N6274222R1319_SPC.pdf
PDF 22 MB Posted
- Attached to
- FY22 P-2005 WORKING DOG TREATMENT FACILITY REPLACEMENT, JOINT BASE PEARL HARBOR-HICKAM, HAWAII
- Solicitation number
- N6274222R1319
About this file
This document provides details for a federal contract solicitation to construct a new veterinary treatment facility at Joint Base Pearl Harbor-Hickam in Hawaii. The solicitation is identified as N6274222R1319 and is seeking construction services to build a full-service facility to provide preventative, diagnostic, surgical and dental care for government-owned working dogs as well as privately-owned animals of service members. The facility will also include food inspection spaces. This is identified as a design-bid-build project being conducted by the Naval Facilities Engineering Command branch of the Department of the Navy.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WORK ORDER NO: 1602243
SPECIFICATIONS
(VOLUME 1 OF 2)
For
FY22 MCON PROJECT
P-2005 WORKING DOG TREATMENT FACILITY REPLACEMENT
JOINT BASE PEARL HARBOR-HICKAM, HAWAII
PREPARED BY:
Architectural: RMAA-API JV, Architects Pacific, Inc.
Interior: RMAA-API JV, Kili LLC Civil: RMAA-API JV, HDR Engineering, Inc.
Landscape: RMAA-API JV, Ki Concepts Structural: RMAA-API JV, Nagamine Okawa Engineers, Inc.
Mechanical: RMAA-API JV, Thermal Engineering Corp.
Fire Protection: RMAA-API JV, Thermal Engineering Corp.
Electrical: RMAA-API JV, MK Engineers, Ltd.
Geotechnical: RMAA-API JV, Geolabs, Inc.
Environmental: RMAA-API JV, Myounghee Noh & Associates Commissioning: RMAA-API JV, AMEL Technologies, Inc.
Medical: RMAA-API JV, Sherlock, Smith & Adams
Submitted By: _______________________________ Date: ____________ Drake Kau, AIA
APPROVED BY:
Specification: _________________________________________________ Clint Hashiba, P.E.
Design Director:________________________________________________ Evan A. Mizue, P.E.
Date: _______________________
7/30/2021
APAAAAA PRPRPPRPPRRROVEDDDDDDD B
________________ ____ ____ ____________ 7/30/2021
8/3/2021
Clint Hashiba, P.
Evan A Mizue P
P-2005 WORKING DOG TREATMENT FACILITY REPLACEMENT, JBPHH, HI 1602243
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 15 LIST OF DRAWINGS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 20 00.00 20 PRICE AND PAYMENT PROCEDURES
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 31 23.13 20 ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT
MANAGEMENT SYSTEM
01 32 17.00 20 COST-LOADED NETWORK ANALYSIS SCHEDULES (NAS)
01 33 00 SUBMITTAL PROCEDURES
01 33 29 SUSTAINABILITY REPORTING
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 45 00.00 20 QUALITY CONTROL
01 45 35 SPECIAL INSPECTIONS
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 57 19.01 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 PROJECT IDENTIFICATION
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
01 78 24.00 20 FACILITY ELECTRONIC OPERATION AND MAINTENANCE SUPPORT
INFORMATION (eOMSI)
01 91 00.15 TOTAL BUILDING COMMISSIONING
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL
02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS
02 82 00 ASBESTOS REMEDIATION
02 83 00 LEAD REMEDIATION
DIVISION 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
DIVISION 04 - MASONRY
04 20 00 UNIT MASONRY
DIVISION 05 - METALS
05 12 00 STRUCTURAL STEEL
05 30 00 STEEL DECKS
05 40 00 COLD-FORMED METAL FRAMING
05 50 13 MISCELLANEOUS METAL FABRICATIONS
05 51 33 METAL LADDERS
PROJECT TABLE OF CONTENTS Page 1
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 20 00 FINISH CARPENTRY
06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS
06 61 16 SOLID SURFACING FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS
07 13 53 ELASTOMERIC SHEET WATERPROOFING
07 21 16 MINERAL FIBER BLANKET INSULATION
07 22 00 ROOF AND DECK INSULATION
07 24 00 EXTERIOR FINISH SYSTEMS
07 27 10.00 10 BUILDING AIR BARRIER SYSTEM
07 27 19.01 SELF-ADHERING AIR BARRIERS
07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIERS
07 60 00 FLASHING AND SHEET METAL
07 61 15.00 20 ALUMINUM STANDING SEAM ROOFING
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 11 16 ALUMINUM DOORS, FRAMES, AND WINDOW WALL
08 31 00 ACCESS DOORS AND PANELS
08 34 73 SOUND CONTROL DOOR ASSEMBLIES
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
DIVISION 09 - FINISHES
09 22 00 SUPPORTS FOR GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 30 10 CERAMIC AND GLASS TILING
09 51 00 ACOUSTICAL CEILINGS
09 65 00 RESILIENT FLOORING
09 67 23.14 SEAMLESS RESINOUS FLOORING
09 90 00 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 11 00 VISUAL DISPLAY UNITS
10 14 00.10 EXTERIOR SIGNAGE
10 14 00.20 INTERIOR SIGNAGE
10 14 53 TRAFFIC SIGNAGE
10 26 00 WALL AND DOOR PROTECTION
10 28 13 TOILET ACCESSORIES
10 44 16 FIRE EXTINGUISHERS
10 44 20 FIRE DEPARTMENT ACCESS BOX
10 99 00 MISCELLANEOUS SPECIALTIES
DIVISION 11 - EQUIPMENT
11 11 37 ELECTRIC VEHICLE SUPPLY EQUIPMENT
11 70 00 GENERAL REQUIREMENTS FOR MEDICAL AND DENTAL EQUIPMENT
11 72 13 MEDICAL EQUIPMENT, MISCELLANEOUS
