NOTES FOR COMPLETING JL.5
1. The indirect rate categories may be adjusted to reflect the offeror’s accounting system. See additional information in Sections G10, H8, H24, and L of the solicitation/contract.
2. Attachment JL.5 is provided in Microsoft Word. Complete in Microsoft Word format, as provided. Additionally, offerors shall provide JL.5 in Microsoft Excel format on CDs with formulas intact to show how the multiplier was calculated.
ATTACHMENT JL.5, N62470-22-R-9014
INDIRECT CEILING RATE AND AWARD FEE APPLICATION FORM
BASE YEAR INDIRECT CEILING RATES
| Cost Element |
| Fringe |
| Home Overhead |
| Field Overhead |
| G&A |
| Award Fee |
| FCCOM |
| Multiplier |
Direct Labor
Provide in Chart below
Materials
Supplies
Equipment (Contractor –Owned)
Equipment (Contractor –Acquired Property)
0.00%
Rental Equipment
Inventory
Travel
0.00%
Subcontracts
Cost Reimbursable Subcontractors (Award Fee shall not be applied to award fee of cost reimbursable subcontractor’s costs at any tier)
Other
| FCCOM POOL |
| COST BASIS |
| RATE |
Field
Home
G&A
Owned Equipment
| COST BASIS |
| RATE |
LVE
Should actual indirect rates experienced during performance of the contract be lower than those shown above, actual rates will be proposed/charged in lieu of the maximum rates.
See additional information in Sections G10, H8, H24, and L of the solicitation/contract.
Please note that the multiplier rate by itself is not an indirect ceiling rate. Each indirect rate (Fringe, Overhead, and G&A) as well as award fee has its own ceiling rate. The multiplier rate is to be provided by each Offeror so that the Government can understand how the indirect rates and award fee are being applied to the different cost elements as well as to see the total potential markup on each cost element.
INDIRECT CEILING RATE AND AWARD FEE APPLICATION FORM
OPTION YEAR 1
| Cost Element |
| Fringe |
| Home Overhead |
| Field Overhead |
| G&A |
| Award Fee |
| FCCOM |
| Multiplier |
Direct Labor
Provide in Chart below
Materials
Supplies
Equipment (Contractor –Owned)
Equipment (Contractor –Acquired Property)
0.00%
Rental Equipment
Inventory
Travel
0.00%
Subcontracts
Cost Reimbursable Subcontractors (Award Fee shall not be applied to award fee of cost reimbursable subcontractor’s costs at any tier)
Other
| FCCOM POOL |
| COST BASIS |
| RATE |
Field
Home
G&A
Owned Equipment
| COST BASIS |
| RATE |
LVE
Should actual indirect rates experienced during performance of the contract be lower than those shown above, actual rates will be proposed/charged in lieu of the maximum rates.
Please note that the multiplier rate by itself is not an indirect ceiling rate. Each indirect rate (Fringe, Overhead, and G&A) as well as award fee has its own ceiling rate. The multiplier rate is to be provided by each Offeror so that the Government can understand how the indirect rates and award fee are being applied to the different cost elements as well as to see the total potential markup on each cost element.
INDIRECT CEILING RATE AND AWARD FEE APPLICATION FORM
OPTION YEAR 2
| Cost Element |
| Fringe |
| Home Overhead |
| Field Overhead |
| G&A |
| Award Fee |
| FCCOM |
| Multiplier |
Direct Labor
Provide in Chart below
Materials
Supplies
Equipment (Contractor –Owned)
Equipment (Contractor –Acquired Property)
0.00%
Rental Equipment
Inventory
Travel
0.00%
Subcontracts
Cost Reimbursable Subcontractors (Award Fee shall not be applied to award fee of cost reimbursable subcontractor’s costs at any tier)
Other
| FCCOM POOL |
| COST BASIS |
| RATE |
Field
Home
G&A
Owned Equipment
| COST BASIS |
| RATE |
LVE
Should actual indirect rates experienced during performance of the contract be lower than those shown above, actual rates will be proposed/charged in lieu of the maximum rates.
Please note that the multiplier rate by itself is not an indirect ceiling rate. Each indirect rate (Fringe, Overhead, and G&A) as well as award fee has its own ceiling rate. The multiplier rate is to be provided by each Offeror so that the Government can understand how the indirect rates and award fee are being applied to the different cost elements as well as to see the total potential markup on each cost element.
INDIRECT CEILING RATE AND AWARD FEE APPLICATION FORM
OPTION YEAR 3
| Cost Element |
| Fringe |
| Home Overhead |
| Field Overhead |
| G&A |
| Award Fee |
| FCCOM |
| Multiplier |
Direct Labor
Provide in Chart below
Materials
Supplies
Equipment (Contractor –Owned)
Equipment (Contractor –Acquired Property)
0.00%
Rental Equipment
Inventory
Travel
0.00%
Subcontracts
Cost Reimbursable Subcontractors (Award Fee shall not be applied to award fee of cost reimbursable subcontractor’s costs at any tier)
Other
| FCCOM POOL |
| COST BASIS |
| RATE |
Field
Home
G&A
Owned Equipment
| COST BASIS |
| RATE |
LVE
Should actual indirect rates experienced during performance of the contract be lower than those shown above, actual rates will be proposed/charged in lieu of the maximum rates.
Please note that the multiplier rate by itself is not an indirect ceiling rate. Each indirect rate (Fringe, Overhead, and G&A) as well as award fee has its own ceiling rate. The multiplier rate is to be provided by each Offeror so that the Government can understand how the indirect rates and award fee are being applied to the different cost elements as well as to see the total potential markup on each cost element.
INDIRECT CEILING RATE AND AWARD FEE APPLICATION FORM
OPTION YEAR 4
| Cost Element |
| Fringe |
| Home Overhead |
| Field Overhead |
| G&A |
| Award Fee |
| FCCOM |
| Multiplier |
Direct Labor
Provide in Chart below
Materials
Supplies
Equipment (Contractor –Owned)
Equipment (Contractor –Acquired Property)
0.00%
Rental Equipment
Inventory
Travel
0.00%
Subcontracts
Cost Reimbursable Subcontractors (Award Fee shall not be applied to award fee of cost reimbursable subcontractor’s costs at any tier)
Other
| FCCOM POOL |
| COST BASIS |
| RATE |
Field
Home
G&A
Owned Equipment
| COST BASIS |
| RATE |
LVE
Should actual indirect rates experienced during performance of the contract be lower than those shown above, actual rates will be proposed/charged in lieu of the maximum rates.
Please note that the multiplier rate by itself is not an indirect ceiling rate. Each indirect rate (Fringe, Overhead, and G&A) as well as award fee has its own ceiling rate. The multiplier rate is to be provided by each Offeror so that the Government can understand how the indirect rates and award fee are being applied to the different cost elements as well as to see the total potential markup on each cost element.