This is a solicitation for a firm-fixed price design-bid-build construction contract for road improvements and related work at Marine Corps Base Camp Lejeune in North Carolina. The solicitation is for a construction project to improve Birch Street Road and Birch Street North. The work includes roadway construction and related site work. The contract will be awarded by the Department of the Navy, Naval Facilities Engineering Command. The solicitation includes standard contract clauses and references Federal Acquisition Regulation requirements. Interested contractors should review the solicitation for additional details on response requirements and dates.
View the file
Other files
Show all 45
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WORK ORDER NO. 1374744
A/E CONTRACT NO.
N40085-18-D-0600
APPROPRIATION: MCON
BIRCH STREET ROAD IMPROVEMENTS
Specifications IFC Submittal 12 June, 2020
At the
Marine Corps Base, Camp Lejeune, NC
SUBMITTED BY:
NAVFAC MIDLANT, Marine Corps AOPS
9324 Virginia Avenue Norfolk, VA 23511
PREPARED BY:
Name: Brian S. Chewning, P.E.
Discipline: Civil
Name: Timothy J. Lowe, P.E.
Discipline: Civil (Roadway)
ACCEPTED BY:
For Commander, NAVFAC MIDLANT: ___________________________________
Date:
Birch Street Road Improvements WON: 1374744 Camp Lejeune, North Carolina IFC
PROJECT TABLE OF CONTENTS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 20 00.00 20 PRICE AND PAYMENT PROCEDURES
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 17.00 20 COST-LOADED NETWORK ANALYSIS SCHEDULES (NAS)
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 20 QUALITY CONTROL
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 57 19.01 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS
01 60 00.00 22 REQUIREMENTS FOR PESTICIDE AND HERBICIDE COORDINATION
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
01 78 30.00 22 GIS DATA DELIVERABLES
DI VI SI ON 02 - EXI STI NG CONDI TI ONS
02 41 00 DEMOLITION
DI VI SI ON 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
DI VI SI ON 31 - EARTHWORK
31 05 19 GEOTEXTILE
31 05 21 GEOGRID REINFORCEMENT
31 23 00.00 20 EXCAVATION AND FILL
DI VI SI ON 32 - EXTERI OR I MPROVEMENTS
32 01 16.71 COLD MILLING ASPHALT PAVING
32 10 00 BITUMINOUS CONCRETE PAVEMENT
32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 PAVEMENT MARKINGS
32 92 23 SODDING
DI VI SI ON 33 - UTI LI TI ES
33 11 00 WATER UTILITY DISTRIBUTION PIPING
33 30 00 SANITARY SEWERAGE
33 40 00 STORM DRAINAGE UTILITIES
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
THIS PAGE INTENTIONALLY LEFT BLANK
PROJECT TABLE OF CONTENTS Page 2
SECTION 01 11 00
SUMMARY OF WORK
08/18
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
INTERNATIONAL CODE COUNCIL (ICC)
ICC IBC (2018) International Building Code
U.S. DEPARTMENT OF DEFENSE (DOD)
UFC 1-200-01 (2016) DoD Building Code (General Building Requirements)
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
1.3 WORK COVERED BY CONTRACT DOCUMENTS
1.3.1 Project Description
The work includes 18 months and incidental related work.
1.3.2 Location
The work is located at the Camp Lejeune, NC, approximately as indicated.
The exact location will be shown by the Contracting Officer.
1.4 BUILDING CODE
Except as indicated otherwise, or as modified by UFC 1-200-01 , use ICC IBC as the building code for this project.
1.5 OCCUPANCY OF PREMISES
Building(s) will be occupied during performance of work under this Contract. Occupancy notifications will be posted in a prominent location in the work area.
Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
SECTION 01 11 00 Page 1
1.6 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation by contacting the Contracting Officer 15 calendar days in advance, and comply with Installation requirements for locating and marking underground utilities.
Contact local utility locating service a minimum of 48 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.
Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities,and any type of underground obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed.
Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.6.1 Notification Prior to Excavation
Notify the Contracting Officer at least 15 days prior to starting excavation work.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 2
SECTION 01 14 00
WORK RESTRICTIONS
11/11
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel; G
1.2 SPECIAL SCHEDULING REQUIREMENTS
a. Order of construction completion preference is as shown below. Any variance requires written approval from the Contracting Officer.
1. Phase 1
2. Phase 2
3. Phase 3
4. Phase 4
5. Phase 5
b. The demolition schedule must be coordinated with the Users.
c. The nearby buildings and utilities will remain in operation during the entire construction period. Conduct operations so as to cause the least possible interference with normal operations of the activity.
d. Permission to interrupt any activity roads, railroads, or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
e. The work under this contract requires special attention to the scheduling and conduct of the work in connection with existing operations. Identify on the construction schedule each factor which constitutes a potential interruption to operations.
