Amendment 0002.pdf
PDF 153 KB Posted
- Solicitation number
- N4008519R9257
About this file
This amendment modifies a solicitation for Hurricane Florence Recovery Facilities at Marine Corps Air Station New River in North Carolina. The scope of work includes replacement facilities for classrooms, bachelor enlisted quarters, CH-53K helicopter maintenance hangars, and C-12W aircraft maintenance hangars. The amendment extends the proposal due date to December 20, 2019, reduces the required font size in non-price proposals from 12-point to 10-point, clarifies that experience must be as a prime contractor, defines relevant experience as single facilities rather than complexes, and modifies experience requirements for construction and design of hangars.
View the file
Other files
Show 40 more
Latest 50 of 52 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
See Continuation.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 12-Dec-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008519R9257
X 9B. DATED (SEE ITEM 11)
15-Nov-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
12-Dec-2019
CODE
NAVFAC MID ATLANTIC
ACQUISITION CORE
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3095
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008519R9257
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0002
This amendment hereby incorporates the following:
1. Extends proposal due date to Friday, 20 December 2019 by 2 pm local time.
2. PPI Responses
1. Incorporates Revision: 3. Basis of Evaluation and Submittal Requirements for Each Factor, b. Non-price Factors, (1) Solicitation Submittal Requirements:
From:
Non-price binder: The offeror shall submit one (1) original, marked “Original”, and nine (9) copies, marked “Copy”, each in a separate three ring binder with the following:
• Cover page with Solicitation Number, Solicitation Title, Prime Contractor Name, Address, Phone Number, Fax Number, DUNS, CAGE Code, Point of Contact, Phone Number, and Email Address;
• 8 ½ x 11 paper, 12-point font;
• Refer to individual factors for page limitations. Pages that exceed indicated page limitations shall not be evaluated; and
• Additionally, include an electronic version of the price and non-price proposal on one
CD-ROM.
To:
Non-price binder: The offeror shall submit one (1) original, marked “Original”, and nine (9) copies, marked “Copy”, each in a separate three ring binder with the following:
• Cover page with Solicitation Number, Solicitation Title, Prime Contractor Name, Address, Phone Number, Fax Number, DUNS, CAGE Code, Point of Contact, Phone Number, and Email Address;
• 8 ½ x 11 paper, 10-point font;
• Refer to individual factors for page limitations. Pages that exceed indicated page limitations shall not be evaluated; and
• Additionally, include an electronic version of the price and non-price proposal on one
CD-ROM.
2. Revision: 3. Basis of Evaluation and Submittal Requirements for Each Factor, b. Non-price Factors, Factor 2 – Experience, (1) Construction Experience From:
Projects submitted for the Offeror shall be completed within the past ten (10) years of the date of issuance of this RFP. Furthermore, the offeror must have been the prime contractor on the project. As such, the offeror’s experience as a subcontractor will not be considered. Further, subcontractor experience will not be considered.
To:
Projects submitted for the Offeror shall be completed within the past ten (10) years of the date of issuance of this RFP. Furthermore, the offeror must have been the prime contractor on the project. Projects completed outside of this window will be considered “Not Relevant.” Furthermore, the offeror must have been the prime contractor (Block 4, Attachment C) on the project. As such, the offeror’s experience as a subcontractor will not be considered. Further, subcontractor experience will not be considered.
3. Addition: Revision: 3. Basis of Evaluation and Submittal Requirements for Each Factor, b. Non-price Factors, Factor 2 – Experience, (1) Construction Experience Added:
Note: For the purpose of this evaluation, a “facility” is considered to be a single building; a facility is not a compound, complex, or campus. Square Footage must be specifically provided per relevant facility type. A total square footage of a compound, complex, or building containing multiple facility types is not sufficient and will be considered Not Relevant.
4. Revision: Revision: 3. Basis of Evaluation and Submittal Requirements for Each Factor, b. Non-price Factors, Factor 2 – Experience, (2) Design Experience From:
Large Project
Submit one (1) relevant construction projects for the Offeror that best demonstrates your experience on relevant projects that are similar in size, scope, and complexity to the RFP. For purposes of this evaluation, a relevant project is further defined as:
Size/Scope/Complexity: Design of the New Construction of a single facility, multiple facilities, compound, campus, installation, or complex with a construction cost of $200,000,000 or greater. Renovation projects will not be considered relevant. Additionally, projects submitted that only include horizontal, civil site work, single-system work, or demolition will not be considered relevant.
To:
Submit one (1) relevant construction projects for the Designer of Record(s) that best demonstrates your experience on relevant projects that are similar in size, scope, and complexity to the RFP. For purposes of this evaluation, a relevant project is further defined as:
Size/Scope/Complexity: Design of the New Construction of a single facility, multiple facilities, compound, campus, installation, or complex with a construction cost of $200,000,000 or greater. Renovation projects will not be considered relevant. Additionally, projects submitted that only include horizontal, civil site work, single-system work, or demolition will not be considered relevant.
5. From:
Projects submitted shall be completed within the past ten (10) years of the date of issuance of this RFP.
For design-build projects, the design portion of the contract shall have been completed within the past ten
(10) years of the date of issuance of this RFP. The design completion date shall be clearly stated on the Construction & Design Experience Project Data sheet under Block 4 next to “Design Completion Date.”
To:
Projects submitted shall be completed within the past ten (10) years of the date of issuance of this RFP.
For design-build projects, the design portion of the contract shall have been completed within the past ten
(10) years of the date of issuance of this RFP. Projects completed outside of this window will be considered “Not Relevant.” The design completion date shall be clearly stated on the Construction & Design Experience Project Data sheet under Block 4 next to “Design Completion Date.”
6. Addition: Revision: 3. Basis of Evaluation and Submittal Requirements for Each Factor, b. Non-price Factors, Factor 2 – Experience, (2) Design Experience Added:
Note: For the purpose of this evaluation, a “facility” is considered to be a single building; a facility is not a compound, complex, or campus. Square Footage must be specifically provided per relevant facility type. A total square footage of a compound, complex, or building containing multiple facility types is not sufficient and will be considered Not Relevant.
Reference Inquiry Government Response
Page Sec tion
Paragraph
13 2 Large Project
(2) Design Experience - Requirements read: "Submit one (1) relevant construction project for the Offeror that best demonstrates our experience on relevant projects that are similar in size, scope, and complexity to the RFP…." Please confirm this is meant for the Designer of Record and not the Offeror.
SEE AMENDMENT 0002
and of
Factor 2 - Experience, (1) Construction Experience, Aircraft Hangar and
(2) Design Experience, Aircraft Hangar
Based on the proposed P378 Type II Hangar project description, we believe that design and construction experience of large, multi-module hangars would be most relevant to this RFP. Historically, UFC 4-211-01 has defined the standard hangar bay module for a type II hangar to be 119’X325’. A typical two-module type II hangar would range in size from approximately 70,000 square feet but less than 100,000 square feet. In our experience, the design and construction of multi-module hangars in this size range involve the same scope/complexity as those above a 100,000 square feet threshold, especially in critical areas like architectural/structural design and construction, aviation-specific systems, including MEP, built-in equipment, bridge cranes, specialty hangar doors, etc.
To increase highly qualified competition, we respectfully request that the size requirement for hangar projects be reduced to 70,000 SF.
Bid per the RFP.
(End of Summary of Changes)