PROJECT TABLE OF CONTENTS Page 2
DIVISION 12 - FURNISHINGS
12 24 13 ROLLER WINDOW SHADES
12 31 00 MANUFACTURED METAL CASEWORK
12 36 00 COUNTERTOPS
12 93 00 SITE FURNISHINGS
DIVISION 13 - SPECIAL CONSTRUCTION
13 48 00 [SEISMIC ]BRACING FOR MISCELLANEOUS EQUIPMENT
DIVISION 21 - FIRE SUPPRESSION
21 13 13.00 20 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION
DIVISION 22 - PLUMBING
22 00 70 PLUMBING FOR HEALTHCARE FACILITIES
22 05 48.00 20 MECHANICAL SOUND, VIBRATION, AND SEISMIC CONTROL
22 60 70 GAS AND VACUUM SYSTEMS FOR HEALTHCARE FACILITIES
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 08 01.00 20 TESTING INDUSTRIAL VENTILATION SYSTEMS
23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC
23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING
CONTROL SYSTEMS
23 23 00 REFRIGERANT PIPING
23 35 19.00 20 INDUSTRIAL VENTILATION AND EXHAUST
23 64 10 WATER CHILLERS, VAPOR COMPRESSION TYPE
23 64 26 CHILLED AND REHEAT WATER PIPING SYSTEMS
23 73 13.00 40 MODULAR INDOOR CENTRAL-STATION AIR-HANDLING UNITS
23 81 00 DECENTRALIZED UNITARY HVAC EQUIPMENT
23 82 19.00 40 FAN COIL UNITS
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS
25 08 11.00 20 RISK MANAGEMENT FRAMEWORK FOR FACILITY-RELATED CONTROL
SYSTEMS
DIVISION 26 - ELECTRICAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 48.00 10 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT
26 08 00 APPARATUS INSPECTION AND TESTING
26 12 19.10 THREE-PHASE, LIQUID-FILLED PAD-MOUNTED TRANSFORMERS
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 24 13 SWITCHBOARDS
26 27 14.00 20 ELECTRICITY METERING
26 29 23 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS UNDER 600 VOLTS
26 32 13.00 20 SINGLE OPERATION GENERATOR SETS
26 36 23.00 20 AUTOMATIC TRANSFER SWITCHES
PROJECT TABLE OF CONTENTS Page 3
26 51 00 INTERIOR LIGHTING
26 56 00 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
27 51 16 PUBLIC ADDRESS SYSTEMS
27 54 00.00 20 COMMUNITY ANTENNA TELEVISION (CATV) SYSTEMS
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 08 10 ELECTRONIC SECURITY SYSTEM ACCEPTANCE TESTING
28 10 05 ELECTRONIC SECURITY SYSTEMS (ESS)
28 15 53 VIDEO INTERCOM SYSTEM
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM
DIVISION 31 - EARTHWORK
31 11 00 CLEARING AND GRUBBING
31 23 00.00 20 EXCAVATION AND FILL
31 31 16.13 CHEMICAL TERMITE CONTROL
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 05 33 LANDSCAPE ESTABLISHMENT
32 11 23 AGGREGATE BASE COURSES
32 12 13 BITUMINOUS TACK AND PRIME COATS
32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS
32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 PAVEMENT MARKINGS
32 31 13 CHAIN LINK FENCES AND GATES
32 92 26 SPRIGGING
32 93 00 EXTERIOR PLANTS
DIVISION 33 - UTILITIES
33 11 00 WATER UTILITY DISTRIBUTION PIPING
33 30 00 SANITARY SEWERAGE
33 40 00 STORM DRAINAGE UTILITIES
33 61 14 EXTERIOR BURIED PREINSULATED WATER PIPING
33 71 01 OVERHEAD TRANSMISSION AND DISTRIBUTION
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 4
DOCUMENT 00 01 15
LIST OF DRAWINGS
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
DRAWING NAVFAC
NO. DWG NO. TITLE
G-101 19089276 COVER SHEET
G-102 19089277 INDEX TO DRAWINGS
G-103 19089278 INDEX TO DRAWINGS CONTINUED
G-104 19089279 EXTERIOR PERSPECTIVE
G-105 19089280 INTERIOR PERSPECTIVE
G-106 19089281 FIRE PROTECTION AND LIFE SAFETY CODE SUMMARY
G-107 19089282 SITE FIRE PROTECTION AND LIFE SAFETY PLAN
G-108 19089283 FIRE PROTECTION AND LIFE SAFETY PLAN
19089284 19089285
H-001 19089286 ENVIRONMENTAL PROTECTION
H-002 19089287 PESTICIDE - CONTAMINATED SOIL LOCATIONS/RELOCATION PLAN
19089288 19089289
B-001 19089290 BORING LOG LEGEND
B-002 19089291 BORING LOG LEGEND
B-101 19089292 BORING LOCATION PLAN
B-701 19089293 BORING LOGS - 1
B-702 19089294 BORING LOGS - 2
B-703 19089295 BORING LOGS - 3
19089296 19089297
C-001 19089298 CIVIL GENERAL NOTES
C-002 19089299 EXISTING CONDITIONS PLAN
EC-101 19089300 ACCESS ROUTE PLAN
EC-102 19089301 TEMPORARY EROSION & SEDIMENT CONTROL PLAN - 1
EC-103 19089302 TEMPORARY EROSION & SEDIMENT CONTROL PLAN - 2, 3, & 4
EC-104 19089303 TEMPORARY EROSION & SEDIMENT CONTROL PLAN - 5, 6, & 7
EC-105 19089304 TEMPORARY EROSION & SEDIMENT CONTROL PLAN - 8 & 9
EC-106 19089305 TEMPORARY EROSION & SEDIMENT CONTROL DETAILS
CD-101 19089306 CIVIL DEMOLITION PLAN
CS-101 19089307 CIVIL SITE PLAN
CS-102 19089308 CIVIL SITE LAYOUT PLAN
CS-201 19089309 PAVEMENT, PARKING, AND SIGNAGE PLAN
CS-301 19089310 CIVIL SITE DETAILS - 1
CS-302 19089311 CIVIL SITE DETAILS - 2
CS-303 19089312 CIVIL SITE DETAILS - 3
CS-304 19089313 CIVIL SITE DETAILS - 4
CS-305 19089314 CIVIL SITE DETAILS - 5
DOCUMENT 00 01 15 Page 1
CS-306 19089315 CIVIL SITE DETAILS - 6
CG-101 19089316 OVERALL GRADING AND DRAINAGE PLAN
CG-102 19089317 ENLARGED GRADING AND DRAINAGE PLAN - DETAIL A
CG-103 19089318 ENLARGED GRADING AND DRAINAGE PLAN - DETAIL B
CG-104 19089319 ENLARGED GRADING AND DRAINAGE PLAN - DETAIL C & DETAIL
D
CG-201 19089320 GRADING AND DRAINAGE DETAILS - 1
CG-202 19089321 GRADING AND DRAINAGE DETAILS - 2
