FY24 MCON P-870 9TH ENGINEERING SUPPORT BATTALION (ESB) TRAINING COMPLEX, US NAVSUPPACT, MARINE CORPS BASE GUAM
Solicitation number
N6274224R1313
Issued by

About this file

This document is a Building Commissioning Plan for the FY24 MCON P-870 9th Engineering Support Battalion (ESB) Training Complex project on Marine Corps Base Camp Blaz, Guam. The plan outlines the scope, strategies, and responsibilities for the commissioning team members during the design and construction phases of the project.

The key details include:

  • The systems to be commissioned include lighting, metering and sub-metering, plumbing fixtures, domestic hot water, and power distribution.
  • The commissioning team includes the Commissioning Authority, Quality Control Manager, subcontractor representatives, construction manager, commissioning specialists, and government representatives.
  • The plan covers tasks such as design reviews, construction submittal reviews, pre-functional testing, functional performance testing, O&M manual reviews, training, and commissioning reporting.
  • The plan provides the commissioning schedule and milestones for the design and construction phases of the project.

View the file

Other files

File Type Posted
24R1313 P870 Notice6.pdf PDF
24R1313 P870 Notice5.pdf PDF
24R1313 P870 Notice4.pdf PDF
N627224R1313_Amd0005.pdf PDF
AMD 0005_P-870_Specifications.pdf PDF
AMD 0004_P-870_Drawings.pdf PDF
AMD 0004_P-870_Specifications.pdf PDF
N627224R1313_Amd0004.pdf PDF
24R1313 P870 Notice5.pdf PDF
AMD 0003_P-870_Specifications.pdf PDF
AMD 0003_P-870_Drawings.pdf PDF
N627224R1313_Amd0003.pdf PDF
24R1313 P870 Notice4.pdf PDF
24R1313 P870 Notice3.pdf PDF
24R1313 P870 Notice3.pdf PDF
24R1313 P870 Notice2.pdf PDF
AMD 0002_P-870_Drawings_Signed.pdf PDF
N627224R1313_Amd0002.pdf PDF
N627224R1313_Amd0002.pdf PDF
24R1313 P870 Notice1.pdf PDF
AMD_0002_P-870_Drawings.pdf PDF
N6274224R1313_0001.pdf PDF
0_24R1313-RFP.pdf PDF
0_24R1313-RFP.pdf PDF
CJA No. 20-016 for AMI Meter_Redacted.pdf PDF
MCBG Knox Box Class JA_Redacted.pdf PDF
1_P870 Specs.pdf PDF
2_P870 Drawings.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1737354

SECTION 01 91 00.15

BUILDING COMMISSIONING

05/23, CHG 1: 08/23

PART 1 GENERAL

Building Commissioning is a systematic, quality-focused process for enhancing the delivery of a project that focuses on verifying and documenting that all of the commissioned systems and assemblies are planned, designed, installed, tested, operated, and maintained to meet the project requirements. The purpose is to reduce the cost and performance risks associated with delivering facilities projects, and to increase value to owners, occupants, and users.

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING

ENGINEERS (ASHRAE)

ASHRAE 90.1 - IP (2019) Energy Standard for Buildings Except Low-Rise Residential Buildings

ASHRAE 202 (2018) Commissioning Process for Buildings and Systems

ASSOCIATED AIR BALANCE COUNCIL (AABC)

ACG Commissioning Guideline (2005) Commissioning Guideline

NATIONAL ENVIRONMENTAL BALANCING BUREAU (NEBB)

NEBB S1110 (2019) Whole Building Technical Commissioning of New Construction; 2nd Edition

SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION

(SMACNA)

ANSI/SMACNA 014 (2013) HVAC Systems Commissioning Manual, 2nd Edition

1.2 DEFINITIONS

Commissioning Process (Cx) - a quality-focused process for enhancing the delivery of a project. Refer to ASHRAE 202 for a comprehensive description of the commissioning process.

Commissioning Provider (CxC) - The entity who leads, plans, and coordinates the Commissioning Team. The terms Commissioning Provider, Commissioning Firm, Lead Commissioning Specialist, Commissioning Specialist, and Commissioning Authority (CA or CxA) when used by sustainable Third Party Certification (TPC) programs, are interchangeable.

SECTION 01 91 00.15 Page 1

AMENDMENT 0002 - 22 MARCH 2024

FY24 MCON P-870 9TH ENGINEERING SUPPORT BATTALION (ESB) TRAINING COMPLEX

US NAVSUPPACT, MARINE CORPS BASE GUAM

Commissioning Authority – The Government retains the authority for oversight and assurance of the entire commissioning process, and final approval of all commissioning deliverables.

Government Acceptance Testing Representatives - Government Acceptance Testing Representatives perform the inherently Governmental function of technical oversight and quality assurance for critical systems, and is distinctly separate from the commissioning process. Government Acceptance Testing Representatives witness final testing of critical systems and report systems' acceptance to the COR. Submittals to be surveilled and approved by Government Acceptance Testing Representatives are identified in Section 01 33 00 SUBMITTAL PROCEDURES . Testing required to be witnessed by Government Acceptance Testing Representatives are identified in system level sections.

Owner's Project Requirements (OPR) - document that details the stakeholders' requirements for the project and the expectations for how it will be used and operated. The OPR is provided for commissioning review purposes only and is not a contract requirement.

1.3 COMMUNICATION WITH THE GOVERNMENT

The Lead Commissioning Specialist (CxC) must submit all plans, schedules, reports, and documentation directly to the Contracting Officer's Representative concurrent with submission to the QC Manager.

The Lead Commissioning Specialist must have direct communication with the Contracting Officer's Representative regarding all elements of the commissioning process; however, the Government has no direct contract authority with the Lead Commissioning Specialist.

