This document is a draft Temporary Dewatering Permit (DWP240001) for Naval Weapon Station Earle's Culvert Repairs project. The permit specifies detailed water diversion limits and requirements, including a maximum diversion rate of 810 gallons per minute and a monthly water diversion cap of 24.18 million gallons. The permit covers multiple proposed wells (labeled 1A through 6B and Well C), each with a rated pump capacity limit of 300 gallons per minute, and dewatering trenches limited to 50 gallons per minute.
The permit includes comprehensive monitoring and reporting requirements, such as monthly meter readings, quarterly dewatering reports, and well drilling permit submissions. Key administrative requirements include maintaining a contingency water supply plan, protecting water sources from vandalism, investigating potential water supply complaints, and submitting a completion report within 60 days of project completion. The permit is subject to potential modification, suspension, or termination by the Department of Environmental Protection, and requires renewal application three months prior to expiration.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Temporary Dewatering Permit : DWP240001
1393D
NAVAL WEAPON STATION EARLE - CULVERT REPAIRS
Permit Requirements
The following limits apply and are the maximum permitted allocation:
Limit Requirements
Final Permit Phase
LimitParameterSubject Item
Maximum Diversion RateNAVAL WEAPONS STATION
EARLE, 1393D TEMP DWP -
ALL DIVERSION SOURCES
(WSWA2077880)
<= 810 Gallons Per Minute. [N.J.A.C. 7:19- 2]
Water Diverted <= 24.18 Million Gallons Per Month. [N.J.A.C. 7:19- 2]
Other Limit Requirements
Final Permit Phase
LimitSubject Item Parameter
<= 50 Gallons Per Minute. [N.J.A.C. 7:19- 2]PROPOSED TRENCHES, DEWATERING TRENCHES
(WSRM2083288)
Rated Pump Capacity
<= 300 Gallons Per Minute. [N.J.A.C. 7:19- 2]PROPOSED, WELL 1A
(WSWL2077142)
Rated Pump Capacity
<= 300 Gallons Per Minute. [N.J.A.C. 7:19- 2]PROPOSED, WELL 2A
(WSWL2077143)
Rated Pump Capacity
<= 300 Gallons Per Minute. [N.J.A.C. 7:19- 2]PROPOSED, WELL 3A
(WSWL2077144)
Rated Pump Capacity
<= 300 Gallons Per Minute. [N.J.A.C. 7:19- 2]PROPOSED, WELL 4A
(WSWL2077145)
Rated Pump Capacity
<= 300 Gallons Per Minute. [N.J.A.C. 7:19- 2]PROPOSED, WELL 5A
(WSWL2077146)
Rated Pump Capacity
<= 300 Gallons Per Minute. [N.J.A.C. 7:19- 2]PROPOSED, WELL 6A
(WSWL2077147)
Rated Pump Capacity
<= 300 Gallons Per Minute. [N.J.A.C. 7:19- 2]PROPOSED, WELL 1B
(WSWL2077148)
Rated Pump Capacity
<= 300 Gallons Per Minute. [N.J.A.C. 7:19- 2]PROPOSED, WELL 2B
(WSWL2077149)
Rated Pump Capacity
<= 300 Gallons Per Minute. [N.J.A.C. 7:19- 2]PROPOSED, WELL 3B
(WSWL2077150)
Rated Pump Capacity
<= 300 Gallons Per Minute. [N.J.A.C. 7:19- 2]PROPOSED, WELL 4B
(WSWL2077151)
Rated Pump Capacity
<= 300 Gallons Per Minute. [N.J.A.C. 7:19- 2]PROPOSED, WELL 5B
(WSWL2077152)
Rated Pump Capacity
<= 300 Gallons Per Minute. [N.J.A.C. 7:19- 2]PROPOSED, WELL 6B
(WSWL2077153)
Rated Pump Capacity
Requirements -- Page 1 of 6
DRAFT
NAVAL WEAPON STATION EARLE - CULVERT REPAIRS
Other Limit Requirements
Final Permit Phase
LimitSubject Item Parameter
<= 300 Gallons Per Minute. [N.J.A.C. 7:19- 2]PROPOSED, WELL C
(WSWL2077154)
Rated Pump Capacity
Monitoring Requirements
Subject Item
Final Permit Phase
Monitored Parameter
Monitoring Method
FrequencyRequirement
SHARED METER SOURCES,
ALL DEWATERING WELLS
AND TRENCHES
(WSMS2077885)
Water Diverted
MeterEach MonthThe monthly diversion for each source indicated shall be monitored. [N.J.A.C. 7:19- 2]
Record Keeping Requirements
Subject Item
Final Permit Phase
Monitored Parameter
Record Keeping Method
FrequencyRequirement
NAVAL WEAPONS STATION
EARLE, 1393D TEMP DWP -
ALL DIVERSION SOURCES
(WSWA2077880)
Meter Reading
Log BookEach MonthA log book of month end meter readings for each diversion source shall be maintained on site.
