AMD 0003_P-870_Specifications.pdf
PDF 77 KB Posted
- Solicitation number
- N6274224R1313
About this file
This document is a technical specification for a fuel-resistant resinous flooring system (3-coat system) to be installed as part of the FY24 MCON P-870 9th Engineering Support Battalion (ESB) Training Complex project at US NAVSUPPACT, Marine Corps Base Guam. The specification covers requirements for joint sealants, primer and topcoat materials, non-skid grit, surface preparation, application procedures, quality control, and warranties. Key details include:
The flooring system consists of a primer coat, two urethane topcoats, and a broadcast of aluminum oxide non-skid grit. Strict requirements are provided for joint sealant properties, qualifications of the coating inspection company and contractors, a required patch test demonstration, and comprehensive inspection and testing procedures. A one-year warranty is required covering adhesion, blistering, and sealant failures. The scope of work also includes joint material removal, concrete degreasing and shot blasting, and marking of walkways and grounding rods.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1737354
SECTION 09 67 23.15
FUEL RESISTIVE RESINOUS FLOORING, 3-COAT SYSTEM
02/21
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM C679 (2015; R 2022) Standard Test Method for Tack-Free Time of Elastomeric Sealants
ASTM D412 (2016) Standard Test Methods for Vulcanized Rubber and Thermoplastic Elastomers - Tension
ASTM D638 (2014) Standard Test Method for Tensile Properties of Plastics
ASTM D1308 (2002; R 2013) Effect of Household Chemicals on Clear and Pigmented Organic Finishes
ASTM D2240 (2015; E 2017) Standard Test Method for Rubber Property - Durometer Hardness
ASTM D3925 (2002; R 2015) Sampling Liquid Paints and Related Pigmented Coatings
ASTM D4541 (2022) Standard Test Method for Pull-Off Strength of Coatings Using Portable Adhesion Testers
ASTM D6237 (2019) Standard Guide for Painting Inspectors (Concrete and Masonry Substrates)
ASTM E11 (2022) Standard Specification for Woven Wire Test Sieve Cloth and Test Sieves
INTERNATIONAL CONCRETE REPAIR INSTITUTE (ICRI)
ICRI 310.2R (2013) Selecting and Specifying Concrete Surface Preparation for Sealers, Coatings, Polymer Overlays, and Concrete Repair
MASTER PAINTERS INSTITUTE (MPI)
MPI 211 (2018) Floor Coating, Primer, Thin Film, for Aircraft Maintenance Facilities
MPI 212 (2018) Floor Coating, Thin Film, for
SECTION 09 67 23.15 Page 1
AMENDMENT 0003 - 18 APRIL 2024
FY24 MCON P-870 9TH ENGINEERING SUPPORT BATTALION (ESB) TRAINING COMPLEX
US NAVSUPPACT, MARINE CORPS BASE GUAM
Aircraft Maintenance Facilities
SOCIETY FOR PROTECTIVE COATINGS (SSPC)
SSPC QP 5 (2022) Standard Procedure for Evaluating the Qualifications of Coating and Lining Inspection Companies
SSPC-TU 2/NACE 6G197 (1997) Design, Installation, and Maintenance of Coating Systems for Concrete Used in Secondary Containment
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1910.134 Respiratory Protection
29 CFR 1910.1000 Air Contaminants
29 CFR 1926.59 Hazard Communication
1.2 SUBMITTALS
Government approval is required for submittals with a "G" classification.
Submittals not having a "G" classification are for Contractor Quality Control approval. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-03 Product Data
Joint Sealant; G
Thin Film Flooring System; G
White Aluminum Oxide Non-Skid Grit; G
SD-06 Test Reports
Joint Sealant Test Report; G
Primer Coat; G
Urethane Topcoat; G
White Aluminum Oxide Non-Skid Grit; G
Patch Test Demonstration; G
Daily Inspection Report; G
Adhesion Testing; G
SD-07 Certificates
Coating Work Plan; G
Joint Sealant Certificates; G
SECTION 09 67 23.15 Page 2
AMENDMENT 0003 - 18 APRIL 2024
Thin Film Flooring System Certificates; G
Qualifications of Certified Protective Coatings Specialist (PCS)
Qualifications of Coating Inspection Company
Qualifications of QC Specialist Coating Inspector
Qualifications of Coating Contractors; G
Warranty; G
SD-08 Manufacturer's Instructions
Joint Sealant Manufacturer's Instructions; G
Thin Film Flooring System Manufacturer's Instructions; G
Water-Based Alkaline Degreaser; G
SD-11 Closeout Submittals
Inspection Logbook; G
1.3 QUALITY ASSURANCE
1.3.1 Qualifications of Certified Protective Coatings Specialist (PCS)
Submit name, address, telephone number, FAX number, and e-mail address of the independent third party PCS. Submit documentation that the specialist is certified by SSPC: The Society for Protective Coatings (SSPC) as a PCS, including certification number and date of certification/recertification.
