About this file

This amendment modifies a solicitation for design-build construction services at Camp Lejeune in North Carolina. The solicitation seeks a firm-fixed price contract to construct several low-rise steel frame facilities including a battalion headquarters, automotive vehicle maintenance shop, humidity controlled warehouse, electronics communications maintenance shop, combat vehicle maintenance shop, and armory addition. The project also includes construction of a high-explosive magazine. The completion schedule is 934 calendar days with a proposal due date of October 8, 2019. The amendment provides responses to pre-proposal inquiries, maintaining the same due date. The related federal contract opportunity notice identifies the solicitation number and describes the project scope in further detail, including requirements for anti-terrorism and force protection features. The contracting agency is the Naval Facilities Engineering Command Mid-Atlantic.

AMENDMENT_0001.pdf

View the file

Other files

File Type Posted
Amendment 0008.pdf PDF
Attachment H - Price Proposal Form (005) - Amendment 0008.pdf PDF
Amendment 0007.pdf PDF
PPI 41 HIMARS Battery Vehicle List.pdf PDF
PPI 43 Designer's Cert.pdf PDF
PPI 75 P1495 Magazine Revised Exhibit.pdf PDF
PPI 43 DWQ Permit Renewal.pdf PDF
PPI 43 Pond Drawings.pdf PDF
Attachment H - Price Proposal Form (004) - Amendment 0006.pdf PDF
AMENDMENT 0006.pdf PDF
PPI 43 DWQ Permit.pdf PDF
WATER FLOW TEST FOR HP500.pdf PDF
AMENDMENT 0005.pdf PDF
2020_01_02_BUILDING_1445_PPI_49.pdf PDF
Attachment H - Price Proposal Form (003).docx DOCX document
2020_01_02_HIMARS_SITE_PPI_53.pdf PDF
WATER FLOW TEST FOR NEW SITE.pdf PDF
P1495 Site Visit.pdf PDF
2020_01_02_HIMARS MAGAZINE_PPI_54.pdf PDF
Amendment 0004 Attachment H - Price Proposal Form.pdf PDF
AMENDMENT 0004.pdf PDF
AMENDMENT 0004 24592 20181026 5090 21 ESS DR P1495.pdf PDF
AMENDMENT 0004 ESSDR_P1495_SYSCOM_Apvl20181105.pdf PDF
AMENDMENT 0003.pdf PDF
Attachment F - Small Business Participation and Commitment Strategy.docx DOCX document
Attachment E - Small Business Subcontracting Record.docx DOCX document
Attachment H - Price Proposal Form.pdf PDF
Attachment G- SBSP Template.doc DOC document
1611501rfp02of05.pdf PDF
1611501rfp01of05.pdf PDF
1611501rfp05of05.pdf PDF
1611501rfp03of05.pdf PDF
Amendment 0002.pdf PDF
1611501rfp04of05.pdf PDF
Attachment_B__SECNAV_5512_Attachment_B.pdf PDF
N40085-19-R-9156.pdf PDF
Attachment_A_PPII_log.doc DOC document
ATTACHMENT_C_Construction_Design_Exp.docx DOCX document
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ACQR5482215

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

SOLICITATION NO. N40085-19-R-9156, DESIGN-BUILD (DB), P-1495, 5TH BATTALION, 10TH MARINES, HIGH MOBILITY ARTILLERY ROCKET

SYSTEM (HIMARS), MARINE CORPS BASE (MCB), CAMP LEJEUNE, NORTH CAROLINA

The purpose of this amendment is to provide responses to Pre-Proposal Inquiries.

The proposal due date of 08 October 2019 NLT 2:00 PM EDT remains unchanged.

See Continuation Page(s).

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 02-Oct-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008519R9156

X 9B. DATED (SEE ITEM 11)

05-Sep-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

02-Oct-2019

CODE

NAVFAC MID ATLANTIC

ACQUISITION CORE

9324 VIRGINIA AVENUE

NORFOLK VA 23511-3095

N40085 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008519R9156

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0001

Contractor

PPI#

Section of RFP or Page Number

Paragraph Reference

Drawing Number

Question RESPONSE

1 RFP page 9 and 10, Factor 2 - Experience

Some of our listed projects in Factor 2 - Experience were projects in which we were not permitted to submit LEED (or similar) through a sustainability organization due to project security, would the Government consider presentation of a LEED Checklist as applicable documentation for evaluation concerning our submitted projects?

Yes, the presentation of a LEED Checklist is acceptable.

(End of Summary of Changes)

File details come from the government source that posted it. Updated .