This document contains responses to pre-award inquiries for solicitation number N4008023R0007. The solicitation is for the construction of a vehicle control center, commercial vehicle inspection building, four bay commercial vehicle inspection canopy, sentry booth, surface parking lot, and incidental related work at Marine Corps Base Quantico in Virginia. The vehicle control center and commercial vehicle inspection building will be single-story structures with reinforced concrete masonry walls, structural steel framing, and concrete slabs on grade supported by reinforced concrete spread footings. Inquiries were answered regarding missing specification sections, the government providing an allowance for furniture, fixtures and equipment, and the government's position on audiovisual costs not being disclosed to bidders. Referenced price sheets were also updated with a preliminary furniture, fixtures and equipment cost and additional notes.
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION NO. N4008023R0007
PROJECT TITLE/LOCATION: P656 VEHICLE INSPECTION AND VISITOR CONTROL CENTER, MARINE CORPS BASE, QUANTICO, VA
PREAWARD INQUIRY FORM
July 2011
Page Section Para.
22 12/19/2022
In reviewing the specifications for the above referenced project, we noticed that sections 7 and 8 are missing. Would you kindly forward to me at your earliest convenience? Also, Is the government providing an allowance for FF&E and Audio- Visual? Please advise.
- Please refer to PPI 12 and 13 for spec sections 7 and 8.
- Please refer to PPI 23 for FF&E.
- GOV position will not be disclosed to the bidders for Audio-Visual.
12/22/2022
23 12/13/2022 Price Sheet
CLIN 0003 FF&E suggest the Government will provide an estimated budget for the KTR provided HAR% rate to multiply the budget by to receive a TOTAL FF&E amount. Please provide an estimated budget for the FF&E on the Pricing Sheet.
Refer to updated Price Schedule for the Preliminary FF&E cost and additional notes.
12/22/2022
Posted on Amend No.
REFERENCEQuestion
No. QUESTION GOVERNMENT RESPONSEDate Received
Sheet1