1.4 COMMUNICATION WITH GOVERNMENT ACCEPTANCE TESTING REPRESENTATIVES

The QC Manager must communicate directly with the Government Acceptance Testing Representatives and Contracting Officer's Representative regarding Government acceptance testing activities. Inform the Contracting Officer's Representative when systems are ready for testing to be witnessed by Government Acceptance Testing Representatives, and allow access to the construction site and system(s) to be tested.

1.5 SYSTEMS TO BE COMMISSIONED

Coordinate commissioning and quality control activities for the following systems, equipment, and associated controls. System-specific requirements are located in the associated specification sections. Commission the following systems, equipment, and associated controls in accordance with this section and the inspection, testing, and quality control requirements of their respective sections:

Lighting systems: interior and exterior, automatic and manual daylighting controls, occupancy sensing devices, automatic shut-off controls, time switching, and other lighting control devices, and dimming systems

Metering and sub-metering

Plumbing Fixtures

Domestic Hot Water

SECTION 01 91 00.15 Page 2

AMENDMENT 0002 - 22 MARCH 2024

Power Distribution Systems

1.6 RELATED SECTIONS

Refer to the following technical sections for additional commissioning requirements for respective systems:

Section 26 08 00 APPARATUS INSPECTION AND TESTING

1.7 COMMISSIONING TEAM

The Commissioning team will include, but is not limited to the following team members.

Ensure all Construction Activities for systems to be commissioned are coordinated with the appropriate commissioning team members.

a. Commissioning Provider

b. Quality Control Manager (QCM)

c. Sub-Contractor Representatives for each trade responsible for construction/installation of systems to be commissioned

d. Construction Manager (CM)

e. Technical Commissioning Specialists for each system to be commissioned

f. TAB Representative f g. Equipment manufacturer representatives

gh. Government Contracting Officer i h. Government Representatives j i . Installation Maintenance Representative kj . Facility End User l k. Government Acceptance Testing Representatives

1.8 PROJECT SCHEDULE

Include the following tasks in the project schedule required by Section 01 32 17.00 20 COST-LOADED NETWORK ANALYSIS SCHEDULES (NAS) . Ensure sufficient time is scheduled to complete each item. The order of items listed below is not intended to imply a specified sequence:

a. Submission and approval of the Commissioning Firm Qualifications

b. Submission and approval of the Design Review Report

c. Submission and approval of the Interim and Final Construction Phase Commissioning Plans

d. Commissioning Kickoff Meeting

SECTION 01 91 00.15 Page 3

AMENDMENT 0002 - 22 MARCH 2024

e. Regular Commissioning Coordination Meetings

f. Installation of permanent utilities (gas, water, electric, steam)

g. Building Enclosure Construction

h. Submission and approval of the Completed Building Enclosure Inspection Checklists

i. Manufacturer's Equipment Start-Up for each of the systems to be commissioned

j. Submission and approval of the Completed Commissioning Observation Checklists

j. Submission and approval of Certificate of Readiness for each system to be commissioned

k. Commissioning Testing, including Functional Performance Testing, for each system to be commissioned

l. Post-test deficiency correction for each system to be commissioned

m. Re-Testing

n. Training for each of the systems to be commissioned

o. Submission and approval of the Initial and Final Commissioning Reports

p. Seasonal Testing

q. Final testing required to be witnessed by Government Acceptance Testing Representatives, as identified in system level sections.

r. Updated Commissioning report

1.9 SUBMITTALS

Government approval is required for submittals with a "G" classification.

Submittals not having a "G" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-06 Test Reports

Completed Construction Observation Checklists; G

Design Review Report; G

Interim Construction Phase Commissioning Plan; G

Final Construction Phase Commissioning Plan; G; S

Initial Commissioning Report; G

Issues Log; G

SD-07 Certificates

SECTION 01 91 00.15 Page 4

AMENDMENT 0002 - 22 MARCH 2024

Commissioning Firm; G

SD-11 Closeout Submittals

Final Commissioning Report; G

1.10 COMMISSIONING FIRM

Employ the services of a Commissioning Firm and all Commissioning Specialists required to perform work for this project. The Commissioning Firm must be a first-tier subcontractor that is financially and corporately independent from prime contractor and all other subcontractors and the Designer of Record and that is not participating in any other work on this Contract, including design, furnishing equipment, construction, or testing, adjusting, and balancing.

a. Submit the Commissioning Firm's and Commissioning Specialists' qualifications, including the name of the firm and each CxC and each certification, no later than 60 calendar days after contract award .

b. If, for any reason, a specialist loses a certification during this period, immediately notify the Contracting Officer and submit another Commissioning Specialist for approval. An approved successor must validate all work performed for this project by the CxC who lost a certification.

1.10.1 Commissioning Specialists (CxC)

Assign Lead Commissioning Specialist and other appropriate Commissioning Specialists for the systems to be commissioned.

1.10.1.1 Lead Commissioning Specialist (CxC)

Lead Commissioning Specialist (CxC) coordinates all aspects of the commissioning process. Duties include leading and overseeing the commissioning work and acting as the primary point of contact for the commissioning work. CxC may serve as a systems Specialist if all requirements for both designations are met. CxC must have a minimum of five years of commissioning experience, including two projects of similar size and complexity to this project.

CxC must be certified in one of the following:

NEBB Building System Commissioning Professional (CxCP)

ACG Certified Commissioning Authority (CxA)

ICB/TABB Certified Commissioning Supervisor

BCA Certified Commissioning Professional (CCP)

AEE Certified Building Commissioning Professional (CBCP)

University of Wisconsin-Madison Qualified Commissioning Process Provider (QCxP)

ASHRAE Building Commissioning Professional (BCxP).

