Amend 0004 Sam Post.pdf
PDF 650 KB Posted
- Attached to
- Repair BEQ HP135
- Solicitation number
- N4008526R9044
About this file
This document is Amendment 0004 to Solicitation N40085-26-R-9044 for the Repair BEQ HP135 project at MCB Camp Lejeune, North Carolina, issued by NAVFAC Mid-Atlantic on July 10, 2026. The amendment answers 10 requests for information (RFI) submitted by prospective contractors. The receipt deadline for proposals remains unchanged, and contractors must acknowledge receipt of this amendment when submitting proposals or risk rejection.
The RFI responses provide clarifications on mechanical and plumbing specifications: exhaust ductwork to DOAS units with energy recovery requires insulation per updated Specification Section 23 07 00; vandal-proof hood vents are not required; Specification Section 23 11 20 on facility gas piping will be provided (included in full in Amendment 02); updated piping details for pre-heat coil systems will be provided; adhesive labels are acceptable for pipe designation instead of snap-on labels; Section 33 61 14 applies to all hot water piping including heating hot water; air distribution grilles require factory-provided opposed blade dampers without security features; a thermostatic mixing valve (TMV-2) on the Laundry Restroom is not required; shower drains must be 2-inch diameter no-caulk drains with PVC bodies and 4.25-inch stainless steel strainers designed for preformed shower stall bases. Specification Section 23 11 20 for Facility Gas Piping addresses natural gas piping requirements, materials standards, installation procedures, testing protocols, and compliance with NFPA 54 and applicable codes. Amendment 02 (July 7, 2026) adds the complete gas piping specification and updates mechanical detail drawings in response to the RFI submissions.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICIATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 11)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPIRATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
1 3
AMENDMENT NO. 0004 07/10/26 25-0011
N40085
NAVFAC Mid-Atlantic Resident Officer in Charge of Construction 1107A Birch Street Camp Lejeune, NC 28547-2521
See Item 6
✘ N40085-26-R-9044
06/18/26
25-0011, Repair BEQ HP135 Amendment 0004, Answer Requests for information
The time and date for receipt of proposals remains unchanged.
This amendment should be acknowledged when your proposal is submitted. Failure to acknowledge the amendment may constitute grounds for rejection of a proposal.
See Continuation Page(s)
N40085-26-R-9044 Amendment 0004
CONTINUATION SHEET
1. QUESTION: Section 23 07 00 Part 3.3 “Duct Insulation Systems Installation” does not require for exhaust ducts to be insulated. However, the exhaust ductwork serving the E1 grilles (in the closets and bathrooms in the sleeping rooms) is being routed to a DOAS unit with energy recovery. Does the exhaust ductwork from the sleeping rooms to the DOAS need to be insulated, and if so, what thickness is required?
ANSWER: Spec section 23 07 00 was updated as part of Amendment 01, 06/30/26
2. QUESTION: Note 6 on P-001 indicates that all vents to have vandal proof hoods. Detail C6 on drawing P-501 indicates for the vent to be installed without a vandal proof hood. Are we to install the vents per detail C6 on drawing P-501?
ANSWER: No. Vandal proof hood vents are not required for this project.
3. QUESTION: There is no specification indicating the type of material to be used for the gas piping. Please provide specification.
ANSWER: Spec section 23 11 20 will be provided.
4. QUESTION: Detail C1 on drawing M-504 Pre-Heat Coil Piping does not show a strainer on the main supply line serving the DOAS Units, nor does it show a check valve on the main supply line to keep the recirculation pump from circulating on the supply side and not through the coil.
See attached drawing and red line valves for possible installation to prevent this issue and protect the coil. Will recommended strainer and check valves be required?
ANSWER: Sheet with updated details will be provided.
5. QUESTION: Adhesive labels with arrows in the specified colors have been sufficient for pipe designation at Camp Lejeune. Will adhesive labels be allowed in lieu of snap on or wrap around labels shown on detail D4 on drawing P-504 and detail A4 on drawing M-504?
ANSWER: DOR takes no exception to the use of adhesive labels in lieu of snap on/wrap around labels.
6. QUESTION: Section 33 61 14 Exterior Buried Preinsulated Water Piping, paragraph 1.2- System Description says “Piping system includes hot domestic water piping, recirculating hot domestic water piping, chilled water piping, and related work.” There is no mention of heating hot water piping. What are the requirements for the exterior buried preinsulated heated hot water piping?
N40085-26-R-9044 Amendment 0004
ANSWER: 33 61 14 applies to hot water piping. Description should read, “Piping system includes hot domestic water piping, recirculating hot domestic water piping, chilled water piping, hot water piping and related work.”
7. QUESTION: Note 5 on Air Distribution Schedule on drawing M-601 calls for a minimum-security face plate with tamperproof screws. Is the intent for this to have a minimum-security type grille, or a standard grilled with a security cover installed over it?
ANSWER: Note 5 states: "PROVIDE GRILLE WITH FACTORY PROVIDED/INSTALLED
OPPOSED BLADE DAMPER."
8. QUESTION: Plumbing Equipment Schedule on P-601 show a thermostatic mixing valve tagged TMV-2 to be located on the Laundry Restroom. We cannot find this mixing valve anywhere on the drawings except the schedule. Where specifically do this mixing valve located?
ANSWER: This mixing valve is not required for this project.
9. QUESTION: Shower drains are listed in specification section 22 00 00 paragraph 2.6.1 Floor & Shower Drains. These drains are listed to have a “galvanized body, integral seepage pan, and adjustable perforated or slotted chromium-plated bronze, nickel-bronze, or nickel-brass strainer, consisting of grate and threaded collar.” However, this description is for drains typically used in tile showers with metallic shower pans and is not compatible with the specified shower stall system. Typically in a solid surface shower pan, the shower drain is 2” no-caulk shower drain designed for use with preformed shower stall bases where the drain body is sealed to the shower base with a fiber/rubber washer and mechanically compressed gasket. The drain body material will be PVC to match the new drain, waste, and vent piping. The shower drain strainer can be 4.25” diameter stainless steel. Will this type of drain be a proposed solution that is acceptable to the government? If not, please clarify what type of drain to use.
ANSWER: Provide and install 2" diameter no-caulk shower drain designed for us with preformed shower stall bases where the drain body is sealed to the shower with a fiber/rubber washer and mechanically compressed gasket. The drain body material will be PVC to match the new drain, waste and vent piping. The shower drain strainer will be 4.25" diameter stainless steel.
10. Please find attached the files need to accompany the above responses.
11. All other terms and conditions remain unchanged.
Repairs BEQ HP135 Project No.: 25-0011 MCB Camp Lejeune, NC
SECTION 23 11 20
FACILITY GAS PIPING
05/20
PART 1 GENERAL
1.1 SUMMARY
This specification section applies to gas piping installed within buildings incidental underground piping under building, above ground steel piping and corrugated stainless steel tubing (CSST) both outside (up to 5 feet beyond exterior walls) and within buildings in compliance with NFPA 54 / AGA Z223.1 , "National Fuel Gas Code" , "Fuel Gas Piping".
