This document contains an amendment to a federal solicitation for construction services. The amendment provides responses to pre-award inquiries regarding requirements for corrosion protection of HVAC equipment, factory finishes for exhaust systems, foundation criteria, and stormwater management across four projects. The solicitation seeks to replace facilities damaged by Hurricane Florence at Marine Corps Air Station New River in North Carolina, including a CNATT classroom building, bachelor enlisted quarters, CH-53K maintenance hangar, and C-12W aircraft maintenance hangar. The deadline for proposals remains unchanged, with submissions due through the DoD SAFE system.
View the file
Other files
Show 40 more
Latest 50 of 52 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this Amendment is to provide responses to PPIs # 366, 446-450, 452-454, 456, and 459-464.
The proposal due date remains unchanged.
The DoD SAFE Submission of the proposal w ill be used to determine timeliness.
See SF30 Block 14 Continuation Page.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 12-May-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008519R9257
X 9B. DATED (SEE ITEM 11)
15-Nov-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
12-May-2020
CODE
NAVFAC MID ATLANTIC
ACQUISITION CORE
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3095
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008519R9257
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0008
On RFP, Part 3a/3b/3c/3d (all projects), Section 6.0 Engineering System Requirements, ESR D30 HVAC, General System Requirements
Revise the following paragraph to read, “Provide corrosion protection for ALL exterior HVAC equipment, including air-handling units (AHUs), heat exchanger coil surfaces, equipment casings, air-cooled water chiller coils, heat pumps, and air conditioning units that are exposed to the weather. Corrosion protection is also required on HVAC equipment within buildings that are subject to the outside weather conditions. Specifically, equipment requiring protection is defined as the first HVAC equipment (unit coils) met by the outside air in the supply air ductwork system. The corrosion protection must meet or exceed the requirements of a 6000 hour salt spray test in accordance with ASTM International (ASTM) B117. The specified capacities on the plans and specifications must be the capacities after the required corrosion protection coatings are applied. Specify manufacturer's standard off-the-shelf anti-corrosion options for "coastal" or "sea coast" installations that meet or exceed the requirements stated above.”
On RFP, Part 3a/3c (CH53K & C12W Hangar projects), Section 6.0 Engineering System Requirements, ESR D30 HVAC, D304007 Exhaust Systems
Revise the following paragraph to read, “Provide factory painted finishes that are designed for 6000-hour duration test for outside equipment and for equipment bringing in outside air.”
On RFP, Part 3b/3d (BEQ & CNATT Projects), Section 6.0 Engineering System Requirements, ESR D30 HVAC, D304007 Exhaust Systems
Add the following paragraph, “Provide factory painted finishes that are designed for 6000-hour duration test for outside equipment and for equipment bringing in outside air.”
On RFP, Part 3c, ESR A10 Superstructure, Section A1010 Standard Foundations
Revise the following sentence to read, “Surcharge material, if required, must remain in place for a duration as directed by the Contractor’s geotechnical engineer.”
(End of Summary of Changes)
SOLICITATION NO. N40085‐19‐R‐9252
PROJECT TITLE/LOCATION: HFRM PACKAGE 2
PREAWARD INQUIRY FORM (TEMPLATE)
Page Section Para.
366 4/21/2020
P378 Part 3 Chapter
6 / ESR
D30 / Section D304007
Please confirm factory finish durability requirements. The General System Requirements indicate 3,000 hour salt spray testing. However, this section indicates 5,000 hours.
Provide coatings capable of withstanding a 6,000 hour salt spray.
See Amendment 0008.
446 4/29/2020
1353 of
VOL 1,
Part 3, CH
D304008
(P695 CNATT) Is there a requirement to provide a dedicated Trainer Bay Mechanical Room or can the Trainer Bay equipment be placed in the same mechanical room with equipment serving the rest of the building (as long as heat‐producing and cold equipment is separated per RFP requirements)?
The CNATT Arch Concept Diagram in Part 6, Attachment C shows a Trainer Mech Room.