If the PCS is employed by the same coating inspection company to which the coating inspector is employed, this does not violate the independent third-party requirements. The PCS must remain certified during the entire project, and the Contracting Officer must be notified of any change in certification status within 10 days of the change. The PCS must not be the designated coating inspector.
1.3.2 Coating Work Plan
a. Include Coating Work Plan in Quality Control Plan.
b. Provide procedures for reviewing Contract Documents immediately after award to identify errors, omissions, and discrepancies so that any such issues can be resolved prior to project planning and development of detailed procedures.
c. Provide procedures for verification of key processes during Initial Phase to ensure that Contract requirements can be met. Key processes must include surface preparation, coating application and curing, inspection, and documentation, and any other process that might adversely impact orderly progression of work.
d. Provide procedures for all phases of coating operations, including planned work, rework, repair, inspection, and documentation. Address mobilization and setup, surface preparation, coating application, coating initial cure, tracking and correction of non-compliant work, and demobilization. Coordinate work processes with health and safety
SECTION 09 67 23.15 Page 3
AMENDMENT 0003 - 18 APRIL 2024
plans and confined space entry plans. For each process, provide procedures that include appropriate work instructions, material and equipment requirements, personnel qualifications, controls, and process verification procedures. Provide procedures for inspecting work to verify and document compliance with Contract requirements, including inspection forms and checklists, and acceptance and rejection criteria.
e. Provide procedures for determining the existing surface profile under paint, and procedures for ensuring that the profile is not increased beyond the maximum profile specified herein.
f. Provide procedures for correcting non-compliant work. Detailed procedures are required in advance to avoid delays in meeting overcoat windows as well as to avoid delays in production. Provide procedures for repairing defects in the coating film, such as runs, drips, sags, holidays, overspray, as well as how to correct coating thickness non-compliance, any other areas of repair or rework that might be adversely affected by delays in preparing and approving new procedures.
g. If a procedure is based on a proposed or approved request for deviation, the deviation must be referenced. Changes to procedures must be noted by submittal number and date approved, clearly delineating old requirements and new requirements, so that the records provide a continuous log of requirements and procedures.
1.3.3 Test Reports
1.3.3.1 Joint Sealant Test Report
Submit test results that confirm sealant complies with the requirements of Table Ia. Samples must have been tested within the last three years.
1.3.3.2 Daily Inspection Report
Submit one copy of the daily inspection report to the Contracting Officer within 24 hours of the date recorded.
1.3.4 Certificates
1.3.4.1 Qualifications of Coating Inspection Company
Submit documentation that the coating inspection company performing all coating inspection functions is certified by SSPC to the requirements of SSPC QP 5 prior to Contract award. The coating inspection company submitted and approved must remain and not changed through completion of the Contract. The coating inspection company must remain so certified for the duration of the project. If a coating inspection company's certification expires, the firm will not be allowed to perform any inspection functions, and all surface preparation and coating application work must stop, until the certification is reissued. Requests for extension of time for any delay to the completion of the project due to an inactive certification will not be considered. Notify the Contracting Officer of any change in coating inspection company certification status.
Notify the Contracting Officer of all scheduled and unannounced on-site inspections from SSPC and furnish a copy of all inspection reports.
SECTION 09 67 23.15 Page 4
AMENDMENT 0003 - 18 APRIL 2024
1.3.4.2 Qualifications of QC Specialist Coating Inspector
Submit documentation that each coating inspector is employed, and qualified to SSPC QP 5 , Level II, by the selected coating inspection company. Each inspector must remain employed by the coating inspection company while performing any coating inspection functions. In addition to the handwritten records, the inspector must employ an electronic reporting program with functionality as outlined in Table II. The Administrator must be the designated Government Representative for the project.
1.3.4.3 Qualifications of Coating Contractors
All Contractors that perform surface preparation or coating application must be certified to SSPC QP 8 and should also be SSPC QS 1 certified prior to Contract award and must remain certified while accomplishing any surface preparation or coating application. The painting Contractors must remain so certified for the duration of the project. If a Contractor's certification expires, the firm will not be allowed to perform any work until the certification is reissued. Requests for extension of time for any delay to the completion of the project due to an inactive certification will not be considered. Notify the Contracting Officer of any change in Contractor certification status. Notify the Contracting Officer of all scheduled and unannounced on-site audits from SSPC and furnish a copy of all audit reports.
For OCONUS, non-US territories where documentation is provided that certified SSPC QP 8 with or without SSPC QS 1 Contractors did not bid and are not available, all Contractors that perform surface preparation or coating application must be certified to ISO 9001 prior to Contract award, and must remain certified while accomplishing any surface preparation or coating application. If a Contractor's certification expires, the firm will not be allowed to perform any work until the certification is reissued. Requests for extension of time for any delay to the completion of the project due to an inactive certification will not be considered.