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN GAS ASSOCIATION (AGA)
AGA ANSI B109.4 (2016) Self-Operated Diaphragm-Type Natural Gas Service Regulators for Nominal Pipe Size 1¼ inches (32 mm) and Smaller with Outlet Pressures of 2 psig (13.8 kPa) and Less
AGA XR0603 (2006; 8th Ed) AGA Plastic Pipe Manual for Gas Service
AGA Z223.1 (2012) National Fuel Gas Code
AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)
ANSI Z21.15/CSA 9.1 (2009; Addenda A 2012, Addenda B 2013; R 2019) Manually Operated Gas Valves for Appliances, Appliance Connector Valves and Hose End Valves
ANSI Z21.18/CSA 6.3 (2007; R 2017) Gas Appliance Pressure Regulators
ANSI Z21.21/CSA 6.5 (2015) Automatic Valves for Gas Appliances
ANSI Z21.24/CSA 6.10 (2015; Errata 2017) Connectors for Gas Appliances
ANSI Z21.41/CSA 6.9 (2014; R 2019) Quick-Disconnect Devices for Use with Gas Fuel Appliances
ANSI Z21.69/CSA 6.16 (2009; Addenda A 2012; R 2014) Connectors for Movable Gas Appliances
ANSI Z21.80/CSA 6.22 (2019) Line Pressure Regulators
SECTION 23 11 20 Page 1 AMDT 02 (07 July 2026)
ANSI Z21.93/CSA 6.30 (2017) Excess Flow Valves for Natural Gas and Propane Gas with Pressures up to 5 psig
AMERICAN PETROLEUM INSTITUTE (API)
API RP 2003 (2015; 8th Ed) Protection Against Ignitions Arising out of Static, Lightning, and Stray Currents
API Std 598 (2009) Valve Inspecting and Testing
API Std 607 (2016) Fire Test for Quarter-turn Valves and Valves Equipped with Non-metallic Seats
AMERICAN SOCIETY OF CIVIL ENGINEERS (ASCE)
ASCE 25-16 (2016) Earthquake-Activated Automatic Gas Shutoff Devices
AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)
ASME A13.1 (2020) Scheme for the Identification of Piping Systems
ASME B1.1 (2003; R 2018) Unified Inch Screw Threads (UN and UNR Thread Form)
ASME B1.20.1 (2013; R 2018) Pipe Threads, General Purpose (Inch)
ASME B16.3 (2021) Malleable Iron Threaded Fittings, Classes 150 and 300
ASME B16.5 (2020) Pipe Flanges and Flanged Fittings NPS 1/2 Through NPS 24 Metric/Inch Standard
ASME B16.9 (2018) Factory-Made Wrought Buttwelding Fittings
ASME B16.11 (2016) Forged Fittings, Socket-Welding and Threaded
ASME B16.21 (2021) Nonmetallic Flat Gaskets for Pipe Flanges
ASME B16.33 (2012; R 2017) Manually Operated Metallic Gas Valves for Use in Gas Piping Systems Up to 125 psi, (Sizes NPS 1/2 - NPS 2)
ASME B16.39 (2020) Standard for Malleable Iron Threaded Pipe Unions; Classes 150, 250, and 300
ASME B18.2.1 (2012; Errata 2013) Square and Hex Bolts and Screws (Inch Series)
ASME B18.2.2 (2015) Nuts for General Applications:
Machine Screw Nuts, Hex, Square, Hex Flange, and Coupling Nuts (Inch Series)
SECTION 23 11 20 Page 2
ASME B31.8 (2018; Supplement 2018) Gas Transmission and Distribution Piping Systems
ASME BPVC SEC VIII D1 ( 2019 ) BPVC Section VIII-Rules for Construction of Pressure Vessels Division 1
ASTM INTERNATIONAL (ASTM)
ASTM 01.01 (2019) Steel - Piping, Tubing, Fittings
ASTM A53/A53M (2020) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless
ASTM A193/A193M (2020) Standard Specification for Alloy-Steel and Stainless Steel Bolting Materials for High-Temperature Service and Other Special Purpose Applications
ASTM A194/A194M (2018) Standard Specification for Carbon Steel, Alloy Steel, and Stainless Steel Nuts for Bolts for High-Pressure or High-Temperature Service, or Both
ASTM A513/A513M (2019) Standard Specification for Electric-Resistance-Welded Carbon and Alloy Steel Mechanical Tubing
ASTM F2015 (2000; R 2013) Standard Specification for Lap Joint Flange Pipe End Applications
CSA GROUP (CSA)
ANSI LC 1/CSA 6.26 (2019) Fuel Gas Piping Systems Using Corrugated Stainless Steel Tubing (CSST)
FM GLOBAL (FM)
FM APP GUIDE (updated on-line) Approval Guide http://www.approvalguide.com/
MANUFACTURERS STANDARDIZATION SOCIETY OF THE VALVE AND FITTINGS
INDUSTRY (MSS)
MSS SP-25 (2018) Standard Marking System for Valves, Fittings, Flanges and Unions
MSS SP-58 (2018) Pipe Hangers and Supports - Materials, Design and Manufacture, Selection, Application, and Installation
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 54 (2021) National Fuel Gas Code
NFPA 58 (2020) Liquefied Petroleum Gas Code
NFPA 70 (2020; ERTA 20-1 2020; ERTA 20-2 2020;
SECTION 23 11 20 Page 3
ERTA 20-3 2020; TIA 20-1; TIA 20-2; TIA
20-3; TIA 20-4; TIA 20-5; TIA 20-6; TIA
20-7; TIA 20-8; TIA 20-9; TIA 20-10; TIA
20-11; TIA 20-12; TIA 20-13; TIA 20-14;
TIA 20-15; TIA 20-16; ERTA 20-4 2022)
National Electrical Code
SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION
(SMACNA)
SMACNA 1981 (2008) Seismic Restraint Manual Guidelines for Mechanical Systems, 3rd Edition
U.S. DEPARTMENT OF DEFENSE (DOD)
MIL-STD-101 (2014; Rev C) Color Code for Pipelines and for Compressed Gas Cylinders
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
49 CFR 192 Transportation of Natural and Other Gas by Pipeline: Minimum Federal Safety Standards
UNDERWRITERS LABORATORIES (UL)
UL FLAMMABLE & COMBUSTIBLE (2012) Flammable and Combustible Liquids and Gases Equipment Directory
1.3 SYSTEM DESCRIPTION
The gas piping system includes natural gas piping and appurtenances from point of connection with supply system, as indicated, to gas operated equipment within the facility. Submit operation and maintenance data in accordance with Section 01 78 23 OPERATION AND MAINTENANCE DATA, in three separate packages. Section 23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS applies to this section, with additions and modifications specified herein. Provide cathodically protected insulating joints connecting aboveground piping from the meter to the building, with lightning arrestors conforming to API RP 2003 , installed where indicated.
