This document contains questions and responses related to a solicitation for maintenance dredging projects at U.S. Fleet Activities in Sasebo, Japan. The solicitation involves dredging Juliet Basin to a depth of 11 meters from the chart datum line, repairing pile guides and decks on Piers 1004, 1005, and 1006, and removing and disposing of sunken sections of Pier 1006. Bidders had questions about requirements for key personnel, dredging methods, disposal locations, construction schedules, and coordination with government activities. The responses provide clarification on acceptable qualifications for quality control managers, flexibility in dredging and disposal methods subject to regulations, potential delays due to government operations, and availability of reference drawings and site visits.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment (7)_Amend 0004
PRE PROPOSAL INQUIRY FORM
RFP No.: IFB N4008420B6501 Project Title: Maintenance Dredging PH-1, Juliet Basin at the CFAS, Japan (eP# 1624336)
Question No.
Reference (Sect/Para/Page)
QUESTION
GOVERNMENT RESPONSE
Can one set of Key Personnel (SSHO, QCM, & Superintendent) be used for all three CLINs (0001, 0002, & 0003)?
Yes, one set of Key Personnel (1-SSHO, 1-QCM, and 1-Superintendent) for this contract action is acceptable.
#1623066 Section 01 45 00.00 33 Para 1.5.1.2
In Amendment 01 on 26 Nov 2019, it is indicated that the number of Key Personnel (SSHO, QC and Superintendent) can be one who fulfill the requirements among all three constructions. Since the QC requirement for Pontoon & Pile Guide work are not required with a graduate of a four-year accredited college.
Shall the qualification of QC as four-year college graduate be still required as one whole project?
It will be acceptable to have a QCM that is not a four year college graduate for the entire project.
Section 01 35 26.00 33 Para 1.7.1.4.3
Regarding the CDSO requirement, can SSHO serve as CDSO in this project?
Also, can dredge or fill crew be selected as CDSO? Is the training of Govt required for CDSO?
Yes, SSHO can serve as CDSO.
No, dredge or fill crew cannot be selected as
CDSO.
As per 1.7.1.4.3 of Section 01 35 26.00 33,
- "The assigned CDSO must be an individual (s) with work oversight responsibilities, such as master, mate, fill foreman, or superintendent", and
- "A CDSO must not be an employee responsible for continuous mechanical or equipment operations, such as an equipment operator."
Yes, training be required.
As per 1.7.1.4.4 of Section 01 35 26.00 33,
- A CDSO for dredging contracts must take either an OSHA 30-hr Construction Safety Course or an equivalent 30-hr ...
- The acceptable equivalents to the 30-Hour OSHA Construction Safety Course are listed in NOTE 1 and NOTE 2 for 1.7.1.1 of Section 01 35
26.00 33.
Section 00 10 Item No.
0001AB ~
0001Ae
There are three kinds of disposal facility for dredged soil: Controlled landfill facility, Uncontrolled landfill facility, and Recycling facility. It is difficult for us to select a proper disposal facility. Is it possible for Government to provide us the instruction for selecting a disposal facility?
No, the information of disposal facility will not be provided by the Government. The Government requires bidders to select each disposal facility.
It can be same unit cost if the disposal soil is controlled in accordance with JEGS, Japanese law, and local regulations indicated spec section 35 20 23. 00 33 Para 3.4.3 Final Processing Facility.
Section 00 10 Item No.
0001AB~
0001AE
According to the dredging company, it is difficult to separate into three types of the dredged soil.
Is it possible for us to dispose the dredged soil in one place?
Soil disposal must in accordance with JEGS, Japanese law, and local regulations indicated spec section 35 20 23. 00 33 Para 3.4.3 Final Processing Facility. If JEGS, Japanese law, and local regulations allow one disposal location then it will be acceptable.
35 20 23 00 Para 3.3.8
It is specified in spec section 35 20 23 00 33 para 3.3.8, "Anchors, chains, firearms, and other articles of value, which are brought to the surface during dredging operations, must remain or become the property of the Government and must be deposited on shore at a convenient location near the site of the work, as directed by the contracting officer."
Could the Government clarify the location to store these items?
The location to store is in Sasebo base.
Convenient location near the dredging work site shall be decided with the Contracting Officer after the award.
35 20 23 00 Para 3.3.8
Regarding a diving survey, is there any special specification for diving equipment and diving method? (Comply with the standard specification of MLIT?)
There is no any special specification. Comply with standard specification of MLIT. But the diving plan is required in this project. See 01 35 26. 00 33
GOVERNMENTAL SAFETY REQUIREMENTS
para 1.15 DIVE SAFETY REQUIREMENTS.
35 20 23 00 Para 3.3.1.1
Regarding the magnetic survey, shall the survey be performed at all areas as indicated on design drawing?
The required magnetic survey area is clearly shown on the design drawing C-101.
In case the estimated quantity for transportation and disposal cost of the excavated and dredged soil and the actual quantity of the unit-priced item varies more than 15% above the estimated quantity, shall be made an adjustment for the contract price?
