Document Summary
This is a Standard Form 30 Amendment of Solicitation/Modification of Contract for NAVFAC project N4008526R0148, Design-Bid-Build P-475 Aircraft Maintenance Hangar at MCAS Beaufort, South Carolina. The amendment, effective February 4, 2026, incorporates Pre-Proposal Inquiry (PPI) responses, revised drawings volumes 1, 2A, 2B, 3, 4, and 6, revised specifications, and an updated price proposal form with changes denoted in red. The proposal due date of February 19, 2026 at 2:00 PM EST remains unchanged. The amendment updates Section 00 70 00 (Conditions of the Contract) and modifies DFARS clause 252.204-7021 regarding Contractor Compliance with Cybersecurity Maturity Model Certification (CMMC) Level Requirements effective November 2025, requiring contractors to maintain CMMC Level 2 (Self) certification for all information systems processing, storing, or transmitting Federal Contract Information (FCI) or Controlled Unclassified Information (CUI). The clause defines assessment types, validity periods, reporting requirements through the Supplier Performance Risk System (SPRS), and subcontract flow-down obligations, with specific emphasis on current certification status and continuous compliance affirmations.
The document also includes PPI responses addressing 165 contractor questions regarding technical specifications, design clarifications, contract requirements, scheduling, small business participation, cybersecurity compliance, quality control qualifications, RF shielding design, fire protection systems, structural details, and coating specifications. Key government responses confirm CMMC Level 2 (Self) is required prior to award, the proposal due date was extended via Amendment 0004, a 5-year general contractor bonded watertightness warranty is required, and specifications are performance-based where not prescriptive. Multiple responses remain pending on topics including RF shielding effectiveness requirements, door hardware specifications, mechanical inspector certifications, fireproofing locations, and construction security plan personnel requirements. Additionally, prior amendments (0001-0003) replaced numerous drawings across all volumes and updated specifications dated January 16, 2026, while providing clarifications on quality control personnel requirements and FOD prevention manager duties.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
R
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBE
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
Created On:
04 Feb 2026, 16:36 PM Greenwich Mean Time
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Block 14 (Description of Amendment/Modification):
N40085-26-R-0148 DESIGN-BID-BUILD, P-475 AIRCRAFT MAINTENANCE HANGAR, MCAS BEAUFORT, SOUTH CAROLINA
The proposal due date of 19 February 2026 NLT 2:00 PM EST remains unchanged.
The Amendment is issued to incorporate the following:
1) Provide Responses to PPIs
2) Provide Revised Drawings Volume 1, 2A, 2B, 3, 4, and 6.
3) Provide Revised Specifications
4) Provide Revised Price Proposal Form (changes denoted in red)
5) Update Section 00 70 00 - Conditions of the Contract
Section 00 70 00 - Conditions of the Contract
Additional Information/Notes
The following clauses were added:
FAR Clauses Incorporated by Reference
Number Title Effective Date Alternate/ Deviation
Variation Effective Date
52.211-13 Time Extensions. Sep 2000
The following clauses were modified:
252.204-7021Contractor Compliance with the Cybersecurity Maturity Model Certification Level Requirements.
Nov 2025 hereby reads as follows:
CONTRACTOR COMPLIANCE WITH THE CYBERSECURITY MATURITY MODEL CERTIFICATION LEVEL REQUIREMENTS (NOV 2025)
(a) . As used in this clause-Definitions
"Controlled unclassified information" means information the Government creates or possesses, or information an entity creates or possesses for or on behalf of the Government, that a law, regulation, or Governmentwide policy requires or permits an agency to handle using safeguarding or dissemination controls (32 CFR 2002.4(h)).
"Current" means-
(1) With regard to Conditional Cybersecurity Maturity Model Certification (CMMC) Status-
(i) Not older than 180 days for Conditional Level 2 (Self) assessments and Conditional Level 2 (certified third-party assessment organization (C3PAO)) assessments, with-
(A) No changes in compliance with the requirements at 32 CFR part 170 since the Conditional CMMC Status date (see 32 CFR
170.16 and 170.17); and
(B) A corresponding affirmation of continuous compliance by an affirming official (see 32 CFR 170.4); and
(ii) Not older than 180 days for Conditional Level 3 (Defense Industrial Base Cybersecurity Assessment Center (DIBCAC)) assessments, with-
(A) No changes in compliance with the requirements at 32 CFR part 170 since the Conditional CMMC Status date (see 32 CFR 170.18); and
(B) A corresponding affirmation of continuous compliance by an affirming official;
N4008526R01480005
(2) With regard to Final CMMC Status-
(i) Not older than 1 year for Final Level 1 (Self), with-
(A) No changes in compliance with the requirements at 32 CFR part 170 since the Final CMMC Status date (see 32 CFR 170.15);
and
(B) A corresponding affirmation of continuous compliance, not older than 1 year, by an affirming official;
(ii) Not older than 3 years for Final Level 2 (Self) assessments and Final Level 2 (C3PAO) assessments, with-
(A) No changes in compliance with the requirements at 32 CFR part 170 since the Final CMMC Status date (see 32 CFR 170.16 and 170.17); and
(B) A corresponding affirmation of continuous compliance, not older than 1 year, by an affirming official; and
(iii) Not older than 3 years for Final Level 3 (DIBCAC) assessments, with-
(A) No changes in compliance with the requirements at 32 CFR part 170 since the Final CMMC Status date (see 32 CFR 170.18);
and
(B) A corresponding affirmation of continuous compliance, not older than 1 year, by an affirming official; and
(3) With regard to affirmation of continuous compliance (32 CFR 170.22), not older than 1 year with no changes in compliance with the requirements at 32 CFR part 170.
"Cybersecurity Maturity Model Certification (CMMC) status" means the result of meeting or exceeding the minimum required score for the corresponding assessment. The potential statuses are as follows:
(1) Final Level 1 (Self).