SECTION 01 91 00.15 Page 5

AMENDMENT 0002 - 22 MARCH 2024

1.10.1.2 Commissioning Specialists

Refer to the related technical commissioning specification section for additional qualifications for each Commissioning Specialist associated with each system. Include all Commissioning Specialist qualifications with the Commissioning Firm submittal:

a. Mechanical Commissioning Specialist: The technical work associated with mechanical systems to be commissioned must be performed by a Commissioning Specialist certified by NEBB, ACG, ICB/TABB, AEE, University of Wisconsin-Madison, ASHRAE, or BCA in the commissioning of HVAC systems with five years of experience in the commissioning of HVAC systems.

ba. Electrical Commissioning Specialist: The technical work associated with electrical systems to be commissioned must be performed by an engineering technician with five years of experience inspecting, testing, and calibrating electrical distribution and generation equipment, systems, and devices. The lead engineering technician specified in specification Section 26 08 00 APPARATUS INSPECTION AND TESTING may serve as the Electrical Commissioning Specialist.

1.11 COMMISSIONING STANDARD

Comply with the requirements of the commissioning standard under which the Commissioning Firm and Specialists qualifications are approved. When the firm and specialists are certified by BCA, AEE, ASHRAE, or the University of Wisconsin-Madison, comply with the requirements of one of these acceptable standards: ACG Commissioning Guideline , NEBB S1110, ANSI/SMACNA 014 , or ASHRAE 202. In a conflict, the most stringent requirements apply. In addition, comply with ASHRAE 90.1 - IP commissioning requirements for all systems. Refer to related technical commissioning specification sections for additional standards requirements. Comply with applicable International Electrical Testing Association (NETA) testing standards for electrical systems. The following requirements apply to all project commissioning and test standards:

a. Implement all recommendations and suggested practices contained in the Commissioning Standard and test standards.

b. Use the Commissioning Standard for all aspects of Commissioning, including calibration of instruments.

c. Where the instrument manufacturer calibration recommendations are more stringent than those listed in the Commissioning Standard, adhere to the manufacturer calibration recommendations.

d. All quality assurance provisions of the Commissioning Standard such as performance guarantees are part of this contract.

e. The Commissioning Specialists must develop commissioning procedures for any systems or system components not covered in the Commissioning Standard.

f. Use any new requirements, recommendations, and procedures published or adopted by the body responsible for the applicable Commissioning

SECTION 01 91 00.15 Page 6

AMENDMENT 0002 - 22 MARCH 2024

Standards at the time of project award.

g. If there is a conflict between the requirements of the contract documents and the commissioning standard used, the contract documents take precedent.

1.12 ISSUES LOG

The Commissioning Specialist develops and maintains an Issues Log for the systems to be commissioned. The issues log documents and tracks resolution of deficiencies identified during submittal reviews, inspection, and testing. At any point during construction, any commissioning team member finding deficiencies may communicate those deficiencies in writing to the Commissioning Specialist for inclusion into the Issues Log. For each issue, the Issues Log includes, but is not limited to, a unique reference number, description of the issue with contract requirement referenced, location of or equipment name/tags exhibiting the issue, the initials of the individual's name whom reported the issue, the date of first observation, the proposed resolution of the issue and date proposed, the date of any subsequent observations with applicable additional information, and the date of implementation of the final resolution of the issue as confirmed by the Commissioning Specialist and Contracting Officer. Issues must not be deleted from the issues log.

CxC must submit the Issues Log monthly and within three working days from changes to the Issue Log. The CxC is responsible for distributing the Issues Log to the Commissioning Team. The QC manager is responsible for notifying the CxC and Contracting Officer of outstanding deficiencies and tracking them to resolution in accordance with Section 01 45 00.00 20 QUALITY CONTROL, "Quality Control Plan".

1.13 CERTIFICATE OF READINESS

Prior to scheduling Commissioning Tests for each system, the Quality Control Manager must issue a Certificate of Readiness for each system, certifying that inspections have been completed, open issues have been resolved, and the system is ready for Commissioning Tests. Refer to each related technical commissioning specification section for additional requirements.

Submit the Certificate of Readiness for each system 20 working days prior to Commissioning Tests of that system. Do not schedule Commissioning Tests for a system until the Certificate of Readiness is approved by the Government.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

3.1 DESIGN REVIEW

The CxC and other Commissioning Specialists must review design documents.

Provide a Design Review Report identifying discrepancies or deficiencies that would prevent the systems to be commissioned from operating or performing in accordance with the design requirements or being safely maintained. Report must include individual list of each deficiency and

SECTION 01 91 00.15 Page 7

AMENDMENT 0002 - 22 MARCH 2024

corresponding corrective action necessary for proper system performance.

Identify any discrepancies between the design and the Owner's Project Requirements Document. The Owner's Project Requirements Document is provided for commissioning review purposes only and does not form a part of the contract documents for this project. Submit the Design Review Report no later than 14 calendar days after approval of the Commissioning Firm and Commissioning Specialists . The Contracting Officer, Construction Manager, the CxC, and the Designers of Record for the associated systems must meet, discuss, and resolve any outstanding items contained in the report no later than 14 calendar days after submission of the report.

3.2 CONSTRUCTION SUBMITTAL REVIEWS

Coordinate construction submittal document reviews for commissioned systems and assemblies with the CxC. The commissioning submittal review does not replace the Government submittal review, in accordance with Section 01 33 00 SUBMITTAL PROCEDURES .

The CxC must identify construction submittals to be provided by the contractor for the commissioned systems. The CxC must evaluate construction submittals for compliance with the contract documents.

Include a copy of the submittal document review transmittal and response in the Commissioning Report.

3.3 COMMISSIONING KICKOFF MEETING

Conduct a Commissioning Kickoff Meeting, led by the CxC, after approval of the Commissioning Firm and Commissioning Specialists, and no later than 60 days following construction notice to proceed. Discuss the commissioning process including contract requirements, lines of communication, roles and responsibilities, schedules, documentation requirements, inspection and test procedures, and logistics as specified in this section.