Notify the Contracting Officer of any change in Contractor certification status. Notify the Contracting Officer of all scheduled and unannounced on-site inspections from the ISO certifying organization and furnish a copy of all inspection reports.
Minimum requirements for the installation Contractor are as follows:
Completed three or more jobs within the past two years applying the specified materials to concrete surfaces in which the total area exceeds 200,000 square feet. Submit documentation listing location of work, point of contact at job site, total square footage of applied materials, listing of both materials and equipment used, and validation from coating manufacturer documenting quality of materials purchased per job for work totaling 200,000 square feet within the past two years. In addition to the above requirements, be certified by the material manufacturer(s) to install the submitted coatings and sealant. Submit copy of certificates.
1.3.4.4 Joint Sealant Certificates
Submit literature documenting the past performance of the sealant's use in automotive or aircraft maintenance shops. Minimum requirements are two or more maintenance shops with joint work totaling 10,000 linear feet where the sealant has performed for two years with less than 1 percent combined sealant failures and defects. List location of shops, total linear feet of sealant applied per shop, shop point of contact, date sealant was applied, and the name of the installed sealant material.
SECTION 09 67 23.15 Page 5
AMENDMENT 0003 - 18 APRIL 2024
1.3.4.5 Thin Film Flooring System Certificates
Provide manufacturer's certification of conformance to Contract requirements.
Submit literature documenting the past performance of the coating system's use in aircraft maintenance shops and over floors with high rates of Moisture Vapor Emission (MVE). Minimum requirements are two or more aircraft maintenance shops totaling 34,000 square feet where the coating system has performed for two years with less than 0.05 percent combined premature coating failures, material defects and surface discoloration; no more than 0.03 percent discoloration from aviation chemicals, tire plasticizers, and UV exposure. Provide a minimum of two additional case histories where successful installation occurred on floor slabs with no less than 3.5 pounds moisture per 24 hours, 1000 square feet. List location of shops, total coated area per shop, shop point of contact, date coating system was applied, successful installation to concrete with high MVE, and the names of the installed coating materials.
1.3.5 Product Data
1.3.5.1 Joint Sealant Manufacturer's Instructions
Submit manufacturer's printed instructions to include detailed application procedures, minimum and maximum application temperatures, and curing procedures. In accordance with 29 CFR 1926.59 , include Safety Data Sheets (SDS) for the sealant to be used at the job site.
1.3.5.2 Thin Film Flooring System Manufacturer's Instructions
Submit manufacturer's printed instructions to include detailed mixing, minimum and maximum application temperatures, acceptable atmospheric and interior climatic conditions, application procedures, curing procedures, and procedures for maintenance cleaning of flooring system. Provide explicit instructions detailing surface preparation, recoat windows and remedial actions in case recoat windows are missed, and, if applicable, solvent-wiping between coats with acceptable types and grades of solvents. In accordance with 29 CFR 1926.59 , include SDSs for the coatings to be used at the job site.
1.3.5.3 Water-Based Alkaline Degreaser
Submit manufacturer's printed instructions to include detailed mixing, rate of dilution, application procedures, and rinsing procedures. In accordance with 29 CFR 1926.59 , include SDSs for the water-based alkaline degreaser to be used at this job site.
1.4 DELIVERY, STORAGE, AND HANDLING
Store coatings and sealant in spaces with temperatures from 40 degrees F to 75 degrees F. Inspect materials on site for damage prior to use. Return to manufacturer packaged materials in dented, rusty, or leaking containers. Conduct testing by manufacture of returned materials with an expired shelf life and if compliant, reissue a shelf life extension.
1.5 COATING HAZARDS
Ensure that employees are trained in all aspects of the safety plan.
SECTION 09 67 23.15 Page 6
AMENDMENT 0003 - 18 APRIL 2024
Follow the coating manufacturer's written safety precautions throughout mixing, application, and curing of coatings. Comply with respiratory protection requirements in 29 CFR 1910.134 and safe levels of airborne contaminants in 29 CFR 1910.1000 .
1.6 JOB SITE REFERENCES
Make available to the Contracting Officer at least one copy each of ASTM D4541, ASTM D6237, SSPC-TU 2/NACE 6G197 , and ICRI 310.2R , including replica standards ICRI 310.2R CSP 1 through CSP 9, at the job site.
1.7 PATCH TEST DEMONSTRATION
Prior to the submitted flooring system's approval, apply the complete coating system to a 10 foot by 10 foot square section of concrete as prepared in accordance with PART 3 EXECUTION. Within this area, perform three adhesion tests as described in the paragraph ADHESION TESTING. If adhesion testing produces cohesive failures within the concrete, no less than 40 mils concrete removed over 95 percent of each pull-off coupon, or adhesion more than 400 psi, patch test adhesion is acceptable. If concrete surface preparation was insufficient, apply an additional coating system patch to properly prepared concrete followed by the above adhesion testing. If adhesion results are unacceptable for both the topcoats and the primer, submit a new coating system manufactured by a different coating vendor. Apply a patch of the new coating system and subject patch to the above requirements for adhesion prior to approval. If customer is not satisfied with the non-skid grit application, adjustments to the specifications can be made. Grit coarser than No. 60 aluminum oxide is not recommended.