In accordance with FAR 52.211-18 Variation in Estimated Quantity, if the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity. Additionally, if the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing, an extension of time, to be received by the Contracting Officer within 10 days from the beginning of the delay, or within such further period as may be granted by the Contracting Officer before the date of final settlement of the contract. Upon the receipt of a written request for an extension, the Contracting Officer shall ascertain the facts and make an adjustment for extending the completion date as, in the judgement of the Contracting Officer, is justified.
Is the unloading location of dredged soil (in the pier) confirmed? If so, please specify.
No, the unloading location of dredged soil is not confirmed. Government requires bidders to select the disposal facility.
35 20 23.00 Para 3.5
Regarding hydrographic survey for JCG to edit the chart after dredging, shall it be done at one time? Or, shall the hydrographic survey be divided into J1~J3?
Hydrographic survey for JCG to edit the chart shall be divided in two area J3 and J1, J2 in accordance with Spec section 01 11 00.00 33 Para 1.6.2 Sequence work.
35 20 23.00 Para 3.5
It will take three months to prepare the hydrographic report after sounding is completed.
(It is understood that it will take up six months for JCG to reflect the survey result in the chart.)
The construction period is determined including mailing period, preparation and site work. Period of work sequence in spec section 01 11 00. 00 33 Para 1.6.2 is government concept. Offeror must propose considering work schedule within total project period mentioned in spec 01 11 00. 00 33 Para 1.6.1.
Since the construction area around PIER-1 thru PIER-1006 is very narrow, the construction shall be performed by using a small backhoe dredger and small sand barge.
In case the soil disposal facility is located distance away, the transportation by a sand barge will become inefficient.
Can the transportation by a gatt barge be considered?
Yes, if safety, environmental and regulations are taken consideration, the contractor can select the construction method.
When the construction being performed around each pier, is it possible for the Government's ship to be reassigned the different pier?
Government ship operation is priority. Contractor must follow the Contracting Officer's decision if work is suspended.
It is shown in the spec section 01 14 00. 00 33 Para 1.3.Special Schedule Requirements d and
1.3.11 Government Berthing Operation c.
When the contractor's vessel must leave the Juliet Basin for the Government's purpose, can vessel anchor offshore within the Government controlled area?
Government ship operation is priority. This is case by case situation. Contractor must follow the Contracting Officer's decision if Contractor’s vessel can anchor offshore within the Government controlled area or not.
35 20 23.00 Para 3.3.7.1
For the construction near the piers, it is hard to use Turbidity Protection Floating Frame. Is it possible to extend Turbidity Protection Curtain instead?
Yes, it is possible.
35 20 23.00 Para 3.3.7
In case that the thickness of soil is shallow, it is difficult for us to dredge by a grab dredging method. Is it allowed for us to use other method?
Yes, it is allowed if Government has the benefits and under Government approval.
01 11 00.00 Para 1.6.1
Although the construction period on the project
"MAINTENANCE DREDGING PH-1, JULIET
BASIN (eProject #1623066)" is maximum 240 calendar days, berthing operations by Government may be taken for an maximum 90days during the construction period. Also, soil sampling which is one of the sequence work (1) will take 40 days. Is it possible for the Government to extend the construction period by 365 days and adjust the contract price?
Extended the construction period by 90 calendar days and changed from 240 calendar days to 330 calendar days. Offeror submit the proposal considering new construction period. Soil sampling is included in 330 calendar days.
An amendment for this will be issued.
ep#1559823 Drawing C- 507, C-103
Regarding Pile Guide Roller P-62 and P-66, it is specified in the DWG C-507, "HOIST AND INSTALL EXIST SUNKEN PILE GUIDE" and
"REPLACE PILE GUIDE ROLLER FLAME W/
NEW ONE (EAST SIDE)". Although P-65, P-67, P-68, P-109~112 are indicated in list of scope of works (PIER 1006) on the DWG C-103, there are no each number on the drawing.
However, they are specified in the drawing for Scope Of Work of the project "Removal and Disposal of Sunken Sections of Pier 1006 Sasebo, Japan." Which is correct?
Government drawing C-103 (NAVFAC DWG NO.
17216052) and C-507 (NAVFAC DWG NO.
17216059) have been revised with deleting the P-numbers on the drawing.
ep#1559823
There are some differences between work list indicated on the drawing and actual condition.
For example, although existing pile guide anchor is broken, there is no work instruction.
Should we estimate a proposal based on the drawing?
The Contractor’s proposal shall be based on the drawings.
ep#1559823 Is the hoisted place of pontoon confirmed?
If so, please specify
Pontoons can be hoisted in various locations throughout the pontoon. See file named:
“Reference dwg_ #1004 #1005 #1006.pdf” ep#1559823 Is it possible for Government to provide us design drawing for damaged pontoons?
Also, if the detailed survey information is available, is it possible for the Government to provide us?
The following reference drawings will be provided.
(1) Reference dwg_Pier-2.pdf
(2) Reference dwg_ #1004 #1005 #1006.pdf ep#1559823 In case that there is no detailed drawing for existing damaged pontoon available, is it possible for us to enter the pontoon area to conduct a survey by a dive in advance?
See #22 response.
ep#1559823 To consider the hoisting method of damaged pontoon with a specialized contractor, is it allowed for us to visit the site to verify the condition?
