P-106 Manufacturing Support Facility 1585933

SECTION 10 51 13

METAL LOCKERS

05/11

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN ARCHITECTURAL MANUFACTURERS ASSOCIATION (AAMA)

AAMA 611 (2014) Voluntary Specification for Anodized Architectural Aluminum

ASTM INTERNATIONAL (ASTM)

ASTM B209 (2014) Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate

U.S. GENERAL SERVICES ADMINISTRATION (GSA)

FS AA-L-00486 (Rev J) Lockers, Clothing, Steel

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-02 Shop Drawings

Types; G Cell Phone Lockers

Location; G O/A Building

Installation

Numbering system; G

SD-03 Product Data

Material

Locking Devices; G

Lock Control Chart; G

Finish

Locker components

SECTION 10 51 13 Page 1

Assembly instructions

SD-04 Samples

Finish chips; G

1.3 DELIVERY, HANDLING, AND STORAGE

Deliver lockers and associated materials in their original packages, containers, or bundles bearing the manufacturer's name and the name of the material. Protect from weather, soil, and damage during delivery, storage, and construction.

1.4 FIELD MEASUREMENTS

To ensure proper fits, make field measurements prior to the preparation of drawings and fabrication. Verify correct location

1.5 QUALITY ASSURANCE

1.5.1 Finish Chips

Provide a minimum of three finish chips, not less than 3 inches square, of finish indicated.

Government may request performance-characteristic tests on assembled lockers. Tests and results must conform to FS AA-L-00486. Lockers not conforming will be rejected.

PART 2 PRODUCTS

2.1 TYPES

Locker must have the following type and size in the location and quantities indicated.

2.1.1 Cell Phone Lockers

Cell Phone lockers must be as follows:

Depth: 8" (nom) Height: 49" Width: Vest 111 - 93 inches(nom) Vest 100 - 67 inches (nom) Vest 100 54 inches (nom)

Basis of Design: Salsbury Cell Phone Lockers

2.2 MATERIAL

2.2.1 Aluminum Sheet

ASTM B209, commercial quality, minimized spangle material. Prepare material surfaces for anodized finishing.

2.2.2 Finish

Clear anodized per AAMA 611.

SECTION 10 51 13 Page 2

2.3 COMPONENTS

2.3.1 Built-In Locks

Provide locking devices as built-in key locks, master-keyd. Submit Lock Control Chart showing each lock required for the project, the locker identification plate number, and the keying.

a. 1 key for each lock, as well as 3 master keys

2.3.2 Doors

Manufacturer's standard aluminum sheet.

2.3.2.1 Hinges

Manufacturer's standard piano hige. Weld or bolt hinges to the door frame. Weld, bolt, or rivet hinges to the door.

2.3.3 Label Holders

Manufacturer's standard plastic card holder.

PART 3 EXECUTION

3.1 ASSEMBLY AND INSTALLATION

Assemble lockers according to the locker manufacturer's instructions.

Align lockers horizontally and vertically. Secure lockers to wall with screws as indicated. Bolt adjacent lockers together. Adjust doors to operate freely without sticking or binding and to ensure they close tightly.

3.2 NUMBERING SYSTEM

Install number plates on lockers consecutively as identified in approved shop drawing..

3.3 FIELD QUALITY CONTROL

3.3.1 Testing

Government may request performance-characteristic tests on assembled lockers in accordance with FS AA-L-00486. Lockers not conforming will be rejected.

3.3.2 Repairing

Remove and replace damaged and unacceptable portions of completed work with new.

3.3.3 Cleaning

Clean surfaces of the work, and adjacent surfaces soiled as a result of the work, in an approved manner. Remove equipment, surplus materials, and rubbish from the site.

-- End of Section --

SECTION 10 51 13 Page 3

10 51 13 - METAL LOCKERS
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 DELIVERY, HANDLING, AND STORAGE
1.4 FIELD MEASUREMENTS
1.5 QUALITY ASSURANCE
1.5.1 Finish Chips
PART 2 PRODUCTS
2.1 TYPES
2.1.1 Cell Phone Lockers
2.2 MATERIAL
2.2.1 Aluminum Sheet
2.2.2 Finish
2.3 COMPONENTS
2.3.1 Built-In Locks
2.3.2 Doors
2.3.2.1 Hinges

2.3.3 Label Holders

PART 3 EXECUTION
3.1 ASSEMBLY AND INSTALLATION
3.2 NUMBERING SYSTEM
3.3 FIELD QUALITY CONTROL
3.3.1 Testing
3.3.2 Repairing
3.3.3 Cleaning