This amendment modifies a solicitation for base operations support services on Guam. The services include general management and administration, port operations, ordnance, facility management, utilities, and vehicles/equipment. The performance period is a one-year base period with six one-year options and one additional twelve-month period.
The amendment incorporates revisions to Sections I, J, L, and M of the solicitation. It replaces attachments in Section J with a combined Microsoft Excel file and updates clauses and addresses in Sections L and M. The pre-proposal conference presentation and site visit itinerary are also attached. The proposal due date of August 30, 2019 remains unchanged. The Naval Facilities Engineering Command Pacific is seeking these services to support operations at Joint Region Marianas facilities on Guam.
Amendment 0005
View the file
Other files
Show 40 more
Latest 50 of 111 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
N62742-19-R-1199 GUAM BASE OPERATIONS SUPPORT SERVICES FOR THE JOINT REGION MARIANAS (JRM).
See Page 2
1. CONTRACT ID CODE PAGE OF PAGES
R 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 06-Aug-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N6274219R1199
X 9B. DATED (SEE ITEM 11)
05-Jul-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 2 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
06-Aug-2019
CODE
NAVFAC PACIFIC
SPECIAL PROJECTS CONTR BR (ACQ22)
258 MAKALAPA DRIVE STE 100
JBPHH HI 96860-3134
N62742 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N6274219R1199
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
SUMMARY OF CHANGES:
CONTINUATION PAGE AMD 0005
The purpose of this amendment is to incorporate the below revisions to the solicitation.
(1) SECTION I: Section I has been replaced in its entirety with the revised Section I (190806_Amendment 0005). Changes are annotated with a vertical line on the right hand border of the page:
CLAUSES INCORPORATED BY REFERENCE: FAR clause 52.219-9 (Dev 2018-O0018) has been removed and replaced with FAR clause 52.219-9 (Dec 2018-O0018) Alt II.
(2) SECTION J: The following three (3) attachments (PDF version) under Section J have been combined into one (1) attachment (Microsoft Excel version) called Attachment J-1502000-01 Facility Asset List (190806):
Attachment J-1502000-01-Dynamics.1 Attachment J-1502000-01-Dynamics.2 Attachment J-1502000-01-Non-Dynamics
(3) SECTION L: Section L has been replaced in its entirety with the revised Section L (190806_Amendment 0005). Changes are annotated with a vertical line on the right hand border of the page:
L.6: The referenced FAR clause 52.219-9 Alt II has been replaced with FAR clause 52.219-9 (Dev
2018-O0018) Alt II.
L.7 / VOLUMES II & III – NON-COST (TECHNICAL) PROPOSAL / B.: Volume II paper copy requirement changed from nine (9) to seven (7) paper copies.
L.7 / Factor C, Management: Adjustment of the following sentence: “The JL-4 shall be submitted in hard copy under Factor D, Technical Approach, and MS EXCEL…”
L.7: Factor B, Corporate Experience: Annex 1 General Information has been removed.
L.7: Factor D, Technical Approach: Annex 1 General Information has been removed.
CLAUSES INCORPORATED BY FULL TEXT / FAR Clause 52.252-1: FAR and DFARS web addresses have been updated.
(4) SECTION M: Section M has been replaced in its entirety with the revised Section M (190806_Amendment 0005). Changes are annotated with a vertical line on the right hand border of the page:
M.1 / D. Non-Cost (Technical) Evaluation Factors / Factor C, Management: Adjustment of the following sentence: “The Government will evaluate the degree to which the proposal demonstrates an effective and resource-efficient management plan. including a complete Attachment JL-4.”
(5) PRE-PROPOSAL CONFERENCE AND SITE-VISIT: The following from the Pre-Proposal
Conference and Site-Visit on Guam are attached:
N6274219R1199
Pre-Proposal Conference Attendee List Pre-Proposal Conference Power Point presentation Site-Visit Itinerary – Updated to reflect the actual sites visited
The proposal due date remains unchanged: 30 August 2019, 2:00 PM Hawaii Standard Time (HST).