Amendment 0005.pdf

PDF 168 KB Posted

Attached to
P898, REPLACE PIER 32 AT NAVSUBASE NEW LONDON, CT
Solicitation number
N4008520R0037
Issued by

View the file

Other files

File Type Posted
Amendment 0010.pdf PDF
Amendment 0009.pdf PDF
Amendment 0008.pdf PDF
Amendment 0007.pdf PDF
Amendment 0006.pdf PDF
Site Visit Log.pdf PDF
Amendment 0004.pdf PDF
Amendment 0003.pdf PDF
dwg 7of11 structural 2of2 R9.pdf PDF
dwg 7of11 structural 2of2 R7.pdf PDF
dwg 7of11 structural 2of2 R8.pdf PDF
Amendment 0002.pdf PDF
dwg 9of11 electrical 1of2.pdf PDF
dwg 8of11 structural utility fire protection mechanical.pdf PDF
dwg 4of11 civil.pdf PDF
dwg 6of11 structural 1of2.pdf PDF
dwg 3of11 geotechnical 2of2.pdf PDF
dwg 5of11 civil dredge.pdf PDF
dwg 2of11 geotechnical 1of2.pdf PDF
dwg 10of11 electrical 2of2.pdf PDF
dwg 1of11 general survey.pdf PDF
dwg 11of11 reference.pdf PDF
Amendment 0001.pdf PDF
Attachment A - Pre-Proposal Inquiry Form.xlsx XLSX spreadsheet
1565917 spc 1of1_appendix c.pdf PDF
1565917 spc 1of1.pdf PDF
Attachment B_SECNAV_5512_1_11787.pdf PDF
1565917 spc 1of1_appendix a 2of3.pdf PDF
1565917 spc 1of1_appendix g.pdf PDF
Solicitation No. N4008520R0037.pdf PDF
Attachment C - Construction Experience Project Data Sheet.docx DOCX document
Attachment G - Small Business Participation and Commitment Strategy.docx DOCX document
Attachment D - Past Performance Questionnaire.docx DOCX document
1565917 spc 1of1_appendix a 3of3.pdf PDF
Attachment F - Small Business Subcontracting Record.docx DOCX document
1565917 spc 1of1_appendix e.pdf PDF
Attachment E - Small Business Subcontracting Plan.docx DOCX document
1565917 spc 1of1_appendix f 2of2.pdf PDF
1565917 spc 1of1_appendix a 1of3.pdf PDF
1565917 spc 1of1_appendix f 1of2.pdf PDF
Attachment H - Price Proposal.docx DOCX document
1565917 spc 1of1_appendix b.pdf PDF
1565917 spc 1of1_appendix d.pdf PDF
Show all 43

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Design-Bid-Build, P898 Replace Pier 32 at NAVSUBASE New London, CT

The purpose of this amendment is to provide the follow ing:

1. Response to PPIs.

See SF 30 Block 14 Continuation Page

1. CONTRACT ID CODE PAGE OF PAGES

J 1 9

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 29-Apr-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008520R0037

X 9B. DATED (SEE ITEM 11)

07-Apr-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

29-Apr-2020

CODE

NAVFAC MID ATLANTIC

ACQUISITION CORE

9324 VIRGINIA AVENUE

NORFOLK VA 23511-3095

N40085 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008520R0037

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

BLOCK 14 CONTINUATION PAGE

The purpose of this amendment is to provide the following:

1. Response to PPIs.

1. Response to PPIs:

PPI

Date Submitted

Reference

Question Response Leave Blank

Page Section Paragraph

1 04/09/20 of 57

(1) Factor 1, Corporate Experience

Size: A final construction cost of $30,000,000 or greater.

Given the construction disciplines required for this project and the relatively few projects of this magnitude and complexity that have been performed over the last 10 years in the U.S., please consider reducing the minimum size of contract required to meet the experience criteria to $25,000,000.

Yes. See Revised Factor 1 listed in Amendment 0004

4 04/21/20 Sheet G006

Drawings Note 6

General note No.6 on sheet G006 says Contractor shall obtain all applicable permits. It appears that NAVFAC has already obtained the regulatory permits. Please clarify what permits are being referred to here.

Refer to Specifications for permit requirements (General Permit for Discharge of Groundwater Remediation Wastewater, Dig Permit, Hot Work Permit, etc.)

5 04/21/20 SF1442

Please clarify how many "copies" of the offer should be submitted. We noticed in section 13 of SF 1442 it says 4 copies, Section 3 on page 6 says 1 copy, and page 8 says 5 copies.

Paragraph 3, Page 6 refers to the 'Price' proposal (original and one copy).

Regarding 'Non- Price' Proposal, follow instructions provided in Section 13, Page 1 of SF 1442.

Provide original and 4 copies of 'Non-Price' Proposal.

6 04/21/20 Sheet S121

Drawings

Is the relocation of the floating security barrier near the crane weight test area to be included in Option 5 or part of the base scope?

Relocation of the floating security barrier near the crane weight test area (Buoy V) as shown on Drawing S-121 shall be included as part of the Base Bid.

7 04/21/20 Sheet S002

Drawings Note 12

Note 12 on sheet S- 002 states that the pile obstruction mitigation items are considered as part of CLIN 0001A. A quantity of (7) is stated in Note 11 of the same page.

Please clarify - Are we supposed to include (7) each in Item CLIN 0001A and Item CLIN 0001I is the unit price for an addition

(7) each, or is note 12 a mistake and all obstruction mitigation is to be included in Item

CLIN 0001I?