F. Government Telecommunications Contractor Access: The Government Telecommunications Contractor must be allowed access to the facility towards the end of construction (finishes 90 percent complete, rough-in 100 percent complete, Inside Plant (ISP)/Outside Plant (OSP) infrastructure in place) to provide equipment in the telecommunications rooms and make final connections. The Contractor will be required to coordinate their efforts with the Government Telecommunications Contractor to facilitate joint use of building spaces during the final phases of construction and work the coordination effort into the construction schedule. Requirements for Government Telecommunications are specified in Part 5, Section 27 10 00
BUILDING TELECOMMUNICATIONS CABLING SYSTEM
SECTION 01 14 00 Page 1
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. To minimize traffic congestion, delivery of materials must be outside of peak traffic hours (6:30 to 8:00 a.m. and 3:30 to 5:00 p.m.) unless otherwise approved by the Contracting Officer. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.
1.3.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.3.1.2 Installation Access
Obtain access to Navy installations through participation in the Defense Biometrics Identification System (DBIDS). No fees are associated with obtaining a DBIDS credential.
Participation in the DBIDS is not mandatory, and Contractor personnel may apply for One-Day Passes at the Contractor Vetting satellite office located at the Piney Green Gate to access an installation.
1.3.1.2.1 Registration for DBIDS
Base access procedures and DBIDS registration info are provided at https://www.lejeune.marines.mil/Base-Access. Procedure includes:
a. Present a letter or official award document (i.e. DD Form 1155 or SF 1442) from the Contracting Officer, that provides the purpose for access, to the base Contractor Vetting Office (CVO) representative.
b. Provide a letter of authorization on company letterhead referencing the applicable contract(s) and identifying the requesting individual as an authorized employee of the awarded company along with the employee's required access days and times.
c. Present two (2) valid forms of identification, such as a passport or Real ID Act-compliant state driver's license. All documents must be originals/certified.
d. Provide completed SECNAV FORM 5512/1 to the base CVO representative to obtain a background check. This form is available for download from the base access website listed in 1.4.1.3.1.
e. Provide vehicle registration and insurance. Contractors driving aboard the installation must provide an original vehicle registration document. Copies of registration are only accepted for company-owned fleet vehicles. Proof of insurance is also required. A declaration
SECTION 01 14 00 Page 2 page is required for insurance originating outside the state of North Carolina. Out of state insurance must meet North Carolina minimums of $30,000/person, $60,000/accident, and $25,000/property damage.
f. Upon successful completion of the background check, the Government will complete the DBIDS enrollment process, which includes Contractor employee photo, finger prints, base restriction and several other assessments.
g. Upon successful completion of the enrollment process, the Contractor employee will be issued a DBIDS credential, and will be allowed to proceed to worksite.
1.3.1.2.2 Denial of Access
Persons requesting access to Marine Corps sites will be denied if:
a. Military or civilian police or VCO/CVO personnel are unable to verify the individual's claimed identity based on reasonable belief the person submitted fraudulent identity information in the attempt to gain access.
b. The individual has a conviction for espionage, sabotage, sedition, treason, terrorism, armed robbery, or murder.
c. The individual has a felony conviction for a firearms or explosives violation, regardless of the date of conviction.
d. The individual has been convicted of crimes encompassing sexual assault or rape.
e. The individual has been convicted of crime encompassing child molestation, or the possession or production of child pornography.
f. The individual has been convicted of trafficking in persons.
g. The individual is a registered sex offender.
h. The individual has been convicted of drug possession with intent to sell or distribute.
i. The individual has an active arrest warrant from Federal, state, local, or other civil law enforcement authorities, regardless of offense or violation.
j. The individual has a felony conviction within the last 10 years, regardless of the offense or violation.
k. The individual's name appears on any Federal or state agency watch list for criminal behavior or terrorist activity.
l. The individual is debarred entry or access to a Marine Corps site, other DoD installations or facilities, or other Federal site or facility.
m. The individual engaged in acts or activities designed to overthrow the U.S. Government by force.
SECTION 01 14 00 Page 3
n. The individual is known to be or reasonably suspected of being a terrorist or belongs to an organization with known terrorism links/support.
o. The individual is identified in the NCIC KST file, or the TSDB report as known to be, or suspected of being, a terrorist or belonging to an organization with known links to terrorism or support of terrorist activity. If an individual is identified on the NCIC KST files or TSDB, PMO/MCPD or other designated site security personnel will immediately call the NCIS Multiple Threat Alert Center (MTAC) for further coordination. The MTAC will coordinate with the Department of Justice or Federal Bureau of Investigation and provide handling instructions to PMO/MCPD or other designated site security personnel.
p. The individual is illegally present in the U.S.
q. The individual has knowingly submitted an employment questionnaire with false or fraudulent information.
r. The individual is a prisoner on a work-release program or currently on felony probation/parole.
s. The individual is pending any felony charge.
t. The individual has been convicted of three or more misdemeanor violations, or attempted violations, within the previous 10 years of the following offenses:
1. Sex crimes;
2. Assaults;
3. Larcenies;
4. Drugs; or
5. Weapons.
u. The individual has criminal arrest information that the site commander determines the person presents a threat to the good order, discipline, or health and safety on the Marine Corps site.
v. Any reason the Installation Commander deems reasonable for good order and discipline.