447 4/29/2020
836 of
VOL 1,
Part 3, CH
Space Tabulation
(P707 BEQ) The Space Tabulation table for Marine Corps 2+0 Room lists Unit SF (Net) as “257.” FC 4‐721‐10N Section 5‐3 Marine Corps 2+0 Room “Net Living/Sleeping Area" indicates "180 ft2 (16.7 m2) is the required MINIMUM size per bedroom", and Section 5‐3.1 “Personal Closets" indicates "22ft2 (2m2) Net area required ‐ Provide at least one (1) closet for each resident."
Based on the required net living/sleeping area, the net personal closet area, and the remainder of the required unit spaces in Figure D‐6 Marine Corps 2+0 Room (Interior Access), the net square footage exceeds the Net SF listed in the RFP. Please confirm if the unit spaces can be reduced to reach the RFP net square footage and if so what percentage can they be reduced.
See response to PPI #397 and amendment to the space tabulation form to show the 2+0 unit net SF maximized within the SF max requirements of the 1391. Final building space sizes to be coordinated with users during project design.
REFERENCE
Question No. QUESTION GOVERNMENT RESPONSEDate Received
Posted on Amend No.
July 2011
PREAWARD INQUIRY FORM (TEMPLATE)
Page Section Para.
Question No. QUESTION GOVERNMENT RESPONSEDate Received
Amend No.
448 4/29/2020
837 of 2523;
873 of
VOL 1,
Part 3, CH 4 and 5
Space Tabulation; 5.0 Room Requirements
(P707 BEQ) The Space Tabulation table for Corridors indicates “Minimum 60” clear corridors. Final SF required by building layout and code requirements.” Page 873 of 2523 Part 3, Chapter 5 "Room Requirements: Circulation – Corridor" indicates "Special Dimensions: Ideal Plan Dimensions: 5’‐0” minimum width. Corridor width and capacities must meet Life Safety Code NFPA 101 for minimum capacities (typical).” Please confirm that while 5’‐0” corridors are ideal, the minimum corridor width can be reduced to the width and capacities required by Life Safety Code NFPA 101
Min 5'‐0" wide corridors are required per RFP.
449 4/29/2020
840 of
Bunk Room 2+0 Room
5.0 Room
Requirements
(P707 BEQ) Chapter 5 "Room Requirements: Bunk ‐ 2+0 Room, B202001 Exterior Windows" indicates “Provide windows for natural light emission. Window area shall be a minimum 30% of the exterior wall surface.” FC 4‐721‐10N Figure D‐6 indicates a window of approximately 4 feet wide based on the scale given, but there is no indication of the height. Please confirm that “Exterior Wall Surface” refers to the linear dimension (width) of the exterior wall within the unit and not the entire area (room width times the interior ceiling height) of the exterior wall within the unit.
Concur that 30% of the exterior wall does not match Figure 6. Howevever, window SF based on 30% of wall area can be achieved and is required per FC 4‐721‐10N, section 3.19. There is no indication in the FC that the 'exterior wall surface' should refer to the linear width of the ext wall vs the entire area of each unit. Bid per RFP direction.
450 4/29/2020
1244 of
VOL 1,
Part 3, CH
3.2.10
(P695 CNATT) In accordance with 3.2.10 we are to tie our stormwater system into the existing system along McAvoy Street. Can we assume that the system is sufficiently deep enough for drainage from both sides of McAvoy to flow by gravity? The utility drawing provided on Volume 1 sheet 2502 of 2523 does not indicate existing storm sewer invert elevations.
Are there any limitations on size of pipe we can utilize when tie‐ ing into this system? Are there any limitations on flow rate at the point of tie‐in?"
A utility survey will need to be performed following award to determine the inverts and capacity of the existing storm drain system. For bidding purposes assume system is adequately sized for P695 project and gravity connection can be made.
452 4/29/2020
Can the P707, P728, and P695 projects be constructed concurrently with the P378 Infiltration Pond?
The P378 and P707 construction can be performed concurrently with the infiltration BMP construction. P695 and P728 must follow the approved permit requirements, once determined.
PREAWARD INQUIRY FORM (TEMPLATE)
Page Section Para.
Question No. QUESTION GOVERNMENT RESPONSEDate Received
Amend No.