1.8 WARRANTY
Warranty materials and workmanship for a minimum period of one year following coating and sealant application. The following terms and conditions form a part of the warranty: If the applied coating system develops either blisters (chemical), checks, softening, or lifting within one year following application, rework each area at Contractor's expense.
The following conditions are excluded from the warranty: A) concrete cracking, flooring system mirrors cracks in concrete; B) cosmetic imperfections due to scratching and gouging; C) application to metallic concrete finishes; and D) application to concrete with a rate of Moisture Vapor Emission (MVE) greater than 3.5 pounds moisture per 24 hours, 1000 square feet. If the coating system's adhesion is in question, perform one adhesion test per 100 square feet as described in the paragraph ADHESION TESTING. To satisfy the warranty, each adhesion test must produce cohesive failures, concrete removal over 95 percent of each pull-off coupon, or adhesion no less than 400 psi. Require two additional adhesion tests to confirm results for each area failing to meet adhesion requirements.
Within the warranty period, remove to sound material and rework all areas unable to meet adhesion requirements. There must be zero percent sealant failures within one year. Within the warranty period, remove and rework all sealant material with chemically attacked surfaces or lifting from joint walls. Topcoat cracking over sealant is excluded from warranty.
PART 2 PRODUCTS
2.1 JOINT SEALANT
Formulate the joint sealant to exhibit the properties as listed in Table
SECTION 09 67 23.15 Page 7
AMENDMENT 0003 - 18 APRIL 2024
Ia.
2.2 THIN FILM FLOORING SYSTEM
A three-coat industrial flooring system consisting of primer and two urethane topcoats. Apply the coating system at a Dry Film Thickness (DFT) ranging from 13 to 20 mils and contain a broadcast of aluminum oxide non-skid grit.
2.2.1 Primer Coat
In addition to the requirements of the thin film flooring system, use MPI 211 primer coat.
2.2.2 Urethane Topcoat
In addition to the requirements of the thin film flooring system, use MPI 212 top coat.
2.3 WHITE ALUMINUM OXIDE NON-SKID GRIT
Size No. 60, dust free (washed and dry), minimum 99 percent pure, having the following sieve analysis when tested using a 2.2 pound sample ( ASTM E11
Sieve No. 40 100 percent passing
Sieve No. 50 15-30 percent retained
Sieve No. 60 70-85 percent retained
Sieve No. 70 0-15 percent retained
PART 3 EXECUTION
3.1 COATING SAMPLE COLLECTION
The Contracting Officer and QC Manager must witness all material sampling. Notify the Contracting Officer a minimum of three days in advance of sampling. Obtain liquid samples of each component of primer and topcoat by random selection from sealed containers and in accordance with ASTM D3925. Samples may be either individual cans of liquid material or 1.0 quart quantities of properly mixed, extracted, and sealed liquid material. Identify samples by designated name, specification number, batch number, project Contract number, sample date, intended use, and quantity involved. When the applied coating system has met the requirements defined in the paragraph ADHESION TESTING, return coating to the installation Contractor for proper disposal.
3.2 JOINT MATERIAL REMOVAL, RE-SAW CUTTING, CRACK CHASING
Remove 100 percent of the existing material in all joints including material bonded to joint walls and base. Rigid material may require saw cutting equipment to remove. Joints may be widened up to 1/8 inch when re-saw cutting. Chase concrete cracks identified for repair and open to a minimum depth of 1/2 inch below crack surface resulting in crack(s) with smooth vertical walls. Cracks greater than 3/4 inch width can be repaired using either epoxy mortar or epoxy concrete.
SECTION 09 67 23.15 Page 8
AMENDMENT 0003 - 18 APRIL 2024
3.3 DEGREASING
On both coated and uncoated concrete, degrease entire floor by scrubbing using a solution of hot potable water, 120 degrees F to 170 degrees F, and a concentrated water-based alkaline degreaser. Perform two complete degreasing cycles on the entire floor surface. Allow solution to soak into surfaces prior to scrubbing and remove using hot potable water under a minimum of 4,000 psi. Rinsing is complete when the rinse water appears clear. If the industrial detergent is not biodegradable, collect all rinse water and dispose as hazardous waste. Squeegees and shop vacuums may be used to collect pooling rinse water. Fans may be used to aid drying of floor surfaces.