The Construction Manager, Quality Control team, Designer of Record, and the Government Acceptance Testing Representatives and other Government team members must attend this meeting. Invite the User and a Public Works Division Representative to attend this meeting.

3.4 REGULAR COMMISSIONING COORDINATION MEETINGS

The Quality Control team, Designer of Record, and the Government Acceptance Testing Representatives and other Government team members must attend this meeting. Sub-Contractor Representatives for each trade responsible for construction/installation of systems to be commissioned must attend this meeting as requested by the CxC. Invite the User and a Public Works Division Representative to attend this meeting.

CxC must conduct monthly commissioning coordination meetings when installation of commissioned systems begins. Provide status of commissioned systems, open issues log items, outstanding submittals, and upcoming commissioning activities. Conduct bi-weekly commissioning coordination meetings within 30 days of the scheduled date for commissioning testing.

3.5 CONSTRUCTION PHASE COMMISSIONING PLANS

The Interim Construction Phase Commissioning Plan identifies the commissioning and testing standards and outline the overall commissioning process, the commissioning schedule, the commissioning team members and

SECTION 01 91 00.15 Page 8

AMENDMENT 0002 - 22 MARCH 2024

responsibilities, lines of communication, documentation requirements for the construction phase of the project. Submit the Interim Construction Phase Commissioning Plan, prepared by the CxC, 14 calendar days after the Construction Commissioning Coordination Meeting and 14 days prior to the start of construction of the building enclosure.

The Final Construction Phase Commissioning Plan includes the information provided in the Interim Construction Phase Commissioning Plan as well as commissioning construction observation checklists and test procedures such as Pre-Functional Checklists and Functional Performance Test Checklists and other Commissioning Test Checklists for each building, for each system required to be commissioned, and for each component for inclusion in the Final Construction Phase Commissioning Plan. Refer to the related technical commissioning specification section for additional requirements for checklists. Submit the Final Construction Phase Commissioning Plan, prepared by the CxC, no later than 90 calendar days prior to the start of Commissioning Inspections.

3.5.1 Construction Observation Checklists

Construction Observation Checklists must include items for physical inspection or testing that demonstrate that installation and start-up of equipment and systems is complete. Refer to paragraph COMMISSIONING INSPECTIONS. Construction observation checklists must be tailored to verify the specific installation requirements and details of the construction documents and manufacturer's instructions.

3.5.2 Test Procedures and Checklists

Test procedures and checklists must include procedures that explain, step-by-step, the actions and expected results that will demonstrate that the systems perform in accordance with the contract. Refer to paragraph COMMISSIONING TESTS. Include the following sections and details appropriate to the systems being tested in the test procedures and checklists:

a. Notable system features including information about controls to facilitate understanding of system operation

b. Conclusions and recommendations. Conclusions must clearly indicate if system does or does not perform in accordance with contract requirements. Recommendation must clearly indicate that the system should or should not be approved by the Government.

c. Test conditions including date, beginning and ending time, and beginning and ending outdoor air conditions

d. Attendees

e. Identification of the equipment involved in the test

f. Control system feature identification

g. As-found condition of the system operation

h. List of test items with step numbers along with the corresponding feature or operation, intended test procedure, expected system response, and pass/fail indication.

SECTION 01 91 00.15 Page 9

AMENDMENT 0002 - 22 MARCH 2024

i. Space for comments for each test item.

3.6 COMMISSIONING INSPECTIONS

Complete inspections using Construction Observation Checklists for each individual item of equipment or system for each system required to be commissioned in accordance with the commissioning plan. Indicate commissioning team member inspection and validation of each checklist item by initials. Validation of each checklist item by each team member indicates that item conforms to the contract documents and design in their area of responsibility. Commissioning Specialist validation of each checklist item indicates that each item has been installed correctly and in accordance with contract documents. Submit the initialed and Completed Construction Observation Checklists no later than 7 calendar days after completion of inspection of all checklists items for each system.

3.7 COMMISSIONING TESTS

Demonstrate that all systems, equipment, and components have been installed correctly and that the systems operate and perform, including interactive operation between systems, in accordance with contract documents. Perform tests as specified in related technical commissioning specifications. Provide all materials, services, and labor required to perform all commissioning tests.

Commissioning Specialist's duties include leading and documenting all tests for the systems to be commissioned with appropriate sub-contractors performing the Tests. The representatives listed in the paragraph COMMISSIONING TEAM must attend the tests with the exception of the Construction Manager .

3.7.1 Test Scheduling and Coordination

Schedule Commissioning Tests for each system only after the Certificate of Readiness has been approved by the Government for the system. Correct all deficiencies identified through any prior review, inspection, or test activity before the start of Commissioning tests.

Commissioning Tests must be performed with the CxC present. Government reserves the right to witness all tests. Coordinate test schedule with Government representatives.

3.7.2 Testing Procedures

Commissioning tests include tests such as functional performance and integrated systems tests. Perform test procedures in accordance with the commissioning standards specified. In addition, comply with the testing procedures specified in the sections listed in paragraph RELATED SECTIONS.

3.7.3 Sample Strategy

Refer to the sections identified in paragraph RELATED SECTIONS for sample strategy.

For electrical systems, test 100 percent of all equipment and systems except for the following. Test at the sample rate shown:

a. Lighting Controls 50%

SECTION 01 91 00.15 Page 10

AMENDMENT 0002 - 22 MARCH 2024

3.7.3 Aborted Tests and Re-Testing

Abort any test if any deficiency prevents successful completion of the test or if any required commissioning team member is not present for the test. Re-test after all deficiencies identified during the original test have been corrected. Contracting Officer may withhold payment equivalent to lost time, re-testing, and aborted tests. These costs may include salary, travel costs, and per diem for Government team members.

