Amendment_0006.pdf
PDF 441 KB Posted
- Solicitation number
- N4008519R9057
About this file
Amendment_0006.pdf
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION
NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.
IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
SOLICITATION NO. N40085-19-R-9057 DESIGN-BID-BUILD (DBB) P-106 SUBMARINE PROPULSOR MANUFACTURING
SUPPORT FACILITY, PHILADELPHIA NAVY YARD, PHILADELPHIA, PA
The purpose of this amendment is provide additional answers to Pre-Proposal Inquiries (PPI's). The proposal due date of Tuesday, 07 May 2019 NLT 2:00 PM EDT remains unchanged.
See Continuation Page(s).
NAVFAC MID-ATLANTIC
ACQUISITION CORE
9324 VIRGINIA AVENUE
NORFOLK, VA 23511-3095
SEE ITEM 6
J
N40085-19-R-9057
1 10
05/03/2019
03/21/2019
05/03/2019
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
CONTINUATION SHEET
ATTACHMENT H - PRICE PROPOSAL FORM
CLIN 0001AG: Delete “3” from the No. Units and replace with “4”.
CLIN 0001AI: Delete “7” from the No. Units and replace with “6”.
DIVISION 07 THERMAL AND MOISTURE PROTECTION
SECTION 07 81 00 SPRAY-APPLIED FIREPROOFING
Paragraph 1.2.2: In the “Fire Rating Schedule Office/Administration Building Only” table, delete “N 925” from the
UL Design Reference for Floor supports and replace with “D925”.
Contractor
PPI#
Section of RFP or Page
Number
Paragraph
Reference
Drawing
Number Question RESPONSE
Volume 2
Cybersecurity 1.3.9.a.
What is the CIA impact level for the Section 14 24
23 HYDRAULIC
PASSENGER
ELEVATORS?
The CIA impact level will be assigned by NAVFAC at a later date.
Volume 2
Cybersecurity 1.3.9.b.
What is the CIA impact level for the Section 21 30
00 FIRE PUMPS?
The CIA impact level will be assigned by NAVFAC at a later date.
Volume 2
Cybersecurity 1.3.9.c.
What is the CIA impact level for the Section 23 09
00 INSTRUMENTATION
AND CONTROL FOR
HVAC?
The CIA impact level will be assigned by NAVFAC at a later date.
Volume 2
Cybersecurity 1.3.9.d.
What is the CIA impact level for the Section 23 09
13 INSTRUMENTATION
AND CONTROL
DEVICES FOR HVAC?
The CIA impact level will be assigned by NAVFAC at a later date.
Volume 2
Cybersecurity 1.3.9.e.
What is the CIA impact level for the Section 23 09
23.02 BACNET DIRECT
DIGITAL CONTROL FOR
HVAC AND OTHER
BUILDING CONTROL
SYSTEMS?
The CIA impact level will be assigned by NAVFAC at a later date.
Volume 2
Cybersecurity 1.3.9.f.
What is the CIA impact level for the Section 26 27
14.00 20 ELECTRICITY
METERING?
The CIA impact level will be assigned by NAVFAC at a later date.
Volume 2
Cybersecurity 1.3.9.g.
What is the CIA impact level for the Section 26 51
00 INTERIOR LIGHTING?
The CIA impact level will be assigned by NAVFAC at a later date.
Volume 2
Cybersecurity 1.3.9.h.
What is the CIA impact level for the Section 26 56
00 EXTERIOR
LIGHTING?
The CIA impact level will be assigned by NAVFAC at a later date.
Volume 2
Cybersecurity 1.3.9.i.
What is the CIA impact level for the Section 28 10
05 ELECTRONIC
SECURITY SYSTEMS?
The CIA impact level will be assigned by NAVFAC at a later date.
Volume 2
Cybersecurity 1.3.9.j.
What is the CIA impact level for the Section 28 31
76 INTERIOR FIRE
ALARM AND MASS
NOTIFICATION
SYSTEM?
The CIA impact level will be assigned by NAVFAC at a later date.
Volume 2
Cybersecurity
Do any of the networked systems is RFI (i.e. life safety, access control, power metering) that reach back to other facilities on the base currently have an authority to operate under the RMF?