3.4 SURFACE PREPARATION
Shot blast entire floor to produce a level of coarseness equal to ICRI 310.2R CSP 3. Overlap each pass of shot blasting by 1/4 inches to 1/2 inches. Add new shot to shot blasting equipment prior to blasting. Prepare surfaces inaccessible to shot blasting, base of perimeter walls and under secured equipment, using diamond disk grinding or light scarification to produce a level of coarseness equal to ICRI 310.2R CSP 2 or ICRI 310.2R CSP 4, respectively. Resulting surfaces must appear clean and contain the appropriate level of surface coarseness. If the resulting level of cleanliness cannot be determined, place numerous drops of water on surfaces that appear contaminated. If the water drops soak into concrete, the surfaces are free of hydrocarbon contamination (oils, grease, skydrol). If the water drops bead up and do not flatten out, surfaces require additional degreasing as detailed in the Article DEGREASING. Shot blasting coarse concrete or broom finished concrete can produce a level of coarseness equal to ICRI 310.2R CSP 5: employ a best-effort attempt to minimize over-shot-blasting of coarse concrete. If coarse concrete is encountered, shot blasting to a level of coarseness equal to ICRI 310.2R CSP 5 is acceptable: however, extremely coarse concrete can require resurfacing prior to the flooring system's installation. Sweep, vacuum, and run a high powered magnet over all surfaces to be coated, including joints.
3.5 JOINT TREATMENT
Use the "Conventional Sealed Joint" as detailed in Figure 1 of SSPC-TU 2/NACE 6G197 to seal joints. Employ measures to reduce contamination from equipment and foot traffic. Limit floor access to essential Contractor personnel. Confirm joint surfaces are sufficiently clean.
3.5.1 Install Backer Rod
Install a continuous length of round, closed-cell polyethylene backer rod into each joint using a backer rod tool. For 1/2 inch, 3/8 inch, and 1/4 inch wide joints, place backer rod to a depth of 3/8 inch (depth equals the distance from the concrete's surface to the highest point on the backer rod). For joints greater than or equal to 3/4 inch width, place backer to a depth of 5/8 inch below the concrete's surface. Fit backer rod tight between joint walls (30 percent compression). Remove and reinstall all backer rod that is installed using either the incorrect size (loose fit) or at the incorrect depth. Following backer rod installation, apply painter's tape to surfaces adjacent joints to protect from sealant.
SECTION 09 67 23.15 Page 9
AMENDMENT 0003 - 18 APRIL 2024
3.5.2 Joint Sealant Application
Apply sealant directly into joints using a bulk-caulking gun. At room temperature, the resulting sealant application must exhibit a concave recess between 1/8 inch to 1/16 inch below the concrete's surface. Remove and reapply cured sealant remaining either flush or greater. Following sealant application, remove painter's tape and sealant drips on concrete surfaces. Cure sealant a minimum of 24 hours, prior to the application of coatings.
3.6 PRE-APPLICATION TESTING FOR CONTAMINATION
Spot check surfaces for oil/grease contamination using the water break test. At a rate of 5 tests per 1000 square feet, place one to two drops of water onto surfaces and observe for beading. Test all other surfaces that show visible signs of potential contamination. Apply additional degreasing techniques to surfaces displaying water beading in accordance with the Article DEGREASING.
3.7 COATING APPLICATION
Vacuum flooring space one additional time prior to coating application.
3.7.1 Primer Application
Apply MPI 211 epoxy primer to flooring space at 7.0 mils to 15.0 mils Dry Film Thickness (DFT). If the prepared concrete resembles an ICRI 310.2R CSP 3 surface, apply the primer at a minimum of 7.0 mils DFT. If the prepared concrete resembles an ICRI 310.2R CSP 5 surface, apply the primer at a maximum of 15.0 mils DFT. The previously applied sealant may be lightly coated.
3.7.2 Non-Skid Grit Broadcast
Broadcast non-skid grit at a rate of 1.5 pounds per 100 square feet into the second urethane top coat and backroll. Map floor into 600 square foot sections where 9.0 pounds of non-skid grit is pre-weighed, placed into clean buckets and used in its entirety per marked 600 square foot section.
3.7.3 Application of Topcoats
Apply two coats of MPI 211 epoxy urethane topcoat to the epoxy primer and broadcast white aluminum oxide non-skid grit directly into the second urethane topcoat.
3.7.3.1 First Topcoat
Apply a full coat of the urethane topcoat at a spreading rate from 2.5 to
3.2 mils Dry Film Thickness (DFT). Stripe coat perimeter edges and around equipment footings. Monitor and record a minimum of one Wet Film Thickness (WFT) reading per 600 square feet of floor surface. Sealant is to be lightly coated.
3.7.3.2 Second Topcoat
Apply a second coat of the urethane topcoat at a spreading rate of 2.5 to
3.2 mils DFT. Stripe coat perimeter edges and around equipment footings.