3.8 TRAINING PLAN

CxC must review the training plan for training associated with the equipment and systems to be commissioned, checking that each plan has the trainer name, trainer contract information, training schedule and location. Submit review at least 30 days prior to the first training event. Incorporate CxC review comments prior to submitting training plan in accordance with Section 01 78 23 OPERATION AND MAINTENANCE DATA and 01 78 24.00 20 FACILITY DATA WORKBOOK (FDW) . Update and resubmit the training plan based on any corrective action taken.

3.9 COMMISSIONING REPORT

Submit an Initial Commissioning Report no later than 14 calendar days following commissioning team validation of all Commissioning Tests, including Functional Performance Tests,, with the exception of Seasonal Tests. Submit a Final Commissioning Report upon completion of training and trend log reviews. Include the following information in the Final Commissioning Report:

a. An executive summary describing the overall commissioning process, the results of the commissioning process, outstanding deficiencies and recommended resolutions, and seasonal testing that must be scheduled for a later date. Indicate, in the executive summary, whether the systems meet the requirements of the contract documents.

b. A list of deficiencies discovered during the commissioning process and the corrective actions taken in the report.

c. Completed Pre-Functional Checklists and other Commissioning Observation Checklists, Commissioning Test Checklists such as Functional Performance Test Checklists the Final Construction Phase Commissioning Plan, the Issues Log, Training Attendance Rosters, the Design Review Reports, Submittal Review Report, and any other documents as specified by related technical commissioning specification sections.

SECTION 01 91 00.15 Page 11

AMENDMENT 0002 - 22 MARCH 2024

APPENDIX A - OWNER'S PROJECT REQUIREMENTS DOCUMENT

-- End of Section --

SECTION 01 91 00.15 Page 12

AMENDMENT 0002 - 22 MARCH 2024

Owner’s Project Requirements

FY24 MCONP-870 9th Engineering Support Battalion (ESB) Training Complex, Camp Blaz, Marine Corps Base, Guam i

Owner’s Project Requirements

1. Owner and User Requirements

a. Primary Purpose, Program, and Use

b. Project History

c. Broad Goals

i. Future Expansion

ii. Flexibility

iii. Quality of Materials

iv. Construction Costs

v. Operational Costs

vi. Broad Goals Relative to Life Cycle of the Equipment

2. Environmental and Sustainability Goals

a. Guiding Principles Assessment

b. Other

3. Energy Efficiency Goals

a. Goals/Policy

b. Systems and Building Features Energy Impact

4. Indoor Environmental Quality Requirements

a. Space Type: Head

i. Intended Use

ii. Occupancy Schedule

iii. Environmental Requirements

iv. Occupant System Control Ability

v. Type of Lighting

vi. After-Hour Use Accommodation

5. Equipment and System Expectations

a. Lighting Systems

i. Quality and Reliability

ii. Type

iii. Automation

iv. Flexibility

v. Maintenance Requirements

b. Domestic Hot Water Systems

i. Quality and Reliability

ii. Type

iii. Automation

iv. Flexibility

v. Maintenance Requirements

6. Building Occupant and O&M Personnel Requirements

a. Facility Operation

b. EMCS

c. Occupant Training and Orientation

d. O&M Staff Training and Orientation

e. O&M Staff Requirements

1. Owner and User Requirements

a. Primary Purpose, Program, and Use

The P-870 project is to construct a Training Complex for the 9th Engineering Support Battalion (ESB). The project is primarily site work with only two buildings, Head and Bleacher. The Head building provides enclosed restrooms with natural ventilation and the Bleacher is open air with exterior lighting. The project will be located on Marine Corps Base Camp Blaz.

b. Project History

The DD1391 dated 03 May 2022 was provided to list the requirements. A Final Charrette Report dated 21 December 2022 was provided as a summary of the Final Design Authorization (FDA) Design Charrette conducted on 24 October 2022. Input was provided from the Users, Government planners, Government AE team and the Design team.

Design-Bid-Build was selected as the contract acquisition method for the project. The DD1391 serves as contract requirement for the Design Team and this OPR does not serve as a contract document.

c. Broad Goals

i. Future Expansion Future expansion was not listed in the DD1391 and was not noted as a requirement during stakeholder meetings.

ii. Flexibility Provide flexibility with respect to the site to provide allow for different field exercises.

Flexibility for Head and Bleacher are not required.

iii. Quality of Materials

The new buildings materials must comply with Unified Facilities Criteria (UFC) and Marianas Navy and Marianas Corps Design and Construction Standards (MDACS).

Building materials shall be compatible with tropical marine climate which is corrosive because of constant sun, rain, salt, humidity, winds and other detrimental environmental aspects. The Head and Bleacher will be unconditioned and exposed to corrosive climate. Specify low maintenance, durable materials.

Sustainable design strategies are required to be integrated into the design as applicable per the requirements of UFC 1-200-02 High Performance and Sustainable Building Requirements to reduce the total cost of ownership of the project using a whole building life-cycle approach. This is to minimize the energy consumption of the facility, integrate design, conserve resources, minimize adverse effects to the environment, and improve occupant productivity, health and comfort.

iv. Construction Costs Construction cost shall be the most economic possible, without compromising the quality of materials, integrity of installation and timeline allowed for the project.

v. Operational Costs Minimize operating costs as much as possible within first budget cost. P-870 must be designed per UFC 1-200-02 High Performance and Sustainable Building Requirements, and meet or exceed 30% energy efficiency for a new construction project. For P-870, the energy savings is only realized for lighting as LED lighting is provided and buildings are unconditioned.

vi. Broad Goals Relative to Life Cycle of the Equipment

HVAC equipment is not required for P-870 and LED lighting was selected for the proposed lighting system.

