This is a Federal Request for Proposals (RFP) for a design-bid-build construction project at Naval Weapons Station Earle in Colts Neck, New Jersey. The project involves repairing sixteen (16) degraded corrugated metal pipe (CMP) culverts supporting the Normandy Road Ammunition Rail crossing over the Swimming River. Specific work includes installing cofferdams, dewatering, removing vegetation and sediment, repairing and relining culverts, compaction grouting of the embankment area surrounding the earth-filled rail trestle, and backfilling sinkholes on the embankment.
The solicitation is an unrestricted, full and open competition construction contract with a firm-fixed price, estimated between $10 million and $25 million. The contract will have a 455-calendar day performance period, with contractors required to begin work within 15 calendar days of award. The project requires performance and payment bonds, and contractors must meet small business subcontracting goals, including 40% small business, 5% small disadvantaged business, 9% women-owned small business, 3% HUBZone, and 5% service-disabled veteran-owned small business participation. Proposals are due by 29 May 2025 at 2:00 PM local time, with award anticipated in August 2025.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ACQR6097049
SOLICITATION NO. N4008525R2611 DESIGN-BID-BUILD, REPAIR AMMUNITION RAIL TRESTLE & CULVERT, NAVAL WEAPONS STATION
EARLE (NWSE), COLTS NECK, NEW JERSERY.
Project w ill repair sixteen (16) degraded corrugated metal pipe (CMP) culverts that support the Normandy Road Ammunition Rail crossing over the Sw imming River. Includes cofferdams, dew atering, removal of vegetation and accumulated sediment, repairs to and lining of the CMPs, compaction grouting of the embankment area surrounding the earth-filled rail trestle, and backfill of sinkholes on teh embankment.
All correspondence regarding this solicitaion shall be directed via email to Mary Ann Pool at mary.a.pool3.civ@us.navy.mil.
MARY A. POOL 757-341-0559
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
14-Apr-2025
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
X
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______15 calendar days and complete it w ithin ________455 calendar days after receiving aw ard, notice to proceed. This performance period is X mandatory, negotiable. (See _________________________FAR 52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________29 May 2025 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
NAVFACSYSCOM MID-ATLANTIC
CONTRACTING CORE
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3095
N40085
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
02:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: TEL: FAX:
N4008525R2611 82
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
N4008525R2611
Section 00 10 00 - Solicitation
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 Project
BASE PRICE
FFP
Total Price for Line Items (0001A -0001P) for the entire work for the Ammunition Rail Trestle and Culvert Repair Project.
FOB: Destination
PURCHASE REQUEST NUMBER: ACQR6097049
PSC CD: Y1LB
NET AMT
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 N/A N/A N/A N/A
Section 00 21 00 - Instructions
INSTRUCTION TO OFFERORS
TABLE OF CONTENTS
1. GENERAL
1.1 GENERAL OVERVIEW OF PROCUREMENT PROCESS
1.2 GENERAL OVERVIEW OF CONTRACT
2. BASIS FOR AWARD
3. EVALUATION FACTORS FOR AWARD
4. PROPOSAL REQUIREMENTS
4.1 PRE-PROPOSAL CONFERENCE AND SITE VISIT
4.2 PROPOSAL SUBMISSION INSTRUCTIONS
4.3 PRE-PROPOSAL INQUIRIES (PPIs)
4.4 CONTRACT OPPORTUNITIES
5. INCORPORATION OF TECHNICAL PROPOSALS
6. ATTACHMENTS: LOCATED ON CONTRACT OPPORTUNITIES UNDER ATTACHMENTS
6.1 ATTACHMENT A – PRE-PROPOSAL INQUIRY (PPI) LOG
6.2 ATTACHMENT B – PIEE VENDOR ACESS INSTRUCTIONS
6.3 ATTACHMENT C – PAST PERFORMANCE QUESTIONAIRE (PPQ)
6.4 ATTACHMENT D – SMALL BUSINESS SUBCONTRACTING PLAN
6.5 ATTACHMENT E – CONSTRUCTION EXPERIENCE PROJECT DATA SHEET
6.6 ATTACHMENT F - HISTORICAL SMALL BUSINESS UTILIZATION
6.7 ATTACHMENT G – SMALL BUSINESS PARTICIPATION COMMITMENT DOCUMENT (SPCD)
6.7 ATTACHMENT H – PRICE PROPOSAL FORM
6.8 ATTACHMENT I – SPECIFICATIONS
6.9 ATTACHMENT J - DRAWINGS
1. GENERAL
1.1 GENERAL OVERVIEW OF PROCUREMENT PROCESS
This solicitation is being issues as UNRESTRICTED FOR FULL AND OPEN COMPETITION.
The NAICS Code for this procurement is 237990 and the Size Standard is $45M.
