This is a pricing sheet for a federal construction solicitation for Phase V Multiple BEQ Room Entry Door Lock Repairs at MCB Camp Lejeune, North Carolina (Solicitation No. N40085-26-R-9021, Project No. 26-0421).
The solicitation contains 31 Exhibit Line Item Numbers (ELINs) representing distinct work areas identified by building codes and location designations (such as HP265, HP485, HP508, WC300, HP235, WC105, WC110, WC115, WC120, WC130, WC135, HP509, M446, M447, MM48, RR122, RR123, WC145, WC165, HP195, 1140, HP175, HP475, HP513, BB270, FC515, HP145, and HP295). Offerors must submit prices for all 31 line items covering door lock repairs and associated work per provided drawings and specifications. Each ELIN price must include all applicable costs, overhead, labor burden, and profit. Failure to propose on all line items will result in rejection as non-responsive. The Government will evaluate offers for award purposes by summing prices for ELINs 0001 through 0031. Per FAR 52.217-5, evaluation of these options does not obligate the Government to exercise them. The pricing sheet requires offerors to calculate and report a total price for all ELINs combined.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Phase V Multiple BEQ Room Entry Door Lock Repairs Solicitation No. N40085-26-R-9021 MCB Camp Lejeune, North Carolina Project No. 26-0421
PRICING SHEET
Under the line items furnished, the offers shall state prices for each Exhibit Line Item Number (ELIN) given hereinafter:
ELIN 0001
Price includes completing all work associated with HP265 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0002-0031. The price for this line item should include all applicable costs, overhead and profit for this work.
ELIN 0002
Price includes completing all work associated with HP485 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001, 0003-0031. The price for this line item should include all applicable costs, overhead and profit for this work.
ELIN 0003
Price includes completing all work associated with HP508 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0002, and 0004-0031.
The price for this line item should include all applicable costs, overhead and profit for this work.
ELIN 0004
Price includes completing all work associated with WC300 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0003 and 0005-0031.
ELIN 0005
Price includes completing all work associated with HP235 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0004, and 0006-0031.
ELIN 0006
Price includes completing all work associated with HP245 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0005, and 0007-0031.
ELIN 0007
Price includes completing all work associated with WC105 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0006, and 0008- 0031The price for this line item should include all applicable costs, overhead and profit for this work.
ELIN 0008
Price includes completing all work associated with WC110 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0007, and 0009-0031.
ELIN 0009
Price includes completing all work associated with WC115 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0008, and 0010-0031.
ELIN 0010
Price includes completing all work associated with WC120 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0009, and 0011-0031.
ELIN 0011
Price includes completing all work associated with WC130 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0010, and 0012-0031.
ELIN 0012
Price includes completing all work associated with WC135 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0011, and 0013-0031.
ELIN 0013
Price includes completing all work associated with HP509 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0012, and 0014-0031.
ELIN 0014
Price includes completing all work associated with WC110 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0013, and 0015-0031.
ELIN 0015
Price includes completing all work associated with M446 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0014, and 0016-0031.
ELIN 0016
Price includes completing all work associated with M447 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0015, and 0017-0031.
ELIN 0017
Price includes completing all work associated with MM48 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0016, and 0018-0031.
ELIN 0018
Price includes completing all work associated with RR122 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0017, and 0019-0031.
ELIN 0019
Price includes completing all work associated with RR123 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0018, and 0020-0031.
ELIN 0020
Price includes completing all work associated with WC145 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0019, and 0021-0031.
ELIN 0021
Price includes completing all work associated with WC165 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0020, and 0022-0031.
ELIN 0022
Price includes completing all work associated with HP195 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0021, and 0023-0031.
ELIN 0023
Price includes completing all work associated with 1140 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0022, and 0024-0031.
ELIN 0024
Price includes completing all work associated with HP175 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0023, and 0025-0031.
ELIN 0025
Price includes completing all work associated with HP475 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0024, and 0026-0031.
ELIN 0026
Price includes completing all work associated with HP513 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0025, and 0027-0031.
ELIN 0027
Price includes completing all work associated with BB270 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0026, and 0028-0031.
ELIN 0028
Price includes completing all work associated with FC515 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0027, and 0029-0031.
ELIN 0029
Price includes completing all work associated with HP145 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0028, and 0030-0031.
ELIN 0030
Price includes completing all work associated with HP295 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0029, and 0031. The price for this line item should include all applicable costs, overhead and profit for this work.
ELIN 0031
Price includes completing all work associated with HP503 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0030. The price for this line item should include all applicable costs, overhead and profit for this work.
TOTAL ELIN 0001 - 0031: $______________________________________
Notes A. Offers must be submitted on all line items. Failure to propose on all line items may result in the offer being rejected as non-responsive.
B. ELINs shall include all markups (overhead, labor burden, and profit).
C. Evaluation of Options (NOV 2025). Except when it is determined in accordance with FAR 17.206(b) Evaluation not to be in the Government's best interest, the Government will evaluate offers for award purposes by adding the price for ELINs 0001 through 0031. In accordance with FAR 52.217-5 Evaluation of Options, evaluation of options will not obligate the Government to exercise the Option(s).