This document contains a pre-award accounting system adequacy checklist and questions for prospective contractors to complete regarding their accounting system, processes and compliance. It requests information about whether the contractor's accounting system has been audited by DCAA, is in accordance with GAAP and CAS, properly segregates direct and indirect costs, and accumulates and allocates costs. It also asks if the system provides financial data necessary for contract cost principles, progress payments and pricing follow-on acquisitions. The contractor must explain their accounting system and compliance in narrative boxes for each question.

The accompanying federal contract opportunity notice is for product family support services for the Southwest Regional Maintenance Center. The cost-plus-fixed-fee IDIQ contract has a one year base period and four one-year options, and requires engineering, technical, repair and program support services across all product families at SWRMC facilities. The follow-on solicitation to the incumbent's contract is expected in 4th quarter FY2019 for award in FY2020. The services are to be performed at SWRMC aboard Naval Base San Diego.

S-6: DCAA Pre-award Accounting system adequacy checklist

View the file

Other files for this federal contract opportunity

Other files attached to Product Family Support Services, newest first.
File Type Posted
Amendment 0004.pdf PDF
00003.pdf PDF
Section_J__-_Revised_S-7_Attachment_(22_July_2019).xlsx XLSX spreadsheet
0002.pdf PDF
N55236-19-R-0003_Amendment_0001.pdf PDF
S-7__Supporting_Hours_Rev.1.xlsx XLSX spreadsheet
S-3__Reference_Information_Sheet_Rev.1.pdf PDF
S-4__Past_Performance_Questionnaire.docx DOCX document
S-5__Cost_Summary_Workbook.xlsx XLSX spreadsheet
J-2__DD_254.pdf PDF
J-3_Contract_Discrepancy_Report_DD_Form_2272.pdf PDF
N55236-19-R-0003.docx DOCX document
J-6__GFP.xlsx XLSX spreadsheet
J-5__List_of_Acronyms.docx DOCX document
S-2__Experience_Matrix.docx DOCX document
J-4__NonDisclosureAgreement.docx DOCX document
S-1__REQUEST_FOR_SPECIFICATION_CLARIFICATION.docx DOCX document
S-3__Reference_Information_Sheet.docx DOCX document
J-1_Department_of_Labor_Wage_determination_15-5635.pdf PDF
J-7__SWRMC_CAM.pdf PDF
S-7__Supporting_Hours.xlsx XLSX spreadsheet
Exhibit_A_Contract_Data_Requirements_List_DD_Form_1423.pdf PDF
Show all 22

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N55236-19-R-0003 Section J Attachment S-6

NAVSEA (NON-SEAPORTe) PRE-AWARD ACCOUNTING SYSTEM ADEQUACY CHECKLIST

(TO BE COMPLETED BY PROSPECTIVE CONTRACTORS)

DATE: ___________

Company Name and Full Address:
Click here to enter text.
Commercial and Government Agency (CAGE) Code Number:

(found at http://www.dlis.dla.mil/cage_welcome.asp) Click here to enter text.

Data Universal Numbering System (DUNS) Number:

(FAR 52.204-6)

Click here to enter text.
Cognizant Defense Contract Audit Agency (DCAA) office info (Address / ph # / /eMail) –

(found at http://www.dcaa.mil/office_locator.html)

Click here to enter text.
Company Point of Contact:

(Name, Title, Phone Number, and E-mail address) Click here to enter text.

Name, Title, and Signature of Company Principal (President / VP / Controller, etc) responsible for the design of the Accounting System.

Name

Title eMail Address

________________________________________________________
SignatureDate

For further information, please review DCAA Manual No. 7641.90, Information for Contractors, dated June 26, 2012, located at http://www.dcaa.mil/audit_process_overview.html .

For each Question, check only one box. ALL Questions must have explanatory narrative text entered in the boxes. Please provide sufficient detail to describe the process (Including Account Numbers / Process Flow etc.). Each Question must be complete. Do NOT refer to previous answers, ( i.e. “See Question 3 Above”). Answer all questions using the space provided (Attachments can be provided to amplify or document the responses, but the Form should be a stand-alone explanation of your Accounting System.