CG-203 19089322 GRADING AND DRAINAGE DETAILS - 3
CU-101 19089323 OVERALL UTILITIES PLAN
CU-201 19089324 SEWER IMPROVEMENT PLAN AND PROFILE
CU-202 19089325 ROOF DRAIN PROFILES
CU-203 19089326 WATER LINE PROFILES
CU-301 19089327 CIVIL UTILITY DETAILS - 1
CU-302 19089328 CIVIL UTILITY DETAILS - 2
CU-303 19089329 CIVIL UTILITY DETAILS - 3
CU-304 19089330 CIVIL UTILITY DETAILS - 4
CU-305 19089331 CIVIL UTILITY DETAILS - 5
19089332 19089333 19089334 19089335
LD001 19089336 TREE PROTECTION NOTES
LD102 19089337 TREE DISPOSITION PLAN -1
LD103 19089338 TREE DISPOSITION PLAN -2
LD104 19089339 TREE DISPOSITION PLAN -3
LD105 19089340 TREE DISPOSITION PLAN -4
LD106 19089341 TREE DISPOSITION PLAN -5
LD107 19089342 TREE DISPOSITION PLAN -6
LD108 19089343 TREE DISPOSITION PLAN -7
LD109 19089344 TREE DISPOSITION PLAN -8
LP101 19089345 LANDSCAPE PLAN -1
LP102 19089346 LANDSCAPE PLAN -2
LP103 19089347 LANDSCAPE PLAN -3
LP104 19089348 LANDSCAPE PLAN -4
LP105 19089349 LANDSCAPE PLAN -5
LP106 19089350 LANDSCAPE PLAN -6
LP107 19089351 LANDSCAPE PLAN -7
LP108 19089352 LANDSCAPE PLAN -8
LP109 19089353 LANDSCAPE PLAN -9
LP110 19089354 LANDSCAPE SCHEDULE
LP501 19089355 LANDSCAPE DETAILS
LP502 19089356 LANDSCAPE DETAILS
19089357 19089358
S-001 19089359 STRUCTURAL GENERAL NOTES
S-002 19089360 STRUCTURAL GENERAL NOTES
S-003 19089361 STRUCTURAL GENERAL NOTES
S-004 19089362 STRUCTURAL GENERAL NOTES
S-005 19089363 TYPICAL DETAILS
S-006 19089364 TYPICAL DETAILS
S-007 19089365 TYPICAL DETAILS
S-008 19089366 TYPICAL DETAILS
S-101 19089367 FOUNDATION PLAN
S-102 19089368 ROOF FRAMING PLAN
S-103 19089369 BOTTOM CHORD PLAN
S-104 19089370 ENLARGED SITE PLAN
S-201 19089371 EXTERIOR ELEVATION
S-301 19089372 WALL SECTIONS
DOCUMENT 00 01 15 Page 2
S-302 19089373 WALL SECTIONS
S-501 19089374 DETAILS
S-502 19089375 DETAILS
S-503 19089376 DETAILS
S-504 19089377 DETAILS
S-505 19089378 DETAILS
19089379 19089380
A-001 19089381 ABBREVIATIONS & SYMBOLS
A-101 19089382 COMPOSITE FLOOR PLAN
A-102 19089383 FLOOR PLAN - BLOCK 1A
A-103 19089384 FLOOR PLAN - BLOCK 1B
A-104 19089385 FLOOR PLAN - BLOCK 1C
A-105 19089386 FLOOR PLAN - BLOCK 1D
A-111 19089387 COMPOSITE GYP. BD. LID PLAN
A-112 19089388 FIRST FLOOR RCP - BLOCK A
A-113 19089389 FIRST FLOOR RCP - BLOCK B
A-114 19089390 FIRST FLOOR RCP - BLOCK C
A-115 19089391 FIRST FLOOR RCP - BLOCK D
A-121 19089392 COMPOSITE ROOF PLAN
A-201 19089393 EXTERIOR ELEVATIONS
A-202 19089394 EXTERIOR ELEVATIONS
A-301 19089395 BUILDING SECTIONS
A-302 19089396 BUILDING SECTION
A-310 19089397 WALL SECTIONS
A-311 19089398 WALL SECTIONS
A-400 19089399 TYPICAL MOUNTING HEIGHTS
A-410 19089400 ENLARGED WET AREA PLANS & ELEVATIONS
A-411 19089401 ENLARGED WET AREA PLANS & ELEVATIONS
A-412 19089402 ENLARGED WET AREA PLANS & ELEVATIONS
A-430 19089403 INTERIOR ELEVATIONS
A-431 19089404 INTERIOR ELEVATIONS
A-432 19089405 INTERIOR ELEVATIONS
A-433 19089406 INTERIOR ELEVATIONS
A-434 19089407 INTERIOR ELEVATIONS
A-435 19089408 INTERIOR ELEVATIONS
A-436 19089409 INTERIOR ELEVATIONS
A-437 19089410 INTERIOR ELEVATIONS
A-438 19089411 INTERIOR ELEVATIONS
A-439 19089412 INTERIOR ELEVATIONS
A-440 19089413 INTERIOR ELEVATIONS
A-441 19089414 INTERIOR ELEVATIONS
A-442 19089415 INTERIOR ELEVATIONS
A-443 19089416 INTERIOR ELEVATIONS
A-444 19089417 INTERIOR ELEVATIONS
A-445 19089418 CASEWORK ELEVATIONS AND SECTIONS
A-446 19089419 CASEWORK ELEVATIONS AND SECTIONS
A-501 19089420 DOOR DETAILS
A-502 19089421 DOOR DETAILS
A-511 19089422 WINDOW DETAILS
A-512 19089423 VIEW PANEL DETAILS
A-521 19089424 ROOF DETAILS
A-522 19089425 ROOF DETAILS
A-523 19089426 AIR BARRIER DETAIL
A-524 19089427 DETAILS
A-531 19089428 INTERIOR WALL TYPES
A-532 19089429 INTERIOR WALL TYPES
A-533 19089430 INTERIOR WALL DETAILS
A-534 19089431 INTERIOR CEILING DETAILS
DOCUMENT 00 01 15 Page 3
A-535 19089432 WALL PROTECTION DETAILS
A-536 19089433 INTERIOR WET AREA DETAILS
A-537 19089434 MISCELLANEOUS DETAILS
A-538 19089435 MILLWORK DETAILS
A-539 19089436 WALL TRANSITION DETAILS
A-540 19089437 TYPICAL INTERIOR FRAMING DETAILS
A-541 19089438 TYPICAL INTERIOR FRAMING DETAILS
A-542 19089439 TYPICAL INTERIOR FRAMING DETAILS
A-601 19089440 DOOR SCHEDULE
A-602 19089441 DOOR AND FRAME TYPES
A-611 19089442 WINDOW & VIEW PANEL TYPES, WINDOW SCHEDULE
A-701 19089443 AIR BARRIER FLOOR PLAN
A-702 19089444 AIR BARRIER BUILDING SECTIONS
19089445 19089446 19089447 19089448
ID-101 19089449 FLOOR FINISHES PLAN
ID-102 19089450 OVERALL ACCENT PAINT PATTERNS PLAN
ID-103 19089451 PARTIAL SIGNAGE PLAN - 1A
ID-104 19089452 PARTIAL SIGNAGE PLAN - B
ID-105 19089453 PARTIAL SIGNAGE PLAN - C
ID-106 19089454 PARTIAL SIGNAGE PLAN - D
ID-410 19089455 ENLARGED WET AREA FINISH PATTERNS
ID-411 19089456 ENLARGED WET AREA FINISH PATTERNS
ID-412 19089457 ENLARGED WET AREA FINISH PATTERNS
ID-501 19089458 SIGN PLACEMENT DETAILS
ID-502 19089459 SIGN TYPES
ID-503 19089460 SIGN TYPES
ID-601 19089461 ROOM FINISH SCHEDULE
ID-602 19089462 ROOM FINISH SCHEDULE - CONTINUED
ID-603 19089463 ROOM FINISH LEGEND
ID-604 19089464 ROOM FINISH LEGEND - CONTINUED