453 4/29/2020
685 of
VOL 1,
Part 3, CH
C3020
(P378, P728) Para C3020 Floor Finishes indicates the 3‐coat fuel resistive epoxy coating system to have a "decorative flake broadcast system appropriate for use as indicated." The 3‐coat system is specified for all corridors and for various 2nd floor spaces in the P378 CH‐53K Hangar. In our experience the flakes cause difficulty in identifying small parts on the floor. Can the Government please confirm they desire use of flake in the 3‐coat epoxy flooring system?
Yes, use flake in 3‐coat epoxy flooring system.
454 4/29/2020 (P378, P695, P7070, P728) The original RFP documents and Amendment 05 contain conflicts regarding which projects are required to implement site specific BMP measures and which projects can instead deduct stormwater credits from the P378 Stormwater Infiltration Pond. Will the Government please clarify?
P728 project would require its own storm water BMPs. P695 and P707 will utilzed credites associated with the new stormwater pond.
456 4/29/2020
10 of 14 Att F CLIN 0027
This CLIN states "Price provision of extending the Hangar Door Pocket to not block the entryways so that all of the aircraft could exit the buildlng at once." The base bid project requirements already require this. Will the Governmet please explain what scope of work this CLIN is supposed to capture?
See PPI Response 193. 8
PREAWARD INQUIRY FORM (TEMPLATE)
Page Section Para.
Question No. QUESTION GOVERNMENT RESPONSEDate Received
Amend No.
459 4/29/2020
659, 1314, 887, and 1092 of
VOL 1,
Part 3, CH
A1010
(P378, P695, P707, P728) Paragraph A1010 "Standard Foundations" indicates "Cast in place concrete slabs on grade post construction total settlement due to permanent loads shall be limited to 1/2 inch." It is the professional opinion of our structural and geotechnical design team that this criteria is unusual in the industry and will lead to excessive cost in construction of the foundation system for these facilities. Given the geotechnical data provided in the RFP, limiting total settlement to a maximum 1/2 inch would impact both cost and schedule by either requiring construction of a structurally supported slab at grade or by placement and monitoring of surcharge that would add a minimum 90 days to each project's construction duration. USACE EM 1110‐1‐1904 Settlement Analysis para 2‐2 states that total settlement should not exceed 2 inches for most facilities, and that a typical specification for total settlement for commercial buildings is 1 inch. Para 2‐3 goes on to state that differential settlement should not usually exceed ½ inch. Will the Government accept a maximum total settlement value of 1 inch in lieu of ½ inch?
Bid per RFP 8
PREAWARD INQUIRY FORM (TEMPLATE)
Page Section Para.
Question No. QUESTION GOVERNMENT RESPONSEDate Received
Amend No.
460 4/29/2020
659, 1314, 887, and 1092 of
VOL 1,
Part 3, CH
A1010
(P378, P695, P707, P728) Paragraph A1010 "Standard Foundations" states "The Contractor's Geotechnical Engineer is responsible for evaluating potential global settlement due to designed grade increases and final structural loads and must develop any settlement mitigation procedures needed to maintain global settlements within tolerable limits. Surcharge material, if required, must remain in place for a minimum of 90 days." The paragraph goes on to indicate "Cast in place concrete slabs on grade post construction total settlement due to permanent loads shall be limited to 1/2 inch." Without site specific soil dissipation testing results, it is not possible for the design team to determine the amount of surcharge needed nor the duration of surcharge loading to meet the stringent 1/2 inch maximum settlement criteria. This uncertainty and lack of technical data represent significant cost and schedule risks for both the Government and the contractor and will potentially result in large differences in bids amounts as some offerors may chance a more risky but economical approach to foundation design in order to drive their price down. In order to effect a level playing field among offerors, we recommend that the Government provide a separate CLIN for site surcharge at a specified depth and duration for each project, as well as a separate CLIN for providing a structured slab‐at‐grade vice unstructured slab‐on‐grade for each project. In this way, once full geotechnical investigations have been completed post‐ award, the Government could elect to award or decline these options with costs and benefits fully understood.