2. Environmental and Sustainability Goals

a. Guiding Principles Assessment

Integrate sustainable strategies and features into the design as applicable to minimize the energy consumption of the facility, conserve resources, minimize adverse effects to the environment, and improve occupant productivity, health, and comfort to reduce the total cost of ownership of the renovation project using a whole building, life-cycle approach. The design and construction shall incorporate sustainable design strategies and features to the fullest extent possible, especially related to energy and water, consistent with mission, budget and client requirements.

b. Other

Site hardscape, stormwater management, site landscape shall meet UFC 1-200-02 High Performance and Sustainable Building Requirements.

3. Energy Efficiency Goals

a. Goals/Policy

The facility shall meet UFC 1-200-02 High Performance and Sustainable Building Requirements, ASHRAE 90.1 2013 Optimize Energy Performance and IgCC 2018 International Green Construction Code. This facility has a targeted goal to achieve a 30% energy use reduction below an ASHRAE 90.1 2013 baseline building.

b. Systems and Building Features Energy Impacts

P-870 buildings shall be constructed of materials that respond well to the tropical and coastal environment, while reducing the effects of heat and humidity on the building interior. Use sustainable building materials with corrosion resistance and low VOC.

4. Indoor Environmental Quality Requirements

a. Space Type: Head

i. Intended Use The intended use of Head is to provide restrooms for the site.

ii. Occupancy Schedule

The Head is typically unoccupied and will be used intermittingly based on site training.

iii. Environmental Requirements

New Lighting: According to UFC 3-501-01 Electrical Engineering, UFC 3-530-01 Interior and Exterior Lighting Systems and Controls, UFGS 26 51 00 Interior Lighting, and Illuminated Engineering Society Lighting Handbook.

Temperature & Humidity: Unconditioned Air Quality: Natural Ventilation Ventilation: Natural Ventilation according to ASHRAE 62.1, 2013.

iv. Occupant System Control Ability

Interior Lighting: Automatic lighting controls with manual override Temperature: Not applicable Humidity: Not applicable Air Quality: Not applicable Ventilation: Not applicable

v. Type of Lighting

Illumination for new lighting fixtures shall be provided with LED light sources.

vi. After-Hour Use Accommodation

The Head can be used at any time depending on site use.

5. Equipment and System Expectations

a. Lighting Systems

i. Quality and Reliability

The building lighting system should meet ASHRAE 90.1 2013 requirements.

ii. Type

Interior and Exterior lighting systems will utilize LED light fixtures.

iii. Automation Occupancy sensors will be installed in applicable areas such as Head building.

iv. Flexibility

Not required.

v. Maintenance Requirements System must be maintainable.

b. Domestic Hot Water Systems

i. Quality and Reliability

The domestic hot water system should meet ASHRAE 90.1 2013 requirements.

Water heating systems should remain serviceable over life of building or to the extent typical of the type of equipment

ii. Type The primary water heating equipment will be instantaneous water heaters.

iii. Automation Not required

iv. Flexibility Plumbing layout will remain mostly unchanged; no flexibility required.

v. Maintenance Requirements Equipment should be located to allow easy maintenance access. Equipment vendors or repair service should be able to respond within 24 hrs.

6. Building Occupant and O&M Personnel Requirements

a. Facility Operation

The facility will be operated and maintained by MCBCB Facilities.

b. EMCS

A building automation system is not required. Industrial Control System (ICS) includes electric and water meter only.

c. Occupant Training and Orientation

The building occupants are to defer to MCBCB Facilities service staff for maintenance.

d. O&M Staff Training and Orientation

The O&M staff will require training in order to maintain the lighting controls and plumbing systems.

e. O&M Staff Requirements

The O&M staff desires clearly documented O&M manuals specific to the equipment installed, first class quality work, and thorough training of lighting systems.

DESIGN PHASE PLAN

Total Building Commissioning

FY24 MCONP-870 9th Engineering Support Battalion (ESB) Training Complex, Camp Blaz, Marine Corps Base, Guam

Prepared by: AMEL Technologies, Inc.

2800 Woodlawn Dr. Ste. 251

Honolulu, Hawaii

AMENDMENT 0002 - 22 MARCH 2024

i P-870 9th Engineering Support Battalion (ESB) Training Complex, Camp Blaz, MCB, Guam

Table of Contents

1.0 Commissioning Program Overview

1.1 Goals and Objectives

1.2 Abbreviations and Definitions

1.3 Building Information

1.4 Systems to be Commissioned

2.0 Commissioning Team Members, Roles and Responsibilities

2.1 Commissioning Team

2.1.1 Owner

2.1.2 Commissioning Authority (CxA)

2.1.3 Commissioning Team Members

2.2 Roles and Responsibilities

2.2.1 General

2.2.2 Roles and Responsibilities

2.3 Communication Protocol, Coordination, Meetings and Management

2.3.1 Coordination of Commissioning During Design

2.3.1.1 Meetings

2.3.2 Coordination of Commissioning During Construction

2.3.3 Communication Protocols

3.0 Commissioning Tasks

3.1 Overview of Commissioning Tasks

3.2 Description of Commissioning Tasks

3.2.1 Basis of Design

3.2.2 Commissioning Specification Development

3.2.3 Review of Drawings and Specifications

3.2.3.1 Commissioning Facilitation

3.2.4 Pre-functional Checklists, Tests and Startup

3.2.4.1 Development of Pre-Functional Checklists and Start-up Forms

3.2.4.2 Execution of Checklists and Startup

3.2.4.3 Deficiencies and Non-conformance

3.2.5 Development of Functional Test and Verification Procedures

3.2.5.1 Overview

ii

3.2.5.2 Scope of Testing

3.2.5.3 Development Process

3.2.5.4 Testing Plan Overview

3.2.6 Execution of Functional Testing Procedures

3.2.6.1 Overview and Process

3.2.6.2 Deficiencies and Retesting

3.2.6.3 Facility Staff and DOR Participation

3.2.6.4 Sampling

3.2.6.5 Electrical System Commissioning

3.2.7 O&M Manuals and Warranties

3.2.7.1 Standard O&M Manuals

3.2.8 Training and Orientation of Owner Personnel

3.2.9 Summary Report

3.3 Warranty Period Activities

4.0 Schedule

4.1 Design Phase Schedule

4.2 Construction Phase Schedule

1.0 Commissioning Program Overview

1.1 Goals and Objectives

Commissioning (Cx) is a systematic process of ensuring that all the building’s energy related systems are installed and calibrated and perform interactively according to the design intent and operational needs. This is achieved by beginning at the design phase with documented design and operating intent and continuing through construction and acceptance with actual verification of performance.

