation controllers, valves or zones, etc. broken out by each site.

11/19/2021

108 of

J - 1503050-03 Common Output Level Standards

(COLS)

3.1.1.1 Mowing

& Trimming

Frequency is listed as "Once in 14 Days" for each of the categories. Can a specific number of services be provided for consistency in bidding? I.e. should each contract bid 26 visits per year? More? Less? It is further stated that the growing season is typically March through November and that, at minimum, the contract shall service at the frequency specified during these months. This would bring the total services visits to approximately 20 vists per year. Please clarify. Also, will any service visits above and beyond those specified by the answer to this question be provided as a separate work order item?

11/19/2021 108 of

J - 1503050-03 Common Output Level Standards

(COLS) N/A

Please clarify the meaning of the abbreviations as listed on this pages. Abbreviations are "A", "M", "Q" and "SA". Are these to be translated to "Annually (1x)", "Monthly (12x)", "Quarterly (4x)" and "Semi-Annually (2x)"? Or other?

Attachment J-0200000-01, page 4 defines the Frequencies of Service.

GOVERNMENT PRE AWARD INQUIRY FORM

Page Section Para.

Amend

No.

REFERENCEQuestion

No.

QUESTION GOVERNMENT RESPONSEDate Received

11/19/2021

91 of

C - 1503050 Grounds Maintenance and Landscaping 2.3.4 Equipment

It is stated here that the "Use of powered equipment is prohibited in operational areas listed on Site Maps provided in J- 1503050-04.". If grounds maintenance is required in these areas, will all powered equipment be prohibited or only fuel powered?

Would battery powered equipment be allowed? If no powered equipment will be allowed of any kind, can information be provided as to how the grounds maintenance is currently provided in these areas so that each contractor can plan to maintain these areas appropriately.

The use of powered equipment refers to motorized equipment that would potentially rut or damage the earth covering of magazines. Gas powered or battery powered weedeaters are acceptable alternatives and have both been used historically.

11/19/2021 94 of

C - 1503050 Grounds Maintenance and Landscaping

3.1 Improved

Grounds

It is stated here that the fertilizer type shall be determined by soil analysis tests performed by the Contractor. How many times per year will soil tests be required at each location? Also, how many separate soil tests will need to be perofrmed at each location?

Unless specifically stated, means and methods are at the contractor's descretion. This is a performance based solicitation. The contractor is responsible for meeting the specified performance objectives and standards.

11/19/2021 99 of

C - 1503050 Grounds Maintenance and Landscaping

3.4 Grounds

Maintenance Service Orders

On average, how many service orders for grounds maintenance services are expected on an annual basis at each individual location?

There are no Grounds Maintenance Service Orders under this contract. Section C will be amended to delete this spec item. These services are covered under the non-recurring work ELINS. 0003

11/19/2021 108 of

J - 1503050-03 Common Output Level Standards

(COLS)

3.1.1.3 Lawn

Services

Top Dress - What depth should top dressing be provided for?

Also, what type of sand should be used. Over Seed - What application rate should the over seed be applied at? Also, what type of seed should be used for over seeding?

Standard industry practices should be used in order to meet the specified performance standards. The only exception being that Installation Design Standards call for the use of Common Bermuda seed.

GOVERNMENT PRE AWARD INQUIRY FORM

Page Section Para.

Amend

No.

REFERENCEQuestion

No.

QUESTION GOVERNMENT RESPONSEDate Received

11/19/2021

97 of

C - 1503050 Grounds Maintenance and Landscaping

3.1.7 Vegetation

Control

It is stated here that "fence lines, fence fabric, brick, walls, curbs, gutters, aggregate areas, and paved surfaces including parking lots are free of all vegetation.". When referencing the site maps, none of the paved areas are highlighted as areas to be included in grounds maintenance. Please confirm whether all parkings lots and hard surfaces must receive weed control as stated above though they are not highlighted on the maps.

Only those areas indicated on the Grounds Maintenance maps are to be included

11/19/2021

97 of

C - 1503050 Grounds Maintenance and Landscaping

3.1.7 Vegetation

Control

In conjunction with the above question, will gravel areas along the various railroad tracks need to be maintained for weed control as well? It was noted at the site visit that the railroad tracks do not appear to have been maintained in some time.

There are also no specific sections within the bid documents that refer to the railroad tracks. Is any grounds maintenance service to be provided for railroad tracks at all?