(2) Conditional Level 2 (Self).
(3) Final Level 2 (Self).
(4) Conditional Level 2 (C3PAO).
(5) Final Level 2 (C3PAO).
(6) Conditional Level 3 (DIBCAC).
(7) Final Level 3 (DIBCAC).
"Cybersecurity Maturity Model Certification unique identifier (CMMC UID)" means 10 alpha-numeric characters assigned to each CMMC assessment and reflected in the Supplier Performance Risk System (SPRS) for each contractor information system.
"Federal contract information (FCI)" means information, not intended for public release, that is provided by or generated for the Government under a contract to develop or deliver a product or service to the Government. It does not include information provided by the Government to the public, such as on public websites, or simple transactional information, such as information necessary to process payments.
"Plan of action and milestones" means a document that identifies tasks to be accomplished. It details resources required to accomplish the elements of the plan, any milestones in meeting the tasks, and scheduled completion dates for the milestones, as defined in National Institute of Standards and Technology Special Publication 800-115 (32 CFR 170.21).
(b) . The Cybersecurity Maturity Model Certification (CMMC) is a framework for assessing a contractor's compliance withFramework applicable information security protections (see 32 CFR part 170).
(c) . The CMMC assessments will not duplicate efforts from any other comparable DoD assessment, except for rare circumstancesDuplication when a reassessment may be necessary, for example, when there are indications of issues with cybersecurity and/or compliance with CMMC requirements.
(d) . The Contractor shall-Requirements
(1) (i) Have and maintain for the duration of the contract a current CMMC status at the following CMMC level, or higher: CMMC Level 2 for all information systems used in performance of the contract, task order, or delivery order that process, store, or transmit FCI or CUI; and(Self)
(ii) Consult 32 CFR 170.23 related to the flowdown of the CMMC requirements, and flow down the correct CMMC level to subcontracts and other contractual instruments;
(2) Only process, store, or transmit FCI or CUI on contractor information systems that have a CMMC status at the CMMC level required in paragraph (d)(1) of this clause, or higher;
(3) Complete on an annual basis, and maintain as current, an affirmation, by the affirming official (see 32 CFR 170.4), of continuous compliance with the requirements associated with the CMMC level required in paragraph (d)(1) of this clause in the Supplier Performance Risk System (SPRS) ( ) for each CMMC UID applicable to each of the contractor information systems that process, store, or transmit FCI https://piee.eb.mil or CUI and that are used in performance of the contract;
(4) Ensure all subcontractors and suppliers complete prior to subcontract award, and maintain on an annual basis, an affirmation, by the affirming official (see 32 CFR 170.4), of continuous compliance with the requirements associated with the CMMC level required for the subcontract or other contractual instrument for each of the subcontractor information systems that process, store, or transmit FCI or CUI and that are used in performance of the subcontract; and
(5) If the Contractor has a CMMC Status of Conditional, successfully close out a valid plan of action and milestones (32 CFR 170.21) to achieve a CMMC Status of Final.
(e) . The Contractor shall-Reporting
(1) Submit to the Contracting Officer-
(i) The CMMC UID(s) issued by SPRS for contractor information systems that will process, store, or transmit FCI or CUI during performance of the contract; and
(ii) Any changes in the CMMC UIDs generated in SPRS throughout the life of the contract, task order, or delivery order, if applicable;
(2) Enter into SPRS the results of a current self-assessment for each CMMC UID, not covered by a C3PAO assessment or DIBCAC assessment, applicable to each of the contractor information systems that process, store, or transmit FCI or CUI and that are used in performance of the contract; and
(3) Complete in SPRS on an annual basis and maintain as current an affirmation of continuous compliance by the affirming official (see 32 CFR 170.4) for each self-assessment, C3PAO assessment, or DIBCAC assessment required under the contract in SPRS.
(f) . The Contractor shall-Subcontracts
(1) Insert the substance of this clause, including this paragraph (f) and excluding paragraph (e)(1), in subcontracts and other contractual instruments, including those for the acquisition of commercial products or commercial services, excluding commercially available off-the-shelf items, if the subcontract or other contractual instrument will contain a requirement to process, store, or transmit FCI or CUI; and
(2) Prior to awarding a subcontract or other contractual instrument, ensure that the subcontractor has a current CMMC certificate or current CMMC status at the CMMC level that is appropriate for the information that is being flowed down to the subcontractor based on the requirements at
32 CFR 170.23.
(End of clause)
The following clauses were deleted:
FAR Clauses Incorporated by Reference
Number Title Effective Date Alternate/ Deviation
Variation Effective Date
52.230-2 Cost Accounting Standards. Jun 2020 52.230-6 Administration of Cost Accounting Standards. Jun 2010
PRE-PROPOSAL INQUIRY RESPONSES:
Question
Reference Question Government Response
Page Section Paragrap h
Per the project Solicitation, the minimum small business participation requirement, through work performed by the small business prime and/or subcontracting with small business, shall meet or exceed 20% of the total contract value. With the inclusion of both a Project Labor Agreement (PLA), and Cybersecurity Maturity Model Certification (CMMC) requirements, many non-union, small business firms are reluctant to sign and/or comply. We request the minimum small business participation requirement to be reduced due to these competing requirements.
The solicitation remains unchanged.
Propose per RFP.
4 1442
The U.S. Small Business Administration (SBA) amended its regulations so prime contractors will receive credit towards it subcontracting plan goals for awards made to small business companies at any tier under the contract. Please confirm that for this contract, prime contractors will receive credit towards subcontracting plan goals for lower tier subcontractors in accordance with this rule.
No, per FAR 52.219-9, prime contractors will not receive credit towards subcontracting plan goals for lower tier subcontractors.