Monitor and record a minimum of one WFT reading per 600 square feet of floor surface prior to broadcasting non-skid grit. When the correct WFT
SECTION 09 67 23.15 Page 10
AMENDMENT 0003 - 18 APRIL 2024
has been applied per 600 square feet of area, immediately and evenly broadcast non-skid grit directly into the second topcoat of urethane and backroll in two directions. Test the adhesion of the thin film flooring system in accordance with the paragraph ADHESION TESTING.
3.7.3.3 Walkway Stripe and Grounding Rod Markings
Place the walkway stripe and grounding rod markings according to Government drawings, if applicable. When the second topcoat is within its recoat window, apply a walkway stripe of the red/orange urethane topcoat at
3.0 mils DFT, completely hiding the top coat, in one coat. If insufficient hiding occurs, apply one additional coat of the walkway stripe. Lightly broadcast non-skid grit into the wet walkway stripe. Use solvent-resistant tape to protect the floor coating against stripe coat bleed. A thin clear coat of either epoxy or urethane may be required to prevent stripe coat bleed prior to the full application of the colored stripe coat. Apply grounding rod markings using similar procedures, urethane top coat, and colors and size according to Government drawings.
3.8 CURING
Cure installed materials to display performance equal to manufacturer's product literature. Remove and reapply improperly cured material.
3.9 FIELD QUALITY CONTROL
3.9.1 Coating Inspector
Consider the Coating Inspector as a QC Specialist, who works for the QC Manager, and qualified in accordance with Section 01 45 00.00 20 QUALITY CONTROL. The Coating Inspector must be present during all field tests, surface preparation, flooring application, initial cure of the flooring system, and during all flooring repair work. The Coating Inspector must provide all tools/equipment necessary to perform field tests and inspection. The Coating Inspector is responsible for field tests and specified level of inspection.
3.9.2 Inspection
Document weather conditions, job site occurrences, and report conditions and occurrences potentially detrimental to the flooring system. The listed inspection requirements are in addition to the QC inspection and reporting requirements defined in Section 01 45 00.00 20 QUALITY CONTROL. The Coating Inspector must prepare a project reference sheet outlining all requirements, tests, test methods, and evaluation criteria, and hold regular meetings with Contractor personnel, including shot blasting operators and applicators, to review requirements/evaluation criteria for upcoming work prior to execution. At the start of coating operations and every hour following until daily work is complete, record air temperature, substrate temperature, and relative humidity. Following the application of each coat, inspect surfaces for improperly cured material, blisters, inadequate or excessive coating thickness, and other defects. Document each inspection, test, non-compliant area, and location of each non-compliant area. List method of evaluation, evaluation criteria, areas requiring rework, and all other pertinent observations.
3.9.2.1 Daily Inspection Report
Submit to the Contracting Officer one copy of the daily inspection report
SECTION 09 67 23.15 Page 11
AMENDMENT 0003 - 18 APRIL 2024
completed each day when performing work under this Section. Use Appendix X1 "Inspection Checklist" of ASTM D6237 to monitor daily activity and to assist in preparing the daily inspection report. Note each non-compliant issue and each issue identified for rework in accordance with the QC documentation procedures of Section 01 45 00.00 20 QUALITY CONTROL. Use of forms containing entry blocks for all required data is encouraged. The data must be legible and presented in a professional format. Submit report within 24 hours of the report date.
3.9.2.2 Inspection Logbook
Maintain a continuous record of all activity related to this Section on a daily basis. A computer / software package as outlined in Table II is preferred to record all information provided in the Daily Inspection Reports, as well as other pertinent observations and information including photo documentation where appropriate. The designated Government Representative for the project is assigned the highest level Administrator privileges and only the Administrator must be able to modify reports. In areas where photography is not allowed, the computer must come with verification that the camera / photo capability has been removed.
Alternatively, a continuous record of all activity related to this Section must be maintained in an Inspection Logbook on a daily basis. The logbook must be hard or spiral bound with consecutively numbered pages, and must be used to record all information provided in the Daily Inspection Reports, as well as other pertinent observations and information. Submit the original Inspection Logbook to the Contracting Officer upon completion of the project and prior to final payment.
3.9.2.3 Inspection Equipment
Use equipment in good condition, operational within its design range, and calibrated as required by the specified standard for use with each device.
3.9.3 Adhesion Testing
Perform a minimum of three adhesion tests in accordance with ASTM D4541 to the thin film flooring system. Select three random flooring locations spaced a minimum of 20 feet between each location. Prior to attaching pull-off coupons, lightly sand flooring surface and attach pull-off coupons containing a grit-blasted anchor profile. Adhere directly to the center of each sanded surface a 3/4 inch diameter pull-off coupon. When pull-off coupon adhesive has sufficiently cured, score circumference of each pull-off coupon to concrete substrate. Test adhesion and evaluate results. If testing produces cohesive failures within the concrete, no less than 40 mils concrete removed over 95 percent of each pull-off coupon, or adhesion more than 400 psi coating system's adhesion is acceptable. If the above requirements are not satisfied, then perform one adhesion test per 100 square feet using the above procedures. Perform two additional tests per non-compliant area to confirm results. Remove to sound material and rework all areas unable to meet adhesion requirements.