The railroad tracks are herbicided by in-house Government workforce and are not a part of this contract.

11/19/2021

CLIN

0001 - Base RW Tab

J-0200000-

14_ELINS

Row 48 & 49 - Navy Exchange

(NEX)

Accoridng to this page, there will be no grounds maintenance provided at the NEX station. Please confirm this to be true. It was noted at the site visit that there are areas of mowing and bed maintenance that exist at this location but no line item for pricing of these services at this location.

11/19/2021

99 of

C - 1503050 Grounds Maintenance and Landscaping

3.3 Storm

Drainage Systems

Is grounds maintenance services to be provided along all concrete storm ditches or only at inlets or drains? It was noted at the site visit that many of these ditches are fairly overgrown along the lengths of the total ditch and that maintenance may only exist for inlets, entrances, exits, etc.

GOVERNMENT PRE AWARD INQUIRY FORM

Page Section Para.

Amend

No.

REFERENCEQuestion

No.

QUESTION GOVERNMENT RESPONSEDate Received

11/19/2021

52.222-42 Statement of Equivalent Rates for Federal Hires (May 2014)

LineWG-3, 2, Laborer, Grounds Maintenance

This section dictates the monetary wages for a grounds maintenance laborer based on the federal wage system. The question is, as long as wage rates fall within the federal dictates based on this page and the other supporting documentation provided with thsi bid, would individuals with H2B work visas who are also E-Verified be allowed to perform work under this contract? Copies of visas, passports, and e-verfification would be made available for verification if allowed.

11/19/2021 77

(1) Factor 1 Corporate Experience

All In evaluation of corporate and past experience, will the Government accept ongoing or completed projects that meet all listed relevancy requirements, from tier one subcontractors?

11/19/2021 CBA pg.

Article XVIII, Section 1

Referencing the CBA, specifically regarding vacation hours for project personnel, the Government has stated that continuous service accumulated with prior contractors will be counted in determining the amount of PTO for which an employee is eligible. In all other cases, service for PTO purposes will date from the employee's date of hire by the Company. However, no seniority/balance list has been provided to bidders to account for accrued time.

Additionally, SCA Length of service includes the whole span of continuous service with the present contractor or successor wherever employed and with the predecessor contractors in the performance of similar work at the same Federal facility. (Reg. 29

CFR 4.173).

Will the Government provide a seniority list for the project to allow bidders to accurately and compliantly meet this requirement?

This information is not currently available. In accordance with FAR 52.222-41(n), 10 days prior to completion of the current contract, the incumbent prime contractor will furnish the Contracting Officer a certified list of the names of all service employees on the Contractor or Subcontractor payroll during the last month of performance. This list will also contain anniversary dates of employment on the contract and will be turned over to the successor Contractor.

This is a performance based contract; therefore the contractor is responsible for pricing the contract requirements.

GOVERNMENT PRE AWARD INQUIRY FORM

Page Section Para.

Amend

No.

REFERENCEQuestion

No.

QUESTION GOVERNMENT RESPONSEDate Received

11/19/2021 3 B.1 1

To allow for aligned bidding and pricing, will the Government include a CLIN for PMO?

11/19/2021 3 B.1 1

For ease of use and improved efficiency in pricing and execution, will the Government include a non-labor CLIN, allowing the awarded contractor to segregate costs and rapidly adjust to changes in material needs and prices, further exacerbated by recent US supply chain shortages?

The CLINS will remain as currently specified.

11/19/2021 1 SF33 1

Will the Government provide a 30 day extension to allow bidders reasonable time to develop their pricing and solution for this effort? Refer to GPI #11.

11/19/2021 66 L 2

Will the Government allow soft copy submissions in lieu of hardcopy production and shipping/travel? Refer to GPI #12.

11/23/2021

Could the government please provide a list of all the subcontractors used? Refer to GPI #13.

11/23/2021

Could the government please provide all the workload data?

The Government has provided available data in Section J Service Order Detail.

11/23/2021

Could the government please provide the senority list for the employees covered within the CBA? Refer to GPI #101.

11/23/2021

Could the government please provide pictures of all major equipment since bidders did not go in any of the buildings or mechanical rooms.

11/24/2021

Who is the current incumbent, their award value and the period of performance? Refer to section A.5 of the solicitation.

11/24/2021 Do the outlaying locations associated with this PWS have satellite maintenance offices

There are no Government Furnished Facilities or satellite maintenance offices at any of the Special Areas associated with this contract.