This acquisition will be advertised utilizing FAR Part 15 – Contracting by Negotiation resulting in a Firm-Fixed Price (FFP) Contract for Construction Services.
In accordance with DFARS 236.204, the estimated magnitude of construction is between $10,000,000 and $25,000,000.
1.2 GENERAL OVERVIEW OF THE CONTRACT
The general intent of this solicitation is to award a Fixed Price Construction Contract for Design-Bid-Build (DBB), Repair Ammunition Rail Trestle & Culvert, Naval Weapons Station Earle (NWSE), Colts Neck, New Jersey.
This project will provide the repairs to an existing railroad embankment and underlying culverts at Naval Weapons Station Earle. This project includes compaction grouting of the embankment, repair of sixteen (16) degraded corrugated metal pipe culverts (which will include installation of cofferdams, dewatering activities, and relining).
The construction activities will take place adjacent to an active railway owned and operated by the Navy which will require coordination with Navy railroad dispatch and require clearance of rail right-of-way in accordance with the plans and specifications herein.
2. BASIS FOR AWARD
The Government reserves the right to eliminate from consideration for award any or all offers at any time prior to award of the contract; to negotiate with offerors in the competitive range; and to award the contract to the offeror submitting the proposal determined to represent the best value—the proposal most advantageous to the Government, price and other factors considered.
The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. In addition, if the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.
The tradeoff process is selected as appropriate for this acquisition. The Government considers it to be in its best interest to allow consideration of award to other than the lowest priced offeror or other than the highest technically rated offeror.
All technical factors when combined are of equal importance to the performance confidence assessment (past performance) rating; and all technical factors and the performance confidence assessment (past performance) rating, when combined are approximately equal to price.
Any proposal found to have a deficiency in meeting the stated solicitation requirements or performance objectives will be considered ineligible for award, unless the deficiency is corrected through discussions. An Unacceptable rating in any of the non-cost/price factors will result in an overall rating of “Unacceptable” for the non-cost/price factors, unless corrected through discussions. Proposals may be found to have either a significant weakness or multiple weaknesses that impact either the individual factor rating or the overall rating for the proposal.
3. EVALUATION FACTORS FOR AWARD
The solicitation requires the evaluation of price and the following non-cost/price factors:
Factor 1 – Corporate Experience
Factor 2 – Management Approach & Schedule Factor 3 – Small Business Utilization and Participation Factor 4 – Safety Factor 5 – Past Performance
The distinction between corporate experience and past performance is that corporate experience pertains to the volume of work completed by a contractor that are comparable to the types of work described under the definition of recent, relevant projects, in terms of size, scope, and complexity. Past performance pertains to both the relevance of recent efforts and how well a contractor has performed on the contracts.
The relative order of importance of the non-cost/price evaluation factors is the technical factors (Factors, 1, 2, 3, and
4) are of equal importance to each other and, when combined are equal in importance to the past performance evaluation/performance confidence assessment factor (Factor 5). When the proposal is evaluated as a whole, the technical factors and past performance/performance confidence assessment factor combined (i.e., the non-cost/price evaluation factors) are approximately equal to price.
The importance of price will increase if the offerors’ non-cost/price proposals are considered essentially equal in terms of overall quality, or if price is so high as to significantly diminish the value of a non-cost/price proposal’s superiority to the Government. Award will be made to the responsible offeror(s) whose offer conforms to the solicitation and represents the best value to the Government, price and non-price factors considered.
Basis of Evaluation and Submittal Requirements for Each Factor.
Price Proposal
(i) Solicitation Submittal Requirements:
The offeror shall submit one (1) electronic copy via PIEE, to include the submittal requirements identified below.
The Price and Non-price proposals shall be submitted in separate files and submitted in Portable Document Format (PDF). In addition, non- price/technical information included in the price proposal will not be considered, likewise, price information included in the non-price/technical proposal will not be considered. All required proposal documents shall be submitted in accordance with FAR 15.208.
All submissions shall include the following:
1. Executed SF1442. Offeror shall insert its company name and address in Block #14, telephone number in Block #15, acknowledge all amendments in Block #19 (if applicable), name and title of person authorized to sign in Block #20A, signature in Block #20B, and offer date in Block #20C of the SF1442. In addition, offeror shall provide a cover page with solicitation number, solicitation title, offeror name, address, phone number, fax number, Unique Identifier Number (UEI), CAGE code, Federal Tax ID number, Point of Contact (POC), POC phone number, and POC email address, with its proposal.
2. Completed Price Proposal Form that includes all CLINs. The offeror is required to submit a complete Price Proposal Form that includes completion of all contract line items numbers (CLINs). Pricing information is not required to be completed under Section 00 10 00 – Solicitation Contract Form in SF 1442.