1.3.1.2.3 DBIDS Eligibility Requirements
Throughout the length of the contract, the Contractor employee must continue to meet background screen standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.
An adjudication process may be initiated when a background screen failure results in disqualification from participation in the DBIDS, and Contractor employee does not agree with the reason for disqualification.
The Government is the final authority.
1.3.1.2.4 DBIDS Notification Requirements
a. Immediately report instances of lost or stolen badges to the Contracting Officer.
SECTION 01 14 00 Page 4
b. Immediately collect DBIDS credentials and notify the Contracting Officer in writing under the following circumstances:
(1) An employee has departed the company without having properly returned or surrendered their DBIDS credentials.
(2) There is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the Installation or anyone therein.
1.3.1.2.5 One-Day Passes
Personnel applying for One-Day passes at the Piney Green Gate are subject to daily mandatory vehicle inspection, and will have limited access to the installation. The Government is not responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the DBIDS.
1.3.1.3 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.3.2 Working Hours
Regular working hours must consist of an 8 1/2 hour period , between 7 a.m. and 5 p.m., Monday through Friday, excluding Government holidays.
After hours work is only permitted with written permission from the Contracting Officer.
1.3.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.
1.3.4 Exclusionary Period
No work must be performed between Parachute Road and Holcomb Boulevard, during the hours of 6:00 AM to 8:00 AM and 3:00 PM to 6:00 PM, without prior written approval of the Contracting Officer. This period has not been considered in computing the time allowed for the performance of this contract.
1.3.5 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or
SECTION 01 14 00 Page 5 on Saturdays, Sundays, and Government holidays. Conform to procedures required in the paragraph WORK OUTSIDE REGULAR HOURS.
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS. This time limit includes time for deactivation and reactivation.
1.3.5.1 Location of Underground Utilities
Notification Prior to Excavation: Notify the Contracting Officer at least 15 days prior to starting excavation work.
Location and Protection of underground utilities shall be the responsibility of the Contractor. Where existing-to-remain piping, utilities, and underground obstructions of any type are indicted in locations to be traversed by new piping, ducts, and other excavations the elevations of the existing utilities and obstructions shall be determined before the new work is completed.
a. In addition, the Contractor will be responsible for obtaining the services of a professional utility locator prior to digging.
Contractor will provide documentation that the site has been surveyed and checked for underground utilities. All utilities must be located, including but not limited to power, water, sewer, storm drains, fiber optics, T.V. cable, telephone, and intrusion detection wiring. A set of known as-built drawings will be available in the ROICC/PWD office for review to assist the locator.
b. It is mandatory that the Contractor also contact the Base Telephone Office (910-451-2531/3100) prior to accomplishing any digging at Camp Lejeune. A telephone office representative will assist in locating telephone lines.
c. It is mandatory that the Contractor also contact Public Works Outside Plumbing (910-451-7190) prior to accomplishing any digging at Camp Lejeune, to ensure that all buried water and sanitary lines are identified
d. It is mandatory that the Contractor also contact Charter Communications, cable TV service prior to accomplishing any digging at Camp Lejeune, to ensure that all buried cable lines are identified.
Contact Mr. Nick Brown at 910-376-1785 for assistance.
e. It is mandatory that the contractor also contact the North Carolina One-Call Center to coordinate the location of underground natural gas infrastructure. North Carolina 811, Inc. can be reached at 811 on a touch-tone phone in the state of North Carolina or toll-free at
1.800.632.4949 if calling from out of state. Work requests may also be submitted online at www.nc811.org
SECTION 01 14 00 Page 6
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 14 00 Page 7
SECTION 01 20 00.00 20
PRICE AND PAYMENT PROCEDURES
11/11
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EP-1110-1-8 (2009) Construction Equipment Ownership and Operating Expense Schedule
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. The following shall be submitted in accordance with Section
01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Schedule of Prices; G
1.3 SCHEDULE OF PRICES
1.3.1 Data Required
Within 15 calendar days of notice of award, prepare and deliver to the Contracting Officer a Schedule of Prices (construction contract) as directed by the Contracting Officer. Provide a detailed breakdown of the contract price, giving quantities for each of the various kinds of work, unit prices, and extended prices. Costs shall be summarized and totals provided for each construction category.