16 C3/PSF501 N/A N/A
C3/PSF501 – Precast Double-Tee depth is not specified but scales as 2’-0”. Typical double-tee depth is 2’-4”. Is this acceptable as related to desired clear height?
Yes, but the Contractor will be responsible for making adjustments to maintain required ceiling heights and clear heights.
17 N/A N/A N/A
Precast Double-Tees are shown 10’-0’ wide with stems at 5’ on-center. Our typical double-tee is 12’-0” wide with stems at 6’-0” on-center. Is our standard double-tee acceptable?
Yes, but the Contractor will be responsible for making adjustments to make them fit the required spaces.
18 N/A N/A N/A
The location of the project and whether it falls into a Coastal Chloride Zone of Zone 1 can be interpreted differently as to its distance from a major saltwater body.
Please advise whether the project will be under Exposure Zone I, or CC-1, or CC-II.
The project Durability Zone is CC-1.
The design and detailing of the parking garage must follow the detail and durability guidelines of MNL-129 -15 (Precast Prestressed Concrete Parking Structures: Recommended Practice for Design and Construction) for CC-1, ACI-318 and PCI MNL-120 in addition to contract specification and drawing requirements. All steel flange edge connectors, exposed plates, embed plates and connector plates must be stainless steel. Site-topped concrete must have control joints. Control joint layout must be submitted as part of the parking garage design submittal and the joint layout must follow industry guidelines.
19 N/A N/A N/A
On coastal projects, we typically include corrosion inhibitor in our concrete mixes for horizontally spanning, non-architectural, floor members such as double tees, IT beams, slabs, and stair units. I don’t see it in the spec. Should it be included on this project?
PENDING RESPONSE
20 C1/PAE522 N/A N/A
C1/PAE522 – Is the spandrel ledge continuous supporting the double-tees or are they be individual haunches as used on the Litewalls shown in
C3/PAE522.
The double-tee support at the spandrel can be continuous or individual haunches. Typically, continuous support at the spandrel provides more tolerance. Design of support must be included in the delegated design submittal.
21 PPP111A N/A N/A
PPP111A shows trench drain in the middle bay at second level. We recommend drains are located near the end of double as typical and topping built up to push water to the drains at each end. Please confirm if this is acceptable.
Propose per RFP.
22 03 45 00 N/A N/A
Spec 03 45 00 - Steel Embeds are called out with several finishes. Please advise if embeds will require either shop-primed or hot-dip-galvanized?
Hot-dipped Galvanized.
23 03 45 00 2.7.1 N/A
Spec 0345 00 -2.7.1: Indicates Extruded Polystyrene Insulation. AE315 Insulation Schedule indicates rigid insulation of R-6 per inch. Extruded Insulation has only R-5 per inch. Is R-20 acceptable or should another higher R-value insulation be used to achieve R-24?
"This condition occurs on details on sheet AE311 and A1/AE312 and is associated with the insulated metal wall panel system.” Refer to Specification 07 42 13 for the Insulated Metal Panel.
24 03 45 00 2.7.2 N/A
Spec 03 45 00 – 2.7.2: Indicates stainless steel pin connectors. Typically, uncoated truss wire is used. If coating is required, is galvanized acceptable? Stainless steel is not an option in wythe connectors.
PENDING RESPONSE
25 03 45 00 2.2.5.3 N/A
Spec 03 45 00 – 2.2.5.3: Indicates Type 1 or II cement. Spec 03 45 33 – 2.2.2.6:
Indicates Type 1L. Our structural cement is Type III and occasionally 1L. Is this acceptable? (For architectural mixes utilizing white cement, we do use Types I or II.)
Type III or Type 1L is acceptable.
26 N/A N/A N/A The specification book is label Volume 1 of 2. We do not have Volume 2 of 2. Is there a Volume 2 of specifications?
Page 11 of the Amendment 0002 provides the instructions for obtaining Volume 2.
27 N/A N/A N/A Due to the size, scope, and complexities -we request a 2 week bid extension to properly respond to the solicitation.
Proposal due date extended via Amendment 0004.
28 Solicitation
In review of the solicitation, section 00 70 00 - Conditions of the Contract (pg. 23) contains FAR 52.230-2 and 52.230-6 clauses which typically appear on cost-type (e.g. CM at risk, GMP, cost plus, etc.)
and T&M contracts. As this contract is a Firm-Fixed-Price Contract, please confirm FAR 52.230-2 (Cost Accounting Standards) and FAR 52.230-6 (Administration of Cost Accounting Standards) does not apply and will be removed from this solicitation.
Confirmed. Amendment 0005 removes 52.230-2 and 52.230-6.
29 09 97 13.27- 1.5.6.8
Spec 09 97 13.27-1.5.6.8 indicates that only ISO 9001 OR SSPC QP 1 and QS1 are the only permitted certifications for the shop applied high performance coatings.
Please confirm that AISC Sophisticated Paint Endorsement is not permitted ILO of one of these certifications.
AISC Sophisticated Paint Endorsement is not permitted in lieu of one of the required certifications.
30 09 97 13.27- 1.5.6.8
Spec 09 97 13.27-1.5.6.8 indicates that SSPC QP 1 is the required certification for the shop applied high performance coatings. QP 1 is the certification for the field application of coatings. Please confirm that BOTH QP 3 for the main shop application of the coatings and QP 1 for the field touchup of the coatings are required.
QP 3 itself is not referenced in Spec 09 97 13.27. If this is part of referenced standards, then proceed with both QP 3 and QP 1 accordingly
OSF102;
OSF102A;
OSF102B;
OSF503
Detail A2/OSF503 calls for mechanical unit support details. The structural roof plans do not make any reference to this detail. Looking at the mechanical drawings, all the equipment seems to be in the building, and none on the roof. Please confirm this detail is not required or clarify location(s).