3. Bid bond (SF-24). Offeror shall submit a Bid Guarantee in accordance with FAR 52.228-1, Bid Guarantee.
A bid bond (SF-24) shall be at least 20 percent of the total proposed price for project but shall not exceed $3M. The bid bond shall be in the name of the offeror identified on the SF1442.
4. System for Award Management (SAM) registration. Offeror shall provide a copy of Representation and Certifications and proof of registration in System for Award Management (SAM) and ensure current registration on the SAM Website, www.sam.gov, including Annual Representations and Certifications are complete and updated for this procurement. If a Representation or Certification required by Section 00 45 00 of the RFP is not provided in SAM, include the representation or certification in your price proposal.
5. FAPIIS. Offeror shall ensure Federal Awardee Performance and Integrity Information System (FAPIIS) is current, accurate, and complete, as required by FAR 52.209-7, Information Regarding Responsibility Matters.
6. VETS-4212 registration. Confirmation of filing of Veterans’ Employment and Training (VETS) VETS- 4212 for the 2023/2024 filing cycle, if the offeror is required to submit. Offeror shall ensure a current VETS-4212 report has been submitted to the Department of Labor (DOL) website, http://www.dol.gov/vets/vets4212.htm. An email confirmation of submission can be requested and received by the offeror from the DOL website and submitted in the price proposal. If the offeror is not required to submit a report to VETS-4212, include a brief statement and justification explaining why the offeror is not required to submit a report. Visit the VETS-4212 website for details concerning if your company is required to submit a VETS-4212 report and to request an email confirmation of submission.
7. Small Business Subcontracting Plan (Reference FAR 52.219-9 ALT II and DFARS 252.219-7003).
In accordance with FAR 19.7, all other than small businesses shall submit a Small Business Subcontracting Plan (SBSP) utilizing the template provided as Attachment D. Acceptability of the SBSP will be considered a responsibility matter. The SBSP will not be evaluated or rated by the SSEB but reviewed by a Small Business Professional/Authorized Representative and the Contracting Officer for acceptability. The SBSP shall be negotiated and/or accepted within the time specified by the Contracting Officer. Failure to negotiate an acceptable subcontracting plan within the time limit prescribed by the Contracting Officer will render the offeror ineligible for award of the contract. The SBSP will be incorporated into the resulting contract.
NAVFAC’s command-wide small business subcontracting targets are shown below. These may be higher or lower than percentages that would represent realistic, challenging, small business subcontracting goals for this acquisition consistent with efficient and effective performance of the contract. These targets are based on a percentage of total planned subcontract dollars. These goals will be incorporated into the solicitation.
Small Business (SB) 40% Small Disadvantaged Business (SDB) 5% Women Owned Small Business (WOSB) 9% HubZone SB 3% Service-Disabled Veteran-Owned Small Business (SDVOSB) 5%
The SBSP shall be consistent with the commitments offered in the Small Business Utilization and Participation factor. In accordance with DFARS 215.304(c)(i), when an evaluation assesses the extent that small businesses are specifically identified in proposals, those small businesses considered in the evaluation shall be listed in the SBSP.
Please note that SBSP goals and the participation rates provided in the Small Business Participation Commitment Document (SBPCD) WILL NOT be the same. The participation rates within the SBPCD are provided as percentages of the total contract value; subcontract plan goals are provided as a percentage of planned subcontracting dollars. While the percentages will differ, the types of products/services identified in the SBSP, should be the same as those products/services identified in the SBPCD. Likewise, the planned small business subcontract dollars in the SBSP will be equal to (or in some cases greater than) the extent of small business participation identified in the SBPCD.
8. Bank Reference. One (1) Signed Bank Reference demonstrating adequate financial resources. If offeror’s firm has a line of credit, provide information on how many figures the offeror can borrow against the line of credit (i.e. medium 6 figures – exact line of credit is not required).
9. Financial Statements. The offeror shall provide the latest three complete fiscal year financial statements for the prime contractor, certified by an independent accounting firm, if practicable, or signed by an authorized officer of the organization. Submit evidence of availability of working/operating capital, which will be used for the performance of the resultant contract. For Joint Venture arrangements, submit the latest three complete fiscal year financial statements for each company in the Joint Venture and discuss the financial responsibilities among the companies.
10. Facilities and Equipment. Provide a description of offeror’s facilities and equipment.
11. Other Work. Provide a list of offeror’s other work presently under contract.
(ii) Basis of Evaluation:
The Government will evaluate price based on the total price. Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:
(i) Comparison of proposed prices received in response to the RFP.
(ii) Comparison of proposed prices with the IGCE.
(iii) Comparison of proposed prices with available historical information.
(iv) Comparison of market survey results.