1.3.1 Gas Facility System and Equipment Operation
Include shop drawings showing piping layout, locations of system valves, gas line markers and cathodic protection system; step-by-step procedures for system start up, operation and shutdown (index system components and equipment to the system drawings); isolation procedures including valve operation to shutdown or isolate each section of the system (index valves to the system maps and provide separate procedures for normal operation and emergency shutdown if required to be different). Submit Data package No. 4.
1.3.2 Gas Facility System Maintenance
Include maintenance procedures and frequency for system and equipment;
identification of pipe materials and manufacturer by locations, pipe repair procedures, and jointing procedures at transitions to other piping material or material from a different manufacturer. Submit Data Package No.4.
SECTION 23 11 20 Page 4
1.3.3 Gas Facility Equipment Maintenance
Include identification of valves, shut-offs, disconnects, and other equipment by materials, manufacturer, vendor identification and location;
maintenance procedures and recommended tool kits for valves and equipment;
recommended repair methods (i.e., field repair, factory repair, or replacement) for each valve and piece of equipment; and preventive maintenance procedures, possible failure modes and troubleshooting guide.
Submit Data Package No. 3.
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-02 Shop Drawings
Gas Piping System ; G
SD-03 Product Data
Pipe and Fittings ; G
Gas Equipment Connectors ; G
Gas Piping System ; G
Pressure Regulators ; G
Valves ; G
SD-06 Test Reports
Testing ; G
Pressure Tests ; G
Test with Gas ; G
SD-07 Certificates
SD-08 Manufacturer's Instructions
SD-10 Operation and Maintenance Data
Gas Facility System and Equipment Operation ; G
Gas Facility System Maintenance ; G
SECTION 23 11 20 Page 5
Gas Facility Equipment Maintenance ; G
1.5 QUALITY ASSURANCE
Submit manufacturer's descriptive data and installation instructions for approval for compression-type mechanical joints used in joining dissimilar materials and for insulating joints. Mark all valves, flanges and fittings in accordance with MSS SP-25 .
1.5.1 Shop Drawings
Submit drawings for complete Gas Piping System , within 30 days of contract award, showing location, size and all branches of pipeline; location of all required shutoff valves; and instructions necessary for the installation of gas equipment connectors and supports.
PART 2 PRODUCTS
2.1 MATERIALS AND EQUIPMENT
Provide materials and equipment which are the standard products of a manufacturer regularly engaged in the manufacture of the products and that essentially duplicate items that have been in satisfactory use for at least 2 years prior to bid opening. Asbestos or products containing asbestos are not allowed. Submit catalog data and installation instructions for pipe, valves, all related system components, pipe coating materials and application procedures. Conform to NFPA 54 and with requirements specified herein. Provide supply piping to appliances or equipment at least as large as the inlets thereof. Provide pipe and fittings submittal data.
2.2 GAS PIPING SYSTEM AND FITTINGS
2.2.1 Steel Pipe, Joints, and Fittings
a. Pipe: Black carbon steel in accordance with ASTM A53/A53M, Schedule 40 , threaded ends for sizes 2 inches and smaller; otherwise, plain end beveled for butt welding.
b. Threaded Fittings: ASME B16.3 , black malleable iron.
c. Socket-Welding Fittings: ASME B16.11 , forged steel.
d. Butt-Welding Fittings: ASME B16.9 , with backing rings of compatible material.
e. Unions: ASME B16.39 , black malleable iron.
f. Flanges and Flanged Fittings: ASME B16.5 steel flanges or convoluted steel flanges conforming to ASME BPVC SEC VIII D1 , with flange faces having integral grooves of rectangular cross sections which afford containment for self-energizing gasket material.
2.2.2 Steel Tubing, Joints and Fittings
Provide steel tubing conforming to ASTM 01.01 , and ASTM A513/A513M , with tubing joints made up with gas tubing fittings recommended by the tubing manufacturer.
SECTION 23 11 20 Page 6
2.2.3 Sealants for Steel Pipe Threaded Joints
Provide joint sealing compound as listed in UL FLAMMABLE & COMBUSTIBLE, Class 20 or less. For taping, use tetrafluoroethylene tape conforming to
UL FLAMMABLE & COMBUSTIBLE.
2.2.4 Flange Gaskets
Provide gaskets of nonasbestos compressed material in accordance with ASME B16.21 , 1/16 inch thickness, full face or self-centering flat ring type, containing aramid fibers bonded with styrene butadiene rubber (SBR) or nitrile butadiene rubber (NBR) suitable for a maximum 600 degree F service, to be used for hydrocarbon service.
2.2.5 Pipe Threads
Provide pipe threads conforming to ASME B1.20.1 .
2.2.6 Escutcheons
Provide chromium-plated steel or chromium-plated brass escutcheons, either one piece or split pattern, held in place by internal spring tension or set screw.
2.2.7 Insulating Pipe Joints
2.2.7.1 Insulating Joint Material
Provide insulating joint material between flanged or threaded metallic pipe systems where shown to control galvanic or electrical action.
2.2.7.2 Threaded Pipe Joints
Provide threaded pipe joints of steel body nut type dielectric unions with insulating gaskets.
2.2.7.3 Flanged Pipe Joints
Provide joints for flanged pipe consisting of full face sandwich-type flange insulating gasket of the dielectric type, insulating sleeves for flange bolts, and insulating washers for flange nuts. Provide lap joint flange pipe ends conforming to ASTM F2015.
2.2.8 Flexible Connectors
a. Provide flexible connectors for connecting gas utilization equipment to building gas piping conforming to ANSI Z21.24/CSA 6.10 or ANSI Z21.41/CSA 6.9 for quick disconnect devices, and flexible connectors for movable food service equipment conforming to
ANSI Z21.69/CSA 6.16 .
b. Do not install the flexible connector through the appliance cabinet face. Provide rigid metallic pipe and fittings to extend the final connection beyond the cabinet, except when appliance is provided with an external connection point.
SECTION 23 11 20 Page 7
2.3 VALVES
Provide lockable shutoff or service isolation valves as indicated in the drawings conforming to the following:
2.3.1 Valves 2 Inches and Smaller
Provide valves 2 inches and smaller conforming to ASME B16.33 of materials and manufacture compatible with system materials used.
2.4 PIPE HANGERS AND SUPPORTS
Provide pipe hangers and supports conforming to MSS SP-58 .
2.5 LINE AND APPLIANCE REGULATORS AND SHUTOFF VALVES
Provide regulators conforming to ANSI Z21.18/CSA 6.3 for appliances , and ANSI Z21.80/CSA 6.22 for line pressure regulators . Provide shutoff valves conforming to ANSI Z21.15/CSA 9.1 for manually controlled gas shutoff valves and ANSI Z21.21/CSA 6.5 for automatic shutoff valves for gas appliances.