PENDING RESPONSE
AE101 thru
AE101F;
AE102D
thru
AE102F
09 97 13.27; 05 12 00; 05 30 00
The locations for the use of the shop applied 3-coat system as outlined in specification 09 97 13.27 is not clear.
Please confirm the following a) The intent of this spec is to be applied to all structural steel in the hangar bay space (room 100 -see AE101A thru AE101C), including the pocket areas for the hangar doors and high bay spaces. b) The Admin space (see areas AE101D thru AE101F and AE102D thru AE102F) are to follow the requirements as outlined in 05 12 00 - 2.6.2. c) Misc metal items in the Hangar Bay, including grating, ladders, bollards, etc. are NOT receiving this coating and should follow the appropriate division 5 specification for the coatings. d) The deck in the Hangar Bay is NOT required to receive the 3-coat shop applied paint system, and will be galvanized as outlined in 05 30 00-2.1.1.
a) The Amendment 0005 specification 09 97 13.27 section 3.2 indicates that ferrous metal primary and secondary (structural) steel framing inside the aircraft maintenance bays and hangar doors are to be coated under this section. The pocket areas and high bay hangar spaces are included. b) Refer to the amended finish schedule on sheet AF601 for areas where surfaces would receive finishes under section 09 96
00. c) Miscellaneous metal items in the hangar bay fabricated from steel and carbon slack steel including those galvanized in accordance with division 5 specifications are to be finished in accordance with 09 96 00 section 1.2.2
d) The metal deck in the hangar bay will receive a finish system per section 09 96 00 1.2.2e as amended previously.
33 05 12 00
"Specification 05 12 00 - 2.6.2 indicates to ""Apply primer in accordance with endorsement SPE-01 of AISC 420 or approved equal...."". The list of certifications in section 05 12 00 - 1.3 only lists AISC category BU for the fabricator and AISC category CSE for the erector.
Please clarify if a P1 endorsement is or is not a requirement."
Yes. P1 endorsement is a requirement.
34 05 52 00
Section 05 52 00 - 2.4 calls for aluminum railing systems with a PVDF finish. The aluminum railings were previously located in the garage, but they appear to now be steel railings (see PAE563). Please confirm there are no aluminum railings on the project any longer and clarify finish requirements for the steel railings in the garage.
PENDING RESPONSE
PSF121;
PSF401;
PSF411
Steel posts are required for the roof framing at the tall end of the stair shaft roofs (see PSF121 and PSF401). The only detail for the tall end of the roof, C1/PSF411, does not indicate any embed plate size or connection requirements.
Please provide required embed plate size and detail. Note there is a detail B2/PSF501 that may be the detail, its just not cut from anywhere. Please confirm.
The carried column indicated on the plan north end of 'Typical Stair Roof Framing Plan' on PSF401 and PSF401Y is a Galvanized HSS4x4x1/4. B2/PSF501 is the 'Typical Carried Column Detail' and would apply for the support of the HSS4x4. The embed plate in detail B2/PSF501 must be galvanized. On sheet PSF401 and PSF401Y and the associated 'Typical Stair Roof framing Plan', revise the size of the HSS8x4 on the plan east and plan west sides of the plan to HSS8x8x1/2. All the joists and HSS members indicated on the 'Typical Stair Roof Framing Plans' must be hot-dipped galvanized.
PSF121Y;
PSF401Y;
PSF411Y
The embed sizes for the light pole posts are not indicated (see PSF121Y, PSF401Y, PSF411Y). Please provide required base plate size.
Embed plate must be GALVANIZED 3/4" X 10" X 12" with four 3/4" diameter headed studs placed 1 1/2" from the edge of the plate in each direction. The headed studs must have 3" embedment. The post must be welded all around with 1/4" fillet weld.
The post must be hot-dipped galvanized.
37 PAE582
typ 26 31 00
The PV option for the garage appears to utilize an aluminum framed system (see PAE582). Is this governed by 26 31 00 - 2.5? If this is not correct, please provide required specification for this work.
Confirmed.
PSF111Y;
PSF121Y;
PSF411Y
The light pole support steel that is along the ramp on the top level in the base bid of the garage (PSF111Y; PSF121Y) has a detail A3/PSF411Y. They have break lines in the vertical post making the TOS height unknown. Previously it was stated that the HSS height was 13'-5". Is that still the case, or is it different?
Refer to A1/PAE582Y for post elevation.
OSF101A;
OAE221;
OAE224;
OAE311
The HSS framing penetrates the precast wall panels on OSF101A. The framing will have to go up first since there is no way to access the steel after the walls are
up. Looking at OAE221 and OAE224, these wall panels are solid panels, they would need to be split at the beam penetration at the wall in order accommodate this condition. Please provide updated panel layout and in addition, at detail needs to be provided showing other elements at this interface.
Please clarify.
Revise the end of the two HSS girts to be connected to the face of the precast panel. Design the embed plate for a vertical load of 5 kips and a combined horizontal ultimate load of 5 kips.
Weld the HSS all around to the embed plate with 1/4" diameter fillet weld.
An alternate bolted connection may be designed and submitted for review.
40 AE582;
MH102D
There is a detail for equipment tie downs for exhaust fans on B2, B3/AE582.
Looking at the mechanical drawings (MH102D) it appears there are two exhaust fans on the lower roof. Please confirm that both are required to receive tie down anchors, and please confirm there are no other locations per the mechanical set of drawings. Previously it was confirmed that the two (2) locations (8 tie downs) are all that were required. Please confirm.
Confirmed, these are the only two fans that would require the tie downs.
41 23 09 00.00 22-1.1.1
Please provide updated contact information for automated logic as the current contact information does not appear to be valid.
The point of contact is for the Base MCAS Beaufort Public Works Utilities Division for coordination not for Automated Logic. Contact public works for POC.