1.3.2 Schedule Instructions
Payments will not be made until the Schedule of Prices has been submitted to and accepted by the Contracting Officer. Identify the cost for site work, and include incidental work to the 5 ft line. Identify costs for the building(s), and include work out to the 5 ft line. Work out to the 5 ft line shall include construction encompassed within a theoretical line 5 ft from the face of exterior walls and shall include attendant construction, such as pad mounted HVAC cooling equipment, cooling towers, and transformers placed beyond the 5 ft line.
1.4 CONTRACT MODIFICATIONS
In conjunction with the Contract Clause "DFARS 252.236-7000, Modification Proposals-Price Breakdown," and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, equipment use rates shall be based upon the applicable provisions of the EP-1110-1-8 .
SECTION 01 20 00.00 20 Page 1
1.5 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.5.1 Content of Invoice
Requests for payment will be processed in accordance with the Contract Clause FAR 52.232-27, Prompt Payment Construction Contracts and FAR 52.232-5, Payments Under Fixed-Price Construction Contracts. The requests for payment shall include the documents listed below.
a. The Contractor's invoice, on NAVFAC Form 7300/30 furnished by the Government, showing in summary form, the basis for arriving at the amount of the invoice. Form 7300/30 shall include certification by Quality Control (QC) Manager as required by the contract.
b. The Estimate for Voucher/ Contract Performance Statement on NAVFAC Form 7300/31 furnished by the Government, showing in detail: the estimated cost, percentage of completion, and value of completed performance for each of the construction categories stated in this contract. Use NAVFAC LANT Form 4-330/110 (New 7/84) on NAVFAC LANT contracts when a Monthly Estimate for Voucher is required.
c. Updated Project Schedule and reports required by the contract.
d. Contractor Safety Self Evaluation Checklist.
e. Other supporting documents as requested.
f. Updated copy of submittal register.
g. Invoices not completed in accordance with contract requirements will be returned to the Contractor for correction of the deficiencies.
h. Contractor's Monthly Estimate for Voucher (NAVFAC LANT Form 4-330/110 (New 7/84)) with Subcontractor and supplier payment certification.
i. Affidavit to accompany invoice (NAVFAC LANT NORVA Form 4-4235/4 (Rev.5/81)).
j. Materials on Site.
1.5.2 Submission of Invoices
If NFAS Clause 5252.232-9301 is included in the contract, the documents listed in paragraph "CONTENT OF INVOICE" shall be provided in their entirety as attachments in Wide Area Work Flow (WAWF) for each invoice submitted. The maximum size of each WAWF attachment is two megabytes, but there are no limits on the number of attachments. If a document cannot be attached in WAWF due to system or size restriction it shall be provided as instructed by the Contracting Officer.
Monthly invoices and supporting forms for work performed through the anniversary award date of the contract shall be submitted to the Contracting Officer within 5 calendar days of the date of invoice. For example, contract award date is the 7th of the month, the date of each monthly invoice shall be the 7th and the invoice shall be submitted by the 12th of the month.
SECTION 01 20 00.00 20 Page 2
1.5.3 Final Invoice
a. A final invoice shall be accompanied by the certification required by DFARS 252.247.7023 TRANSPORTATION OF SUPPLIES BY SEA, and the Contractor's Final Release. If the Contractor is incorporated, the Final Release shall contain the corporate seal. An officer of the corporation shall sign and the corporate secretary shall certify the Final Release.
b. For final invoices being submitted via WAWF, the original Contractor's Final Release Form and required certification of Transportation of Supplies by Sea must be provided directly to the respective Contracting Officer prior to submission of the final invoice. Once receipt of the original Final Release Form and required certification of Transportation of Supplies by Sea has been confirmed by the Contracting Officer, the Contractor shall then submit final invoice and attach a copy of the Final Release Form and required certification of Transportation of Supplies by Sea in WAWF.
c. Final invoices not accompanied by the Contractor's Final Release and required certification of Transportation of Supplies by Sea will be considered incomplete and will be returned to the Contractor.
1.6 PAYMENTS TO THE CONTRACTOR
Payments will be made on submission of itemized requests by the Contractor which comply with the requirements of this section, and will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.
1.6.1 Obligation of Government Payments
The obligation of the Government to make payments required under the provisions of this contract will, at the discretion of the Contracting Officer, be subject to reductions and/or suspensions permitted under the FAR and agency regulations including the following in accordance with "FAR 32.503-6:
a. Reasonable deductions due to defects in material or workmanship;
b. Claims which the Government may have against the Contractor under or in connection with this contract;
c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor; and
d. Failure to provide up to date record drawings not current as stated in Contract Clause "FAC 5252.236-9310, Record Drawings."