2.6 NATURAL GAS SERVICE
2.6.1 Service Regulators
a. Provide ferrous bodied pressure regulators for individual service lines, capable of reducing distribution line pressure to pressures required for users. Provide service regulators conforming to AGA ANSI B109.4 CGA-6.18-M95 with full capacity internal relief and overpressure shutoff. Set pressure relief at a lower pressure than would cause unsafe operation of any connected user.
b. Adjust regulators for liquified petroleum gas to 2.5 to 3 kPa 10 to 12 inches of water column, with pressure relief set at 4 kPa 16 inches of water column.
c. Provide regulator(s) having a single port with orifice diameter no greater than that recommended by the manufacturer for the maximum gas flow rate at the regulator inlet pressure. Provide regulator valve vent of resilient materials designed to withstand flow conditions when pressed against the valve port, capable of regulating downstream pressure within limits of accuracy and limiting the buildup of pressure under no-flow conditions to 50 percent or less of the discharge pressure maintained under flow conditions. Provide a self-contained service regulator, and pipe not exceeding exceed 2 inch size.
2.7 SEISMIC PROVISIONS
Provide earthquake automatic gas shutoff valve conforming to ASCE 25-16 , SMACNA 1981 or excess flow valve (EFV) conforming with ANSI Z21.93/CSA 6.30 and UL listed or AGA listed or International Association of Plumbing and Mechanical Officials (IAPMO) listed. The earthquake valve may be either pendulum or ball construction with remote electronic actuator. The EFV may be either a bypass (automatic reset) or a non-bypass type (manual reset).
SECTION 23 11 20 Page 8
2.8 AUTOMATIC GAS SHUT-OFF
Provide low pressure automatic gas shutoff or excess flow valve (EFV) downstream of the point of delivery after the meter/regulator conforming to ANSI Z21.93/CSA 6.30 and UL listed or CSA listed or International Association of Plumbing and Mechanical Officials (IAPMO) listed. The EFV may be either a bypass (automatic reset) or a non-bypass type (manual reset).
2.9 BOLTING (BOLTS AND NUTS)
Stainless steel bolting; ASTM A193/A193M , Grade B8M or B8MA, Type 316, for bolts; and ASTM A194/A194M , Grade 8M, Type 316, for nuts. Dimensions of bolts, studs, and nuts must conform with ASME B18.2.1 and ASME B18.2.2 with coarse threads conforming to ASME B1.1 , with Class 2A fit for bolts and studs and Class 2B fit for nuts. Bolts or bolt-studs must extend through the nuts and may have reduced shanks of a diameter not less than the diameter at root of threads. Bolts must have American Standard regular square or heavy hexagon heads; nuts must be American Standard heavy semifinished hexagonal.
2.10 GASKETS
Fluorinated elastomer, compatible with flange faces.
2.11 IDENTIFICATION FOR ABOVEGROUND PIPING
MIL-STD-101 for legends and type and size of characters. For pipes 3/4 inch od and larger, provide printed legends to identify contents of pipes and arrows to show direction of flow. Color code label backgrounds to signify levels of hazard. Make labels of plastic sheet with pressure-sensitive adhesive suitable for the intended application. For pipes smaller than 3/4 inch od, provide brass identification tags 1 1/2 inches in diameter with legends in depressed black-filled characters.
PART 3 EXECUTION
3.1 EXAMINATION
After becoming familiar with all details of the work, verify all dimensions in the field, and advise the Contracting Officer of any discrepancy or areas of conflict before performing the work.
3.2 GAS PIPING SYSTEM
Provide a gas piping system from the point of delivery, defined as the outlet of the meter set assembly , as specified under "Gas Service" within this specification, to the connections to each gas utilization device that is in compliance with NFPA 54 ..
3.2.1 Protection and Cleaning of Materials and Components
Protect equipment, pipe, and tube openings by closing with caps or plugs during installation. At the completion of all work, thoroughly clean the entire system.
3.2.2 Workmanship and Defects
Piping, tubing and fittings must be clear and free of cutting burrs and
SECTION 23 11 20 Page 9 defects in structure or threading and must be thoroughly brushed and chip-and scale-blown. Repair of defects in piping, tubing or fittings is not allowed; replace defective items when found.
3.3 PROTECTIVE COVERING
3.3.1 Aboveground Metallic Piping Systems
3.3.1.1 Ferrous Surfaces
Touch up shop primed surfaces with ferrous metal primer. Solvent clean surfaces that have not been shop primed . Mechanically clean surfaces that contain loose rust, loose mill scale and other foreign substances by power wire brushing and prime with ferrous metal primer or vinyl type wash coat. Finish primed surfaces with two coats of exterior oil paint or vinyl paint.
3.4 INSTALLATION
Install the gas system in conformance with the manufacturer's recommendations and applicable provisions of NFPA 54 and AGA XR0603, and as indicated. Perform all pipe cutting without damage to the pipe, with an approved type of mechanical cutter, unless otherwise authorized. Use wheel cutters where practicable. On steel pipe 6 inches and larger, an approved gas cutting and beveling machine may be used. Cut thermoplastic and fiberglass pipe in accordance with AGA XR0603.
3.4.1 Metallic Piping Installation
Bury underground piping a minimum of 18 inches below grade. Make changes in direction of piping with fittings only; mitering or notching pipe to form elbows and tees or other similar type construction is not permitted.
Branch connection may be made with either tees or forged branch outlet fittings. Provide branch outlet fittings which are forged, flared for improvement of flow where attached to the run, and reinforced against external strains. Do not use aluminum alloy pipe in exterior locations or underground.
3.4.2 Concealed Piping in Buildings
Do not use combinations of fittings ( unions, tubing fittings, running threads, right- and left-hand couplings, bushings, and swing joints) to conceal piping within buildings.
3.4.2.1 Piping and Tubing in Partitions
Locate concealed piping and tubing in hollow, rather than solid, partitions. Protect tubing passing through walls or partitions against physical damage both during and after construction, and provide appropriate safety markings and labels. Provide protection of concealed pipe and tubing in accordance with ANSI LC 1/CSA 6.26 .
3.4.3 Aboveground Piping
Run aboveground piping as straight as practicable along the alignment and elevation indicated, with a minimum of joints, and separately supported from other piping system and equipment. Install exposed horizontal piping no farther than 6 inches from nearest parallel wall and at an elevation which prevents standing, sitting, or placement of objects on the piping.
SECTION 23 11 20 Page 10
3.4.4 Final Gas Connections
Unless otherwise specified, make final connections with rigid metallic pipe and fittings. Provide accessible gas shutoff valve and coupling for each gas equipment item.
3.4.5 Seismic Requirements
Support and brace piping and attached valves to resist seismic loads in conformance with ASCE 25-16 . CSST tubing and fittings that are seismically qualified in accordance with the FM APP GUIDE: Flexible Piping Systems for Flammable Gases must meet the seismic requirements in accordance with the manufacturer's installation instructions.
3.5 PIPE JOINTS
Design and install pipe joints to effectively sustain the longitudinal pull-out forces caused by contraction of the piping or superimposed loads.