The purpose of commissioning plan is to identify the scope, strategies and responsibilities for all of the team members within the commissioning process for design and construction phases of the project. It outlines the overall process, schedule, organization, responsibilities and documentation for the commissioning process.

Commissioning during design is intended to achieve the following specific objectives:

Ensure that the design and operational intent are clearly documented.

Ensure that recommendations are communicated to the design team during design to aid the development of commissioning and avoid later contract modifications.

Ensure that commissioning for the construction phase is adequately reflected in the construction documents.

Commissioning during the construction of this project is intended to achieve the following specific objectives:

Ensure that applicable equipment and systems are installed properly and receive adequate operational checkout by installing contractors.

Ensure building envelope is air-tight and spaces receive positive pressurization when specified.

Verify and document proper performance of equipment and systems through normal and other likely operational modes necessary to meet design intent.

Ensure that O&M documentation provided to Owner is complete.

Ensure that the Owner’s operating personnel are adequately trained.

1.2 Abbreviations and Definitions

The following are common abbreviations used in this document.

BOD Basis of Design HVAC Heating, Ventilating and Air

Conditioning CxA Commissioning Authority FT Functional Performance Test CxM Commissioning – Mechanical

Systems Technical Specialist (under CxA)

GC General Contractor

CxE Commissioning – Electrical HC HVAC Contractor Systems Technician Specialist

(under CxA)

CxB Commissioning – Building Envelope Specialist (under CxA)

MER Mechanical Engineer Rep

CC Controls Contractor MMR Maintenance Management Rep (Gov) CM Construction Manager (Govt) OPR Owner’s Project Requirements Cx Commissioning Cx Plan Commissioning Plan Document OSR Operating Staff Rep (Gov) DM Design Manager (Gov) QCR Quality Control Rep (under GC) DOR Designer of Record PC Pre-functional Checklist EC Electrical Contractor PLC Plumbing Contractor EER Electrical Engineer Rep Subs Subcontractors to General EMR Energy Management Rep (Gov) TAB Test and Balance Contractor ESR Engineering Staff Rep (Govt) USER Facility User/Occupant

1.3 Building Information

Project Name: P-870 9th Engineering Support Battalion (ESB) Training Complex

Location: Marine Corps Base Camp Blaz, Guam

Agency: NAVFAC Pacific

Tenants: Marines

Building Type: Public Head and Covered Bleachers, Primarily outdoor training site

Area: 900 SF Expected number of stories: 1

Design Period: 2022-2023 Construction Period: 2024-2026

1.4 Systems to be Commissioned

The following systems will be commissioned in this project for the building:

Energy and Water Utility Metering Systems

2.0 Commissioning Team Members, Roles and Responsibilities

2.1 Commissioning Team

The members of the commissioning team consist of the CxA and CxA-Technical Specialists, the Government’s Acceptance Engineer, DM, CM, GC and QCR, assigned members of the AE Team (particularly the mechanical engineer, architect and electrical engineer), the general contractor, mechanical contractor, electrical contractor and any other installing subcontractors or suppliers of equipment. The Owner’s engineering staff, operating staff, and maintenance staff are also members of the commissioning team.

2.1.1 Owner

The facility is a Government facility, maintained and operated by MCB Camp Blaz Facilities.

The User is the 9th Engineering Support Battalion. The Design Team follows the Navy design standards and guidelines. The design review team includes members from NAVFAC Pacific and MCB Camp Blaz. CxA and CxA-Technical Specialists provide reviews from a commissioning standpoint. The Government’s acceptance engineer will participate in acceptance testing during the construction phase.

2.1.2 Commissioning Authority (CxA)

During the design phase, the CxA for this project is a consultant of the DOR firm who is not on the DOR team. AMEL Technologies will perform Cx Design Reviews and will lead design phase commissioning. During the construction phase, the Cx will be provided by contractor.

2.1.3 Commissioning Team Members

Team Member

Co. & Contact Names

Tel, email address

Owner Project Manager

Design Managers

Michael Lau NAVFAC Pacific DC2

Shannon Kimoto NAVFAC Pacific DC45 michael.d.lau.civ@us.navy.mil shannon.m.kimoto.civ@us.navy.mil

Construction Manager Engineering Staff Rep Operating Staff Rep Maintenance Management Rep.

Energy Management Rep General Contractor Project Manager

Contractor Commissioning Coordinator

Commissioning Authority

Steve Hobus Melek Yalcintas AMEL Technologies

(808) 988-0200 steve@ameltech.com melek@ameltech.com

Architect

Betty Gayle Setiadi Architects

(671) 477-3566 b.gayle@satiadiarchitects.com

Electrical Designer/Eng.

Abner Mariano EMCE Consulting Engineers

(671) 649-0166 am@emceconsulting.com

Mechanical Designer/Eng.

Carey Nakagawa Thermal Engineering Corporation

(808) 356-2453 cnakagawa@thermaleng.com

Electrical Sub-Contractor

Plumbing Sub-Contractor

Electric System Testing Contractor

2.2 Roles and Responsibilities

2.2.1 General

General descriptions of the commissioning roles are as follows:

CxA: Primary point of contact for the government regarding the commissioning work. Coordinates the Cx process, develops and updates Cx Plan, provide review of design documents in reference to Owner’s Project Requirements, reports any deficiencies that would prevent the building systems and features from operating or performing effectively, reviews construction documents for commissioning requirements, oversees the commissioning work. Develops and maintains an Issues Log for tracking and resolution of all deficiencies discovered through commissioning review, inspection, and testing.