1.6.2 Payment for Onsite and Offsite Materials
Progress payments may be made to the contractor for materials delivered on the site, for materials stored off construction sites, or materials that are in transit to the construction sites under the following conditions:
a. FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts.
b. Materials delivered on the site but not installed, including completed preparatory work, and off-site materials to be considered for progress
SECTION 01 20 00.00 20 Page 3 payment shall be major high cost, long lead, special order, or specialty items, not susceptible to deterioration or physical damage in storage or in transit to the construction site. Examples of materials acceptable for payment consideration include, but are not limited to, structural steel, non-magnetic steel, non-magnetic aggregate, equipment, machinery, large pipe and fittings,precast/prestressed concrete products, plastic lumber (e.g., fender piles/curbs), and high-voltage electrical cable. Materials not acceptable for payment include consumable materials such as nails, fasteners, conduits, gypsum board, glass, insulation, and wall coverings.
c. Materials to be considered for progress payment prior to installation shall be specifically and separately identified in the Contractor's estimates of work submitted for the Contracting Officer's approval in accordance with Schedule of Prices requirement of this contract.
Requests for progress payment consideration for such items shall be supported by documents establishing their value and that the title requirements of the clause at FAR 52.232-5 have been met.
d. Materials are adequately insured and protected from theft and exposure.
e. Provide a written consent from the surety company with each payment request for offsite materials.
f. Materials to be considered for progress payments prior to installation shall be stored either in Hawaii, Guam, Puerto Rico, or the Continental United States. Other locations are subject to written approval by the Contracting Officer.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 20 00.00 20 Page 4
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
08/15
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
View Location Map; G
Progress and Completion Pictures; G
1.3 VIEW LOCATION MAP
Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.
1.4 PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten views from points located by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures. Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file. Include a date designator in file names. Cross reference submittals in the appropriate daily report. Photographs provided are for unrestricted use by the Government.
1.5 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage required by FAR 28.307-2 Liability, SECTION 01 30 00 Page 1 during the entire period of performance under this contract. Provide other insurance coverage as required by State law.
1.6 SUPERVISION
1.6.1 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of contract work. In addition, if a Quality Control (QC) representative is required on the contract, then that individual must also have fluent English communication skills.
1.6.2 Superintendent Qualifications
The project superintendent must have a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
1.6.2.1 Duties
The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.
The superintendent is required to attend NAVFAC Red Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.6.3 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion.
Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
1.7 PRECONSTRUCTION MEETING
After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work must also attend.
SECTION 01 30 00 Page 2
1.8 FACILITY TURNOVER PLANNING MEETINGS (NAVFAC Red Zone - NRZ)
Meet with the Government to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client. Start the turnover process at the Pre-Construction Conference meeting with a discussion of the NAVFAC Red Zone (NRZ) process and convene at regularly scheduled NRZ Meetings. Include the following in the facility Turnover effort:
1.8.1 NRZ Checklist
a. Contracting Officer's Technical Representative (COTR) will provide the Contractor a copy of the NRZ Checklist template prior to 75 percent completion. See attached NRZ Checklist Items.
b. Prior to 75 percent completion add/delete critical activities to the NRZ Checklist template as necessary to match the project scope, and schedule critical activities and insert planned completion dates in the NRZ checklist for each critical activity. Present the NRZ Checklist to COTR and review during a regularly scheduled QC Meeting.
1.8.2 Meetings
a. Upon Government acceptance of the NRZ Checklist, the Project Superintendent is required to lead regular NRZ Meetings beginning at approximately 75 percent project completion, or three to six months prior to Beneficial Occupancy Date (BOD), whichever comes first.
b. The Contracting Officer will determine the frequency of the meetings, which is expected to increase as the project completion draws nearer.
c. Using the NRZ Checklist as a Plan of Action and Milestones (POAM) and basis for discussion, review upcoming critical activities and strategies to ensure work is completed on time.
d. Coordinate with the COTR any upcoming activities that require Government involvement.
e. Maintain the NRZ Checklist by documenting the actual completion dates as work is completed and update the NRZ Checklist with revised planned completion dates as necessary to match progress. Distribute copies of the current NRZ Checklist to attendees at each NRZ Meeting.
1.9 PARTNERING
To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership within the Project Team whose members are from the Government, the Contractor and their Subcontractors. Key personnel from the Supported Command, the End User (who will occupy the facility), the Government Design and Construction team and Subject Matter Experts, the Installation, the Contractor and Subcontractors, and the Designer of Record will be invited to participate in the Partnering process. The Partnership will draw on the strength of each organization in an effort to achieve a project that is without any safety mishaps, conforms to the Contract, and stays within budget and on schedule.
The Contracting Officer will provide Information on the Partnering Process and a list of key and optional personnel who should attend the Partnering meeting.