Instruction: Please complete the Form and provide explanatory narrative for all of the following questions.

1. Has your organization’s Accounting System ever been audited by DCAA?

|_| YES (if YES, the Offeror should attach a copy of their most recent DCAA audit report to this Modified Pre-Award Survey) or provide DCAA Report # or DCAA POC info.

|_| NO (if NO, answer N/A to Questions 1.A., 1.B., and 1.C. below)

1.A. If the answer is “Yes” to Question 1 above, when was the audit performed?

|_| Within the past 1 Year.

|_| Within the past 3 Years.

|_| Greater than 3 Years ( PROVIDE THE YEAR THE AUDIT WAS PERFORMED HERE - ________ ).

|_| N/A (Answer to Question 1 is NO)

1.B. If the answer is “Yes” to Question 1 above, did DCAA / DCMA determine the Accounting System acceptable for award of prospective contracts?

|_| YES

|_| NO (if NO provide an explanation in the box below)

|_| N/A (Answer to Question 1 is NO)

Click here to enter text.

1.C. If the answer is “Yes” to Question 1 above, have there been any changes to the Accounting System since the DCAA audit?

|_| YES (if YES, describe the changes in the box below)

|_| NO

|_| N/A (Answer to Question 1 is NO))

Click here to enter text.

1.D. If the answer is “Yes” to Question 1 above, and your audit is older than 3 years, have you had any past proposals rejected due to the age of your DCAA audit?

|_| YES

|_| NO

|_| N/A (Answer to Question 1 is NO))

Click here to enter text.

2. Is your organization subject to CAS (48 CFR Chapter 99)?

|_| YES (If YES, is it FULL or MODIFIED CAS?) |_| FULL |_| MODIFIED

(If YES (FULL or MODIFIED), the Offeror MUST attach a copy of their most recent audit reports/documentation regarding all CAS compliance or non-compliance issues to this Modified Pre-Award Survey)

|_| NO (if NO, provide an explanation in the box below why your organization is exempt and answer N/A to Questions 2.A., 2.B., and 2.C. below)

Click here to enter text.

2.A. Has your organization submitted a CASB disclosure statement (CASB DS-1) to DCAA and has it been determined adequate?

|_| YES (if YES, provide an explanation that validates your answer in the box below)

|_| NO (if NO, provide an explanation in the box below)

|_| N/A (Answer to Question 2 is NO)

Click here to enter text.

2.B. Has your organization been notified by DCAA / DCMA that it is in (or may be in) noncompliance with its disclosure statement or CAS?

|_| NO (if NO, provide an explanation in the box below)

|_| N/A (N/A, if the answer to Question 2 is NO)

Click here to enter text.

2.C. Is any aspect of this proposal inconsistent with your organization’s disclosed practices or applicable CAS?

|_| NO (if NO, provide an explanation in the box below)

|_| N/A (N/A, if the answer to Question 2 is NO or if you have no current, active proposal being considered)

Click here to enter text.

3. Has your organization’s Accounting System been audited by an outside Certified Public Accountant/Consultant or other Cognizant Federal Agency other than DCAA?

|_| YES (If YES, the Offeror MUST attach a copy of their most recent audit report to this Modified Pre-Award Survey ) NOTE: Do not submit your Annual Financial Audit.

|_| NO

4. Is your organization’s Accounting System currently in full operation?

|_| NO (if NO, provide an explanation in the box below which portions are (1) in operation, (2) set up, but not yet in operation, (3) anticipated, or (4) non-existent)

|_| N/A (if N/A, provide an explanation in the box below)

Click here to enter text.

5. Is your organization’s Accounting System in accord with Generally Accepted Accounting Principles (GAAP) Applicable in the Circumstances?

|_| NO (if NO, provide an explanation in the box below)

Click here to enter text.

6. Is your organization’s Accounting System ready for a DCAA audit?

|_| NO (if NO, provide an explanation in the box below as to when you will be ready for an Audit)

Click here to enter text.

7. Does the Accounting System provide for the proper segregation of Direct Costs from Indirect Costs?

|_| NO (if NO, provide an explanation in the box below)

Click here to enter text.