[N.J.A.C. 7:19- 2]
Submittal/Action Requirements
Final Permit Phase
Applicable Subject Items
Submittal/Action Type
Requirement
SHARED METER SOURCES,
ALL DEWATERING WELLS
AND TRENCHES
(WSMS2077885)
Submit Dewatering Quarterly Report
The required monitoring results shall be recorded on the form provided by the Department. The completed form shall be submitted within 30 days after the end of each quarter. [N.J.A.C. 7:19- 2]
PROPOSED, WELL 1A
(WSWL2077142)
Submit Well Drilling Permit Application for Proposed Well
The permittee shall obtain a well drilling permit for each proposed well prior to drilling well . A well drilling permit application shall be submitted to the Well Permitting Section of the Bureau of Water Allocation and Well Permitting, and the Water Allocation Section shall be notified about the submission. No well shall be constructed until the well permit is approved.
[N.J.A.C. 7:19- 2]
Requirements -- Page 2 of 6
NAVAL WEAPON STATION EARLE - CULVERT REPAIRS
Submittal/Action Requirements
Final Permit Phase
Applicable Subject Items
Submittal/Action Type
Requirement
PROPOSED, WELL 2A
(WSWL2077143)
Submit Well Drilling Permit Application for Proposed Well
The permittee shall obtain a well drilling permit for each proposed well prior to drilling well . A well drilling permit application shall be submitted to the Well Permitting Section of the Bureau of Water Allocation and Well Permitting, and the Water Allocation Section shall be notified about the submission. No well shall be constructed until the well permit is approved.
[N.J.A.C. 7:19- 2]
PROPOSED, WELL 3A
(WSWL2077144)
PROPOSED, WELL 4A
(WSWL2077145)
PROPOSED, WELL 5A
(WSWL2077146)
PROPOSED, WELL 6A
(WSWL2077147)
PROPOSED, WELL 1B
(WSWL2077148)
PROPOSED, WELL 2B
(WSWL2077149)
Requirements -- Page 3 of 6
NAVAL WEAPON STATION EARLE - CULVERT REPAIRS
Submittal/Action Requirements
Final Permit Phase
Applicable Subject Items
Submittal/Action Type
Requirement
PROPOSED, WELL 3B
(WSWL2077150)
Submit Well Drilling Permit Application for Proposed Well
The permittee shall obtain a well drilling permit for each proposed well prior to drilling well . A well drilling permit application shall be submitted to the Well Permitting Section of the Bureau of Water Allocation and Well Permitting, and the Water Allocation Section shall be notified about the submission. No well shall be constructed until the well permit is approved.
[N.J.A.C. 7:19- 2]
PROPOSED, WELL 4B
(WSWL2077151)
PROPOSED, WELL 5B
(WSWL2077152)
PROPOSED, WELL 6B
(WSWL2077153)
PROPOSED, WELL C
(WSWL2077154)
NAVAL WEAPONS STATION
EARLE, 1393D TEMP DWP -
ALL DIVERSION SOURCES
(WSWA2077880)
Submit Dewatering Completion Report
The permittee shall submit a completion report including the date the project was completed and abandonment reports for all wells and/or wellpoints used.
The completed report shall be submitted within 60 days of completion of the project. [N.J.A.C. 7:19- 2]
NAVAL WEAPONS STATION
EARLE, 1393D TEMP DWP -
ALL DIVERSION SOURCES
(WSWA2077880)
Submit Renewal Application
A renewal application must be submitted three months prior to the expiration date. [N.J.A.C. 7:19- 2]
Requirements -- Page 4 of 6
NAVAL WEAPON STATION EARLE - CULVERT REPAIRS
Text Requirements
All Phases
NAVAL WEAPONS STATION EARLE, 1393D TEMP DWP - ALL DIVERSION SOURCES (WSWA2077880)
1. A modification of the temporary dewatering permit will be required before diversion may commence from that source once the wells are installed. In order for the wells to be added through a minor modification, every well must meet replacement well criteria in relation to the proposed location, depth, pumping capacity, and aquifer. If any well does not meet replacement criteria a major modification will be required. [N.J.A.C. 7:19- 2]
2. The permittee shall investigate any complaints by users of wells or surface water supplies which become damaged, dry, have reduced capacity, reduced water quality or are otherwise rendered unusable as a result of the permittee's dewatering operations. A report on these investigations shall be forwarded to the Bureau of Water Allocation and Well Permitting.