42 AE431;
SB111E
Drawing AE431 has a keynote 6 which indicates to provide steel posts for the elevator guide rail. Structural drawing SB111E does not indicate any support framing. Please confirm the support framing is required, and provide the required member size, and show details of how it connects to the slab and back to the walls.
The steel post must be HSS 3 ½ x 3 ½ x 5/16” for the full height of the shaft.
The post must bear on ¾”x10x10 bearing plate with four 5/8” diameter adhesive anchors and 4” embedment.
The post must be braced at the second floor elevation and the roof elevation to the CMU wall with two L2 ½ x 2 ½ x ¼ diagonal braces. Each brace must be anchored to the CMU wall with four 5/8” diameter adhesive anchors and 4” embedment. 12” of grout must be placed around all anchors. Final design and details must be coordinated with elevator design.
43 AE626
Details B4,C4/AE626 indicate to have a metal channel frame (054000.A02) at the jambs/headers to the masonry wall OH doors. The channel is not sized. Please provide the required channel size.
PENDING RESPONSE
44 AE101E;
AE802
Partition type Q on AE802 indicates steel tube supports for the partial height walls.
They appear to be located in 134 Maintenance Control on AE101E. The walls appear to be 6' high based on the floor plan. Please confirm this is correct, and clarify post size, spacing and baseplate information.
Keynote 7 states that tube steel column to be located 4' o.c. Coordinate rectangular baseplate to fit within scheduled stud size. Confirmed top of wall is 6' AFF.
45 QJ501
The details for the countertop framing on QJ501 appear to show steel supports, but the framing sizes are missing from the detail. Please clarify framing sizes, and if there are vertical posts or if the framing ties to the stud framing.
"Steel supports and concealed vertical posts are required. Where counter end wall support is not available, extend tubes to structure above.
Coordinate location of counter supports with bowl locations.
3""x 2""x 3/16"" Horizontal Steel Tube.
3""x 2""x 3/16"" Horizontal Steel Tube Post Welded to Vertical Steel Tube.
2"" x 2"" x 3/16"" Vertical Steel Tube Post.
Vertical Post Welded to 4"" x 5"" x 3/8"" steel base plate. Base plate includes four 1/2 dia. exposed anchors with 2 ¼” min embedment."
46 AE585;
SF411
Detail A1 on AE585 references a steel plate bent per 051200.E03 at the light gauge parapet. Detail A1 on SF411 seems to conflict with this detail. In previous responses, it was indicated that in addition to the structural, the balance of the architectural detail is cold form. Please confirm.
PENDING RESPONSE
47 AE591 09 90 00; 09 97
13.27
Per Note 14 on Sheet AE591, "draft curtain and support to be primed to accept field applied paint system in accordance with specification section 09 90 00." There are multiple areas throughout the hangar bay with exposed light gauge framing along with the draft curtains (hangar door pockets, z-girts, clips, studs, etc.). Please confirm that all exposed light gauge framing in the hangar bays are to be primed and painted per specification 09 90
00. Note that a previous response indicated that it was to receive coatings per 09 97
13.27. Please clarify which is correct and
that all sides of the draft curtains should be coated.
Spec 09 97 13.27 applies to primary and secondary structural members in the hangar and the hangar doors. All other ferrous metal components in the hangar would be finished in accordance with specification 09 96 00.
SF201;
SF203;
SF204;
SF206;
SF208
SF208: column HJ & HK-H1 & H23 has base plate called out F6 but SF201, SF203, SF204 & SF206 has F1. Please verify which is to be used. Note the previous response was to utilize F1. Please confirm this is still correct.
The base plate is F1 and is called out as F1 on sheet SF208.
49 SF207;
SF209
SF209: column HE-H19 has base plate called out F7 but SF207 has F3. Please verify F7 is to be used. Note the previous response was to utilize F3. Please confirm this is still correct.
The base plate is F3 and is called out as F3 on sheet SF209.
50 Solicitation Solicitation
Our firm is privately held and our financial statements are highly confidential and proprietary corporate information. Is it acceptable to submit a letter signed by our CFO regarding our financial capabilities in lieu of financial statements?
No, your CFO’s signature will not be enough to comply with FAR 9.104- 3(a)
51 Solicitation
Our firm is privately held, and our financial information is confidential, corporate information. Is it acceptable for Offerors to submit financial statements, separately from the Price Proposal, via password-protected PDF files sent directly to the Contracting Officer?
Yes. For those planning on submitting financial statements separate from the Price Proposal, contact contract specialist Amber Stovall via email to receive a “Request for Drop Off” through DOD Safe. ONLY financial statements will be accepted if submitted separately from the Price Proposal.
52 13 49 20.00 10
Specification 1.6.2.4 refers to a HEMP standard/ SELDs required in test kit and a permanent SELDs test system (2.11). Please confirm whether two (2) complete sets of this equipment are required. If so, please provide specifications on the kit required.
Review the bid documents and solicitation. We suspect you may be referencing a different solicitation. Use 13 49 20.00 10 that was included with the solicitation.
53 13 49 20.00 10
Section 2.4.4/ 28-gauge flashing fully soldered at every seam. Rest of spec shows metallic tape. Please confirm that the designer intends to flash at every corner to joint foil to foil and foil to floor.
See Response to PPI #52
54 13 49 20.00 10
Section 2.4.5/ ‘bolts sealed with puddle weld’ to foil. Please confirm that the designer does not intend to weld to RF Foil. This will destroy the foil and compromise shielding effectiveness.
See response to PPI#52.
55 13 49 20.00 10
Specification 2.5.5.2 to 2.5.5.5 Door testing refers to HEMP rated assemblies. Please confirm that these tests are not required as they cannot be performed on the doors specified in the Door Schedule and Details
(AE602, AE611/B1/3, AE834).
See response to PPI#52.