Possibly if it is still necessary once the reference drawings provided by a future amendment are reviewed.
Should the worker engaged in ship work acquire the base access pass?
Also, is it possible for us to enter from outside of Juliet Basin to worksite area by work barge or passage?
Yes, a base access pass is required for all personnel entering the installation.
Yes, it is possible to enter from outside of Juliet Basin to worksite area by work barge or passage.
ep#1623066 ep#1559823
When the work is suspended due to the Government reasons, is it possible for Government to reimburse the cost of restricted vessels?
A line item will be added to the CLIN structure to account for possible down time due to Government operations so costs will already be a part of the contract once awarded.
ep#1559823
On the site visit of this project, the Government said that the estimated quantity and the actual quantity of the unit-priced item varies of increase and decrease in 15% estimated quantity, an adjustment in the contract price shall be made.
What is the maximum percent in case the contract price will be increased?
The Government has not identified a maximum amount at this time.
ep#1559823
Although the proposal due date on this project is 10 December 2019, we need more time to confirm the scope of work, site investigation by subcontractor, and estimated duration.
Is it possible for the Gov.to extend the closing date by one month?
The Government will extending the Bid Opening date. New due date is 10 JAN 2020, 10:00 am.
Amend 02 PPI response (No.21)
The question below is re-submitted to clarify the question No.21 in amend 02; Is there any place where the hoisted pontoon shall be placed to demolish?
The location for the disposal/demolish of the pontoons will be off base as determined by the Contractor.
Is it possible for us to visit the site? The 2nd Site Visit will be conducted. See Amendment 0003.
If the construction method considered at the time of proposal has been changed, shall an adjustment for the contract price be made?
The construction method is determined by the Contractor. The appropriate method should be selected based on the contract plans, specifications, & site visit(s) prior to contract award.
A contract price adjustment will not be made based on the Contractor selecting a different construction method after the contract is awarded.
If JCG directs us to perform the hydrographic survey at one time, shall it be done at one time?
Yes, follow the JCG direction and report to the Contracting officer.
Gov. answer No.16 In Amend 02
After the Turbidity Protection Floating Frame is provided, vessel will not be able to berth. Is it allowed?
Yes, the vessel of Government will not berth at work area during dredging construction.
However contractor must follow the Contracting Officer’s decision if work is suspended for Government ship operation.
Gov. answer No.27 In Amend 02
Although it is indicated as "There is no maximum percentage increase or decrease specified in FAR 52.211-18" on the Gov.
answer, is there no maximum amount to increase the contract price?
There is no maximum percentage increase or decrease specified in FAR 52.211-18. As such, there is no maximum JPY increase or decrease in contract price.
The contractor shall promptly notify the Government if they expect the quantity to vary more than 15 percent above or below the estimated quantity.
According to the drawing, dredged soil shall be included YOBORI (30cm). Should we maintain the maintenance depth indicated on the drawing? It seems to become deeper if YOBORI is included.
Yes, the maintenance depth indicated on the drawing must be maintained.
Dredged soil volume on the drawing is included YOBORI (30cm).
For dredging work, is there any possibility that dredging work will be interrupted by other than related Gov. regulation.
There is a possibility that dredging work can be interrupted by Non-Government related actions….i.e. weather/natural disasters.
Currently, there is no accurate sounding measurement data existed.
Also, the size and quantity of construction area are not clear, and also it is not clear in those of transporting distance to a sediment disposal facility; treatment capacity per day; accepting agency's requirement.
After pre-survey is completed and sediment disposal facility is determined, the specification of workship and the number of ships will be considered.
Is it possible for the Gov. to modify the design including the extension of construction period?
Dredging area is clearly shown in drawing C-101.
Dredging volume is shown in drawing and spec for biding purposes, so offeror should bid based on the provided information.
If dredging volume is much different from the assumption, a modification will be done to include additional contract time.
The disposal facility shall be determined by the Offeror and the Offeror shall provide their bid based on the disposal facility selected.
Although it is specified that YOHORI is 0.3m, in case that the depth of water is more than - 0.9m, the depth of YOHORI at the bottom is 0.6m and the width of YOHORI is 4.0m according to the estimate standard by the Japanese Government (Kokudo Kotsu Shou).
And it looks difficult to meet 0.3m, is it possible to change it?
Government requires the dredging depth shown in drawing and consider the YOBORI volume 0.3m.
Offeror can dredge only depth to keep the required dredging depth. But government will count the dredging volume with required depth plus YOBORI 0.3m.
According to the drawing, required dredging depth is 11.0m from C.D.L.
However, it is assumed that the survey error might affect the accuracy of dredging when managing the production.
Is it possible for Gov to modify the dredging depth from -11.0m to -11.2m?
Government requirement for dredging depth is 11.0m from C.D.L.
Contractor shall provide accurate survey.
Regarding hoisting work for pontoon, is it possible for workers to perform drainage work on the pontoon while it is hoisted at sea level by a floating crane?
The decision to perform drainage work of the pontoon is the Contractor’s responsibility. The Government requires the sunken pontoons removed and disposed of.