Note 12 on Drawing S-002 is in error. The pile obstruction mitigation (7 total) should be included in CLIN 0001I instead of CLIN 0001A as indicated.

8 04/21/20

1-4 MM

Plan 01 35 40.00 25 3

Are the Marine Mammal Observers, including the vessels, hired by the Contractor, or are they being provided by the Client?

They are to be provided by the Contractor

9 04/21/20

4-1 MM

Plan 01 35 40.00 25 4

Is the Acoustic monitoring and dedicated vessel hired by the Contractor, or being provided by the Client?

They are to be provided by the Contractor

10 04/21/20 1 SF1442 Section 13

Due to the complex nature of the scope of work, the variety of documents, and the decrease in productivity with working at home provisions because of the COVID19 pandemic, we respectfully request a four (4) week extension from the current bid due date of May 21, 2020.

This will also allow for the much needed time of soliciting and evaluating potential Small Business Subcontractors and Suppliers.

No

11 04/21/20 7 SF1442 3

Are the Small Businesses that count toward the Small Business Contracting goals required to be certified by specific agencies? For instance, do local DOT certified companies count toward the goals or are only Federally certified companies (i.e. companies listed in the SBA.GOV registry) allowed to count toward goals?

Companies must be registered on sam.gov and have the required Small Business Adminstration (SBA) certification in order to be eligible for federal contracts; Only federally registered companies will count for the NAVFAC-Midlant Small Business goals.

12 04/21/20 Sheet S002

Drawings Note 1

Note 1 under "Foundation Notes - Steel Pipe Piles" on Drawing S-002 states that PDA piles shall be driven with the first 10% of production piles, however Specification 31 62 16.19, Section 3.4.1 states that the PDA piles shall be driven first and a refined WAVE equation be completed before we finalize the pile order length.

Please clarify what the Client's intent is.

Can the PDA's be driven among the other production piles or must they be driven prior to ordering the rest of the production piles?

PDA test piles shall be installed in accordance with Specification Section 31 62 16.19, Paragraph 3.4.1.

13 04/21/20 6 31 63 29 1.7.1

Please confirm that soils excavated from Steel Pipe piles and drilled shafts are to be disposed at the CAD Cell in the Thames River.

Disposal of the soils excavated from pile installation operations into the CAD Cell is not required.

14 04/21/20 6 31 63 29 1.7.1

Regarding the time requirements in Section 1.7.1 of Specification 31 63 29, please confirm that the requirement for open excavations only applies to the rock socket portion below the tip of the steel casing.

Confirmed, the same day restriction only applies to the rock socket portion of the Drilled Shaft.

15 04/21/20 7 31 63 29 2.3.4, 2.3.5

Is CSL Testing and Thermal Integrity Testing required for both the Drilled shafts with rock sockets and the driven piles that are concrete filled, or just the drilled shafts? If required in the driven piles, please confirm that the length of CSL and thermal wires is only the length of the short rebar cage.

CSL and Thermal Integrity Testing is for the Drilled Shaft Construction only.

16 04/21/20 Sheet S002

Drawings Note 14

Please confirm that eight (8) CSL tubes are required in these 36" diameter shafts. The drawings don't show the CSL spacing, but the notes mention a quantity of eight (8) which seems like a lot of tubes for this diameter shaft.

The number of CSL tubes could be reduced to four (4).

17 04/21/20 8 31 63 29 3.2.2

Referencing section 3.2.2, Specification 31 63 29, is the Contractor's Geotechnical Inspector required on site full time during drilled shaft installation to complete the logs?

Full-time monitoring may or may not be required. The stated requirement is . . . "The Contractor's Geotechnical Inspector shall maintain construction method log during shaft excavation.

The log shall contain information such as:the description and approximate top and bottom elevation of each soil or rock material, level of water, and remarks." The Contractor's geotechnical inspector must be able to observe and document the above.

18 04/23/20 Appendix C -

Permit Documents

Referring to Appendix C water quality and USACE permits, it is not clear whether only the "cap" material placed in the CAD cell needs to be placed via tremie tube method, or all disposed material needs to be placed with a tremie tube.

Item 2 on page 3 of 3 of the water quality certificate seems to indicate all sediment needs to be placed in the CAD cell with a tremie tube. Page 2 of 6, Item 5. talks about point-dumping of barges.

Finally, the USACE Corps memorandum only talks about the cap being placed with a tremie tube. Please confirm if all material, or just the cap material needs to be placed with a tremie tube.

Only capping material is required to be placed into the CAD cell via a tremie pipe.

19 04/23/20 S-502 Drawings B1

Regarding the HDPE pipe sleeves, 40” OD pipe with 1” wall is not a standard pipe size in the US. Is there an identified source in the United States that can be provided? If not, is the intent to have custom size sleeves manufactured in the US or to source the

HDPE

internationally?

The Contractor is allowed to utilize a standard size HDPE pipe sleeve (i.e. 42" dia OD) or have the sleeves custom manufacturered to the size indicated on the project drawings. Note that if a standard size HDPE sleeve is utilized, the minimum grout fill at annulus shall be 1" as is currently shown on the drawings.

20 04/23/20 7

Appendix C - Permit

Documents;

Spec. 01 14 00

1.4.5

The language in the permit documents state that unconfined in-water excavation, dredging, filling or removal of debris or other material is prohibited in any year from February 1 to September 30.

Similar language is included in Specification 01 14

00. Since the language does not mention pile installation, please confirm that there are no in-water restrictions for the installation of piles and shafts.

The Time-of-Year- Restrictions do not apply to pile installation.

However, contractor must follow the requirements in the contract documents for turpidity curtains and turbidity monitoring.