Those wells or surface water supplies which become damaged, dry, have reduced capacity, reduced water quality or are otherwise rendered unusable as a result of the dewatering operation shall be repaired or replaced at the expense of the permittee. The permittee shall assume financial responsibility for the reparation, or replacement and sealing of such wells which have been rendered unusable and have been abandoned by the owner in accordance with N.J.S.A. 58:4A-4.1. The Department of Environmental Protection will make the final determination regarding the validity of such complaints and will determine how to resolve any problems resulting from the diversion. [N.J.A.C. 7:19- 2]
3. The permittee shall have a contingency plan in place to temporarily supply potable water in the event that the diversion adversely impacts the water supply of other users. [N.J.A.C. 7:19- 2]
4. The total diversion shall be metered with a totalizing flow meter. [N.J.A.C. 7:19- 2]
5. All wells and points shall be examined after use and properly sealed in accordance with N.J.A.C. 7:9D-3.1 et seq. [N.J.A.C.
7: 9D- 3]
6. The Department may modify, suspend or terminate this permit, after due process, for violations of permit conditions, N.J.S.A. 58:1A-1, N.J.A.C. 7:19-1 et seq., any orders issued by the Department, or when in the public interest. [N.J.A.C.
7:19- 2]
7. The permittee is subject to such initial, modification and annual fees as may be prescribed by the regulations. [N.J.A.C.
7:19- 3]
8. The permittee shall have the right to apply at any time for modification of this permit by submission of the appropriate application forms. [N.J.A.C. 7:19- 2]
9. The permittee may informally discuss the terms and conditions of this permit at any time with the Bureau of Water Allocation and Well Permitting. [N.J.A.C. 7:19- 2]
10. This permit is revocable, or subject to modification or change at any time, pursuant to the applicable regulations, when in the judgement of the Department of Environmental Protection of the State of New Jersey such revocation, modification or change shall be necessary. [N.J.A.C. 7:19- 2]
11. The issuance of this permit shall not be deemed to affect in any way action by the Department of Environmental Protection of the State of New Jersey on any future application. [N.J.A.C. 7:19- 2]
12. No change in plans or specifications shall be made except with the prior written permission of the Department of Environmental Protection of the State of New Jersey. [N.J.A.C. 7:19- 2]
13. The granting of this permit shall not be construed to in any way affect the title or ownership of property, and shall not make the Department of Environmental Protection or the State a party in any suit or question of ownership of property. [N.J.A.C.
7:19- 2]
14. This permit does not waive the obtaining of Federal or other State or local government consent when necessary. This permit is not valid and no work shall be undertaken until such time as all other required approval and permits have been obtained. [N.J.A.C. 7:19- 2]
15. A copy of this permit shall be kept at the work site, and shall be exhibited upon request of any authorized Department representative. [N.J.A.C. 7:19- 2]
Requirements -- Page 5 of 6
NAVAL WEAPON STATION EARLE - CULVERT REPAIRS
Text Requirements
All Phases
NAVAL WEAPONS STATION EARLE, 1393D TEMP DWP - ALL DIVERSION SOURCES (WSWA2077880)
16. The Department has the right to enter and inspect any site, building, or equipment, or any portion thereof, owned or operated by the permittee, at any time, in order to ascertain compliance or noncompliance with N.J.S.A. 58:1A-1 et seq., 58:4A-4.1 et seq., 58:12A-1 et seq., these rules, or any other agreement or order issued or entered into pursuant thereto.
Such right shall include, but not be limited to, the right to require the testing of any equipment at the facility, to sketch or photograph any portion of the site, building or equipment, to copy or photograph any document or records necessary to determine such compliance or noncompliance, and to interview any employees or representative of the owner, operator, or permittee. Such right shall be absolute and shall not be conditioned upon any action by the Department, except the presentation of appropriate credentials as requested and compliance with appropriate standard safety procedures. [N.J.A.C.
7:19- 2]
17. This permit may be transferred, with the consent of the Department, but only for the identical use of the waters. [N.J.A.C.
7:19- 2]
18. If the authorized diversion privileges are not currently diverted, subject to contract, or reasonably required for a demonstrated future need, they shall revert back to the State upon renewal or modification of the permit. [N.J.A.C. 7:19- 2]
19. The permittee shall protect each source from vandalism, tampering, and contamination at all times. [N.J.A.C. 7:19- 2]
20. This permit shall expire as indicated on the permit approval cover page. [N.J.A.C. 7:19- 2]
Requirements -- Page 6 of 6