ID-605 19089465 SIGNAGE SCHEDULES
19089466 19089467
F-001 19089468 FIRE PROTECTION NOTES, LEGEND AND ABBREVIATIONS
F-101 19089469 FIRE SUPPRESSION PLAN
F-102 19089470 FIRE ALARM AND MASS NOTIFICATION PLAN
F-501 19089471 FIRE PROTECTION DETAILS
F-502 19089472 FIRE PROTECTION DETAILS
F-503 19089473 FIRE PROTECTION DETAILS
F-504 19089474 FIRE PROTECTION DETAILS
F-505 19089475 FIRE PROTECTION DETAILS
F-601 19089476 FIRE ALARM/MASS NOTIFICATION MATRIX
F-602 19089477 FIRE ALARM/MASS NOTIFICATION RISER DIAGRAM
19089478 19089479
P-001 19089480 PLUMBING LEGEND AND ABBREVIATIONS AND PLUMBING FIXTURE
SCHEDULE
P-002 19089481 PLUMBING NOTES
P-003 19089482 PLUMBING SITE PLAN
P-004 19089483 PLUMBING KEY PLAN
P-401 19089484 PARTIAL FIRST FLOOR PLUMBING PLAN - BLOCK 1A
P-402 19089485 PARTIAL FIRST FLOOR PLUMBING PLAN - BLOCK 1B
P-403 19089486 PARTIAL FIRST FLOOR PLUMBING PLAN - BLOCK 1C
P-404 19089487 PARTIAL FIRST FLOOR PLUMBING PLAN - BLOCK 1D
P-405 19089488 CHILLER PLANT PLUMBING PLAN
P-406 19089489 PARTIAL FIRST FLOOR MED GAS PLAN - BLOCK 1C
DOCUMENT 00 01 15 Page 4
P-407 19089490 PARTIAL FIRST FLOOR MED GAS PLAN - BLOCK 1D
P-501 19089491 DETAILS
P-502 19089492 DETAILS
P-503 19089493 DETAILS
P-601 19089494 DOMESTIC HOT WATER SYSTEM SCHEMATIC DIAGRAM AND
SEQUENCE OF OPERATION
P-602 19089495 MEDICAL GAS SCHEMATIC DIAGRAMS
P-603 19089496 CONTROL DIAGRAMS
P-604 19089497 EQUIPMENT SCHEDULES
P-901 19089498 SANITARY PIPING DIAGRAM
P-902 19089499 SANITARY PIPING DIAGRAM
P-903 19089500 WATER PIPING DIAGRAM
P-904 19089501 WATER PIPING DIAGRAM
P-905 19089502 WATER PIPING DIAGRAM
P-906 19089503 MEDICAL GAS PIPING DIAGRAM
19089504 19089505 19089506 19089507
M-001 19089508 MECHANICAL LEGEND AND ABBREVIATIONS
M-002 19089509 MECHANICAL NOTES
M-003 19089510 MECHANICAL SITE PLAN
M-004 19089511 MECHANICAL KEY PLAN
M-301 19089512 SECTION
M-302 19089513 SECTIONS
M-303 19089514 SECTION
M-304 19089515 SECTION
M-401 19089516 PARTIAL FIRST FLOOR MECHANICAL PLAN - BLOCK 1A
M-402 19089517 PARTIAL FIRST FLOOR MECHANICAL PLAN - BLOCK 1B
M-403 19089518 PARTIAL FIRST FLOOR MECHANICAL PLAN - BLOCK 1C
M-404 19089519 PARTIAL FIRST FLOOR MECHANICAL PLAN - BLOCK 1D
M-405 19089520 PARTIAL ROOF MECHANICAL PLAN - BLOCK 1C
M-406 19089521 PARTIAL ROOF MECHANICAL PLAN - BLOCK 1D
M-407 19089522 PARTIAL FIRST FLOOR MECHANICAL REFLECTED CEILING PLAN -
BLOCK 1A
M-408 19089523 PARTIAL FIRST FLOOR MECHANICAL REFLECTED CEILING PLAN -
BLOCK 1B
M-409 19089524 PARTIAL FIRST FLOOR MECHANICAL REFLECTED CEILING PLAN -
BLOCK 1C
M-410 19089525 PARTIAL FIRST FLOOR MECHANICAL REFLECTED CEILING PLAN -
BLOCK 1D
M-411 19089526 CHILLER PLANT MECHANICAL PLAN
M-412 19089527 PARTIAL FIRST FLOOR CHILLED WATER PIPING PLAN - BLOCK
1C
M-413 19089528 PARTIAL FIRST FLOOR CHILLED WATER PIPING PLAN - BLOCK
1D
M-414 19089529 PARTIAL FIRST FLOOR REFRIGERANT PIPING PLAN - BLOCK 1B
M-415 19089530 PARTIAL FIRST FLOOR REFRIGERANT PIPING PLAN - BLOCK 1C
M-416 19089531 PARTIAL FIRST FLOOR REFRIGERANT PIPING PLAN - BLOCK 1D
M-417 19089532 PARTIAL FIRST FLOOR REHEAT PIPING PLAN - BLOCK 1A
M-418 19089533 PARTIAL FIRST FLOOR REHEAT PIPING PLAN - BLOCK 1B
M-419 19089534 PARTIAL FIRST FLOOR REHEAT PIPING PLAN - BLOCK 1C
M-420 19089535 PARTIAL FIRST FLOOR REHEAT PIPING PLAN - BLOCK 1D
M-501 19089536 DETAILS
M-502 19089537 DETAILS
M-503 19089538 DETAILS
M-601 19089539 CHILLED WATER SCHEMATIC FLOW DIAGRAM
M-602 19089540 CHILLED WATER TEMPERATURE CONTROL SCHEMATIC DIAGRAM AND
SEQUENCE OF OPERATION
DOCUMENT 00 01 15 Page 5
M-603 19089541 REHEAT WATER SYSTEM FLOW DIAGRAM
M-604 19089542 REHEAT WATER SYSTEM SCHEMATIC DIAGRAM
M-605 19089543 DOAS SCHEMATIC AIR CONDITIONING SYSTEM
M-606 19089544 POA AND VTF AHU SCHEMATIC AIR CONDITIONING SYSTEM
M-607 19089545 SURGERY AHU SCHEMATIC AIR CONDITIONING SYSTEM
M-608 19089546 SEQUENCE OF OPERATION
M-609 19089547 TYPICAL AIRSIDE FCU SYSTEM SCHEMATIC DIAGRAM AND
SEQUENCE OF OPERATION
M-610 19089548 CONTROL DIAGRAMS
M-611 19089549 DDC SYSTEM RISER DIAGRAM
M-612 19089550 DDC SYSTEM POINTS LIST
M-613 19089551 DDC SYSTEM POINTS LIST
M-614 19089552 DDC SYSTEM POINTS LIST
M-615 19089553 DDC SYSTEM POINTS LIST
M-616 19089554 EQUIPMENT SCHEDULES
M-617 19089555 EQUIPMENT SCHEDULES
M-618 19089556 EQUIPMENT SCHEDULES
M-619 19089557 EQUIPMENT SCHEDULES
M-901 19089558 CHILLED WATER PIPING DIAGRAM
M-902 19089559 CHILLED WATER PIPING DIAGRAM
M-903 19089560 REFRIGERANT PIPING DIAGRAM
M-904 19089561 REHEAT WATER PIPING DIAGRAM
M-905 19089562 REHEAT WATER PIPING DIAGRAM
19089563 19089564 19089565 19089566
E-001 19089567 ELECTRICAL SYMBOLS
E-002 19089568 ELECTRICAL SYMBOLS AND GENERAL NOTES
E-003 19089569 ABBREVIATIONS
ED101 19089570 ELECTRICAL SITE PLAN - DEMOLITION
ED102 19089571 ELECTRICAL SITE PLAN - DEMOLITION
ED501 19089572 UTILITY POLE E25
ED601 19089573 PARTIAL "EARHART" (11.5KV) ONE-LINE DIAGRAM - EXISTING
E-101 19089574 ELECTRICAL SITE PLAN
E-102 19089575 LIGHTING SITE PLAN
E-103 19089576 OVERALL ELECTRICAL PLAN
E-104 19089577 ELECTRICAL PLAN - BLOCK 1A
E-105 19089578 ELECTRICAL PLAN - BLOCK 1B