Repair each adhesion test using a combination of primer, sand-filled epoxy mortar (for deep cohesive failures, if applicable), and two urethane topcoats. Make repairs flush with adjacent coatings and display an equivalent appearance.
3.10 FINAL CLEANUP
Following completion of the work, remove debris, equipment, and materials
SECTION 09 67 23.15 Page 12
AMENDMENT 0003 - 18 APRIL 2024
from the site. Remove temporary connections to Government or Contractor furnished water and electrical services. Restore existing facilities in and around the work areas to their original condition.
TABLE I - MATERIALS REQUIREMENTS
TABLE Ia
Test Minimum Requirement (maximum where indicated)
Sealant System (two-pack: self-leveling) Polysulfide (Manganese Cure; MnO2) or Urethane
Percent Volume Solids 100 percent
Chemical Resistance to JP-8 plus 100 Fuel at 70 de grees F (ASTM D1308) (see note 1)
48 hours immersion: 2.0 percent (max) weight incre ase, 5.0 percent (max) volume increase, 2.0 percent (max) weight loss
Chemical Resistance to Motor Oils at 70 degrees F (ASTM D1308) (see note 1)
48 hours immersion: 2.0 percent (max) weight increase, 5.0 percent (max) volume incr ease, 2.0 percent (max) weight loss
Chemical Resistance to Skydrols at 70 degrees F (ASTM D1308) (see note 1)
48 hours immersion: 2.0 percent (max) weight increase, 5.0 percent (max) volume increase, 2.0 percent (max) weight loss
Hardness (ASTM D2240: Shore A) 20
Tensile Strength (ASTM D412) (or ASTM D638
150 psi
Percent Elongation (ASTM D412) (or
ASTM D638)
500 percent
Tack Free at 65 degrees F (ASTM C679) 12 hours maximum
Adhesion to Concrete 140 psi
Adhesion to Urethane Topcoats (paintable sealant)
140 psi
NOTES: (1) Immerse and test a minimum of three 2 inch by 1/2 inch by 1/2 inch sect ion of cured sealant.
TABLE II
Reporting Program Requirements QA/QC
Administrative Controls:
SECTION 09 67 23.15 Page 13
AMENDMENT 0003 - 18 APRIL 2024
TABLE II
Administrators must be able to turn on and off unique access to specific jobs and Contracts.
Administrators must be able to remotely enable and disable access for users.
All enabled users must view the same active report in real time. There must be no opportunity for multiple versions of the same report to exist.
Administrators must be able to setup unique approval processes for each project and promote or remove unique people from this process at any time.
Administrators must be able to associate Contract specific documents and specificati on limits quickly and easily.
Administrators must be able to associate PDS, SDS, blueprints, scope of work and Contracts uniquely to each job.
Objectivity Controls:
Data Entry fields must be by multi-selectable choices, numeric keypads, pickers and skip logic to ensure repeatable data entry in a way that makes running analytics and metrics easy and objective.
The program / hardware package must be able to communicate with inspection devices t hat provide (batch) data export capability such as Elcometer and Defelsko gages.
The program / hardware package must automatically time, date and GPS stamp all repor ts without input or interference from the inspector.
Real Time Syncing:
Forms must be available for approved associates to view at all times.
Retrievable storage must be provided for all job related reports and documents for a minimum time of 5 years from completion of the job or project. Archiving of the documents after 5 years will be the responsibility of the Government.
Document Library:
All reports must be in searchable and annotatable PDF format.
The Administrator must be able to upload and annotate job specific reports in real t ime. Examples include but not limited to Safety Data Sheets, Product Data Sheets and Blueprints.
Annotations and modifications must be locked and associated with the document. Only the Administrator has rights to modify or delete annotations or allow modifications t o the document library especially all related inspection reports.
Customization:
SECTION 09 67 23.15 Page 14
AMENDMENT 0003 - 18 APRIL 2024
TABLE II
The program must be capable of being customized to specific jobs, Contracts or specifications.
-- End of Section --
SECTION 09 67 23.15 Page 15
AMENDMENT 0003 - 18 APRIL 2024
of footing level or below exterior grades before the start of construction, whichever is deeper, and at least 12 inches horizontally beyond the footing limits. Perform additional over excavation to remove any pockets of soft, loose, or unsatisfactory soils.
Over excavate at least 24 inches below the bottom of wall footing, and 24 inches horizontally beyond the wall footing limits.
For paved areas, over excavate at least 24 inches below grades that existed before the start of construction and replace with properly compacted select granular material.
Excavate to contours, elevation, and dimensions indicated. Reuse excavated materials that meet the specified requirements for the material type required at the intended location. Keep excavations free from water.
