This federal contract opportunity solicitation is for the construction of a vehicle inspection and visitor control center (VCC), commercial vehicle inspection building (CVI), four bay commercial vehicle inspection canopy, sentry booth, surface parking lot, and incidental related work at a Navy facility. The Department of the Navy Naval Facilities Engineering Command is seeking these construction services with the VCC and CVI as single-story facilities utilizing reinforced concrete masonry walls, structural steel framing, and concrete slabs on-grade supported by reinforced concrete spread footings. Offerors should respond to solicitation number N4008023R0007 by the specified due date for consideration of this contract award.
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WORK ORDER NO. 1620397
Installation Project No. P656
IFC SPECIFICATIONS
9/12/2022
VEHICLE INSPECTION AND
VISITOR CONTROL CENTER
Marine Corps Base Quantico – Quantico, Virginia
PREPARED BY:
NAVFAC Washington, Design and Construction 1314 Harwood Street, SE, Bldg. 212
Washington, DC 20374
Architectural: Edward Monroe Mechanical: Andrew Gibson Interior: Erika Beard Plumbing: Wilson Wingo, PE Civil: Robert Williams, PE Electrical: Eu Chuah Structural: Adam Thomas, PE Communications: Richard Kemp, RCDD Geotechnical: Karl Hren, PE Fire Protection: Shay Wu, PE Traffic: Mark Tuch, PE Physical Security: Shawn Whalen, PE Landscape: Brian Niemann Cybersecurity: Aaron Brittain, GICSP ATFP: Coy Burney, RA Specifications: Christian Olivera, PE
Submitted By: Date: Harold Rodriguez, PE
Gov. Design Manager
Project Manager: Hector Fernandez, AIA Date:
Approved By: Date: Jennifer E. Blaess, RA
Design Production Director harold.rodriguez Stamp harold.rodriguez Text Box 09-12-2022
P-656 VEHICLE INSPECTION & VISITOR CONTROL CENTER JON 1620397
Marine Corps Base Quantico Quantico, VA
PROJECT TABLE OF CONTENTS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 20 00 PRICE AND PAYMENT PROCEDURES
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 30 01.00 23 DESIGN, PROCUREMENT, AND INSTALLATION OF FURNITURE,
FIXTURES, AND EQUIPMENT
01 31 23.13 20 ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT
MANAGEMENT SYSTEM
01 32 17.00 20 COST-LOADED NETWORK ANALYSIS SCHEDULES (NAS)
01 33 00 SUBMITTAL PROCEDURES
01 33 29 SUSTAINABILITY REQUIREMENTS AND REPORTING
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 20 QUALITY CONTROL
01 45 35 SPECIAL INSPECTIONS
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 57 19.01 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 PROJECT IDENTIFICATION
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
01 78 24.00 20 FACILITY ELECTRONIC OPERATION AND MAINTENANCE SUPPORT
INFORMATION (eOMSI)
01 78 30.00 23 CADD DATA FOR GIS DELIVERABLES
01 91 00.15 20 TOTAL BUILDING COMMISSIONING
DI VI SI ON 02 - EXI STI NG CONDI TI ONS
02 41 00 DEMOLITION
DI VI SI ON 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
03 45 33 PRECAST PRESTRESSED STRUCTURAL CONCRETE
DI VI SI ON 04 - MASONRY
04 20 00 UNIT MASONRY
DI VI SI ON 05 - METALS
05 05 20.00 27 POST-INSTALLED CONCRETE AND MASONRY ANCHORS
05 05 23.16 STRUCTURAL WELDING
05 12 00 STRUCTURAL STEEL
05 21 00 STEEL JOIST FRAMING
05 30 00 STEEL DECKS
05 40 00 COLD-FORMED METAL FRAMING
DI VI SI ON 06 - WOOD, PLASTI CS, AND COMPOSI TES
06 20 13 EXTERIOR FINISH CARPENTRY
DI VI SI ON 09 - FI NI SHES
PROJECT TABLE OF CONTENTS Page 1
09 30 10 CERAMIC, QUARRY, AND GLASS TILING
09 65 00 RESILIENT FLOORING
09 68 00 CARPETING
09 72 00 WALLCOVERINGS
09 90 00 PAINTS AND COATINGS
DI VI SI ON 10 - SPECI ALTI ES
10 14 00.20 INTERIOR SIGNAGE