E-106 19089579 ELECTRICAL PLAN - BLOCK 1C
E-107 19089580 ELECTRICAL PLAN - BLOCK 1D
E-108 19089581 ELECTRICAL MECHANICAL PLAN - BLOCK 1A
E-109 19089582 ELECTRICAL MECHANICAL PLAN - BLOCK 1B
E-110 19089583 ELECTRICAL MECHANICAL PLAN - BLOCK 1C
E-111 19089584 ELECTRICAL MECHANICAL PLAN - BLOCK 1D
E-112 19089585 OVERALL ROOF MECHANICAL PLAN
E-113 19089586 LIGHTING PLAN - BLOCK 1A
E-114 19089587 LIGHTING PLAN - BLOCK 1B
E-115 19089588 LIGHTING PLAN - BLOCK 1C
E-116 19089589 LIGHTING PLAN - BLOCK 1D
E-117 19089590 LIGHTING CONTROL PLAN - BLOCK 1A
E-118 19089591 LIGHTING CONTROL PLAN - BLOCK 1B
E-119 19089592 LIGHTING CONTROL PLAN - BLOCK 1C
E-120 19089593 LIGHTING CONTROL PLAN - BLOCK 1D
E-201 19089594 MAIN SWITCHBOARD ELEVATION
E-401 19089595 ENLARGED ELECTRICAL PLANS
E-402 19089596 CHILLER YARD ENLARGED PLAN
E-403 19089597 ENLARGED COMM ROOM ELECTRICAL PLAN
E-404 19089598 ENLARGED OPERATING ROOM ELECTRICAL PLAN
DOCUMENT 00 01 15 Page 6
E-501 19089599 DUCT SECTION DETAILS
E-502 19089600 RISER POLE DETAIL
E-503 19089601 GUY ANCHOR DETAILS
E-504 19089602 TRANSFORMER PAD DETAIL
E-505 19089603 TYPE 39 OCTAGONAL MANHOLE DETAILS
E-506 19089604 SMALL POLYMER CONCRETE PULLBOX DETAIL
E-510 19089605 RECEPTACLE DETAILS
E-521 19089606 MOUNTING DETAILS
E-531 19089607 LIGHT FIXTURE DETAILS -1
E-532 19089608 LIGHT FIXTURE DETAILS - 2
E-533 19089609 LIGHT FIXTURE DETAILS - 3
E-534 19089610 LIGHT POLE DETAILS
E-535 19089611 LIGHT POLE DETAILS
E-540 19089612 WALL LIGHT SWITCH WITH OCCUPANCY SENSOR DETAIL
E-541 19089613 OCCUPANCY SENSOR DETAILS
E-542 19089614 OCCUPANCY SENSOR DETAILS
E-601 19089615 PARTIAL "EARHART" (11.5KV) ONE-LINE DIAGRAM - NEW
E-602 19089616 ONE-LINE DIAGRAM
E-603 19089617 GROUNDING SCHEMATIC DIAGRAM
E-610 19089618 DUAL ISOLATED POWER PANEL "ISOD1" DIAGRAM
E-611 19089619 ISOLATED POWER PANEL DIAGRAMS
E-612 19089620 ISOLATED POWER PANEL DIAGRAMS
E-621 19089621 OCCUPANCY SENSOR SCHEMATIC DIAGRAMS
E-622 19089622 OCCUPANCY SENSOR SCHEMATIC DIAGRAM
E-701 19089623 ELECTRICAL MANHOLE DEVELOPMENT PLAN
E-801 19089624 PANEL SCHEDULES
E-802 19089625 PANEL SCHEDULES
E-803 19089626 PANEL SCHEDULES
E-810 19089627 MEDICAL EQUIPMENT SCHEDULE
19089628 19089629 19089630 19089631
ET001 19089632 ELECTRICAL SYMBOLS
ET002 19089633 ELECTRICAL SYMBOLS AND GENERAL NOTES
ET003 19089634 SPECTRUM NOTES
ET100 19089635 OVERALL TELECOMMUNICATION SITE PLAN
ET101 19089636 TELECOMMUNICATION SITE PLAN - 1
ET102 19089637 TELECOMMUNICATION SITE PLAN - 2
ET103 19089638 TELECOMMUNICATION SITE PLAN - 3
ET104 19089639 TELECOMMUNICATION SITE PLAN - 4
ET105 19089640 TELECOMMUNICATION SITE PLAN - 5
ET106 19089641 TELECOMMUNICATION SITE PLAN - 6
ET107 19089642 TELECOMMUNICATION SITE PLAN - 7
ET108 19089643 TELECOMMUNICATION SITE PLAN - 8
ET109 19089644 TELECOM PLAN - BLOCK 1A
ET110 19089645 TELECOM PLAN - BLOCK 1B
ET111 19089646 TELECOM PLAN - BLOCK 1C
ET112 19089647 TELECOM PLAN - BLOCK 1D
ET113 19089648 PUBLIC ADDRESS SYSTEM - BLOCK 1A
ET114 19089649 PUBLIC ADDRESS SYSTEM - BLOCK 1B
ET115 19089650 PUBLIC ADDRESS SYSTEM - BLOCK 1C
ET116 19089651 PUBLIC ADDRESS SYSTEM - BLOCK 1D
ET117 19089652 WIRELESS ACCESS POINT OUTLET PLAN
ET118 19089653 ACCESS CONTROL SYSTEM PLAN
ET119 19089654 CCTV PLAN
ET120 19089655 CCTV SITE PLAN
ET201 19089656 TELECOM RACK ELEVATION
ET202 19089657 DOOR DETAILS
DOCUMENT 00 01 15 Page 7
ET203 19089658 BUILDING 2115 - NORTH ELEVATION
ET401 19089659 ENLARGED TELECOM ROOM PLAN
ET501 19089660 TELECOMMUNICATION TYPE 72 1219 X 1219 (4'X4')
MAINTENANCE HOLE DETAIL
ET502 19089661 TELECOM DETAILS
ET503 19089662 MISCELLANEOUS ELECTRICAL DETAILS
ET504 19089663 MISCELLANEOUS ELECTRICAL DETAIL
ET505 19089664 DUCT SECTION DETAILS
ET510 19089665 CABLE TRAY DETAILS
ET511 19089666 CABLE RUNWAY DETAILS
ET512 19089667 HANGING CABLE TRAY SUPPORT DETAIL
ET513 19089668 WIRELESS ACCESS POINT TELECOM OUTLET DETAIL
ET514 19089669 MISCELLANEOUS TELECOMMUNICATION DETAILS
ET515 19089670 TELECOMMUNICATION DETAILS
ET516 19089671 CATV F-CONNECTOR AND PATCH PANEL DETAILS
ET520 19089672 GROUND BAR DETAILS
ET521 19089673 TELECOM PATHWAY WALL PENETRATION DETAILS
ET522 19089674 FLUSH FLOOR MOUNTED LOCAL PRESENTATION OUTLET DETAIL
ET523 19089675 CCTV CAMERA DETAILS
ET601 19089676 TELECOM SCHEMATIC DIAGRAM
ET602 19089677 TELECOM SCHEMATIC DIAGRAM
ET603 19089678 MISCELLANEOUS TELECOM SCHEMATIC DIAGRAMS
ET604 19089679 PUBLIC ADDRESS SYSTEM SCHEMATIC DIAGRAM
ET605 19089680 TELECOM GROUNDING SCHEMATIC DIAGRAM
ET606 19089681 ACCESS CONTROL SYSTEM SCHEMATIC DIAGRAM
ET607 19089682 TELECOM OUTLET DIAGRAM
ET608 19089683 CCTV HEADEND SYSTEM SCHEMATIC DIAGRAM
ET609 19089684 CCTV SCHEMATIC DIAGRAMS
ET701 19089685 TELECOM HANDHOLE DIAGRAMS
ET702 19089686 TELECOM HANDHOLE DIAGRAMS
ET703 19089687 TELECOM MAINTENANCE HOLE DIAGRAMS
ET704 19089688 TELECOM MAINTENANCE HOLE DIAGRAM - TMH 215A
19089689 19089690 19089691 19089692
Q-102 19089693 EQUIPMENT PLAN - BLOCK A
Q-103 19089694 EQUIPMENT PLAN - BLOCK B
Q-104 19089695 EQUIPMENT PLAN - BLOCK C
Q-105 19089696 EQUIPMENT PLAN - BLOCK D
Q-601 19089697 EQUIPMENT SCHEDULE