3.5.1 Threaded Metallic Joints
Provide threaded joints in metallic pipe with tapered threads evenly cut and made with UL approved graphite joint sealing compound for gas service or tetrafluoroethylene tape applied to the male threads only. Threaded joints up to 1-1/2 inches in diameter may be made with approved tetrafluoroethylene tape. Threaded joints up to 2 inches in diameter may be made with approved joint sealing compound. After cutting and before threading, ream pipe and remove all burrs. Caulking of threaded joints to stop or prevent leaks is not permitted.
3.5.2 Welded Metallic Joints
Conform beveling, alignment, heat treatment, and inspection of welds to NFPA 54 . Remove weld defects and make repairs to the weld, or remove the weld joints entirely and reweld. After filler metal has been removed from its original package, protect and store so that its characteristics or welding properties are not affected adversely. Do not use electrodes that have been wetted or have lost any of their coating.
3.5.3 Solder or Brazed Joints
Make all joints in metallic tubing and fittings with materials and procedures recommended by the tubing supplier. Braze joints with material having a melting point above 1000 degrees F , containing no phosphorous.
3.5.4 Press Connections
Make press connections in accordance with manufacturer's installation instructions using tools approved by the manufacturer. Fully insert the tubing into the fitting and then mark at the shoulder of the fitting.
Check the fitting alignment against the mark on the tubing to assure the tubing is fully inserted before the joint is pressed.
3.6 PIPE SLEEVES
Provide pipes passing through concrete or masonry walls or concrete floors or roofs with pipe sleeves fitted into place at the time of construction.
Do not install sleeves in structural members except where indicated or
SECTION 23 11 20 Page 11 approved. Make all rectangular and square openings as detailed. Extend each sleeve through its respective wall, floor or roof, and cut flush with each surface, except in mechanical room floors not located on grade where clamping flanges or riser pipe clamps are used. Extend sleeves in mechanical room floors above grade at least 4 inches above finish floor.
Unless otherwise indicated, use sleeves large enough to provide a minimum clearance of 1/4 inch all around the pipe. Provide steel pipe for sleeves in bearing walls, waterproofing membrane floors, and wet areas . Provide sleeves in nonbearing walls, floors, or ceilings of steel pipe, galvanized sheet metal with lock-type longitudinal seam, or moisture-resistant fiber or plastic. For penetrations of fire walls, fire partitions and floors which are not on grade, seal the annular space between the pipe and sleeve with fire-stopping material and sealant that meet the requirement of Section 07 84 00 FIRESTOPPINGG.
3.7 PIPES PENETRATING WATERPROOFING MEMBRANES
Install pipes penetrating waterproofing membranes as specified in Section
22 00 00 PLUMBING, GENERAL PURPOSE.
3.8 FIRE SEAL
Fire seal all penetrations of fire rated partitions, walls and floors in accordance with Section 07 84 00 FIRESTOPPING.
3.9 ESCUTCHEONS
Provide escutcheons for all finished surfaces where gas piping passes through floors, walls, or ceilings except in boiler, utility, or equipment rooms.
3.10 SPECIAL REQUIREMENTS
Provide drips, grading of the lines, freeze protection, and branch outlet locations as shown and conforming to the requirements of NFPA 54 .
3.11 BUILDING STRUCTURE
Do not weaken any building structure by the installation of any gas piping. Do not cut or notch beams, joists or columns. Attach piping supports to metal decking. Do not attach supports to the underside of concrete filled floors or concrete roof decks unless approved by the Contracting Officer.
3.12 PIPING SYSTEM SUPPORTS
Support gas piping systems in buildings with pipe hooks, metal pipe straps, bands or hangers suitable for the size of piping or tubing. Do not support any gas piping system by other piping. Conform spacing of supports in gas piping and tubing installations to the requirements of NFPA 54 . Conform the selection and application of supports in gas piping and tubing installations to the requirements of MSS SP-58 . In the support of multiple pipe runs on a common base member, use a clip or clamp where each pipe crosses the base support member. Spacing of the base support members is not to exceed the hanger and support spacing required for any of the individual pipes in the multiple pipe run. Rigidly connect the clips or clamps to the common base member. Provide a clearance of 1/8 inch between the pipe and clip or clamp for all piping which may be subjected to thermal expansion.
SECTION 23 11 20 Page 12
3.13 ELECTRICAL BONDING AND GROUNDING
Provide a gas piping system within the building that is electrically continuous and bonded to a grounding electrode as required by NFPA 54 , NFPA 58 , and NFPA 70 .
3.14 SHUTOFF VALVE
Install the main gas shutoff valve controlling the gas piping system to be easily accessible for operation, as indicated, protected from physical damage, and marked with a metal tag to clearly identify the piping system controlled. Install valves approximately at locations indicated. Orient stems vertically, with operators on top, or horizontally. Provide stop valve on service branch at connection to main and shut-off valve on riser outside of building.
3.15 LINE AND APPLIANCE PRESSURE REGULATORS
Install line pressure regulators and appliance regulators in accordance with the manufacturer's requirements and in accordance with NFPA 54 .
Install each regulator in an accessible location and install shutoff valves ahead of each line and appliance regulator to allow for maintenance. Where vent limiting devices are not included in the regulators, install a vent pipe to the exterior of the building.
Terminate all service regulator vents and relief vents in the outside air in rain and insect resistant fittings. Locate the open end of the vent where gas can escape freely into the atmosphere, away from any openings into the building and above areas subject to flooding.
3.16 GAS SERVICE INSTALLATION
Installations must be in accordance with 49 CFR 192 and ASME B31.8 .
Contractor must submit and use only tested and approved work procedures.
Contractor must use only welders and jointers who have been recently qualified by training and test for joining and installing the gas pipe material used on this job. The finished product must be inspected by a person qualified to inspect joints made by the particular procedures used to make joints.
3.17 TESTING
Submit test procedures and reports in booklet form tabulating test and measurements performed; dated after award of this contract, and stating the Contractor's name and address, the project name and location, and a list of the specific requirements which are being certified. Test entire gas piping system to ensure that it is gastight prior to putting into service. Prior to testing, purge the system, clean, and clear all foreign material. Test each joint with an approved gas detector, soap and water, or an equivalent nonflammable solution. Inspect and test each valve in conformance with API Std 598 and API Std 607 . Complete testing before any work is covered, enclosed, or concealed, and perform with due regard for the safety of employees and the public during the test. Install bulkheads, anchorage and bracing suitably designed to resist test pressures if necessary, and as directed and or approved by the Contracting Officer. Do not use oxygen as a testing medium.
SECTION 23 11 20 Page 13
3.17.1 Pressure Tests
Submit test procedures and reports in booklet form tabulating test and measurements performed; dated after award of this contract, and stating the Contractor's name and address, the project name and location, and a list of the specific requirements which are being certified. Before appliances are connected, test by filling the piping systems with air or an inert gas to withstand a minimum pressure of 3 pounds gauge for a period of not less than 10 minutes as specified in NFPA 54 without showing any drop in pressure. Do not use Oxygen for test. Measure pressure with a mercury manometer, slope gauge, or an equivalent device calibrated to be read in increments of not greater than 0.1 pound . Isolate the source of pressure before the pressure tests are made.
