This document is Amendment 0002 to Solicitation N40085-26-R-9044 for repair work on Bachelor Enlisted Quarters (BEQ) Building HP135 at Camp Lejeune, North Carolina. The amendment was issued on June 29, 2026, by NAVFAC Mid-Atlantic and does not extend the proposal receipt deadline.
The amendment addresses two key questions regarding asbestos-containing material (ACM) abatement scope and clarifies the government's intent to manage asbestos in place rather than undertake complete removal. Specifically, contractors are directed to focus asbestos removal only on areas disturbed by proposed renovations, with the abatement contractor responsible for removing windows, doors, louvers, and performing necessary demolition to disturb ACM. Exposed ACM must be abated or encapsulated per specification 02 82 00 to allow general trades to perform replacement work. Contractors should limit damp-proofing removal to areas where perimeter walls are demolished for new man doors, louvers, and HVAC units rather than removing all brick veneer. The amendment also requires replacing Section 01 31 50 (Transfer and Acceptance of Military Real Property) dated 04/22 with the version dated 09/25. Contractors must acknowledge receipt of this amendment with their proposal submission, and failure to do so may result in proposal rejection.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICIATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 11)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPIRATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
AMENDMENT NO. 0002 06/29/26 25-0011
N40085
NAVFAC Mid-Atlantic Resident Officer in Charge of Construction 1107A Birch Street Camp Lejeune, NC 28547-2521
See Item 6
✘ N40085-26-R-9044
06/18/26
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
25-0011, Repair BEQ HP135 Amendment 0002, Answer Requests for information
The time and date for receipt of proposals remains unchanged.
This amendment should be acknowledged when your proposal is submitted. Failure to acknowledge the amendment may constitute grounds for rejection of a proposal.
See Continuation Page(s) Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
N40085-26-R-9044 Amendment 0002 Page 2 of
CONTINUATION SHEET
1. QUESTION: Spec 02 82 00 Page 7 Section 1.3.1 Description of Work states “The asbestos work includes the demolition, removal, or encapsulation of approximately 8,000 square feet of vinyl floor tiles and mastic located throughout the living quarters, approximately 16,000 square feet of built up roofing, approximately 3,000 square feet of flashing material located on parapet walls, and approximately 21,000 square feet of damp-proofing mastic behind exterior brick veneer”. To access the asbestos damp proofing we would need to remove all of the brick veneer from the building. We would also need to remove the elevated walkways to access the brick behind them. Can you clarify if this is the appropriate scope to remove and replace all brick veneer? In addition we can not guarantee we can remove all the damp proofing or protect the existing block from being damaged.
ANSWER: No, only areas of disturbance by the proposed renovations. Recommend abatement contractor perform removal of windows, doors, louvers and any demolition necessary that would disturb the ACM. Exposed ACM abated/encapsulated in accordance with 02 82 00 so that general trades may perform the replacement.
2. QUESTION: Spec 02 82 00 Page 7 Section 1.3.1 Description of Work. Instead of removing all brick veneer to access the damp proofing. Should we only focus on removing damp proofing from the areas where the perimeter walls are to be demolished/removed for new man door, louvers, and/or HVAC units?
ANSWER: Yes, it is assumed that the intent of the government is to manage asbestos in place.
3. Omit SECTION 01 31 50 TRANSFER AND ACCEPTANCE OF MILITARY REAL PROPERTY 04/22 in its entirety and replace with SECTION 01 31 50 TRANSFER AND
ACCEPTANCE OF MILITARY REAL PROPERTY 09/25.
4. All other terms and conditions remain unchanged.