Excavate soil disturbed or weakened by Contractor's operations, soils softened or made unsuitable for subsequent construction due to exposure to weather. Excavations below indicated depths will not be permitted except to remove unsatisfactory material. Unsatisfactory material encountered below the grades shown shall be removed as directed by the Contracting Officer unless otherwise specified herein. Refill with select granular material and compact to 95 percent of ASTM D1557 maximum dry density.
Unless specified otherwise, refill excavations cut below indicated depth with select granular material and compact to 95 percent of ASTM D1557 maximum dry density. Satisfactory material removed below the depths indicated, without specific direction of the Contracting Officer, shall be replaced with satisfactory materials to the indicated excavation grade;
except as specified for spread foundations. Determination of elevations and measurements of approved overdepth excavation of unsatisfactory material below grades indicated shall be done by the CQC Geotechnical Specialist or their Geotechnical Field Representative with the approval of of the Contracting Officer.
3.3.1 Structures With Spread Footings
Perform over excavation as indicated and specified. Probe and grout the foundations and proof roll and compact bottom of excavations prior to placement of fill.
Ensure that footing subgrades have been observed, documented, and inspected by the CQC Geotechnical Specialist or Geotechnical Field Representative and submit that information to the Contracting Officer for approval prior to concrete placement. Fill over excavations with concrete during foundation placement or backfill with select granular material compacted as specified herein.
3.3.2 Pipe Trenches
Excavate to the dimension indicated. Grade bottom of trenches to provide uniform support for each section of pipe after pipe bedding placement.
Compact the bottom of trench excavations to a firm consistency as evidenced by little to no settlement under repeated asses of suitable compaction equipment, but not less than 6 passes. Excavate yielding, soft, loose, or unstable areas to firm soils but not less than 6 inches, and replace with bedding material. Place bedding material in not more than 6 inch thick loose horizontal lifts and compact each lift to a dense consistency using hand operated equipment as evident by little to no settlement of the material under repeated passes with the equipment, but not less than 6 passes per lift. Completely wrap bedding material with
SECTION 31 23 00.00 20 Page 14
AMENDMENT 0003 - 18 APRIL 2024
tests thereafter. Test each lift at randomly selected locations every 2000 square feet or fraction thereof, of subgrade and each lift of backfill for structures and pavements, but not less than one test per lift per footing or slab or every 50 linear feet of wall footing. When test results indicate that compaction is not as specified, the material must be removed, replaced, and recompacted to meet specification requirements.
Tests on recompacted areas must be performed to determine conformance with specification requirements.
Include density test results in Contractor Quality Control (CQC) Report.
The density test results must include a plan showing density test identification, elevation, density test location coordinates, and location of density tests, and a table of the results and action taken for non-conforming items.
Bedding and backfill in trenches: One test per 100 linear feet in each lift.
-- End of Section --
SECTION 31 23 00.00 20 Page 24
AMENDMENT 0003 - 18 APRIL 2024
2.3.6 Resilient Connectors
Provide flexible, watertight connectors conforming to ASTM C923/C923M for connecting pipe to manholes trench drains and inlets.
2.3.7 Flared End Sections
2.3.7.1 Metal Flared End Sections
Provide sections of a standard design fabricated from zinc or aluminum (Type 2) coated steel sheets meeting requirements of ASTM A929/A929M .
2.3.7.2 Concrete Flared End Sections
Provide sections of a standard design fabricated with reinforced concrete.
2.3.8 Modular Trench Drains
Provide modular trench drains consisting of precast concrete sections.
Provide trench with width and invert slope as indicated on the drawings.
Provide trench drain sections and grates rated for HS- 215 loading.
2.3.8.1 Precast Concrete Sections
Provide concrete sections made of fiber reinforced concrete or polyester polymer concrete with male/female connections between channel sections.
Provide channels with ductile iron edge rails.
2.3.8.2 Grates
Utilize ductile iron trench grates with a minimum load rating for HS-25.
Attach trench grates to sections as recommended by the manufacturer.
2.4 TESTS, INSPECTIONS, AND VERIFICATIONS
2.4.1 Hydrostatic Test on Watertight Joints
Perform a hydrostatic test on the watertight joint at bulk fuel pad drainage system. This test will be conducted at the plant or by an independent laboratory. Only one sample joint of each type needs testing;
however, if the sample joint fails because of faulty design or workmanship, an additional sample joint may be tested.
2.4.1.1 Concrete Pipe
Provide joints in reinforced and nonreinforced concrete pipe meeting the performance requirements in ASTM C990M ASTM C990 or ASTM C443M ASTM C443.
2.4.1.2 Corrugated Steel Pipe
Perform a hydrostatic pressure test on the proposed joining system in accordance with ASTM A760/A760M . The joining system must not leak when subjected to an internal hydrostatic pressure of 10 psi for a 10 minute period
SECTION 33 40 00 Page 6