This document is an amendment to a federal solicitation that extends the price proposal due date for the Multiple Award Construction Contract (MACC) from 16 July 2025 to 31 July 2025, while maintaining the non-price proposal due date of 16 July 2025. The amendment revises proposal submission instructions, requiring offerors to submit separate price and non-price proposals in PIEE, with previous non-price proposals remaining valid unless an offeror indicates withdrawal.
The amendment also addresses several inquiries related to the Project Labor Agreement (PLA) requirement, with the government consistently responding that PLA requirements remain in effect and should conform to FAR 22.504, Executive Order 14063, and related orders. Offerors raised concerns about PLA impacts on competition, market feasibility, and subcontractor labor requirements, but the government maintained its stance on the PLA mandate. One offeror requested additional time to negotiate the PLA and resolicit subcontractor pricing, which will be addressed in a subsequent amendment.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The purpose of this amendment is to:
1. Extend the price proposal due date to 31 July 2025 NLT 1400 local time
Non-Price Proposal due date remains unchanged at 16 July 2025 NLT 1400 local time
2. Revise the submittal structure for Price and Non-Price Proposals
3. Provide PPI responses
1. The price proposal due date for N4008025R9500 is hereby extended from 16 July 2025 to 31 July 2025 NLT 1400 Local Time.
Non-price proposals remain due on 16 July 2025 NLT 1400 Local Time.
Offerors must submit both a price and non-price proposal in order to be eligible for award.
2. Section 00 21 00 - Instructions
INSTRUCTIONS TO PROPOSERS
5.2 PROPOSAL SUBMISSION INSTRUCTIONS
5.2.1 In response to this request for proposal, Offerors shall submit a separate Price Proposal and Non- Cost/Price Factors Proposal, submitted in accordance with the Basis of Evaluation and Submittal Requirements for Each Factor and as follows:
Non-Price Proposal: Offerors shall submit a non-price proposal in PIEE by the established due date and time. Offerors who have previously submitted a non-price proposal need not re-submit unless there are revisions. Offerors who wish to use a previously submitted non-price proposal do not need to submit again in PIEE. If an offeror intends to revise their non-price proposal, the Offeror must re-submit the non-price proposal IN WHOLE. The Government will not accept partially revised proposals. The Government intends to evaluate non-price proposals previously received unless an Offeror indicates their withdrawal by 16 July 2025.
Price Proposal: Price proposals shall be submitted in PIEE in accordance with the requirements established in Amendment 0016 and this amendment (including ATT H Price Proposal From (REV 05132025) and a fully executed PLA)
3. PPI Responses:
Reference Inquiry Government Response
# Page Section Para
Amendment
The addition of a PLA requirement substantially impacts our interest in this procurement and the location of the seed project makes a PLA even more challenging.
As previously discussed, the terms of the PLA previously proposed for this market limits competition at the subcontract level which we believe is a violation of the Competition in Contracting Act. We will be unable to submit a revised proposal with a PLA by the requested date and would recommend that NAVFAC perform market research for the PLA requirement first.
PLA requirement remains, Bid per RFP.
693 Amendment 0016 Please confirm that executing a PLA with one trade organization is sufficient to meet the PLA requirement for this solicitation as per FAR 52.222-33(b)(1), and 52.222- 34 Alt II (b)(1).
PLAs should conform to FAR 22.504, EO 14063, and related orders.
694 Amendment 0016 Please confirm that the only parties that would need to use unionized labor for this project are the relevant subcontractors/vendors that would solicit labor through the organization that is signatory to the PLA.
PLAs should conform to FAR 22.504, EO 14063, and related orders.
695 Amendment 0016 Please confirm that market research has been done in the geographic area of the seed project to confirm the economic and physical feasibility of the PLA requirement.
Confirmed, Bid per RFP.
696 Amendment 0016 We are requesting additional time to negotiate a PLA with
See Amendment 0017.
the labor unions as well as solicit new pricing from the subcontractor market. The four (4) weeks provided in the last amendment is not adequate enough and we are requesting an additional four
(4) weeks to negotiate a PLA and resolicit pricing for this project.