Attachment_JL4_Indirect_Ceiling_Rates_Build_Up_Form.doc

DOC document 127 KB Posted

Attached to
Environmental Remediation Services Federal contract opportunity
Solicitation number
N6247022R9014
Issued by
Department of the Navy Naval Facilities Engineering Command

View the file

Other files for this federal contract opportunity

Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NOTES FOR COMPLETING JL.4

1. Only use the base indirect rates, as applicable and in accordance with disclosed accounting practices, for the base year and each option year. The listed indirect rate categories may be adjusted to reflect the offeror’s accounting system. See additional information in Section L of the solicitation.

2. Attachment JL.4 is provided in Microsoft Word. Complete in Microsoft Word format, as provided. Additionally, offerors shall provide JL.4 in Microsoft Excel format on CDs with formulas intact to show how the multiplier was calculated.

3. Provide the percentage of work expected to be performed by the prime, each joint venture partner, and each cost reimbursable subcontractor under “Proposed Distribution of Work.”

ATTACHMENT JL.4, N62470-22-R-9014

INDIRECT CEILING RATES BUILD-UP, AWARD FEE APPLICATION AND DISTRIBUTION OF COST-REIMBURSABLE WORK FORM

BASE INDIRECT RATES USED TO DERIVE CEILING RATES

BASE YEAR

Cost Element
Fringe
Home Overhead
Field Overhead
G&A
Award Fee
FCCOM
Multiplier

Direct Labor

Provide in Chart below

Materials

Supplies

Equipment (Contractor –Owned)

Equipment (Contractor –Acquired Property)

0.00%

Rental Equipment

Inventory

Travel

0.00%

Subcontracts

Cost Reimbursable Subcontractors (Award Fee shall not be applied to award fee of cost reimbursable subcontractor’s costs at any tier)

Other

FCCOM POOL
COST BASIS
RATE

Field

Home

G&A

Owned Equipment

COST BASIS
RATE

LVE

INDIRECT CEILING RATES BUILD-UP, AWARD FEE APPLICATION AND DISTRIBUTION OF COST-REIMBURSABLE WORK FORM

BASE INDIRECT RATES USED TO DERIVE CEILING RATES

OPTION YEAR 1

Cost Element
Fringe
Home Overhead
Field Overhead
G&A
Award Fee
FCCOM
Multiplier

Direct Labor

Provide in Chart below

Materials

Supplies

Equipment (Contractor –Owned)

Equipment (Contractor –Acquired Property)

0.00%

Rental Equipment

Inventory

Travel

0.00%

Subcontracts

Cost Reimbursable Subcontractors (Award Fee shall not be applied to award fee of cost reimbursable subcontractor’s costs at any tier)

Other

FCCOM POOL
COST BASIS
RATE

Field

Home

G&A

Owned Equipment

COST BASIS
RATE

LVE

INDIRECT CEILING RATES BUILD-UP, AWARD FEE APPLICATION AND DISTRIBUTION OF COST-REIMBURSABLE WORK FORM

OPTION YEAR 2

Cost Element
Fringe
Home Overhead
Field Overhead
G&A
Award Fee
FCCOM
Multiplier

Direct Labor

Provide in Chart below

Materials

Supplies

Equipment (Contractor –Owned)

Equipment (Contractor –Acquired Property)

0.00%

Rental Equipment

Inventory

Travel

0.00%

Subcontracts

Cost Reimbursable Subcontractors (Award Fee shall not be applied to award fee of cost reimbursable subcontractor’s costs at any tier)

Other

FCCOM POOL
COST BASIS
RATE

Field

Home

G&A

Owned Equipment

COST BASIS
RATE

LVE

INDIRECT CEILING RATES BUILD-UP, AWARD FEE APPLICATION AND DISTRIBUTION OF COST-REIMBURSABLE WORK FORM

OPTION YEAR 3

Cost Element
Fringe
Home Overhead
Field Overhead
G&A
Award Fee
FCCOM
Multiplier

Direct Labor

Provide in Chart below

Materials

Supplies

Equipment (Contractor –Owned)

Equipment (Contractor –Acquired Property)

0.00%

Rental Equipment

Inventory

Travel

0.00%

Subcontracts

Cost Reimbursable Subcontractors (Award Fee shall not be applied to award fee of cost reimbursable subcontractor’s costs at any tier)

Other

FCCOM POOL
COST BASIS
RATE

Field

Home

G&A

Owned Equipment

COST BASIS
RATE

LVE

INDIRECT CEILING RATES BUILD-UP, AWARD FEE APPLICATION AND DISTRIBUTION OF COST-REIMBURSABLE WORK FORM

OPTION YEAR 4

Cost Element
Fringe
Home Overhead
Field Overhead
G&A
Award Fee
FCCOM
Multiplier

Direct Labor

Provide in Chart below

Materials

Supplies

Equipment (Contractor –Owned)

Equipment (Contractor –Acquired Property)

0.00%

Rental Equipment

Inventory

Travel

0.00%

Subcontracts

Cost Reimbursable Subcontractors (Award Fee shall not be applied to award fee of cost reimbursable subcontractor’s costs at any tier)

Other

FCCOM POOL
COST BASIS
RATE

Field

Home

G&A

Owned Equipment

COST BASIS
RATE

LVE

INDIRECT CEILING RATES BUILD-UP, AWARD FEE APPLICATION AND DISTRIBUTION OF COST-REIMBURSABLE WORK FORM Proposed Distribution of Work Offerors shall include the percentage of work expected to be performed by the prime, each joint venture partner, and each cost reimbursable subcontractor.

Prime

Joint Venture

Company A

_______% (if applicable)

Company B

_______% (if applicable)

Cost Reimbursable Subcontractor

_______% (if applicable)

Cost Reimbursable Subcontractor

_______% (if applicable)

Total

100 %