8. Does the Accounting System provide for the identification and accumulation of Direct Costs by contract?

|_| NO (if NO, provide an explanation in the box below)

Click here to enter text.

9. Does the Accounting System provide for a logical and consistent method for the allocation of Indirect Costs to intermediate and final cost objectives? (A contract is a final cost objective.)

|_| NO (if NO, provide an explanation in the box below)

Click here to enter text.

10. Does the Accounting System provide for the accumulation of costs under general ledger control?

|_| NO (if NO, provide an explanation in the box below)

Click here to enter text.

11. Does the Accounting System provide for a timekeeping system that identifies employees’ labor by intermediate or final cost objectives?

|_| NO (if NO, provide an explanation in the box below)

Click here to enter text.

12. Does the Accounting System provide for a labor distribution system that charges Direct and Indirect labor to the appropriate cost objectives?

|_| NO (if NO, provide an explanation in the box below)

Click here to enter text.

13. Does the Accounting System provide for an interim (at least monthly) determination of costs charged to a contract through routine posting of books of account?

Click here to enter text.

14. Does the Accounting System provide for an exclusion of costs charged to government contracts of amounts which are not allowable in terms of FAR 31, Contract Cost Principles and Procedures, or other contract provisions?

Click here to enter text.

15. Does the Accounting System provide for the identification of costs by contract line item and by units (as if each unit or line item were a separate contract) if required by the proposed contract?

|_| NO (if NO, provide an explanation in the box below)

Click here to enter text.

16. Does the Accounting System provide for the segregation of preproduction costs from production costs?

|_| NO (if NO, provide an explanation in the box below)

Click here to enter text.

17. Does the Accounting System provide financial information as required by contract clauses concerning Limitation of Cost (FAR 52.232-20 and 21) or Limitation on Payments (FAR 52.216-16)?

|_| NO (if NO, provide an explanation in the box below)

Click here to enter text.

18. Does the Accounting System provide financial information required to support requests for Progress Payments?

|_| NO (if NO, provide an explanation in the box below)

Click here to enter text.

19. Is the Accounting System designed, and are the records maintained, in such a manner that adequate, reliable data are developed for use in pricing follow-on acquisitions?

|_| NO (if NO, provide an explanation in the box below)

Click here to enter text.

20. Is your organization required to submit Incurred Cost Proposals to DCAA/DCMA?

|_| YES (If Yes, indicate below whether you are current with your ICE submission and the Last year an audit was performed by DCAA)

|_| NO

|_| N/A

Click here to enter text.

21. Has your organization submitted Cost Vouchers or Progress Payments to DCAA/DCMA?

|_| YES (If Yes, indicate below whether any Cost Vouchers have been rejected by DCAA)

|_| NO

Click here to enter text.

22. Does your organization have FPRR/FPRA or Provisional Billing Rates with DCMA or DCAA?

|_| YES (If Yes, please provide a copy)

|_| NO

Click here to enter text.

23. Is your organization planning on submitting proposals on Cost-Type (FAR 16.3) contracts/task orders?

|_| NO (if NO, provide an explanation in the box below)

Click here to enter text.

24. Is your organization currently performing on Cost-Type (FAR 16.3) contracts/task orders?

|_| NO (If No, indicate below whether your Organization ever performed Cost Type Contracts (When?)

Click here to enter text.

25. Does your Company bid/propose Uncompensated Overtime (UCOT)?

|_| YES (If Yes describe your methodology below)

|_| NO

Click here to enter text.

NOTE: Before returning the WORD FILE as part of your proposal submission, Rename file in the Following Format:

Please note that responsibility for "Financial Capability" reviews was separated from the Pre-Award Accounting System Audit and transferred from DCAA to DCMA in 2010.

DO NOT SEND ANY FINANCIAL DOCUMENTS TO the PCO OR DCMA AT THIS TIME. To prevent contractor from expending resources prematurely, a DCMA Financial Capability reviews will be requested only after successful completion of a DCAA Pre-Award Accounting System Audit.

(If your “Word” Version does not permit Signatures, you may send the Signature Page as a separate pdf, using naming convention referred to above)

File details come from the government source that posted it. Updated .