There is a DDC ALC control systems at the Philly Navy
Yard having an RMF, the contractor should coordinate with Joshua Stephens
(Joshua.stephens@navy.mil) in CIO4 for any possible interface requirements to this system.
82 25 50 00 Page 2 1.3.1
Who are the designated
System Owner (SO) and
Authorizing Official (AO) for this project?
These representatives will be assigned by NAVFAC at a later date.
83 25 50 00 Page 2 1.3.1
Cybersecurity Design, notes a 5 step process to facilitate implementation of Cyber
Security, the five step process, dictates that the
System Owner (SO) and
Authorizing Official (AO) determine the
Confidentiality, Integrity and Availability of impact levels. This appears to be an owner driven requirement, not a contractor requirement.
Please provide further detail regarding the contractor’s responsibilities.
Yes. This is the responsibility of NAVFAC to define.
84 25 50 00 Page 2 1.3.2
Authority to Operate – please provide information regarding quantity and duration of RMF meetings.
The quantity and duration of
RMF meetings cannot be defined at this time. The offerors should provide a bid based on one, one-hour meeting for each Facility-related Control System.
85 25 50 00 Page 2 1.3.6
Cybersecurity Specialist, please confirm the DoD assigns this individual to the project as an owner representative. Civilian contractors do not employ this skill set.
No. The Contractor is required to have a Cybersecurity
Specialist per the specifications.
mailto:Joshua.stephens@navy.mil mailto:Joshua.stephens@navy.mil mailto:Joshua.stephens@navy.mil mailto:Joshua.stephens@navy.mil mailto:Joshua.stephens@navy.mil mailto:Joshua.stephens@navy.mil mailto:Joshua.stephens@navy.mil mailto:Joshua.stephens@navy.mil mailto:Joshua.stephens@navy.mil
At the OA building, is the design intent to provide an exterior wall configuration with a specific level of sound transmission classification (STC) for a secure work environment?
The secure boundary on the
1st floor of the OA building seems to have some inconsistency in relation to the STC rating. Along the boundary the rated walls range from STC 49-58, the glass in the spec calls for a minimum of STC 26, and in the north east and south west corners by the stairwells there is no STC rating. What is the desired sound attenuation level to be achieved by the secure boundary?
Wall types indicated on the drawings are correct.
The vestibule entering the secure area is only STC rated on two sides. Should the entire vestibule carry the same STC rating on all walls?
No.
The doors and glass that are in the STC walls do not carry an STC rating. This will be a point of failure in regard to sound attenuation if installed as designed.
Please advise.
Specified doors and glass indicated on the drawings are correct.
Please confirm the foil backed drywall on the exterior walls is only being used as a vapor barrier and not for Tempest protections.
Correct.
90 09 72 00 1A408
The spec section for
Wallcoverings does not include any information for the Digital Wall Covering.
Please provide a spec or cut sheet that can be referenced.
Information is provided in the contract documents. In addition to 1A408 and 09 72
00 paragraph 2.2, see also
1I601.
91 07 27 10.00 10 1.8
Specification states that Air
Barrier Inspector should review the design and list deficiencies and propose corrective action. With the drawings complete thru
CD’s. Is this still required?
WT intention is to have inspector review submittals for any interface concerns.
Is this acceptable?
Yes, Air Barrier Inspector must review the design and list deficiencies and propose corrective action. Having inspector review submittals for any interface concerns is appropriate.
92 07 27 10.00 10 3.1.1
Spec requires daily reports for ENTIRE installation process. It reads that these reports are to be completed by AB Inspector.
Section 07 27 10.00 10 paragraph 3.1.1 requires the contractor to provide a daily inspector for the entire installation process. Section
01 91 00.15 22 paragraph
3.1.4.2.b. is referring to the
Government-provided third-party Comissioning Authority.
Spec section 01 91 00.15 22 paragraph 3.1.4.2.b. clearly states that Inspector will be on site at least twice for each building envelope to inspect installation prior to testing.
What is the desired intent for Air Barrier Inspections prior to testing?
