WC115-1.png
PNG image 271 KB Posted
- Attached to
- FY26 Wallace Creek BEQ Chiller Repairs
- Solicitation number
- N4008526R9013
About this file
This is a technical equipment schedule document containing specifications for HVAC systems and related mechanical equipment. The document consists of five detailed schedules: Air Handling Unit Schedule, Energy Recovery Unit Schedule, Boiler Schedule, Split System Air Conditioning Unit Schedule, and Air-Cooled Chiller Schedule.
The Air Handling Unit schedule specifies a unit (AHU-B-1) with a nominal CFM of 25,000, featuring a double-width/double-inlet configuration with airfoil wheels and external static pressure exclusions for casing and filters. The Energy Recovery Unit (ERU-B-1) is designated for summer design operation at 5,460 CFM with MERV 7 filters and variable frequency drive capability. The Boiler Schedule includes two units (B-B-1 and B-B-2) with Type C-H configuration, 500 and 250 MBH output respectively, with hot water supply at 180°F and return at 120°F. The Split System Air Conditioning Unit Schedule lists five units (SAC-1 through SAC-5) with varying cooling capacities ranging from 12.6 to 28.1 kW, featuring scroll compressors, TELECOM indoor units, and maximum amperage requirements of 13 to 25 amps. The Air-Cooled Chiller (CH-B-1) is rated at 85-ton capacity with 100 kW power input and includes specifications for low ambient operation down to 30°F. All schedules include notes regarding capacity calculations, external static pressure inclusions/exclusions, electrical characteristics, and operational parameters. The document is revised as of September 3, 2009.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .