RFP_QUESTIONS_&_ANSWERS_Amendment_0009_(190816).pdf

PDF 478 KB Posted

Attached to
Operation of Government-Owned Facilities
Solicitation number
N6274219R1199
Issued by

About this file

This solicitation requests proposals for base operations support services at Joint Region Marianas facilities on Guam. Services include general management, port operations, ordnance, facilities management, utilities, electrical systems, wastewater treatment, steam production, water services, and vehicle/equipment maintenance. The contract term is one base year with six one-year options and one additional option period for close-out. The award type is cost-plus-award-fee.

The pre-proposal conference will be held on July 23, 2019 in Guam, with site visits from July 23-31. Proposals are due in July 2019. Evaluation factors are past performance, corporate experience, management, technical approach, safety, and small business participation. This is a full and open competition with an estimated value over $38.5 million. The solicitation and any amendments must be monitored through FBO and NECO.

RFP QUESTIONS & ANSWERS_Amendment 0009 (190816)

View the file

Other files

File Type Posted
Section_K_(190827_Amendment_0013).pdf PDF
C_0200000_Mgmt__Admin_(190827).pdf PDF
Section_A_(190827_Amendment_0013).pdf PDF
Section_I_(190827_Amendment_0013).pdf PDF
C_1601000_Utility_Management_(190827).pdf PDF
RFP_QUESTIONS_&_ANSWERS_Amendment_0013_(190827).pdf PDF
Amendment_0013.pdf PDF
RFP_QUESTIONS_&_ANSWERS_Amendment_0012_(190820).pdf PDF
JH-3_Collective_Bargaining_Agreement_Amendment_0012_190820.pdf PDF
Section_J_Table_of_Contents_(190820_Amendment_0012).pdf PDF
Amendment_0012.pdf PDF
SF33_(190816_Amendment_0011).pdf PDF
Amendment_0011.pdf PDF
Section_L_(190816_Amendment_0011).pdf PDF
Amendment_0010_(Not_Issued).pdf PDF
Amendment_0009.pdf PDF
C_1601000_Utility_Management_(190816).pdf PDF
C_1700000_BSVE_(190816).pdf PDF
C_0600000_Port_Operations_(190816).pdf PDF
JL-2_Department_of_Defense_Contract_Security_Classification_Specification_Amendment_0009_190816.pdf PDF
Attachment_J-1502000-01_Facility_Asset_List_(190816).xlsx XLSX spreadsheet
C_0200000_Mgmt__Admin_(190816).pdf PDF
JH-3_Collective_Bargaining_Agreement_Amendment_0009_190816.pdf PDF
J-0200000-01_Definitions__Acronyms_(190815).pdf PDF
Section_L_(190815_Amendment_0008).pdf PDF
Amendment_0008.pdf PDF
C_1605000_Steam_(190815).pdf PDF
Attachment_J-1502000-17_FY18_Historical_Workload_Data_(190815).xlsx XLSX spreadsheet
RFP_QUESTIONS_&_ANSWERS_Amendment_0008_(190815).pdf PDF
F_1502000_Facility_Investment_(190815).pdf PDF
C_1502000_Facility_Investment__(190815).pdf PDF
Attachment_J-0200000-07_Government_Furnished_Equipment_(190815).xlsx XLSX spreadsheet
Section_M_(190813_Amendment_0007).pdf PDF
C_0200000_Mgmt__Admin_(190813).pdf PDF
Amendment_0007.pdf PDF
RFP_QUESTIONS_&_ANSWERS_Amendment_0007_(190813).pdf PDF
JL-9_Corporate_Experience_Project_Data_Sheet_Amendment_0007_190813.xlsx XLSX spreadsheet
Section_J_Table_of_Contents_(190813_Amendment_0007).pdf PDF
JH-2_Wage_Determination_No._2015-5693_(Rev._9).pdf PDF
Amend_0006_N6274219R1199.zip ZIP file
Section_I_(190806_Amendment_0005).pdf PDF
Section_M_(190806_Amendment_0005).pdf PDF
Amendment_0005.pdf PDF
SITE_VISIT_ITINERARY_ACTUAL.pdf PDF
PRE-PROPOSAL_CONFERENCE_ATTENDEES.pdf PDF
Attachment_J-1502000-01_Facility_Asset_List_(190806).xlsx XLSX spreadsheet
RFP_QUESTIONS_&_ANSWERS_Amendment_0005_(190806).pdf PDF
PRE-PROPOSAL_CONFERENCE_SLIDES.pdf PDF
Section_L_(190806_Amendment_0005).pdf PDF
Notice_No._3_Attachment.pdf PDF
Show 40 more

Latest 50 of 111 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP QUESTIONS ANSWERS

SOLICITATION N62742-19-R-1199

GUAM BASE OPERATIONS SUPPORT SERVICES, JOINT REGION MARIANAS (JRM)

Amendment 0009

Ques. # Reference (Sect/Para/Page or PWS Sect) Question Government Response

Section C 1602000 Section C - 1602000 Electrical, Section 3.1.1, Berthing and Hotel Services requires the contractor to "Connect sewer, steam, potable water and power within one hour of ship's arrival".

1. Is it the Government's inten on that 1 hour is the mandatory requirement?

2. Is it the Government's inten on that the Contractor should use any and all resources to accomplish the connec ons within the 1 hour time allotted?