Although required to be submitted with offeror’s price proposal, Items 3 through 11 above will not be evaluated as part of the price proposal. This information will be utilized by the Government in the responsibility determination and for considering responsiveness to the solicitation requirements.
Non-Price Factors:
All submissions shall include the following:
The offeror shall submit one (1) electronic copy via PIEE, in accordance with the solicitation submittal requirements identified below. The Price and Non-Price proposals shall be submitted in separate files and submitted in Portable Document Format (PDF). In addition, non-price/technical information included in the price proposal will not be considered. Likewise, price information included in the non-price/technical proposal will not be considered. All required proposal documents shall be submitted in accordance with FAR 15.208.
Offeror shall provide a cover page with solicitation number, solicitation title, offeror name, address, phone number, fax number, Unique Entity Identifier (UEI), CAGE code, Federal Tax ID number, Point of Contact (POC), POC phone number, and POC email address with its proposal.
Refer to individual factors for page limitations. Pages that exceed indicated page limitations shall not be evaluated.
Note: If proposing as a Joint-Venture (JV), please submit the POC, UEI, and CAGE Code for each JV partner.
Factor 1, Corporate Experience:
Submit a minimum of two (2) up to a maximum of five (5) relevant construction projects for the offeror that best demonstrate your experience on relevant projects (similar in Size, Scope, and Complexity as defined below).
Experience shall be that of the offeror, performed as the Prime Contractor. Experience of proposed subcontractors will not be considered. Furthermore, experience of the offeror while working as a subcontractor will not be considered.
For purposes of this evaluation, a relevant project is further defined as:
Size: Projects demonstrating a final construction cost of $10,000,000 or greater. Final construction cost is defined as the total price paid by the customer for the construction services, including original contract award amount and any modifications executed during performance.
Scope: Projects demonstrating experience in reinforced concrete restoration and repair, relining of existing culverts, dewatering for construction, and embankment stabilization.
Complexity: Offerors are not required to demonstrate all complexity elements (listed below) in each relevant project submitted, but shall collectively demonstrate experience with the following elements, while meeting the size and scope relevancy requirements:
a) Experience in repair of damaged culvert pipes or utilities.
b) Experience with cofferdam installation.
c) Experience with environmental permitting planning and submission and compliance.
The offeror’s body of submitted work, considered as a whole, will be reviewed to determine if it possesses all of the complexity elements listed above. Complexity will only be satisfied on projects that are considered relevant in terms of size and scope.
Projects submitted for the offeror shall be completed within the past ten (10) years from the date of issuance of this RFP. Projects which are not complete as of the date of issuance of this RFP will be considered “Not Relevant”. Additionally, projects completed prior to ten (10) years from the date of issuance of this RFP will be considered “Not Relevant.”
For all submitted projects, ensure that the project description clearly addresses how the project meets the required timeframe as well as the Scope and Complexity requirements and clearly provides the final construction cost. The absence of any such information or information that does not clearly address the requirements may result in the project being considered Not Relevant, which could result in a rating of UNACCEPTABLE for this Factor if the minimum requirements are not met.
A project is defined as a construction project performed under a single task order or contract. For multiple award and indefinite delivery/indefinite quantity type contracts, the contract as a whole shall not be submitted as a project;
rather offerors shall submit the work performed under a task order as a project. The submission of a multiple award and/or indefinite delivery/indefinite quantity type contract as a whole will be considered Not Relevant.
The attached Construction Experience Project Data Sheet (Attachment E) is MANDATORY and SHALL be used to submit project information. Except as specifically requested, the Government will not consider information submitted in addition to this form nor will the Government consider submissions via any other medium. Individual blocks on this form may be expanded; however, total length for each project data sheet shall not exceed two (2) pages.
If the offeror is a Joint Venture (JV), relevant project experience should be submitted for projects completed by the Joint Venture entity. If the Joint Venture does not have shared experience, projects may be submitted for the Joint Venture members. If a project was performed by a JV, and not all partners from that JV are on the JV proposed for this contract, the offeror shall clearly demonstrate what portion of the work was performed by the JV member offering on this contract and shall not include work performed by the JV as a whole. The JV member proposed for this contract shall specifically address field work performed by that JV member including field staffing and direct field work oversight. The JV member proposed for this contract shall also address home office management performed by that JV member including the number/percentage of employees provided for the overall contract by the JV members as well as the overall percentage of work performed by the JV member. The offeror shall also submit a SIGNED copy of the Joint Venture agreement indicating the proposed participation of each Joint Venture member. Offerors are still limited to a total of five (5) projects combined.
For a JV, the offeror shall submit a signed JV agreement. For an 8(a) Mentor-Protégé Joint Venture, the offeror shall submit the signed SBA Mentor-Protégé Approval Letter and signed JV agreement.