56 13 49 20.00 10
Sections 2.6.1 to 2.6.5.11/ RF Filter Enclosure and testing. Please confirm all references to tests and Specifications regarding HEMP and IAW MIL-STD-188-125-1 are not required.
See response to PPI#52.
57 13 49 20.00 10 Section 2.7/ Electrical Surge arrestors refer to HEMP standards. Please confirm that this entire section is not required.
See response to PPI#52.
58 13 49 20.00 10
Section 2.8 references waveguides below cutoff assemblies. Please confirm that these are to be replaced with standard waveguides, as HEMP level waveguide assemblies do not appear to be required.
See response to PPI#52.
59 13 49 20.00 10
Section 2.11/ References built in SELDS testing ports, which are typical of HEMP requirements. Please confirm that these ports are not required.
See response to PPI#52.
60 13 49 20.00 10
Section 3.8/ References HEMP Hardness Critical items schedule and testing. Please confirm that these requirements are not applicable to this project.
See response to PPI#52.
61 13 49 20.00 10
Section 2.3.3.8/ Indicates welded frame connections to RF foil. Please confirm this is not required, as frames cannot be welded directly to RF foil without damaging the shielding material.
See response to PPI#52.
62 13 49 20.00 10
Section 2.5.1.5/ Interlocking devices. As designed, there are no vestibules.
Please confirm that interlocking devices are not required.
Doors 2AC01.1 and 2AC01.2 are to interlock along 2AC01 Vestibule.
63 13 49 20.00 10 Section 2.5.1.7/ Threshold alarm. This is not a normal SCIF requirement.
Please confirm that this is not required.
See response to PPI#52.
64 13 49 20.00 10
Section 2.5.1.8/Hold open and stop device. This is not a normal SCIF requirement. Please confirm that this is not required.
See response to PPI#52.
65 13 49 20.00 10
Section 2.5.2/ Latching type doors. The door schedule is not consistent with this specification. The door header details on sheet AE834 contradicts this description. Please confirm this should be a steel-panel STC rated door with RF gasketing with a drop-sill to ensure an acoustic barrier.
See response to PPI#52.
66 13 49 20.00 10
Section 3.3.3/ Placement of Floor shield. This section references placement of floor shielding in a manner that conflicts with Section 3.3.2. Please confirm that Section 3.3.3, which requires lap joints and mechanical fasteners through floor shielding, is not required.
See response to PPI#52.
67 13 49 20.00 10
Section 3.8.5.1/ This section references HEMP MIL-STD-188-125. The structure designed will not meet HEMP testing requirements. Please confirm that IEEE 299 testing criteria are the governing acceptance standard for this project.
See response to PPI#52.
68 13 49 20.00 10
Section 134920/2.4.2 calls out (2) layers 5mil RFoil - Drawings: Note 17/AE801 call out 2mil & 5mil. Please confirm RFoil assembly.
Use a panel with (1) 2 mil layer and
(1) 5 mil layer as shown on drawings.
69 13 49 20.00 10
RF Design/ TLT rooms 2A04 & 2A06 and BREAK 2A08 are shown within the secured RF shield line. Sanitary piping systems cannot be effectively filtered or attenuated to the required shielding performance. These elements create unavoidable leakage paths that compromise the integrity of the RF envelope. Please confirm that these rooms shall be relocated outside of the secured shield boundary or account for leakage at these areas during final testing.
See response to PPI#52.
70 13 49 20.00 10
RF Design/ Based on the architectural shielding design shown in the drawings and specifications, a target attenuation of 60 DB does not appear achievable. The current design is more likely to achieve attenuation in the 40 DB range. Please confirm the required target attenuation performance.
RF Shielding Effectiveness to meet minimum effective of 60 dB
71 13 49 20.00 10 Please confirm whether the RF installer can also conduct final attenuation testing.
Per Section 3.8, testing shall be performed by an independent testing firm.
72 13 49 20.00 10
RF Design/ Door Openings 2AC01.1 & 2AC05 as specified do not carry any RF rating. All entry doors penetrating the shield line must be RF rated and tested to meet attenuation requirements. Please confirm these openings required RF-rated assemblies and provide updated DFH specifications.
Confirmed, 2AC01.1 and 2AC05 are to be RF shielded doors to maintain RF Enclosure. Refer to sheet AE602.
73 13 49 20.00 10
For RF shielding testing, paragraph 3.8.1 indicates there will be three parts: 1) In- Progress 2) Initial effectiveness 3) final acceptance. Whereas paragraph 3.8.3 only list 2 parts. Please clarify.
See response to PPI#52.
74 08 34 16, 09 96 00, 09 97 13.27
In previous RFIs to this solicitation, it was clarified that section 09 97 13.27 applies to the hangar door framing (instead of 09 96 00 as called out in the specifications).
Please clarify which painting section applies to the hangar door framing.
Spec 09 97 13.27 applies to the hangar doors as well as hangar door primary and secondary framing.
75 05 50 13 2.10.3 Fall
Protection
In previous RFIs to this solicitation, it was clarified that the Rigid Rail Fall Protection system should be comprised of three single-beam systems, each with the capacity to accommodate 2 users per track for each bay. Please confirm.
"Refer to sheet AE304 and Keynote 4.
The design capacity of the fall protection should meet the requirements of ANSI/ASSE Z359.6, Specifications and Design Requirements for Active Fall Protection Systems. The fall arrest load is 5,000lbs and defined on S-001."
76 3 2374260 1.5.2
Spec 078400 1.5.2, which lists qualifications of firestopping inspector, references "the criteria contained in ASTM E699 for agencies involved in quality assurance". ASTM E699 appears to have been withdrawn. Is the FPQC/QFPE permitted to serve as the firestopping inspector if they meet all conditions of
1.5.2 except for ASTM E699 criteria?