3.17.2 Test With Gas
Before turning on gas under pressure into any piping, close all openings from which gas can escape. Immediately after turning on the gas, check the piping system for leakage by using a laboratory-certified gas meter, an appliance orifice, a manometer, or equivalent device. Conform all testing to the requirements of NFPA 54 . If leakage is recorded, shut off the gas supply, repair the leak , and repeat the tests until all leaks have been stopped.
3.17.3 Purging
After testing is completed, and before connecting any appliances, fully purge all gas piping. Do not purge piping into the combustion chamber of an appliance. Do not purge the open end of piping systems into confined spaces or areas where there are ignition sources unless the safety precautions recommended in NFPA 54 are followed.
3.17.4 Labor, Materials and Equipment
Furnish all labor, materials and equipment necessary for conducting the testing and purging.
3.18 PIPE COLOR CODE MARKING
Provide color code marking of piping as specified in Section 09 90 00 PAINTS AND COATINGS, conforming to ASME A13.1 .
-- End of Section --
SECTION 23 11 20 Page 14
MIN. WATTS PER FOOT
HEAT TRACE CABLE SIZING CHART
PIPE SIZE
3/4" - 2-1/2" 3" - 4" 5" - 10"
POWER CONNECTION -
ELEC. CONTR. TO MAKE FINAL
CONNECTION TO HEAT TAPE
THERMOSTAT
PRESSURE GAGE
VALVE
PIPE
STRAP
(TYPICAL)
SPLICE
KIT
GLASS TAPE
(TYPICAL)
HEAT TRACE CABLE:
RAYCHEM # BTV1 (# INDICATES WATTS/FOOT
REQUIRED FROM SIZING CHART ABOVE) (120V) WITH POWER
CONNECTION KIT AND #AMC-F5 T-STAT SET AT 40°F. HVAC
CONTR.
TO PROVIDE AND INSTALL HEAT TRACE CABLE AND ALL
ACCESSORIES.
INSTALL PER MANUFACTURER'S INSTRUCTIONS.
PILOT LIGHT KIT/ END
SEAL KIT - RAYCHEM
E-100-L AT EACH END OF
HEAT TRACE
THERMAL
INSULATION
WITH ALUM. JACKET
NOTES
1. PROVIDE A TEE KIT WHEN CONNECTING THREE LENGTHS HEAT TRACE
CABLE TOGETHER.
2. INSTALL HEAT TRACE CABLE ON ALL DEVICES PER THIS DETAIL AND
NOTES. THIS INCLUDES BUT IS NOT LIMITED TO TEES, ELBOWS, AND
SUPPORTS EXPOSED ON EXTERIOR.
3. PROVIDE ELECTRICAL HEAT TRACE WARNING LABELS ON ALUMINUM
JACKET ON PIPE INSULATION.
S
NOTES:
INSTALL ALL FLOW CONTROL BALANCING
VALVES WITH A MINIMUM STRAIGHT,
UNOBSTRUCTED LENGTH OF PIPE OF 5
DIAMETERS UPSTREAM AND 3
DOWNSTREAM OF THE DEVICES (MORE IF
REQUIRED BY SPECIFIC MANUFATURERS).
SEE CONTROL SHEETS FOR LIST OF
EQUIPMENT WITH 2-WAY VALVES.
ISOLATION VALVE MUST BE SEPARATE FROM
THE MANUAL BALANCING VALVE. DEVICES
WITH COMBINED BALANCING AND SHUT-OFF
CAPABILITIES ARE PROHIBITED.
MV
FLOW
AIR
R
R
S
AUTOMATIC CONTROL VALVE
DRAIN VALVE
(TYPICAL)
P/T PLUG
(TYP)
BYPASS
WITH VALVE
STRAINER WITH THREADED HOSE BIB WITH
CHAIN AND CAP.
S
NOTES:
INSTALL ALL FLOW CONTROL BALANCING
VALVES WITH A MINIMUM STRAIGHT,
UNOBSTRUCTED LENGTH OF PIPE OF 5
DIAMETERS UPSTREAM AND 3
DOWNSTREAM OF THE DEVICES (MORE IF
REQUIRED BY SPECIFIC MANUFATURERS).
SEE CONTROL SHEETS FOR LIST OF
EQUIPMENT WITH 3-WAY VALVES.
ISOLATION VALVE MUST BE SEPARATE FROM
THE MANUAL BALANCING VALVE. DEVICES
WITH COMBINED BALANCING AND SHUT-OFF
CAPABILITIES ARE PROHIBITED.
MV
AIR
FLOW
3-WAY AUTOMATIC CONTROL VALVE
CNC
NO
S
R
P/T PLUG
(TYP)
DRAIN VALVE
(TYPICAL)
STRAINER WITH THREADED HOSE BIB
WITH CHAIN AND CAP.
BYPASS
WITH VALVE
BALANCING
VALVE
S
NOTES:
INSTALL ALL FLOW CONTROL BALANCING
VALVES WITH A MINIMUM STRAIGHT,
UNOBSTRUCTED LENGTH OF PIPE OF 5
DIAMETERS UPSTREAM AND 3
DOWNSTREAM OF THE DEVICES (MORE IF
REQUIRED BY SPECIFIC MANUFATURERS).
SEE CONTROL SHEETS FOR LIST OF
EQUIPMENT WITH 3-WAY VALVES.
ISOLATION VALVE MUST BE SEPARATE FROM
THE MANUAL BALANCING VALVE. DEVICES
WITH COMBINED BALANCING AND SHUT-OFF
CAPABILITIES ARE PROHIBITED.
MV
AIR
FLOW
3-WAY AUTOMATIC CONTROL VALVE
CNC
NO
S
R
P/T PLUG
(TYP)
DRAIN VALVE
(TYPICAL)
STRAINER WITH THREADED HOSE BIB
WITH CHAIN AND CAP.
BYPASS
WITH VALVE
BALANCING
VALVE
1/4" MANUAL AIR
VENT
CIRCUIT
SETTER
HWR
HANGER RODS
BALL
VALVE
(TYPICAL)
HWS
UNION (TYPICAL)
BALL VALVE
(TYP)
HWR
HWS
GAS CONNECTION
FLEXIBLE PIPE
CONNECTION (TYP)
FULL SIZE BY-PASS
WITH SHUT OFF VALVE
FLUE OUTLET, CPVC
MATERIAL, HEAT-FAB
SAF-T VENT EZ SEAL
COMBUSTION AIR INLET,
PIPE WITH FLUE TO
CONCENTRIC WALL VENT
THERMOMETER (TYP)
DRAIN ASSY. WITH 1/2"
BARB CONNECTION TO
NEAREST FLOOR DRAIN
2-GALLON NEUTRALIZATION TANK, TO
REDUCE THE PH OF BOILER
CONDENSATE, FLOOR MOUNT AND PIPE
AS SHOWN. SERVES B-1,2.