If an Offeror is utilizing experience information of affiliates/subsidiaries/parent/LLC/LTD member companies (name is not exactly as stated on the SF1442), the Factor 1 Project Data Sheet shall clearly demonstrate that the affiliate/subsidiary/parent firm will have meaningful involvement and clearly describe the role that firm will have in the performance of the contract. If meaningful involvement is not demonstrated, experience of the affiliate/subsidiary/parent firm will not be considered
(ii) Basis of Evaluation:
The basis of evaluation will include the offeror’s demonstrated experience and depth of experience in performing relevant construction projects as defined in the solicitation submittal requirements. The assessment of the offeror’s relevant experience will be used as a means of evaluating the capability of the offeror to successfully meet the requirements of the RFP. The Government will only review five (5) projects total. Any projects submitted in excess of the five (5) for Corporate Experience will not be considered.
The Government will review the first five projects if more are submitted. An offeror that does not submit a minimum of two (2) relevant projects as defined above will be assigned a Deficiency and receive a rating of UNACCEPTABLE. An offeror with an UNACCEPTABLE rating in any Factor will not be eligible for award.
Proposals that do not demonstrate relevant project experience for each JV member may be considered less favorably.
Offerors that demonstrate all required complexity elements in a single project may be considered more favorably.
Factor 2, Management Approach & Schedule
Submit the following documentation, as detailed throughout this Factor, in order to describe your approach to managing the project, risk, and ensuring adherence to the project schedule:
1) Management Approach Narrative
2) Critical Path Schedule
See below for details concerning the required content of each item listed above. Factor submission shall not exceed ten (10) pages. There are no page restrictions on the project schedule.
1. Management Approach Narrative The narrative shall include, but is not limited to:
• Demonstrate understanding of the scope, all phases and major milestones, technical complexities, and construction schedule require to achieve work as identified in the RFP.
• Identify activities that may affect the project timeline, including environmental restrictions.
• Identify key project risks including their likelihood and consequences, along with mitigation or management strategies to minimize or element impacts to the project cost and schedule.
• Address the following technical complexities.
o Phased construction of the ground improvements and temporary cofferdam installation and dewatering.
o Seasonal work restrictions to meet environmental requirements.
o Culvert repair and lining.
o Track movement monitoring plan and survey method.
o Plan to accommodate active rail restrictions.
2. Critical Path Schedule
The project schedule shall illustrate the offeror’s ability to achieve or improve on the contract completion date set out in the RFP. The total duration of the contract is 455 calendar days. Identify the overall completion time for this project, in accordance with the RFP, as well as interim completion times and key milestones for sequences as required to complete construction. The schedule shall demonstrate an understanding of the work, a logical sequence of events to accomplish the work, and contain enough information to identify all the major milestones, as defined in the phasing plans of the RFP.
The schedule shall be based on a contract award date of AUGUST 2025. This is for proposal purposes only and not dispositive of an anticipated/planned award date.
If an offeror proposes a realistic and feasible schedule that is shorter than the required duration and is selected for award, that schedule and duration will be incorporated into the award document and replace the advertised required duration.
A Deficiency will be assigned to any offeror whose schedule proposes a contract duration longer than indicated in the RFP which will result a rating of UNACCEPTABLE.
Offeror shall provide a critical path method (CPM) schedule for execution and completion of the work to achieve the required interim and final completion milestones for the project. At a minimum, the CPM schedule shall address the following:
- Identify major activities and milestones o Ground improvements o Temporary construction access o Phased cofferdam installation and dewatering o Phased culvert rehab and relining o Structural repairs o Site restoration.
- Provide sequencing (precedence/succession) of critical activities
- Demonstrate knowledge of project regulatory constraints
- Sufficiently detailed to identify critical and near critical activities
Offerors will be evaluated on the extent to which they demonstrate a clear understanding of the above solicitation submittal requirements for this factor. A management approach narrative work plan and schedule that do not address all items listed above may be rated as UNACCEPTABLE.
1. Management Approach
A management approach that provides a feasible strategy for communication with multiple on-site stakeholders, including a plan to accommodate active rail restrictions may be considered more favorably.
A track movement monitoring plan and survey method that includes automated deformation monitoring points and inclinometers will be considered more favorably than manual monitoring.
A narrative that details the firms proposed approach for the temporary cofferdam installation and dewatering will be considered more favorably.
2. Schedule
A schedule that proposes a realistic and feasible contract duration shorter than the required duration indicated in the RFP may be considered more favorably than those that do not.