Confirmed, there is no replacement for withdrawn ASTM E699. Inspector must meet other requirements of 1.5.2 and adhere to standards of ASTM E2174 and E2393
77 12 211316 2.5
Spec 211316 2.5 requires supervisory nitrogen system to pressurize dry pipe sprinkler system within 20 minutes. 2.5.1 requires capability of "achieving system pressure within 30 minutes". Please confirm if 30 minutes or 30 minutes is correct.
30 minutes is correct.
78 14 211316 2.7
Spec 211313 2.5 says fire sprinkler systems connected to potable water distribution system require reduced-pressure backflow preventers, while sprinkler systems connected to non-potable water distribution system require double-check backflow preventers. Spec 211316 2.7 requires a double-check backflow preventer for the parking garage sprinkler system, which appears to be supplied by the potable system. Please confirm required type of backflow preventer for each fire suppression system throughout the project.
Provide reduced-pressure backflow preventer.
79 4 211325.002 1.3.1.8
Spec 211325.0020 1.3.1.8 requires controls to divert low-level hangar fire suppression system discharge (water only) to underground containment tank(s). This spec appears to correspond to the bid option which does not include foam fire suppression in the hangar. Please confirm that diverter valve and containment system are required for water-only low-level fire extinguishing system.
Diverter valve and containment system are required for water-only fire suppression system.
80 18 283170 2.10.1 Spec 283170 2.10.1 requires "120 VAC 50 Hz" power to fire alarm system. Please confirm utility frequency.
Provide 60 Hz power.
81 25 283176 2.13.1
Hangar fire alarm drawings (Volume 2B) show "ceiling mounted speaker clusters" throughout the hangar bay. Spec 283176
2.13.1 appears to include generic requirements for fire alarm/mass notification speakers. Please clarify performance criteria and basis of design for "ceiling mounted speaker clusters".
PENDING RESPONSE
Fire alarm/mass notification system matrix on drawing FA502 refers to "fire pump supervisory signals". The Project doesn't appear to include new fire pumps; please clarify requirement for fire alarm supervision of fire pumps.
Fire pump supervision is not required.
Hangar, OSF, and parking garage drawings (multiple disciplines) require "exterior exposure corrosion protection and control in accordance with an environmental severity classification (ESC) of C4 for building systems and components" in several areas. Please clarify required corrosion protection and control methods.
Corrosion protection and control methods are outlined throughout the specifications for the applicable building systems and components.
Please differentiate the four dry pipe sprinkler systems shown on parking garage drawing PFX501 (Volume 4). It's unclear which part of the building is served by each system.
Each system serves half of a level of the parking garage (less than 52,000 sq.ft. per system in accordance with NFPA 13 requirements). Final configuration of the system piping is the responsibility of the contractor.
Please clarify routing of vertical distribution for fire protection system piping in hangar (Volume 2B) and parking garage (Volume 4). It's unclear where sprinkler system risers will penetrate each floor.
Second floor fire protection piping in the hangar penetrates the floor in Mech
243. Second level fire protection piping in the parking garage penetrates the floor of the parking space plan east of column line 5.
Parking garage fire protection drawing PFX121 appears to show interior hose connections along column line B. Please confirm whether interior hose connections are required.
Interior hose connections are not required.
87 09 09 00 3.3.3
Section 3.3.3 09 90 00 Indicated the cleaning and prep requirements for galvanized metal that shows damage.
Please confirm that if galvanized coating is in tact it does not require a top coat of paint and can remain exposed.
Galvanized steel requires top coats under 09 90 00, 09 96 00, and 09 97
13.27 respectively.
88 13 49 20.00 10
Please clarify the extent of filters and waveguides required for the RF shielding.
For example, electrical power drawing EP102E only appears to show power filters at the three interior secondary containment spaces, but not at the perimeter of the primary containment space.
See response to PPI#52.
89 AE611 13 49 20.00 10
6 & A1/AE611 – RF Window – Please confirm that the basis of design for the RF/STC window is Krieger. This window is tested at 68 dB to 95dB with IEEE-299 standards. If this is not the basis of design, please specify correct product. If it is the BOD, please note that it fails short of the RF shielding requirement.
This is a performance based specification. Refer to Section 13 49
20.00 10 as provided in the solicitation.
90 Amendment 2
Per Amendment 2, RFI #2, it appears the proposal due date will remain unchanged.
This will not allow adequate time to finalize negotiations with the local union for a PLA, and engage compliant/willing subcontractors to participate in the procurement. Additionally, with the inclusion of CMMC Far Clauses, it is abundantly clear that most of the subcontracting community is not currently registered/self-assessed or compliant with CMMC which will not support the requirements of the solicitation, as per the FAR, is required prior to an award. If the proposal due date is not extended, it is unlikely the project will have adequate compliant interest from the subcontracting market.
See Response to PPI #27.
91 2127 13 1.4
May framing for tensioned fabric structures be excluded from additional protective packaging since standard industry practice is to ship them in bundles and the steel framing does not require additional protection?
PENDING RESPONSE
92 2128 13 2.1 a.
The overall exterior width and interior minimum clear dimension both state 60'.
The adjacent flightline has existing 60' wide structures which clear 56' inside. Will 64' wide structures clearing 60' width inside be sufficient while still meeting airfield clearance requirements?
PENDING RESPONSE
93 2128 13 2.1 a.
Can the structures reach 30.5' exterior height? This allows the frame to clear 28'6" at the peak.
Provide interior clear dimensions per 2.1a. Frame dimensions to be confirmed with the engineered shop drawings.
94 2128 13 2.1 a.
Fabric is described as a "laminated " fabic cover, which is inconsistent with a coated 28oz./sq. yd. material described in 2.3.1.
Please confirm "coated" material is correct since lamination is a different process used on lighter weight materials.