19089698 19089699 19089700 19089701 19089702 19089703 19089704 19089705
1.3 DRAWINGS
1.3.1 Boring Logs
The Government does not guarantee that borings indicate actual conditions, except for the exact locations and the time that they were made.
DOCUMENT 00 01 15 Page 8
1.3.2 Subsurface Data
Subsurface data, not specified or indicated, have been obtained by the Government prospective bidders and is included as part of the solicitation.
-- End of Document --
DOCUMENT 00 01 15 Page 9
Government for the information of prospective bidders and is included as part of the solicitation.
-- End of Document --
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
The work includes constructing a replacement Veterinary Treatment Facility supporting military working dogs and other animals. The facility will provide full service preventative, diagnostic, surgical and dental care to Government-Owned Animals (GOA), food inspection spaces, and preventative and diagnostic services to the Privately-Owned Animals (POA) of service members on the installation. Supporting facilities include utilities, site improvements, parking ,signage, antiterrorism/force protection measures, and environmental mitigation measures. The existing facility to be replaced by this construction will be returned to the installation for removal by others.
1.1.2 Location
The work is located at Joint Base Pearl Harbor Hickam, Hawaii, as indicated.
1.2 OCCUPANCY OF PREMISES
Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment.
1.3 EXISTING WORK
In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.4 LOCATION OF UNDERGROUND UTILITIES
Contact the Contracting Officer to obtain the latest Dig Permit form.
Contractor must obtain an approved digging permit a minimum of 90 calendar days prior to the start of excavation. The Contractor is responsible for accurately completing the form, routing for all signatures and obtaining Hawaii One Call Center consultation. Upon approval by the Assistant Public Works Officer (APWO) office, Contractor must submit completed form to the Contracting Officer. Verify existing utility locations indicated on contract drawings, within area of work.
Identify and mark all other utilities not managed and located by the local
SECTION 01 11 00 Page 1 utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities,and any type of underground obstruction including those indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work.
1.4.1 Notification Prior to Excavation
Notify the Contracting Officer at least 90 calendar days prior to starting excavation work.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 2
SECTION 01 14 00
WORK RESTRICTIONS
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel
Personnel List
Vehicle List; G
Statement Of Acknowledgement Form SF 1413; G
1.2 SPECIAL SCHEDULING REQUIREMENTS
a. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work.
b. Permission to interrupt any Activity roads, or utility service must be requested in writing a minimum of 30 calendar days prior to the desired date of interruption.
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. To minimize traffic congestion, delivery of materials must be outside of peak traffic hours (5:30 to 8:00 a.m. and 3:00 to 5:00 p.m.) unless otherwise approved by the Contracting Officer. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.
1.3.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
SECTION 01 14 00 Page 1
1.3.1.2 Installation Access
Obtain access to Navy installations through participation in the Defense Biometrics Identification System (DBIDS). Requirements for Contractor employee registration, and transition for employees currently under Navy Commercial Access Control System (NCACS), are available at https://www.cnic.navy.mil/om/dbids.html. No fees are associated with obtaining a DBIDS credential.
Participation in the DBIDS is not mandatory, and Contractor personnel may apply for One-Day Passes at the Base Visitor Control Office to access an installation.
1.3.1.2.1 Registration for DBIDS
Registration for DBIDS is available at https://www.cnic.navy.mil/om/dbids.html. Procedure includes:
a. Present a letter or official award document (i.e. DD Form 1155 or SF 1442) from the Contracting Officer, that provides the purpose for access, to the base Visitor Control Center representative.
b. Present valid identification, such as a passport or Real ID Act-compliant state driver's license.
c. Provide completed SECNAV FORM 5512/1 to the base Visitor Control Center representative to obtain a background check. This form is available for download at https://www.cnic.navy.mil/om/dbids.html.
d. Upon successful completion of the background check, the Government will complete the DBIDS enrollment process, which includes Contractor employee photo, fingerprints, base restriction and several other assessments.
e. Upon successful completion of the enrollment process, the Contractor employee will be issued a DBIDS credential, and will be allowed to proceed to worksite.