Factor 3, Small Business Utilization and Participation
It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to Small Business (SB) concerns, including Small Disadvantaged Business (SDB), Woman-Owned Small Business (WOSB), Historically Underutilized Business Zone Small Business (HUBZone SB), Veteran-Owned Small Business (VOSB), Service-Disabled Veteran Owned Small Business (SDVOSB), and other small business concerns. Further, it is the policy of the Government that such concerns will have the maximum practicable opportunity to participate in contract performance consistent with its efficient performance.
This Factor assesses both the historical achievements in utilizing small business concerns and the proposed small business participation commitment for this requirement. The offeror is required to demonstrate its previous commitment to SBs through its record of past utilization of SBs and the level of commitment to small business if awarded a contract under this solicitation.
1. All offerors (large AND small businesses) shall use Attachment F (Historical Small Business Utilization) to demonstrate their historical utilization of SBs. Each project submitted under Factor 1, Corporate Experience, shall be included on Attachment F. Failure to include each project submitted under Factor 1, Corporate Experience, on Attachment F, or the failure to fully complete Attachment F for each project may result in a Deficiency. Only complete Attachment F. Information provided in a different format and/or on a form created by the offeror will not be evaluated. Attachments or addendums to Attachment F will not be evaluated. Offerors are permitted to expand portions of the form, as needed, to provide sufficient response. Instructions regarding how to complete Attachment F are included at the beginning of the attachment.
2. All Offerors (large AND small businesses) shall use Attachment E (Small Business Participation Commitment Document (SBPCD)) to submit the following required information for evaluation of this factor:
- To demonstrate commitment to use small business concerns in the performance of this contract, identify by name the subcontractors that will be used to support each small business category, including SDB, WOSB, HUBZone SB, VOSB, and SDVOSBs. Identify the type and complexity of product/service to be subcontracted, and the type of commitment (i.e., teaming agreement, joint venture agreement, mentor protégé agreement, letter of commitment, etc.) with each subcontractor.
o If subcontractors are not identified by name, offerors shall provide a detailed explanation why subcontractors are not identified. If firm written commitments with SBs are not in place, offerors shall provide an explanation and rationale on the ability to achieve the proposed participation. (See Attachment E, paragraph 5) o If a LB offeror does not intend to subcontract, provide a detailed explanation why subcontracting would not result in efficient contract performance. SBs intending to 100% self-perform are not required to provide an explanation. (See Attachment G, paragraph 6)
- To demonstrate maximum practicable participation of small businesses, identify (in terms of dollar value and percentage of the total contract value) the offeror’s proposed small business participation. The minimum required small business participation (i.e., work to be performed by small business as the prime contractor and/or work to be performed by small business subcontractors) is 20% (this amount will be modified based on market research). Offerors who are not able to meet the minimum total small business participation requirement of 20% (of the total contract value) shall provide a detailed explanation why the minimum total small business participation requirement cannot be achieved.
- Only complete Attachment E. Information provided in a different format and/or on a form created by the offeror will not be evaluated. Attachments or addendums to Attachment E will not be evaluated.
- Large business offerors may achieve the minimum total small business participation requirement through subcontracting to small businesses.
- Small business offerors may achieve the minimum total small business participation requirement through their own performance/participation as a prime as well as through a joint venture, teaming arrangement, and/or subcontracting with other small business concerns.
The Government will evaluate the likelihood of success in achieving the small business objectives of this acquisition based on the following:
1. The extent to which the offeror is able to demonstrate a history of supporting Government policies concerning the utilization of small business concerns, including SDB, WOSB, HUBZone SB, VOSB, and SDVOSB and the success in achieving goals established by subcontracting plans on prior contracts. For projects submitted for Factor 1, Corporate Experience, that did not have established small business goals, consideration will be given to the utilization of the small business concerns and the degree of usage of small business relative to the total contract value. Historical Small Business Utilization will only be evaluated if performed by the offeror.
2. The extent to which the offeror has demonstrated an achievable commitment to use small businesses, including SDB, WOSB, HUBZone SB, VOSB, and SDVOSB in the performance of this contract within the
SBPCD.
3.
• The minimum small business participation requirement, through work performed by the small business prime and/or subcontracting with small businesses, shall meet or exceed 20% of the total contract value, unless the offeror provides a reasonable and well-documented explanation for why the minimum 20% small business participation requirement cannot be achieved.
o Offerors that demonstrate a commitment to providing maximum practical opportunity to small businesses may be rated higher.
o Proposing less than 20% total small business participation requirement may result in a Deficiency.
o Offerors that do not demonstrate commitment to providing maximum practical opportunity to small businesses may result in a Deficiency.