11/24/2021 Pg. 51 of the PWS Section 1.1 Concepts of Operations list Roofing as a requirement for contractor performed maintenance. Can the Government provide information of past roofing maintenance?

GOVERNMENT PRE AWARD INQUIRY FORM

Page Section Para.

Amend

No.

REFERENCEQuestion

No.

QUESTION GOVERNMENT RESPONSEDate Received

11/24/2021 On Pg. 51 Under Miscellaneous, the Government list Sign repair/maintenance as part of the contractor’s responsibility.

Will the contractor have access to the government’s sheet metal facility aboard NCBN Gulfport?

Sign repair/maintenance is not a part of the recurring maintenance requirements of this contract, but such work may be ordered via Task Order if needed. Only the Government-Furnished Facilities listed in Annex 0200000, Spec Item 2.4 are available to the contractor.

However, a forthcoming amendment will add locksmith facilities to Annex 0200000, Spec Item 2.4.

11/24/2021 Does the Government intend for custodial services to be performed during normal working hours or will the contractor custodial staff have access for afterhours service?

11/24/2021

As this contract encompasses multiply locations, can the Government provide the landscaping depth/height requirements, distance to be maintained from structures, fence lines and roadways for each location, and grounds maintenance /landscaping yearly schedule requirement if any?

Please refer to the Grounds Maintenance maps in Section J and the work requirements in Section C.

11/24/2021

Can the Government provide information on any fees, fines and penalties that were assessed during past contractor’s performance of wastewater management?

11/24/2021 Annex 15 Facilities Support list sub annex 1503020 Pest Control.

This sub annex is not provided. Will the requirements listed under Section C 1503050 Grounds Maintenance and Landscaping meet the requirements for sub annex 1503020 Pest Control? Refer to GPI #7. 0003

11/24/2021 Will the service/maintenance of the solar panel power system located at Gulfport fall under this PWS?

No. The Solar Panels are not owned or maintained by the Government and are not a part of this contract.

GOVERNMENT PRE AWARD INQUIRY FORM

Page Section Para.

Amend

No.

REFERENCEQuestion

No.

QUESTION GOVERNMENT RESPONSEDate Received

11/24/2021

Section C 2.7.1.1 calls out the requirement for the PM to have a PMP certification. In addition, it states that an org chart with names of personnel and their positions titles be called out.

Amendment 1 Section F calls for this information to be provided within 15 days of the contract start date. Given that supposition, do the government expect that only the positions to be staffed (on site staff titles) to be called out in the Factor 2, Technical Approach organizational chart?

11/24/2021

Section C -1502000 Facility Investment page 63 mentions the NEX Fuel System Maintenance. Can the Government provide the type of system (Manufacturer & Model) and a snapshot of past historical maintenance or repairs conducted on the system in question?

NEX Fuel system inventory is listed in J-1502000-09.

The system is relatively new and has had little work performed beyond basic maintenance, except for some storm damage.

11/24/2021

Section J Inventories Please provide the tonnage for the water cooled systems

Tonnage for water cooled HVAC systems has been added to the applicable line items on attachment J- 1502000-04, HVAC inventory, to be provided in a forthcoming amendment. Note total tonnage is as follows: Cooling Towers: 2,045;

Chillers: 4,177.

11/24/2021 Section J Inventories Can you provide the horsepower for the boilers?

The boiler inventory has been revised to include make and model so offerors can determine technical specifications that may be required. These revisions will be provided in a forthcoming amendment. 0003

GOVERNMENT PRE AWARD INQUIRY FORM

Page Section Para.

Amend

No.

REFERENCEQuestion

No.

QUESTION GOVERNMENT RESPONSEDate Received

11/24/2021

CBA

Has the existing contractor received or requested an audit from the pension Trust Funds as to the financial status, health and strength of tehir trust funds (and have they ever received any notices from the Trust Funds in the last 3-5 years related to the health and strength of their trust funds?

The CBA is between the contractor and the Bargaining Entity. The Government is not involved in the agreeement negotiations nor does it have any visibility or liability with respect to trust funds.

11/24/2021

CBA

Will the Government be responsibel for any withdralwal liablity as part of the regular reimbursement for expenses/labor (assumng the Company complies with all fund contribution requirements)?

The CBA is between the contractor and the Bargaining Entity. The Government is not involved in the agreeement negotiations nor does it have any visibility or liability with respect to trust funds.