SECTION 01 30 00 Page 3
1.10 ELECTRONIC MAIL (E-MAIL) ADDRESS
Establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments as text files, pdf files, and other similar formats. Within 10 days after contract award, provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats. Multiple email addresses are not allowed.
It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). Promptly notify the Contracting Officer, in writing, of any changes to this email address.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 30 00 Page 4
NAVFAC Red Zone Facility Turnover Planning Meeting
AGENDA
I. Introduction and Overview – Purpose CM
The purpose of the Facility Turnover Planning Meeting is to address elements within the project team’s purview – schedule management, assure completed facility complies with contract requirements, and other contractual issues. Each member of the project delivery team (Client, NAVFAC, and the contractor) has critical responsibilities to ensure timely completion and turnover of the new facility and each member should execute the NRZ process to achieve this end. The NRZ process provides a final re-focusing of attention to details of those key elements critical for a successful construction contract completion. In implementing NRZ processes, the NAVFAC/Contractor/Client team take a collective “snapshot” of contract status, identifying remaining actions to be accomplished, and confirm required resources needed for successful contract completion and turnover to the Client.
The Facility Turnover Planning Meeting is a collaborative effort between the Client, NAVFAC, and the contractor and results in a completed “NRZ Checklist/POAM Items” list that identifies the major items (and their due dates) that must be completed by the Contractor, the Client and the NAVFAC team to ensure timely completion of the contract.
II. Attendees
NAVFAC Echelon IV (PM); NAVFAC FEAD/ROICC Team (AROICC, CM, ET/QA, Contracting Officer); Client Team (Project Manager, Program Coordinator, User/Tenant); Contractor Team (Project Manager, Project Superintendent, CQC Manager)
III. Schedule to Completion (POAM) Contractor
IV. Schedule of Final Outfitting and Occupancy (POAM) Client
V. Critical feature(s) of project (POAM) CM
VI. Transfer of Maintenance Responsibility CM
VII. Systems training & O&M Manuals (POAM) CQC Manager
VIII. Other Items to include on NRZ checklists All
IX. Summary of Required Actions and Responsibility CM
Guidelines for conducting Facility Turnover Planning Meeting are as follows:
a. Meeting is held at approximately 75% construction contract completion or three to six months prior to BOD. NAVFAC representatives will include the Project Manager, Construction Manager/AROICC (CM) and Design Manager (DM), as appropriate. The contractor representatives include applicable prime contractor staff and decision-makers from major subcontractors. Design- Build contractors will have A-E representatives attending. The Client should include representatives from Public Works Officer (PWO) staff, a Client scope and financial decision maker, a user tenant representative, a facility start-up person, and others such as SPAWAR, Government Telecommunications Contractor, telephone, and furniture contractor, etc.
b. The purpose of the meeting is to plan the remaining work, identify critical project features that still need to be completed (such as “soft” construction contract requirements as shown on the NRZ Checklist/POAM Items), and to complete the filling out of the “NRZ Checklist/POAM Items”.
c. The contractor, client and NAVFAC provide a POC and due date for each item on their checklist. The team fills in the checklists by selecting items applicable to the project, selects due dates on each item, and appoints a person who has responsibility to ensure the item gets completed by the due date. The CM will be responsible to monitor the milestones.
P ag e of
N R
Z C h ec kl is t/ P
O A
M I te m s T he ta bl es b el ow p ro vi de ty pi ca l N R
Z c he ck li st it em s fo r co nt ra ct or
, C li en t, an d
N A
V F
A C a ct io ns
T ab le s 1, , a nd
, r es pe ct iv el
y) . I te m s li st ed o n th e ch ec kl is ts a re r eq ui re d to r em ai n on th e ch ec kl is ts if th ey a re p ar t o f th e pr oj ec t/ co nt ra ct o r re qu ir ed b y co ns tr uc ti on c on ve nt io n.
It em s no t l is te d on th e ch ec kl is ts , b ut r eq ui re d in th e co nt ra ct o r by c on st ru ct io n co nv en ti on
, m us t b e ad de d to th e ch ec kl is ts b y th e co nt ra ct or
, C li en t a nd N
A V
F A
C . C he ck li st s ar e ap pl ic ab le to a ll c on tr ac ts n o m at te r w ha t C at eg or y of
W or k.
T he
P oi nt o f C on ta ct a nd d ue d at e sh al l i ni ti al ly b e de te rm in ed d ur in g th e
F ac il it y T ur no ve r
P la nn in g M ee ti ng b y th e N
A V
F A
C , c li en t a nd co nt ra ct or le ad s.
D ur in g ex ec ut io n of th e N
R Z p ro ce ss
, f or e ac h it em o n th e en ti re li st
, t he
C on st ru ct io n M an ag er
C M sh al l i nd ic at e da te co m pl et ed a nd in it ia l t o in di ca te c om pl et io n of th e it em
. I f a pa rt y fa il s to c om pl et e an it em b y th e du e da te
, t hi s sh ou ld b e no te d on th e ch ec kl is t a nd n ew d ue d at e es ta bl is he d an d in di ca te d.