3. How will the Government measure the me to connect on those vessels where Contractor personnel only bring the cabling up to the vessel and have to wait for vessel personnel to make the actual connection at whatever schedule they determine is appropriate?

1. Annex 0600000 Port Operations contains the Berthing and Hotel Services requirement. Yes, per Spec Item 3.1.1 in Annex 0600000 Port Operations, Berthing and Hotel Services, the requirement identified in Item K states that the Contractor shall "Connect sewer, steam, potable water and power within one hour of ship's arrival".

2. Yes, the Contractor should use available resources to meet the requirement per Spec Item 3.1.1 in Annex 0600000 Port Operations.

3. In these instances, the Contractor would only be responsible for bringing utility cabling up to the point of turnover per Spec Item 3.1.1 in Annex 0600000 Port Operations.

J-152000-01-Dynamics 2 On page one in the column "Sub System" there is a a sum total quantity of 24,588 for "D3040106 - Air Handling Unit, Field Fab", which consists of 20 lines. Will the Government please confirm that these quantity's are correct?

Attachment J-1502000-01 Facility Asset List quantities have been revised. See Amendment No. 0009.

JL-2 Department of Defense Contract Security Classification Specification

Will the Government provide a completed Form DD254, to include blocks 10-15? Yes. Please see revised JL-2 DoD Contract Security Classification Specification (Form DD254) in Amendment No. 0009.

Spec Item 3.1 Utility work orders Annex 1601000-Utility management

Annex 1601000 Spec Item 3.1 indicates the Government may combine multiple repair requirements received for the same trade in the same location at the same time into one work order as long as the work order threshold is not exceeded. Please define the work order threshold.

There are no work order thresholds under any of the Utilities sub-annexes, 1601000, 1602000, 1604000, 1605000 or 1606000. In addition, please see response to Question #133 from Amendment No. 0008.

Spec Item 3.1 Utility work orders Annex 1601000-Utility management and J-1601000-03

Annex 1601000 Spec Item 3.1 indicates Information related to estimated utility maintenance and repair workload is provided in J-1601000-03. J-1601000-03 identifies 414 Project work types. Please define the project work order threshold and the Routine work order threshold.

Please see response to Question #148.

Annex 10502000 Spec Item 3.3 Integrated Maintenance Program and Attachment J-1502000-07.

Annex 1502000 Spec Item 3.3 requires and Integrated Maintenance Program. Attachment J-1502000-07 identifies functions and locations, but does not identify the equipment items for the Integrated Maintenance Program. Please provide the Equipment List for the Integrated Maintenance Program.

The Contractor should review all J Attachments especially J-1502000-01, J-1502000-02, and J- 1502000-07 for the equipment items for the Integrated Maintenance Program.

JH-3 CBA Will Memorandum of Agreement #4, dated 07/17/2019, that increases wages $2.00 per hour effective 08/01/2019 for all Journeyman Water Plant and Waste Water Plant Operators level II thru IV be incorporated in a future amendment?

Yes. Memorandums of Agreement #3 and #4 have been added to the JH-3 Collective Bargaining Agreement. Please see revised JH-3 Collective Bargaining Agreement in Amendment No. 0009.

Section C - 1502000 Electrical, Spec Item 3.3 Section C - 1502000 Electrical, Spec Item 3.3 states "Naval Hospital standby power plant shall conform to The Joint Commission (TJC) standard". Attachment J-1502000-07 indicates the Back-up Generator at the NAVHOSP is critical.

Section C - 1602000 Electrical, Spec Item 3.14 states "NBGTS and Naval Hospital Standby Power Plants are NOT included in this requirement". Is the Contractor responsible for the Naval Hospital Generator's conformance with JTC standard?

Yes, the Contractor is responsible for the Naval Hospital Generator's conformance with JTC standard as specified in Spec Item 3.3 in Section C 1502000 Facility Investment issued in Amendment No. 0008 and Attachment J-1502000-07 Critical Functional Areas.

Notice 1 Questions & Answers

In the Cover/Summary page of the three Notices issued the Government states, "NOTE: The questions and answers on the attached sheet(s) (Notice No. [# reference] Attachment) are provided for INFORMATION ONLY. The solicitation remains unchanged unless it is amended in writing on a Standard Form 30."

Notice No. 1 answered 18 questions however only question #17 and its answer is included in an amendment (Amendment 4). Will the Government issue an amendment to include the answers to questions in the solicitation?

Yes, a subsequesnt amdendment will be issued to incorporate all RFP questions and responses.

JB-1

They way the JB-1 is laid out offeror's could infer that Materials are subject to G&A? Are offeror's to apply G&A to Materials?

In accordance with the RFP, offerors shall propose in accordance with its established accounting practices. For example, if the offeror's established accounting practices applies G&A to Materials, then the offeror would do so.

JB-1

They way the JB-1 is laid out offeror's could infer that Materials are subject to Award Fee? Are offeror's to apply Award Fee to Materials?

Yes, in accordance with the RFP, the maximum available award fee pool shall be established by multiplying the total allowable estimated contract costs excluding BPT by the Offeror's proposed percentage. Estimated contract costs include materials.

JB-1

They way the JB-1 is laid out offeror's could infer that Materials are subject to Gross Receipt Tax? Are offeror's to apply Gross Receipt Tax to Materials?

Yes, in accordance with the RFP, offerors shall apply 5% Guam BPT to Estimated Costs plus Award Fee.

Estimated costs include materials.

Amendment No. 0009

File details come from the government source that posted it. Updated .