PREAWARD INQUIRY FORM (TEMPLATE)
Page Section Para.
Question No. QUESTION GOVERNMENT RESPONSEDate Received
Amend No.
461 4/29/2020
659 of
VOL 1,
Part 3, CH
A1010
(P378, P695, P707, P728) Paragraph A1010 "Standard Foundations" states "The Contractor's Geotechnical Engineer is responsible for evaluating potential global settlement due to designed grade increases and final structural loads and must develop any settlement mitigation procedures needed to maintain global settlements within tolerable limits. Surcharge material, if required, must remain in place for a minimum of 90 days." The paragraph goes on to indicate "Cast in place concrete slabs on grade post construction total settlement due to permanent loads shall be limited to 1/2 inch." Without site specific soil dissipation testing results, it is not possible for the design team to determine the amount of surcharge needed nor the duration of surcharge loading to meet the stringent 1/2 inch maximum settlement criteria. The geotechnical investigation reports provided in Volume 15 do not include this information.
In order for contractor's to make a consistent evaluation of the required surcharge amount and duration for each site will the Government provide soil dissipation values to assume for the subgrade soils at each site for bidding purposes?
PREAWARD INQUIRY FORM (TEMPLATE)
Page Section Para.
Question No. QUESTION GOVERNMENT RESPONSEDate Received
Amend No.
462 4/29/2020
1017 of 2523;
1091 of 2523;
1092 of
VOL 1,
Part 3, CH 3 and 6
3.2.15.1, A1010, A1040
[P728 C12W Hangar) Based on USGS topographical maps, the elevation of the existing taxiway immediately to the west of the hangar site is approximately 3+ feet above existing grade at the new hangar footprint. In order to accommodate the elevation of the adjacent apron, the finish floor elevation of the C12W Hangar will then need to be approximately 3+ feet above existing grade. Para 3.2.15.1 "Criteria for Bidding" states "surcharging with monitoring will be provided to address global consolidation settlement associated with site grading impacts in areas where finished site grade increases are more than 2 feet above existing grades." Para A1010 "Standard Foundations" states "surcharge material, if required, must remain in place for a minimum of 90 days." If deemed acceptable by the Contractor's geotechnical engineer based on field testing, will the Government allow the Contractor to proceed with construction of a 1st floor Structurally Supported Slab in accordance with A1040 without having to wait the 90+ days of monitoring the settlement of the fill required to meet finish floor elevation?
Bid per RFP 8
463 4/29/2020
574 of
VOL 1,
Part 3, CH 3 and 6
3.2.15.2
(P378) Paragraph 3.2.15.2 "Earthwork and Site Preparation Criteria" states "Excavated existing on‐site soils will only be reused as common/general fill beyond the limits of surface bearing structures (i.e. pavements, buildings, pipe trenches, etc.)
and beyond the limits of any undercut excavations, provided the material meets the project requirements. All soil material must exhibit the characteristics required to compact the soil to the density and performance specified for the intended locations.
Excavated on‐site soils will be reworked and amended (i.e. mixed with lime, cement, or blended with imported structural materials, etc.) as necessary to facilitate reuse as fill material." If deemed acceptable by the Geotechnical Engineer, will it be acceptable to use soils excavated from the Infiltration Pond project, modified if necessary, for deeper levels of fill placement required at the Airfield Apron up to a specified distance (e.g., 6 feet) below the bottom of new pavement base?
Bid per RFP; If there are suitable materials that meet the requirements of the RFP for reuse from required excavations to construct the infiltration basin, they may be reused
PREAWARD INQUIRY FORM (TEMPLATE)
Page Section Para.
Question No. QUESTION GOVERNMENT RESPONSEDate Received
Amend No.
464 4/29/2020
659 of
VOL 1,
Part 3, CH
A1010
(P378 Garage) Paragraph A1010 "Standard Foundations" indicates "Cast in place concrete slabs on grade post construction total settlement due to permanent loads shall be limited to 1/2 inch." Does this apply to the parking garage first floor?
see response in PPI #459 8
| Amendment 0008 |
| Phase II - PPI Log Master |