T he c om pl et ed N
R Z
C he ck li st /P
O A
M s ha ll b e pl ac ed in th e co nt ra ct f il e.
e ab le
C on tr ac to r
C h ec k li st
I te m s
P oi n t ta ct
D u e
D at e A ct al om p at e
M
In it ia ls ot es a.
on st ru ct io n
C om p le ti on
S ch ed b . F ac il it y
D el iv er y C lo se ou t:
uc t A ir
L ea ka ge
T es ti ng
H V
A C
S ys te m
T es t & B al an ce
A
A
T S
C on tr ol s T es du ct S ec on d S ea so ns T
B
E ct ri ca l S ys te m s
T es
F in al u ti li ty s ys te m s co nn ec ti on s
(p ow er , w at er
, e tc
S up er ch lo ri na ti on o f po ta bl e w at er s ys te s lu m bi ng
O th er
M ec ha ni ca l T es
E va to r
C er ti fi ca ti on (s pe ci al iz ed
E qu ip m en t &
S ys te m s In sp ec ti on s (B oi le rs , U
PV
et c.
ir e P ro te ct io n S ys te m s
In sp ec ti on s an d
P er fo rm ce er if ic at n m un ic at io ns
IT
S ys te m s T es ec ur it y
S ys te m s T es
O th er
S pe ci fi ed B ui ld in g
P er fo rm an ce
R eq ui re m en ts c.
th er C on tr ac to r It s:
el iv er y of
O
M M an ua iv er y of E qu ip m en t/ P ro du ct W ar ra nt y
L is t/
M
/O M
S I
T ra in in g of
N av y P er so nn e R es to ra ti on , i f ap pl ic e tr ac to r C h ec k li st I te m s P oi n e D at e
A ct p e
L ds ca pi ng
C om pl et e re
-F in al I ns pe ct al I ns pe ct io n an d A cc ep ta nc iv er y of
S pa re P ar ts
, E xt ra S to ck
, S pe ci al
T oo ls , e tc iv er y of A s- B ui lt
D ra w gs iv er y of U ti li ty R ec or d D ra w in gs if a pp li ca bl e) iv er y of
U ti li ty
A s-
B ui lt D ra w in gs if a pp li ca bl e)
B ef ic ia l O cc up an cy
D at e (B
O al D em ob il iz at io n an d C le an
-u p
C om pl ed ov e C on st ru ct io n
Fe nc e
A ss oc ia te d
C oo rd in at
-w ar ra nt y C on fe re ro je ct
C lo se -o ut M ee oo rd in at io n an d
D el iv er y of
F ac il it y S ig na ge al
C le an g ep la ce
C on st ru ct io n L oc k
C or es a nd R e-ke yi un ch L is t C om pl et vi de
D D to G ov er nm en t C e li en t
C h ec k li st
I te m s
P oi n e
D at e A ct p e ia ls N od if ic at io n to
F S
C o r B
O S
C to m ai nt ai n/ se rv ic e ne w f ac il it y
T el ep ho ne s er vi ce c on tr ac t
U ti li ti es s er vi ce c on tr ac t
C us to di al s er vi ce c on tr ac st al la ti on o f co m m un ic at io ns f or p ho ne s an d co m pu rs
G ov er nm en t T el ec om m un ic at io ns
I ns ta lla ti on s or o th er n et w ks iv er y an d in st al la ti on o f cl ie nt f ur ni sh ed f ur ni tu iv er y an d in st al la ti on o f cl ie nt f ur ni sh ed e qu ip m
U se r m ov e-
E s ta tu s/ de li ve ry s ch ed ul e
(G F
C I, G F
I) rd in at io n of
I nt ru si on D et ec ti on
S ys te m s an d P hy si ca l
S ec ur it y E qu ip m ce ss o pe ra ti ng p er m yc le d/ re co ve re d m at er ia ls r ep rd in at io n of I
T a nd C om m un ic at io n In fr as tr uc tu re a ev ic es in cl
. C A
T I ib bo n-cu tt in g ce re m y e
V F
A C
C h ec k li st
I te m s
P oi n e D at e
A ct p e ia ls N li en t w al k-th ru p ri or to p re
-f in al in sp ec ti on s, if a pp ro pr ch ed ul e cl ie nt s at is fa ct io n po st B
O D f ol lo w
-u p ch ed ul e G ov er nm en t i ns pe ct io ns o f sp ec ia li ze d eq ui pm en t (e
.g
B oi le r/ pr es su re v es se ls
, e le va to rs , U
P S
, S ec ur e
R sh ie ld in g re qu ir em en ts , m ed ic al c er ti fi ca ti s, ge ne ra to rs /s w it ch ge ar vi de k ey in g pl an to c on tr ac to r fi rm u ti li ti es a va il ab il it y fo r fi na l c on ne ct io ns b y co nt ra rt up u ti li ha ni ca l A cc ep ta ol ve c on tr ac t m od if ic at io ns r eq ue st s fo r eq ui ta bl e ad ju st m tr ac to r fi na l r el ea se ur n un ob li ga te d fu ce ss f in al p ay m ce ss r ec yc le d/ re co ve re d m at er ia ls r ep lo se ou t a ct io ns o n co ns tr uc ti on p er m it s (e