1.3.1.2.2 DBIDS Eligibility Requirements
Throughout the length of the contract, the Contractor employee must continue to meet background screen standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.
An adjudication process may be initiated when a background screen failure results in disqualification from participation in the DBIDS, and Contractor employee does not agree with the reason for disqualification. The Government is the final authority.
1.3.1.2.3 DBIDS Notification Requirements
a. Immediately report instances of lost or stolen badges to the Contracting Officer.
b. Immediately collect DBIDS credentials and notify the Contracting Officer in writing under the following circumstances:
SECTION 01 14 00 Page 2
(1) An employee has departed the company without having properly returned or surrendered their DBIDS credentials.
(2) There is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the Installation or anyone therein.
1.3.1.2.4 One-Day Passes
Personnel applying for One-Day passes at the Base Visitor Control Office are subject to daily mandatory vehicle inspection, and will have limited access to the installation. The Government is not responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the DBIDS.
1.3.1.3 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. E-cigs are also subject to smoking rules. The Contracting Officer will identify designated smoking areas.
1.3.2 Working Hours
Regular working hours must consist of an 8 1/2 hour period , between 7 a.m.
and 3:30 p.m., Monday through Friday, excluding Government holidays.
1.3.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 30 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.
1.3.4 Occupied Facility
The Contractor shall be working around existing buildings which are occupied. Do not enter the buildings without prior approval of the Contracting Officer.
1.3.5 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS, except as noted in the electrical drawings.
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
SECTION 01 14 00 Page 3
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS. Such interruptions are further limited to eight hours. This time limit includes time for deactivation and reactivation.
d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.
e. Contractor to have a Minor Work Request account opened and used for NAVFAC Shops personnel to charge their hours to for all on-site support work, outages and training purposes.
f. Interruption to Bilge and Oily Waste pipeline is limited to 24 hours and requires 45 calendar days advance notice.
1.4 SECURITY REQUIREMENTS
1.4.1 Personnel List
Submit for approval, at least 21 calendar days prior to the desired date of entry, an original alphabetical list of personnel who require entry into Government property to perform work on the project. Furnish for each person:
a. Name
b. Date and place of birth
c. Citizenship
d. Home address
e. Telephone number
f. Social security number
g. Current pass expiration date
h. Naturalization number
i. Passport number, place of issue, and expiration date
The request for personnel passes must be accompanied with the following certification:
"I hereby certify that all personnel on this list are either born U.S.
citizens, naturalized U.S. citizens with the naturalization number shown."
Signature/Firm Name
1.4.1.1 Citizenship Requirements
Aliens are not allowed on the project site. Work under this contract is restricted to U.S. citizens.
SECTION 01 14 00 Page 4
1.4.2 Vehicle List
Submit an original list of vehicles to be utilized at the work site with the following information for each vehicle:
a. Make
b. Year
c. Model
d. License number
e. Registered owner
f. Current NAVBASE Pearl Harbor pass expiration date.
1.4.3 Passes
Submit request for personnel and vehicle passes together. Include the Certificate of Insurance for Contractor and Subcontractor(s) and the Statement of Acknowledgement Form SF 1413 with the submittal. Passes will normally be issued within 21 calendar days.
1.4.3.1 Control
Maintain strict accountability over passes. Immediately report to the source of issue, passes missing or lost and the circumstances. If the Contractor has another active contract or one commencing immediately, employees' names may be transferred from one contract to the other. Final payment will not be effected until employees are transferred to another contract or the records are cleared. Furnish a signed letter, countersigned by the source of issue, stating that passes have been turned in.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 14 00 Page 5
SECTION 01 20 00.00 20
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EP 1110-1-8 (2016) Construction Equipment Ownership and Operating Expense Schedule
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Earned Value Report; G
1.3 EARNED VALUE REPORT
1.3.1 Data Required
This contract requires the use of a cost-loaded Network Analysis Schedule (NAS). Schedule of Prices must not be used with cost-loaded Network Analysis Schedule (NAS). Use Earned Value Report derived from cost-loaded NAS. Provide a detailed breakdown of the contract price, giving quantities for each of the various kinds of work, unit prices and extended prices.
Within 30 calendar days of notice of award, prepare and deliver to the Contracting Officer a Schedule of Prices (construction contract) as directed by the Contracting Officer. Schedule of Prices must have cost summarized and totals provided for each construction category.
1.3.2 Schedule Instructions
Payments will not be made until the Earned Value Report from the cost-loaded NAS has been submitted to and accepted by the Contracting Officer. Identify the cost for site work, and include incidental work.
1.3.3 Real Property Assets
The Government will provide the Draft DD Form 1354, Transfer and Acceptance of Military Real Property filled in with the appropriate Real Property Unique Identifiers (RPUID) and related construction Category Codes to summarize the designed real property assets that apply to this contract.
The Contractor shall meet with the Contracting Officer and the Real
SECTION 01 20 00.00 20 Page 1
Property Accounting Officer during the Pre Construction Meeting and the Project Closeout Meetings to modify and include any necessary changes to the DD Form 1354. The Contractor shall provide the Interim DD Form 1354 that uses the appropriate division of the RPUIDs/ Category Codes to represent the final constructed facility and include all associated cost.
Coordinate the Contractor's Price and Payment structure with the structure of the RPUIDs/ Category Codes.
Divide detailed asset breakdown into the RPUIDs and related construction Category Codes and populate associated costs which represent all aspects of the work. Where assets diverge into multiple RPUID/ Category Codes, divide the asset and provide the proportion of the assets in each RPUID/ Category Code. Assets and related RPUID/ Category Codes may be modified by the Contracting Officer as necessary during course of the work. Coordinate identification and proportion of these assets with the Government Real Property Accounting Officer.
Cost data accumulated under this section are required in the preparation of DD Form 1354.
1.4 CONTRACT MODIFICATIONS
In conjunction with the Contract Clause DFARS 252.236-7000 Modification Proposals-Price Breakdown, and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, equipment use rates shall be based upon the applicable provisions of the EP 1110-1-8.
1.5 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.5.1 Content of Invoice
Requests for payment will be processed in accordance with the Contract Clause FAR 52.232-27 Prompt Payment for Construction Contracts and FAR 52.232-5 Payments Under Fixed-Price Construction Contracts. The requests for payment shall include the documents listed below.
a. The Contractor's invoice, on NAVFAC Form 7300/30 furnished by the Government, showing in summary form, the basis for arriving at the amount of the invoice. Form 7300/30 shall include certification by Contractor and Quality Control (QC) Manager.
b. The Earned Value Report from the cost-loaded NAS, showing in detail:
the estimated cost, percentage of completion, and value of completed performance for each of the construction categories stated in this contract. Use NAVFAC Form 4330/54 on NAVFAC contracts when a Monthly Estimate for Voucher is required.
c. Updated Project Schedule and reports required by the contract.
d. Contractor Safety Self Evaluation Checklist.
e. Other supporting documents as requested.
f. Updated copy of submittal register.
g. Invoices not completed in accordance with contract requirements will be returned to the Contractor for correction of the deficiencies.