PENDING RESPONSE
95 2129 13 2.4
The stated design requirements for the lightning protection system do not match the actual air terminal placement for a code compliant lightning protection system. Is the lightning protection system to be installed to match the previously protected shelters? Additionally, aluminum materials must be used due to corrosion of dissimilar metals (copper cannot be used on galvanized steel).
The lightning protection system must be designed and installed to comply with NFPA 780 and to receive a UL Master labeled once installed.
Aluminum is acceptable as a substitute for copper to avoid corrosion due to dissimilar metals.
96 Site Walk
During the site walk, it was indicated that the 2nd tier security fence would be relocated by the GC for the duration of the project. Will the temporary fence be set between the active ramp/airfield and the locations for the new sun shades while allowing sufficient laydown space for the sun shade work?
Refer to Volume 1 Sheets C-007 through C-010.
97 Site Walk Are there at present any surveys and design information available concerning the existing concrete for the apron?
Refer to Existing Pavement Notes on Volume 1 Sheet CD100.
98 22 00 70 00 N/A
The Conditions of the Contract did not include FAR 52.211-13 Time Extensions. Please confirm this clause is applicable to this contract.
Confirmed. Amendment 0005 adds
FAR 52.211-13.
99 Attachment G - Price Form
CLIN 2B is Foundation Piling for the Parking Garage. CLIN 3 is for the Operational Support Facility/Hangar Annex, however, SubCLIN 3B is Foundation Piling for the Parking Garage.
Please confirm SubCLIN 3B should be Foundation Piling for the Operational Support Facility/Hangar Annex.
Confirmed, 3B is foundation pilings for the OSF part of Option 2 CLIN 3.
An updated Price Proposal Form was provided via Amendment 0002.
100 Attachment G - Price Form
CLIN 10 - Option 9 is for the Framed Fabric Structures Planned Modification.
Options 7, 8& 9 Bid Notes on the Price Form, specifically "b" notes Requirements to follow requirements of 01 30 01.00 22 - Design Procurement and Installations of FF&E. There is already a specification, 13 31 33.00 22, for the delegated design of this. Please confirm if the Offeror's Interior Designer is required to perform all the requirements of 01 30 01.00 22 including a design and Best Value Determination or since there is already a specification only a Best Value Determination for the Framed Fabric Structures.
Offers are to follow the Best Value Determination “Process”, outlined in 01 30 01.00 22, and provide a comparison from 3 manufacturers. It is the responsibility of the Offer’s team to perform the requirements outlined in 01 30 01.00 22; be that by the Interior Designer or other person, would be the offer’s decision. The 13 31 33.00 22 specification provides guidance to inform the Best Value Determination.
Attachment F - Small Business Subcontracting
Plan
The last page of Attachment F - Individual Small Business Subcontracting Plan is for Base Period and Option Year Subcontracting Goals. There are no option periods for this solicitation. Please confirm that we do not need to include/fill out the last page of this Attachment.
PENDING RESPONSE
23 81 23.00 20 & 23 81
There are two Computer Room Air Conditioning Units specifications given, 23 81 00 & 23 81 23.00 20. Please verify only 23 81 00 is valid
Both specifications are required. 23 80 00 is for DX split systems 23 81 23.00 20 is for the computer room units.
103 21 13 13 2.3.1.1
21 13 13-2.3.1.1 Steel Pipe for Wet Pipe Sprinkler Systems, Fire Protection notes that steel pipe must be black. It is also noted in 21 13 20.00 20 -3.16.1 that pipe is not to be painted red but painted same color as the walls and/or ceiling, except piping in mechanical and fire protection rooms which can be left as unpainted.
Please verify all fire protection pipes shall either be painted to match ceilings or walls or it is to be left unpainted as noted.
Paint sprinkler pipe as noted in specification section 09 90 00. Paint foam system pipe as noted in section 21 13 20.00 20. Paint low level water only piping (option) as noted in section 21 13 25.00 20. Please note the reference to black steel pipe is a material reference, not a color reference.
104 S-001 Volume 2A
S-001 (Volume 2A): Seismic Design Data notes the Seismic Design Category is D for this project. Please verify D is the correct Design Category.
Seismic Design Category of D is correct.
105 25 01 11
A div 25 cybersecurity specification for Building HVAC systems is not given.
Please verify Cybersecurity requirements for building HVAC and Control Systems.
There are no applicable cybersecurity requirements for the HVAC control system for this effort.
106 MS101,
CU104
Gas line is shown on CU104 and MS101.
Please verify that the contractor is not to include costs to design/install of the site gas line shown as this line is owned by Dominion Energy per Keynote 3. This gas line doesn't appear to connect to existing line outside the LOD. If the Contractor is to include cost for this line, please provide an allowance from Dominion Energy and
CLIN.
The contractor is not responsible for providing costs for the design or installation of the site gas line.
Dominion Energy provides the supply piping through the meter regulator assembly.
CU103,
FX011A to C
How does the FSS pipe from the hangar low level fire protection trenches exit the hangar bay and tie into the 30" FSS line in front of the hangar bay? See CU103 and FX011A to C. No tie in is noted.
Refer to Volume 1 Sheets CU103, CU104, and CU302. Refer to Volume 6 Sheets CU302X and CU511X.
108 13 49 20
Section 13 49 20.00 10 is calling for the shielded spaces to meet the effectiveness of the dB ranges and KHz frequencies listed in Section 2.3. Section 2.3 notes “when tested” per IEEE 299 and "other methods of shielded enclosure testing", and Section 1.3.1.1 notes the testing specialist must have 5 years of experience in IEEE 299 testing. Sections 3.8.1 through 3.8.5.3 does not specifically mention the IEEE 299 testing, but it is assumed to be required per 1.3.1.1 and 2.3.
The General Contractor and the Shielding Specialist…