10 28 13 TOILET ACCESSORIES
10 51 13 METAL LOCKERS
DI VI SI ON 12 - FURNI SHI NGS
12 00 01.00 20 FURNITURE, FIXTURES AND EQUIPMENT (FF&E) PACKAGE
12 24 13 ROLLER WINDOW SHADES
12 93 00 SITE FURNISHINGS
DI VI SI ON 22 - PLUMBI NG
22 00 00 PLUMBING, GENERAL PURPOSE
DI VI SI ON 23 - HEATI NG, VENTI LATI NG, AND AI R CONDI TI ONI NG ( HVAC)
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC
23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING
CONTROL SYSTEMS
23 11 20 FACILITY GAS PIPING
23 23 00 REFRIGERANT PIPING
23 30 00 HVAC AIR DISTRIBUTION
23 81 00 DECENTRALIZED UNITARY HVAC EQUIPMENT
23 81 29 VARIABLE REFRIGERANT FLOW HVAC SYSTEMS
23 82 00.00 20 TERMINAL HEATING UNITS
23 83 00.00 20 ELECTRIC SPACE HEATING EQUIPMENT
DI VI SI ON 25 - I NTEGRATED AUTOMATI ON
25 05 11 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS
25 10 10 UTILITY MONITORING AND CONTROL SYSTEM (UMCS) FRONT END
AND INTEGRATION
DI VI SI ON 26 - ELECTRI CAL
26 08 00 APPARATUS INSPECTION AND TESTING
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 27 14.00 20 ELECTRICITY METERING
26 32 15.00 ENGINE-GENERATOR SET STATIONARY 15-2500 KW, WITH
AUXILIARIES
26 36 23 AUTOMATIC TRANSFER SWITCHES AND BY-PASS/ISOLATION SWITCH
26 41 00 LIGHTNING PROTECTION SYSTEM
26 51 00 INTERIOR LIGHTING
26 56 00 EXTERIOR LIGHTING
DI VI SI ON 27 - COMMUNI CATI ONS
PROJECT TABLE OF CONTENTS Page 2
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
27 40 00 AUDIO-VIDEO COMMUNICATIONS
DI VI SI ON 28 - ELECTRONI C SAFETY AND SECURI TY
28 08 10 ELECTRONIC SECURITY SYSTEM ACCEPTANCE TESTING
28 10 05 ELECTRONIC SECURITY SYSTEMS (ESS)
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM,
ADDRESSABLE
DI VI SI ON 31 - EARTHWORK
31 11 00 CLEARING AND GRUBBING
31 23 00.00 20 EXCAVATION AND FILL
DI VI SI ON 32 - EXTERI OR I MPROVEMENTS
32 05 33 LANDSCAPE ESTABLISHMENT
32 11 20 BASE COURSE FOR RIGID AND SUBBASES FOR FLEXIBLE PAVING
32 11 23 AGGREGATE BASE COURSES
32 11 23.23 BASE COURSE DRAINAGE LAYERS
32 11 26 HOT-MIX BITUMINOUS BASE COURSE FOR ROADS AND STREETS
32 12 16.16 ROAD-MIX ASPHALT PAVING
32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE
FACILITIES
32 14 13.13 INTERLOCKING PRECAST CONCRETE UNIT PAVING
32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 PAVEMENT MARKINGS
32 84 24 IRRIGATION SPRINKLER SYSTEMS
32 92 19 SEEDING
32 92 23 SODDING
32 93 00 EXTERIOR PLANTS
DI VI SI ON 33 - UTI LI TI ES
33 11 00 WATER UTILITY DISTRIBUTION PIPING
33 11 23 NATURAL GAS AND LIQUID PETROLEUM PIPING
33 30 00 SANITARY SEWERAGE
33 31 23.00 10 SANITARY SEWER FORCE MAIN PIPING
33 32 16 PACKAGED UTILITY WASTEWATER PUMPING STATIONS
33 40 00 STORMWATER UTILITIES
33 46 13 FOUNDATION DRAINAGE
33 46 16 SUBDRAINAGE PIPING
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
DI VI SI ON 34 - TRANSPORTATI ON
34 40 00 TRAFFIC SIGNALIZATION
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 3
THIS PAGE INTENTIONALLY LEFT BLANK
PROJECT TABLE OF CONTENTS Page 4
SECTION 01 11 00
SUMMARY OF WORK
08/ 15, CHG 1: 05/ 21
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals Salvage Plan ; G
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The project includes the construction of a vehicle control center (VCC, 3,326 GSF), commercial vehicle inspection building (CVI, 860 GSF), four bay commercial vehicle inspection canopy (5,880 GSF), sentry booth (64 GSF), surface parking lot, and incidental related work. The VCC and CVI facilities will be single-story with reinforced concrete masonry walls, structural steel framing, and concrete slabs on-grade supported by reinforced concrete spread footings.