CxM: Member of CxA Team. Reviews construction documents for commissioning requirements for HVAC Systems, plumbing systems and lighting controls, reports any HVAC and plumbing design deficiencies that would prevent the building systems and features from operating or performing effectively. Writes or approves commissioning tests, oversees and documents performance tests.

Develops commissioning report.

CxE: Member of CxA Team. Conducts electrical systems tests.

CxB: Member of CxA Team. Reviews construction documents for commissioning requirements for Building Envelope, reports any building envelope design deficiencies that would prevent the building systems and features from operating or performing effectively. Conducts building envelope tests.

CM: Performs construction management. Coordinates with GC and CxA.

Facilitates the Cx process. Approves test plans and signs-off on performance.

Performs construction observation, approves O&M manuals (design- build contracts).

GC: Facilitates the Cx process. Ensures that Subs perform their responsibilities and integrates Cx into the construction process and schedule.

QCR: Responsible for overall coordination of the General Contractor and sub-contractors in the execution of the commissioning activities.

Subs: Demonstrate proper system performance.

DOR: Develops and updates Basis of Design, incorporates commissioning requirements in construction documents. Performs construction observation, approves O&M manuals (design-build contracts) and assists in resolving problems.

DM: Supports the Cx process.

Mfr.: The equipment manufacturers and vendors provide documentation to facilitate the commissioning work and perform contracted startup.

2.2.2 Roles and Responsibilities

Detailed roles and responsibilities for this project’s commissioning tasks are indicated in the following table:

Commissioning Tasks and Responsibilities Responsibility of Task

Commissioning Plan DM DOR CxA EMR ESR OSR MMR CM GC TAB CC MC EC Subs

Prepare and update

Coordinate input from involved parties

Review and approve (incl. updates)

Provide to AE at start of design

Provide to GC at start of construction

Owners Project Requirements

Participate in development/update

Provide to AE at start of design

Basis of Design Document

Commissioning Specifications

Design Reviews for Commissioning

Prefunctional Checklists, Testing & Startup

Coordinate schedule

Prepare prefunctional checklists checklists

Execute prefunctional tests

Witness prefunctional tests

Verify prefunctional tests and startup are complete

Functional Testing

Coordinate schedule

Develop functional test procedures

Develop Testing Plan Overview

Execute tests Witness tests

Document test results

O&M Manuals & Warranties

Include requirements in specifications

Review

Prepare submittals Review submittals

Assemble approved submittals

Coordinate transfer to Facility Manager

Owner Training

Include requirements in

Review

Prepare training plan submittals

Review submittals Provide Training

Coordinate Training Attendance

Verify training completion

Assemble training documents

Commissioning Report

Prepare report

2.3 Communication Protocol, Coordination, Meetings and Management

2.3.1 Coordination of Commissioning During Design

The DM will be the coordinator of the commissioning activities during design. The CxA for the design phase makes any necessary clarifications and changes to the Commissioning Plan.

2.3.1.1 Meetings

The DM will be the coordinator of the commissioning meetings during design. A kick-off meeting will be held with the design team at the beginning of Construction Documents Phase.

This meeting is held after the Cx Plan has been finalized. The meeting includes reviewing the process and outlining each party’s responsibilities. This meeting may be combined with a larger meeting agenda.

Design review conferences will include an agenda item for commissioning if the CxA or the DOR asks the DM to place it on the meeting agenda. The CxA will attend all design review meetings that include an agenda item for commissioning.

2.3.2 Coordination of Commissioning During Construction

In general, the CxA coordinates the commissioning activities and reports to the CM and GC.

The CxA’s responsibilities, along with all other contractors’ commissioning responsibilities are detailed in the specifications. The Specifications will take precedence over this Cx Plan. All members work together to fulfill their contracted responsibilities and meet the objectives of the Contract Documents.

2.3.3 Communication Protocols

The following protocols will be used on this project.

Issue Protocol

For requests for information (RFI) or formal documentation requests:

Construction: The CxA goes through the CM.

For minor or verbal information and clarifications:

The CxA goes directly to the informed party.

For notifying contractors of deficiencies: Construction: The CxA documents deficiencies through the CM, but may discuss deficiency issues with contractors prior to notifying the CM.

For scheduling functional tests or training: The CxA may provide input for and do some coordination of training and testing, but does not do any scheduling.

For scheduling commissioning meetings: Construction: The CxA selects the date and schedules through the CM and GC.

For making a request for significant changes: The CxA has no authority to issue change orders.

Issue

For making small changes in specified sequences of operations:

Protocol

The CxA- may make small sequences of operations changes to improve efficiency or control or to correct deficiencies, through the responsible contractor, but shall document the change and provide all changes of specified sequences to the CM, MER and DOR.

The CxA may not make changes to specified major sequences without approval from the MER and DOR.

Subcontractors disagreeing with requests or interpretations by the CxA shall:

Try and resolve with the CxA first. Then work through GC who will work with CxA directly or through the CM to resolve the situation.

3.0 Commissioning Tasks

3.1 Overview of Commissioning Tasks

The following tasks comprise the commissioning work:

1. Develop Owner’s Project Requirements documentation with input from Government’s Design Manager.

2. Perform a review of Basis of Design documentation

3. Perform a review of Design Development

4. Develop commissioning specifications for the construction bid documents

5. Perform a final review of the drawings and specifications

6. Prepare and execute pre-functional checklists, tests and startup

7. Develop functional test and verification procedures with integrated points list.

8. Execute functional testing

9. Review O&M manuals and warranties

10. Verify…