SECTION 01 20 00.00 20 Page 2
h. Monthly Work-hour report.
i. Solid Waste Disposal Report.
1.5.2 Submission of Invoices
If DFARS Clause 252.232-7006 Wide Area WorkFlow Payment Instructions is included in the contract, provide the documents listed in paragraph CONTENT OF INVOICE in their entirety as attachments in Wide Area Work Flow (WAWF) for each invoice submitted. The maximum size of each WAWF attachment is two megabytes, but there are no limits on the number of attachments. If a document cannot be attached in WAWF due to system or size restriction, provide it as instructed by the Contracting Officer.
1.5.3 Final Invoice
a. A final invoice shall be accompanied by the certification required by DFARS 252.247.7023 Transportation of Supplies by Sea, and the Contractor's Final Release. If the Contractor is incorporated, the Final Release shall contain the corporate seal. An officer of the corporation shall sign and the corporate secretary shall certify the Final Release.
b. For final invoices being submitted via WAWF, the original Contractor's Final Release Form and required certification of Transportation of Supplies by Sea must be provided directly to the respective Contracting Officer prior to submission of the final invoice. Once receipt of the original Final Release Form and required certification of Transportation of Supplies by Sea has been confirmed by the Contracting Officer, the Contractor shall then submit final invoice and attach a copy of the Final Release Form and required certification of Transportation of Supplies by Sea in WAWF.
c. Final invoices not accompanied by the Contractor's Final Release and required certification of Transportation of Supplies by Sea will be considered incomplete and will be returned to the Contractor.
1.6 PAYMENTS TO THE CONTRACTOR
Payments will be made on submission of itemized requests by the Contractor which comply with the requirements of this section, and will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.
1.6.1 Obligation of Government Payments
The obligation of the Government to make payments required under the provisions of this contract will, at the discretion of the Contracting Officer, be subject to reductions and suspensions permitted under the FAR and agency regulations including the following in accordance with FAR 32.503-6 Suspension or Reduction of Payments:
a. Reasonable deductions due to defects in material or workmanship;
b. Claims which the Government may have against the Contractor under or in connection with this contract;
c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor; and
SECTION 01 20 00.00 20 Page 3
d. Failure to provide up to date record drawings.
1.6.2 Payment for Onsite and Offsite Materials
Progress payments may be made to the contractor for materials delivered on the site, for materials stored off construction sites, or materials that are in transit to the construction sites under the following conditions:
a. FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts.
b. Materials delivered on the site but not installed, including completed preparatory work, and off-site materials to be considered for progress payment shall be major high cost, long lead, special order, or specialty items, not susceptible to deterioration or physical damage in storage or in transit to the construction site. Examples of materials acceptable for payment consideration include, but are not limited to, structural steel, non-magnetic steel, non-magnetic aggregate, equipment, machinery, large pipe and fittings,precast/prestressed concrete products, plastic lumber (e.g., fender piles/curbs), and high-voltage electrical cable. Materials not acceptable for payment include consumable materials such as nails, fasteners, conduits, gypsum board, glass, insulation, and wall coverings.
c. Materials to be considered for progress payment prior to installation shall be specifically and separately identified in the Contractor's estimates of work submitted for the Contracting Officer's approval in accordance with Earned Value Report requirement of this contract.
Requests for progress payment consideration for such items shall be supported by documents establishing their value and that the title requirements of the clause at FAR 52.232-5 Payments Under Fixed-Price Construction Contracts have been met.
d. Materials are adequately insured and protected from theft and exposure.
e. Provide a written consent from the surety company with each payment request for offsite materials.
f. Materials to be considered for progress payments prior to installation shall be stored on Oahu. Other locations are subject to written approval by the Contracting Officer.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 20 00.00 20 Page 4
PAGE 1 OF 2 PAGES
c. TYPE (X one )
AREA
15.
PRI UM
16.
PRI QTY
17.
SEC UM
18.
SEC QTY
1 530-45
WORKING DOG
TREATMENT FACILITY
M2 1,148 SF 12,361 NEW ASSET
2 135-10
COMMUNICATION LINES
OTHER THAN TELEPHONE
MI 0.9 ADD TO EXISTING ASSET
3 135-20 TELEPHONE LINES MI 0.16 ADD TO EXISTING ASSET
4 811-60 STANDBY GENERATOR KW 125 NEW ASSET
5 812-12 TRANSFORMERS KVA 500 NEW ASSET
6 812-20 STREET LIGHTING LF 1,045 ADD TO EXISTING ASSET
7 812-32
UNDERGROUND
ELECTRICAL DISTRIBUTION
LINE
LF 240 ADD TO EXISTING ASSET
8 832-10 SANITARY SEWER LF 105 ADD TO EXISTING ASSET
9 842-10
WATER DISTRIBUTION
LINES
LF 295 ADD TO EXISTING ASSET
10 843-10 FIRE PROTECTION LINES LF 145 ADD TO EXISTING ASSET
11 852-10 PARKING M2 2,480 SY 2,966 ADD TO EXISTING ASSET
TRANSFER AND ACCEPTANCE OF DoD REAL PROPERTY Form Approved
OMB No. 0704-0188
7. CONTRACT NUMBER(S)
1. FROM (Organization Name)
5. TO (Organization – Installation Code and Name)
8. TRANSACTION DETAILS
The public reporting burden for this collection of information is estimated to average 30 minutes per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information.
Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Washington Headquarters Services, Executive Services
Directorate, Information Management Division, 4800 Mark Center Drive, Alexandria, VA 22350-3100 (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.
4. SERIAL NUMBER
20210204
a. METHOD (X all that apply) b. WHEN/EVENT (X one)
6. SITE RPSUID/CODE/NAME
XXX JBPHH
3. PROJECT/JOB NUMBER2. DATE PREPARED (YYYYMMDD)
(TBD)
10b.
RPUID
11.
CATEGORY
CODE
COMMANDER, NAVAL FACILITIES ENGINEERING
COMMAND PACIFIC
258 MAKALAPA DRIVE, SUITE 100
JBPHH, HI 96860-3134
COMMANDER, JOINT BASE PEARL HARBOR-
HICKAM
850 TICONDEROGA STREET
JBPHH, HI 96860
7a. PLACED-IN-SERVICE DATE
(YYYYMMDD)
INST CODE/NAME
XXX JBPHH
22.
INTER-
EST
CODE
21.
FUND
ORG
23. REMARKS12.
CATCODE
DESCRIPTION
20.
FUND
SOURCE
OTHER 19. COST13.
TYPE
CODE
14.
SUST…
This is the start of the file's text. The full file is on GovTribe.