• The SBPCD will be evaluated to determine the extent to which small business concerns are specifically identified by name and socioeconomic category in the document and the degree to which small business concerns, including SDB, WOSB, HUBZone SB, VOSB, and SDVOSB will participate relative to the total contract value. The complexity and variety of the work small business concerns will perform and the degree of commitment to use named sources through formal teaming agreements, joint venture agreements, mentor protégé agreements, written/signed letters of /commitment, etc. will be evaluated to assess achievability of the commitment.
o The offeror may receive a Deficiency if firm commitments with subcontractors are not provided, and the offeror fails to provide a detailed explanation for how the proposed small business participation requirement will be achieved.
o The offeror may be rated lower, if they fail to provide a detailed explanation for why subcontracting would not result in efficient contract performance. (Not applicable to SBs intending to 100% self-perform or LBs and who intend to subcontract.)
Factor 4, Safety
The offeror shall submit the following information:
The Days Away from Work, Restricted Duty, or Job Transfer (DART) Rate; and Total Case Rate (TCR) for the specified five (5) Calendar Years (CY), as well as a safety narrative as described further below. For a partnership, joint venture, the offeror shall submit separate DART, TCR for the specified five (5) CY for each contractor who is part of the partnership or joint venture; however, only one safety narrative is required. Any fatalities experienced within this 5-year timeframe must be explained in detail, to include root cause and corrective actions.
NOTE: DART and TCR shall not be submitted for subcontractors.
(1) DART Rate: Submit five (5) previous complete calendar years’ [CY2024, CY2023, CY2022, CY2021, and CY2020] worth of data (not an overall average). If the offeror has no DART rate, for any year, affirmatively state so and explain why. Should a negative trend occur above moderate risk levels, an acceptable/detailed explanation is required, that includes any corrective actions taken for improvement.
a. Dart cases include injuries or illnesses resulting in death, days away from work, and/or restricted work or transfer to another job days beyond the day of injury/illness.
b. Calculation of DART rate: Multiply the total number of DART cases by 200,000, and then divide by the number of employee labor hours worked.
𝑫𝑨𝑹𝑻 𝑹𝑨𝑻𝑬
Number of DART Incidents x 200,000
Total Number of Enployee Labor Hours Worked
(2) TCR Rate: Submit five (5) previous complete calendar years’ [CY2024, CY2023, CY2022, CY2021, and CY2020] worth of data (not an overall average). If the offeror has no TCR rate, for any year, affirmatively state so and explain why. Should a negative trend occur above moderate risk levels, an acceptable/detailed explanation is required, that includes any corrective actions taken for improvement.
a. TCR cases include injuries or illnesses resulting in death, days away from work, restricted work or transfer to another job days beyond the day of injury/illness, medical treatment beyond first aid, or loss of consciousness.
b. Calculation of TCR rate: Multiply the total number of TCR incidents by 200,000, and then divide by the number of employee labor hours worked.
𝑻𝑪𝑹 𝑹𝑨𝑻𝑬
Number of TCR Incidents x 200,000
Total Number of Enployee Labor Hours Worked
(3) Technical Approach for Safety: Submit a narrative that addresses the following:
a. Describe the offeror’s approach to implementing and executing a Safety Management System (SMS) including Management/Leadership involvement, Employee involvement, Hazard prevention, Hazard control, Worksite analysis, and Safety and health training, to include the standard(s) used to benchmark the SMS.
b. Describe the evaluation process used to select potential subcontractors.
c. Describe the processes of how the offeror will oversee safety compliance of subcontractors at all levels throughout the performance of the contract (to include their own in-house workforce).
d. The Technical Approach to Safety narrative shall be limited to two (2) pages.
(4) The Government reserves the right to review other available sources (public/Government internal) of information. These may include but are not limited to OSHA data, NAVFAC’s Contractor Incident Reporting System (CIRS), Contractor Performance Assessment Reporting System (CPARS), Electronic Contract Management System (eCMS), etc.
The Government is seeking to determine that the offeror has consistently demonstrated a commitment to safety and that the offeror plans to properly manage and implement safety procedures for itself and its subcontractors. The evaluation will collectively consider the DART rate, TCR, Technical Approach to Safety, and other sources of information available to the Government as part of such collective evaluation. The board will evaluate the DART rates and TCR to determine if the offeror has demonstrated a history of safe work practices taking into account any negative trends and extenuating circumstances that impact the rating.