.g
N P
D E
-E a nd C on st ru ct io n
C on tr ac to r
E va lu at io ns
A
C A
S S
/C C
A S tr ac to r Q
C E va lu at pl et e In st al le d
P ro pe rt y L is t a nd D
D ig n p ro vi de I nt er im D
D to a ct iv it y R ea l P ro pe rt y
A cc ou nt ab il it y
O ff ic er
N L
T B
Performance Assessment Plan – Page 1
Performance Assessment Plan
MONTHLY EVALUATION
MONTH: __________YEAR:______
Evaluation Factor Yes No N/A Comments
Experience of Personnel
1. Did the team identified in the proposal actively participate in the project?
2. If personnel substitutions were needed, was the degree of technical competence maintained?
Working Relationships
1. Did the Construction team participate in the design process (i.e. attend meetings, provide insight, etc.)?
Were the coordination meetings between Construction and Design team personnel documented?
2. Did the Design team participate in the construction process (i.e. attend CQC meetings, perform field oversight, etc.)? Were coordination meetings between Construction and Design team personnel documented?
3. Did the collaboration between the Construction and Design Team deliver a high value innovative facility?
- Were Total Operating Cost minimized
- What LEED points can be obtained
- Was energy efficiency optimized, and the energy goals exceeded.
4. Was the budget management process clear; was an estimate submitted on time with each design submittal. Was the estimate updated to reflect the changes in the design submittal?
5. Did the Contractor's team effectively manage the project budget and the User's requirements to meet the customer's needs? Was project budget and emphasis in cost control exhibited in the estimate?
(Contractor to document in comments block
Performance Assessment Plan – Page 2 materials/systems innovations and provision of higher quality than required in the RFP Part 4)
Additional factors to be developed during Partnering.
Quality Control
1. Were re-submittals of design deliverables or construction rework required this month?
2. Were as built redlines updated this month?
Timely Performance
1. Is the Contractor on schedule?
2. Is the Contractor maintaining the schedule? (Can the Government confirm the project is on schedule?)
3. Is the Contractor following his schedule?
Effectiveness of Management
1. Did the Government need to intercede in resolving a subcontractor issue?
Compliance with Labor Standards
1. Did payrolls have to be resubmitted this month due to inaccuracies or errors?
Compliance with Safety Standards
1. Were there any lost time accidents this month?
Performance Assessment Plan – Page 3
GENERAL PERFORMANCE COMMENTS THIS MONTH:
Concurrence:
CM/ROICC Representative ______________Date______.
Project Manager ______________________Date_______.
Contractor Representative ______________Date______.
SECTION 01 32 17.00 20
COST-LOADED NETWORK ANALYSIS SCHEDULES (NAS)
08/18
PART 1 GENERAL
1.1 DEFINITIONS
The cost-loaded Network Analysis Schedule (NAS) is a tool to manage the project, both for Contractor and Government activities. The NAS is also used to report progress, evaluate time extensions, and provide the basis for progress payments.
For consistency, when scheduling software terminology is used in this section, the terms in Primavera's scheduling programs are used.
1.2 SCHEDULE REQUIREMENTS PRIOR TO THE START OF WORK
1.2.1 Preliminary Scheduling Meeting
Before preparation of the Project Baseline Schedule, and prior to the start of work, meet with the Contracting Officer to discuss the proposed schedule and the requirements of this section.
1.2.2 Project Baseline Schedule
Submit the Baseline NAS within 30 calendar days after contract award.
Government review comments on the Contractor's schedule(s) do not relieve the Contractor from compliance with requirements of the Contract Documents. Only bonds may be paid prior to acceptance of the Baseline NAS. The acceptance of a Baseline NAS is a condition precedent to:
a. The Contractor starting demolition work or construction stage(s) of the contract.
b. Processing Contractor's invoices(s) for construction activities/items of work.
c. Review of any schedule updates.
Submittal of the Baseline NAS, and subsequent schedule updates, is understood to be the Contractor's certification that the submitted schedule meets the requirements of the Contract Documents, represents the Contractor's plan on how the work will be accomplished, and accurately reflects the work that has been accomplished and how it was…