NOTES:
INSTALL ALL FLOW CONTROL BALANCING
VALVES WITH A MINIMUM STRAIGHT,
UNOBSTRUCTED LENGTH OF PIPE OF 5
DIAMETERS UPSTREAM AND 3 DOWNSTREAM
OF THE DEVICES (MORE IF REQUIRED BY
SPECIFIC MANUFACTURERS).
BALANCING VALVE
PRESSURE
RELIEF
VALVE
FLOW
SWITCH
P/T
PROVIDE LOW WATER
CUT-OFF WITH BOILER
STRAINER /
FILTER
INLINE
CIRCULATION
PUMP
CHECK
VALVE
ASME BLADDER
TANK
COALESCING AIR/DIRT SEPARATOR WITH REMOVABLE HEAD.
INSTALL UNIT LEAVING ADEQUATE CLEARANCE TO REMOVE
HEAD
HIGH CAPACITY AUTO AIR VENT
AUTO AIR VENT
MANUAL BLOWDOWN VALVE WITH
HOSE CONNECTION
PRESSURE GAUGE
(0-100 PSI) WITH
NEEDLE VALVE
TO SYSTEM
DRAIN VALVE WITH
HOSE CONNECTION
UNDERSLUNG CONNECTION CREATES
THERMAL TRAP (12" MIN. DROP)
ASME RELIEF VALVE, SET AT 50 PSI CHILLED
AND 30 PSI HOT. PIPE TO FLOOR DRAIN
3/4" PRV. SET INITIAL
PRESSURE TO 12-1/2 PSI.
BALL VALVE
PRESSURE GAUGE
(0-100 PSI) WITH NEEDLE VALVE
UNION
HOUSEKEEPING PAD
3/4" MAKE-UP SUPPLY LINE,
RPZ BFP AND SHUT-OFF VALVE
BY PLUMBING CONTRACTOR
FROM SYSTEM
SYSTEM CONNECTION (CONNECT TO SIDE OR
BOTTOM OF MAIN HEADER)
P
P BUTTERFLY SHUT-OFF
VALVE (TYP.)
ROUTE NEW CHWS/R
BELOW GRADE TO
BUILDING
FLEX PIPE CONNECTION
2" DRAIN W/VALVE
PETE'S PLUG
CIRCUIT SETTER
BYPASS WITH VALVE
CHILLER
CHWR
CHWS
FS
CONCRETE PAD. VERIFY WITH PLAN
SHEETS. PAD DIMENSIONS TO
ALLOW 12" CONCRETE BEYOND
CHILLER FOOTPRINT ON ALL SIDES
PIPE STUB-OUTS WITH
BUTTERFLY VALVES AND
BLIND FLANGE FOR
EMERGENCY CHILLED
WATER CONNECTION
BT-1
MECHANICAL
BUILDING
SEE ENLARGED
PLAN ON SHEET
M-401 FOR
CONTINUATION
UNDERGROUND
PIPING
UNDERGROUND
PIPINGCHWR
NOTE:
WRAP ALL PIPING, VALVES, FITTINGS,
AND CONNECTIONS SUBJECT TO
FREEZING WITH ELECTRIC HEAT
TRACE AND INSULATE SAME.
EVAPORATOR HEAT TRACE AND
INSULATION SHALL BE FACTORY
INSTALLED.
CHECK VALVE
UNION (TYPICAL)
MULTIPORT
PRESSURE
INDICATOR
(4-PORT)
SUCTION DIFFUSER
WITH STRAINER
P/T (TYP.)
REDUCER (TYPICAL)
MANUALLY
BALANCED
CIRCUIT SETTER
NOTES:
INSTALL ALL FLOW CONTROL BALANCING VALVES WITH A MINIMUM STRAIGHT, UNOBSTRUCTED LENGTH OF PIPE OF 5 DIAMETERS UPSTREAM AND 3 DOWNSTREAM OF THE DEVICES (MORE IF REQUIRED BY SPECIFIC MANUFACTURERS).
DRAIN: TERMINATE AT
FLOOR DRAIN
4" HIGH CONCRETE HOUSE
KEEPING PAD
1" NEOPRENE VIBRATION PADSEISMIC
ANCHORS
FINISHED FLOOR
PIPE SUPPORT
FLEX
CONNECTION
(TYP.)
S
BALANCING COCK
P/T (TYP.)
CHECK VALVE
(TYP)
UNION (TYP)
STRAINER WITH
BLOWDOWN
VALVE
RECIRCULATION PUMP
MV
FLOW
AIR
R
R
S
NOTES:
INSTALL CIRCUIT SETTER WITH INLET AND
OUTLET STRAIGHT PIPE IN ACCORDANCE
WITH MANUFACTURER'S REQUIREMENTS.
SEE CONTROL VALVE SCHEDULE FOR LIST
OF EQUIPMENT WITH 2-WAY VALVES.
AUTOMATIC CONTROL VALVE
DRAIN
VALVE
(TYPICAL)
BYPASS
WITH
VALVE
SYM. DESCRIPTION DATE APP.
REVISIONS
DR.
DES.
CHK.
SUBMITTED BY:
DESIGN DIR.
APPROVED: PWO OR OICC
SATISFACTORY TO:
DATE
DATE
DEPARTMENT OF THE NAVY NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND
CAMP LEJEUNE, NORTH CAROLINA
MARINE CORPS BASE
SIZE CODE IDENT. NO. NAVFAC DRAWING NO.
E1 80091
CONSTR. CONTR. NO.
AS NOTEDSCALE SHEET
M B
F A
N O
SPEC.
M-504
PJR
LWM
CHRIS MAAS
PJR
REPAIR BEQ HP135
MECHANICAL DETAILS
60042950 N40085-25-B-0011
05-25-0011 153 OF 206
X X
X X
NTS
D1
HEAT TRACING DETAIL
NTS
B1
HW & CHW COIL 2-WAY VALVE PIPING DETAIL
NTS
A1
HW & CHW COIL 3-WAY VALVE PIPING DETAIL
NTS
D3
HOT WATER UNIT HEATER DETAIL
NTS
A3
HOT WATER BOILER DETAIL
NTS
C5
HW & CHW AIR CONTROL PIPING DETAIL
NTS
A5
AIR COOLED CHILLER INSTALLATION DETAIL
NTS
B3
INLINE PUMP INSTALLATION DETAIL
NTS
C1
PREHEAT HW 2-WAY VALVE PIPING DETAIL
1 PPI REVISION 07.07.26
REPAIR BEQ HP135
N40085-25-B-0011
AMENDMENT 02
07 July 2026
SPECIFICATIONS:
PROJECT TABLE OF CONTENTS
REPLACE:
- Replace the project specification PROJECT TABLE OF CONTENTS with the revised table of contents footnoted “AMDT 02 (07 July 2026)”.
DESCRIPTION OF CHANGE:
- Includes specification section 23 11 20 added in response to PPI item 5
SECTION SUBMITTAL REGISTER
ADD:
- Add the specification SECTION SUBMITTAL REGISTER including submittal requirements for added specification section 23 11 20.