(1) DART Rate: The board will evaluate trends over the last five years considering changes that take it from one risk level (or more) to the next up or down. Negative trends occurring above moderate risk levels require the offeror to provide a detailed explanation that includes any corrective actions taken for improvement.
a. Missing data without an explanation is considered a Deficiency.
b. Declining trends that push the risk levels from Moderate Risk (MR) or higher to Low Risk (LR) or
Very Low Risk (VLR) would indicate a Strength.
c. An increasing DART rate trend could be considered a Weakness (i.e. MR or better to High Risk (HR) or Extremely High Risk EHR)) if an acceptable explanation is not provided for any trends that rise above Moderate.
d. This chart correlates the DART rate to the level of risk:
Risk DART Rate Very Low Risk Less Than 1.0
Low Risk From 1.0 to 1.99 Moderate Risk From 2.0 to 2.99 High Risk From 3.0 to 4.0 Extremely High Risk Greater than 4.0
(2) TCR Rate: The board will evaluate trends over the last five years considering changes that take it from one risk level (or more) to the next up or down. Negative trends occurring above moderate risk levels require the Offeror to provide a detailed explanation that includes any corrective actions taken for improvement.
a. Missing data without an explanation is considered a Deficiency.
b. Declining trends that push the risk levels from Moderate Risk (MR) or higher to Low Risk (LR) or
Very Low Risk (VLR) would indicate a Strength.
c. An increasing TCR rate trend could be considered a Weakness (i.e. MR or better to High Risk (HR) or Extremely High Risk EHR)) if an acceptable explanation is not provided for any trends that rise above Moderate.
d. This chart correlates the TCR rate to the level of risk:
Risk TCR Rate Very Low Risk Less Than 2.49 Low Risk From 2.5 to 3.49 Moderate Risk From 3.5 to 4.49 High Risk From 4.5 to 5.99 Extremely High Risk Greater than 6.0
(3) The Technical Approach to Safety Narrative. To determine the degree to which the offeror:
a. Describes a viable SMS that addresses elements, such as Management/Leadership involvement, Employee involvement, Hazard prevention, Hazard control, Worksite analysis, and Safety and health training, to include the standard(s) used to benchmark the SMS.
b. Describes a methodical process of evaluating subcontractor’s safety performance in their selection process.
c. Describes a logical management plan to hold themselves and their subcontractors accountable for adhering to the safety requirements of the contract.
d. The Technical Approach to Safety narrative shall be limited to two (2) pages. Information on pages beyond this will not be considered.
(4) The Government reserves the right to review other available sources (public/Government internal) of information. These may include but are not limited to OSHA data, NAVFAC’s Contractor Incident Reporting System (CIRS), Contractor Performance Assessment Reporting System (CPARS), Electronic Contract Management System (eCMS), etc.
Factor 5, Past Performance:
Recent, relevant projects are determined within the requirements for Factor 1, Corporate Experience.
If a completed Contractor Performance Assessment Reporting System (CPARS) evaluation is available, it shall be submitted with the proposal for each project included in Factor 1. The offeror shall include all completed CPARS evaluations (interim and final) for a project. If there is not a completed CPARS evaluation, the Past Performance Questionnaire (PPQ) included in the solicitation is provided for the offeror or its team members to submit to the client for each project submitted for Factor 1, Corporate Experience. AN OFFEROR SHALL NOT SUBMIT A PPQ
WHEN A COMPLETED CPARS IS AVAILABLE.
If a CPARS evaluation is not available, completed PPQs should be submitted with your proposal. If the offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror should complete and submit with the proposal the first page of the PPQ (Attachment C), which will provide contract and client information for the respective project(s). Offerors should ensure correct phone numbers and email addresses are provided for the client point of contact. Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government's point of contact, Mary Ann Pool, via email at mary.a.pool3.civ@us.navy.mil prior to proposal closing date. Offerors shall not incorporate by reference into their proposal PPQs or CPARS previously submitted for other RFPs.
However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation.
Offerors are highly encouraged to provide any information on problems encountered and the corrective actions taken on projects submitted under Factor 1 – Corporate Experience. Additionally, offerors are highly encouraged to address any adverse past performance issues. Such explanations shall not exceed four (4) pages in total. Information beyond this page limitation will not be considered.
In addition to the above, the Government may review any other sources of information for evaluating past performance. Other sources may include, but are not limited to, past performance information retrieved through the Contractor Performance Assessment Reporting System (CPARS) using all CAGE/Entity Identifier numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the offeror’s proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the offeror.
While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the offeror.
IMPORTANT: It is the responsibility of the offeror to provide accurate points of contact for each identified contract and current telephone numbers and/or email addresses. Failure to provide requested data, accessible points of contact, or valid phone numbers could result in a firm being considered less qualified.
The Government reserves the right to contact references for verification or additional information. The Government’s inability to contact any of the offeror’s references or the references unwillingness to provide the information requested may affect the Government’s evaluation of this factor.
A copy of the blank Past Performance Questionnaire to be used for requesting client references is included as Attachment C.
This evaluation focuses on how well the offeror performed on the projects submitted under Factor 1 – Corporate Experience and past performance on other projects currently documented in known sources.
The Government will consider the degree to which past performance evaluations and all other past performance information reviewed by the Government (e.g., CPARS, Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), performance recognition…
This is the start of the file's text. The full file is on GovTribe.