93 Attachment H
1S101, 2S101
Attachment H indicates 3
CTP Compression Test
Piles and 7 Pile-Driving
Test Piles. Dwgs 1S101 and
2S101 and the spec indicate a total of 4 CTPs and 6 Pile-
Driving Test Piles. Please clarify.
Number of test piles indicated on the drawings are correct.
94 Attachment H CLIN 0005
Neither the project specs nor the Details A2 and B2 on
2A503 call out what type of metal siding is desired.
Please provide a spec or cut sheet that can be referenced.
Refer to spec section 07 42 13.
95 02 41 00
Will the Government be removing any material that is being stored in building
121? If not and the contractor is to do so, does any of it contain hazardous material?
Material in Building 121 (as shown in the photos on the drawings) must be removed by the contractor. Refer to hazardous material reports in the specifications.
96 02 41 00
Is mold present in either building 121 or 49? The photos do not clearly show, nor was it able to assess from the site visit. The documents do not state either. If so this is an EHS consideration for PPE, among other possible ramifications. Please advise.
Please see attachment regarding mold presence in building 121.
97 02 41 00
Are there any liquids or powders contained in the piping systems of buildings
121 or 49 that are hazardous or require special handling?
Unknown.
01 30 01.00 22 and 1.3
The Government estimates for the FF&E and A/V on
Refer to Amendment 0002
Continuation Sheet.
Attachment H
Attachment H are in conflict with the estimates stated in spec section 01 30 01.00
22. Please clarify.
99 09 72 00 2A407
A1/2A407 refers to the
“Fabric Liner System Seal to Structure All sides”.
There is no description of the desired system in the specifications. What system is required? Does this require stick pins adhered to the back side of the metal panels? Is there supplemental framing required?
Refer to spec section 07 21 16 paragraph 2.3.5.
100 Attachment H
CLIN
0001AR
Please confirm that of all of the work described in this
CLIN the Contractor shall only be responsible for furnish and installation of all new cables and splices to existing cables.
The contractor is responsible for the entire CLIN, including work done by DTE.
101 Attachment H Amendme nt 02
Should the Total Price for
CLINs 0001-00010 now read “Total CLINs 0001-
0009”?
See updated Attachment H -
Price Proposal Form included with Amendment 0006.
102 07 81 00 1.2.2 1G103
Spec refers to UL Design
Reference N 925 for Fire
Proofing of Floor Supports.
This UL Design Reference cannot be located. Both the line item for Floor Decks in the same paragraph and the
Building Code Summary on
1G103 refer to D925 for
Floor Decks. Should this also read D925?
Yes, the spec should read
D925 for floor supports.
103 1A111
Please clarify where exactly is the wood veneer applied on the bulkhead? Which rooms are applicable? (Ref-
A3-1A512)
Refer to 1A401 and referenced elevations for extent of wood veneer.
104 01 30 01.00 22 1.4.1
Section 1.4.1 of Spec
Section states that the
Interior Designer of Record is to be NCIDQ certified. Is this flexible for a professional, specifically a registered architect whose practice has been concentrated on Interior
Design? If NCIDQ certification is absolutely required, can Interior
Design professionals work under the NCIDQ certified professional?
Propose per the specifications.
105 33 41 00 Note 16 1C118
For the Amendment 0002 notes regarding the requirement for a PE to be onsite while installing the jellyfish filters, is this to be a PE provided by the
Contractor or Government?
If by Contractor is the intent that it be a PE from Contec
Engineered Solutions or does it matter?
The PE must be provided by the contractor. The PE is not required to be from Contec
Engineered Solutions.
1S002, 2S002
Pile capacities have been provided per each of the three structures. As it is a delegated design, please provide the actual column loads (dead and live loads) at the base plate of the footings for each of the three structures in order to prepare an appropriate proposal based on the capacities achievable per the subcontractor design.
Piles are not a delegated design item.
107 10 22 39 3.2.3
Spec 3.2.3 states (NIC) of
52 plus or minus – Operable
Partitions typically use STC for the acoustic Sound
Rating. For a NIC rating of
52 the panel would need to be approx. STC 60 plus, which is not available.
Please verify that the BOD should be the Modernfold
Encore STC 52?
Verified.
| Amendment 0006-1 |