- Adds submittal requirements for specification section 23 11 20 added in response to PPI item 5
Section 23 11 20 FACILITY GAS PIPING
ADD:
- Add Specification Section 23 11 20 – Facility Gas Piping footnoted “AMDT 02 (07 July 2026)” to the project specifications.
- Specification added in response to PPI item 5
DRAWINGS:
NAVFAC No. 60042950, M-503 – MECHANICAL DETAILS
REPLACE:
- Replace existing sheet with sheet including Amendment 02 dated 07 July 2026.
o Update/revise Room Finish Schedule in response to PPI item 6
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 08/25 SUMMARY OF WORK
01 14 00 04/22 WORK RESTRICTIONS (MCBL)
01 20 00 11/20, CHG 3: 02/23 PRICE AND PAYMENT PROCEDURES
01 30 00 08/25 ADMINISTRATIVE REQUIREMENTS
01 31 23.13 20 05/17, CHG 7: 11/21 ELECTRONIC CONSTRUCTION AND FACILITY
SUPPORT CONTRACT MANAGEMENT SYSTEM
01 31 50 04/22 TRANSFER AND ACCEPTANCE OF MILITARY
REAL PROPERTY
01 32 16.00 20 08/18, CHG 1: 08/20 SMALL PROJECT CONSTRUCTION PROGRESS
SCHEDULES
01 33 00 04/22 SUBMITTAL PROCEDURES
01 33 29 02/21 SUSTAINABILITY REQUIREMENTS AND
REPORTING
01 35 26 11/20, CHG 3: 02/22 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 08/23 QUALITY CONTROL
01 50 00 12/21 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19 09/25 TEMPORARY ENVIRONMENTAL CONTROLS
01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 00 04/22 CLOSEOUT SUBMITTALS
01 78 23 04/22 OPERATION AND MAINTENANCE DATA
01 78 24.00 20 03/23 FACILITY ELECTRONIC OPERATION AND
MAINTENANCE SUPPORT INFORMATION (eOMSI)
01 78 30.00 22 5/22 GIS DATA DELIVERABLES
DIVISION 02 - EXISTING CONDITIONS
02 41 00 08/22 DEMOLITION
02 41 01 08/22 BUILDING DECONSTRUCTION
02 82 00 08/25 ASBESTOS REMEDIATION
02 83 00 08/25 LEAD REMEDIATION
DIVISION 03 - CONCRETE
03 30 00 02/19, CHG 10: 08/25 CAST-IN-PLACE CONCRETE
03 30 53 05/14 MISCELLANEOUS CAST-IN-PLACE CONCRETE
(SIDEWALKS)
03 45 33 05/16, CHG 1: 11/21 PRECAST STRUCTURAL CONCRETE
DIVISION 04 - MASONRY
04 20 01 11/15, CHG 2: 05/19 MASONRY INFILL AND PATCHING
DIVISION 05 - METALS
05 30 00 05/15, CHG 2: 08/18 STEEL DECKS
05 40 00 05/15, CHG 1: 08/18 COLD-FORMED METAL FRAMING
05 50 13 08/24, CHG 1: 08/25 MISCELLANEOUS METAL FABRICATIONS
05 51 33 02/16, CHG 2: 02/18 METAL LADDERS
05 52 01 02/18, CHG 1: 02/20 ALUMINUM RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
PROJECT TABLE OF CONTENTS Page 1
06 10 00 08/16, CHG 3: 05/25 ROUGH CARPENTRY
06 41 16.00 10 08/10, CHG 1: 11/18 PLASTIC-LAMINATE-CLAD ARCHITECTURAL
CABINETS
06 61 16 08/20 SOLID SURFACING FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 19 00 05/11, CHG 1: 08/17 WATER REPELLENTS
07 21 13 08/23, CHG 1: 08/25 BOARD AND BLOCK INSULATION
07 21 16 08/23, CHG 1: 08/25 MINERAL FIBER BLANKET INSULATION
07 22 00 08/23 ROOF AND DECK INSULATION
07 27 19.01 08/23, CHG 1: 08/24 SELF-ADHERING AIR BARRIERS
07 27 26 08/23 FLUID-APPLIED MEMBRANE AIR BARRIERS
07 27 36 08/23 SPRAY FOAM AIR BARRIERS
07 60 00 08/23, CHG 1: 05/25 FLASHING AND SHEET METAL
07 61 15.00 20 08 March 2021 CL ALUMINUM STANDING SEAM ROOFING
07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING
07 92 00 08/23 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 08/20 STEEL DOORS AND FRAMES
08 14 00 08/16, CHG 1: 08/18 WOOD DOORS
08 31 00 05/17, CHG 1: 08/18 ACCESS DOORS AND PANELS
08 33 25 08/20, CHG 1: 02/22 STAINLESS STEEL OVERHEAD COILING DOORS
08 51 13 05/19 ALUMINUM WINDOWS
08 71 00 02/16, CHG 4: 02/22 DOOR HARDWARE
08 81 00 05/19 GLAZING
08 91 00 06/24 MCBCL CL ALUMINUM WALL LOUVERS
DIVISION 09 - FINISHES
09 03 00 03/22 LOW PRESSURE BUILDING CLEANING
09 22 00 02/10, CHG 2: 08/18 SUPPORTS FOR GYPSUM BOARD
09 29 00 08/16, CHG 4: 02/20 GYPSUM BOARD
09 30 10 08/20 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 08/20 ACOUSTICAL CEILINGS
09 65 00 11/24 RESILIENT FLOORING
09 67 23.13 11/19 STANDARD RESINOUS FLOORING
09 72 00 08/17, CHG 1: 08/18 WALLCOVERINGS
09 90 00 02/21 PAINTS AND COATINGS
09 97 11 05/24 PEDESTRIAN TRAFFIC EPOXY COATINGS
DIVISION 10 - SPECIALTIES
10 14 00.10 08/17, CHG 1: 11/18 EXTERIOR SIGNAGE
10 14 00.20 08/20 INTERIOR SIGNAGE
10 26 00 08/20 WALL AND DOOR PROTECTION
10 28 13 08/20 TOILET ACCESSORIES
10 44 16 11/19 FIRE EXTINGUISHERS
10 50 00 02/16 MISCELLANEOUS SPECIALTIES
DIVISION 11 - EQUIPMENT
11 24 24 08/20 PERMANENT HORIZONTAL FALL PROTECTION,
METAL ROOFING
DIVISION 12 - FURNISHINGS
PROJECT TABLE OF CONTENTS Page 2
12 24 13 08/20 ROLLER WINDOW SHADES
DIVISION 21 - FIRE SUPPRESSION
21 13 13 08/20 WET PIPE SPRINKLER SYSTEMS, FIRE
PROTECTION
DIVISION 22 - PLUMBING
22 00 00 05/24, CHG 1: 11/24 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 03 00.00 20 08/24 MCBCL BASIC MECHANICAL…