AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
ENVIRONMENTAL REMEDIAL ACTION CONTRACT
This amendment is being issued to address questions received in response to the solicitation and to extend the closing date of the solicitation. It is the Offerors responsibility to read the entire solicitation including all amendments.
The closing date of the solicitation has been extended to 14 June 2023 at 02:00 PM Eastern Time. No additional questions/clarif ications w ill be entertained.
1. CONTRACT ID CODE PAGE OF PAGES
R 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 31-May-2023
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6247022R9014
X 9B. DATED (SEE ITEM 11)
11-May-2023
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
31-May-2023
CODE
COMNAVFACSYSCOM ATLANTIC
6506 HAMPTON BLVD
NORFOLK VA 23508-1278
N62470 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N6247022R9014
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0002
Questions and Answers:
1. Question: The hard copy submittal and number of copies requires considerable time for production and QC review prior to submission. Shipping and confirming hard copy delivery also adds a couple of days. These factors— coupled with a Monday due date and work over the Memorial Day Federal holiday—condenses the time allowed to prepare a quality proposal. Would the Navy please considering extending the due date by 2 weeks and shift to a midweek due day to allow sufficient time to receive/review answers to questions and support time for quality hard copy production and delivery.
Response: The closing date of the solicitation has been extended by two days to 14 June 2023 at 02:00 PM
Eastern Time.
2. Question: Is the safety stat page with the DART Rate and TCR rate page counted in the 40-page limit of Volume 1?
Response: Yes, the page(s) the offerors use to present their Days Away from Work, Restricted Duty, or
Job Transfer (DART) Rate and Total Case Rate (TCR) will count towards the 40-page limit.
3. Question: Are any detailed explanations for the DART and TCR Rates included in the 40-page limit of Volume 1?
Response: Yes, the page(s) the offerors use to provide any detailed explanations for their DART and TCR rates will count towards the 40-page limit.
4. Question: If Table 2 of Section II of Attachment JL.12 is submitted in 11 x 17 format, will it count as 1 page (numbered as “Page X of X”) or 2 pages (numbered as “Pages X & X of X”)?
Response: If the 11 x 17 format is used for Table 2 of Section II on Attachment JL.12, then the table should be printed single sided and each 11 X 17 single sided page will be counted as one page.
5. Question: In Volume 1, may we provide information in tables/figures that are NOT standard attachments (e.g., a DART/TPR Rate table in Factor 2; CPARs summary sheet) in a font size no smaller than 10?
Response: Yes, a font size no smaller than 10 can be used for tables/figures in Volume 1 that are not standard JL attachments.
6. Question: May acronyms be shown/defined in a List of Acronyms (introductory sheet) for both Volumes I and II and only the acronym used within the text of each volume?
Response: Yes, acronyms can be used within the text of Volumes I and II if shown/defined on the List of
Acronyms as part of the introductory sheets.
7. Question: Amendment 0001, Summary of Changes, Pg. 2: The response to Question 1 states “…delivery of proposals will not be accepted on Saturday, June 10th…” Will deliveries of proposals be accepted on Friday June 9, 2023?
N6247022R9014
Response: Yes, proposals will be accepted on Friday, 09 June 2023. Please note that the closing date of the solicitation has been extended to 14 June 2023 at 02:00 PM Eastern Time.
8. Question: We respectfully request that the due date be extended 2 days, to June 14. Due to the requirement for hard copies to be submitted and not accepting delivery on Saturday, most offerors will ship their proposals on June 8 rather than risk delays with express carriers. With a due date of June 14 and assumed ship date of June 12, that will provide offerors with 4 extra days to prepare proposals, which is critical for such extensive proposal requirements and a relatively quick turnaround.
Response: The closing date of the solicitation has been extended to 14 June 2023 at 02:00 PM Eastern Time.
9. Question: If a proposal is being submitted as a joint venture and one of the partners wishes to submit certain cost proposal sections in a sealed envelope, please confirm that a single sealed envelope per volume copy may be provided as long as the sections/tabs are provided accordingly in the envelopes. In other words, separate sealed envelopes are not required to be provided in each tab.
Response: If a proposal is being submitted as a joint venture and one of the partners wishes to submit certain cost proposal sections separately for proposal purposes, then that joint member may submit each copy of those cost proposal sections in a sealed envelope with the sections/tabs appropriately identified. Separate sealed envelopes are not required for each tab. It is the offeror’s responsibility to ensure that all cost information is submitted in accordance with Section L2.2, Proposal Format, Volume 2: Cost Proposal, Section L2.3.A, Evaluation Factors, and Section L2.3.C, Evaluation Factors, Organization of Volume II – Cost Proposal. The Direct Labor Bid and Billing Rate (JL.2), Indirect Ceiling Rates and Award Fee Application (JL.5), and Service Contract Labor Standards (SCA) and Wage Rate Requirements (Construction) (DBA) Ceiling Labor Rates (JL.6) for each joint venture member will be incorporated into any resulting Contract.
(End of Summary of Changes)