1.2.2 Location
The work is located at Marine Corps Base Quantico in Quantico, Virginia, as shown in the contract drawings . The exact location will be shown by the Contracting Officer.
1.3 OCCUPANCY OF PREMISES
The project site is an undeveloped, grassed and wooded area. The site is bound by Russell Road to the south, and grassed/wooded area to the north, east, and west. The Contractor will have control of the project premises within the limits of disturbance shown in the contract drawings, as limited and coordinated with the Contracting Officer.
Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, and space for storage of materials and equipment.
1.4 ON-SITE PERMITS
1.4.1 Utility Outage Requests and Utility Connection Requests
Schedule work to minimize outages. For utility outages and connections required during the execution of work that affect existing systems, schedule outside the regular working hours or on weekends, as approved by the Contracting Officer. Schedule utility outages and connections to minimize disruptions to the Government. No additional payment will be provided for utility outages and connections required to be performed outside the regular work hours.
SECTION 01 11 00 Page 1
Submit requests for utility outages and connections in writing to the Contracting Officer for approval at least 21 calendar days in advance of the time required. In each request, state the system involved, area involved, approximate duration of outage, and the nature of work involved.
1.4.2 Excavation Permits
Provide Excavation Permits within 21 calendar days prior to work
1.5 EXISTING WORK
In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.6 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.
Contact local utility locating service a minimum of 48 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.
Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities,and any type of underground or encased obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
Submit for an Excavation permit in accordance with the attached Standard Operating Procedures (SOP) for the MCB-Quantico Excavation Permit. An example EXCAVATION PERMIT REQUEST FORM is attached at the end of this section. Confirm with Contracting Officer at the Construction kick off meeting for the most updated permit process and forms.
1.6.1 Notification Prior to Excavation
Notify the Contracting Officer at least 48 hours prior to starting excavation work.
SECTION 01 11 00 Page 2
1.7 NAVY AND MARINE CORPS (GOVERNMENT) COORDINATION REQUIREMENTS
1.7.1 Government Contractor Access
Allow the Government Contractor access to the facility towards the end of construction (finishes 90 percent complete, rough-in 100 percent complete, Inside Plant (ISP)/Outside Plant (OSP) infrastructure in place) to provide equipment in the telecommunications rooms and make final connections.
Coordinate efforts with the Government Contractor to facilitate joint use of building spaces during the final phases of construction. After the Contracting Officer has facilitated coordination meetings between the two contractors, within one week, incorporate the effort of additional coordination with the Government Contractor into the construction schedule to demonstrate a plan for maintaining the contract duration.
1.8 SALVAGE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated area in the MCBQ, as determined by the Contracting Officer.
Provide a salvage plan , listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Use a system of property control that is approved by the Contracting Officer. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 3
SECTION 01 11 00 Page 4
SECTION 01 14 00
WORK RESTRICTIONS
11/ 11, CHG 12: 05/ 21
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel
1.2 CONTRACTOR ACCESS AND USE OF PREMISES
1.2.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.
1.2.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.2.1.2 Installation Access
Obtain access to Navy installations through participation in the Defense Biometrics Identification System (DBIDS). Requirements for Contractor employee registration, and transition for employees currently under Navy Commercial Access Control System (NCACS), are available at https://www.cnic.navy.mil/om/dbids.html . No fees are associated with obtaining a DBIDS credential.
Participation in the DBIDS is not mandatory, and Contractor personnel may apply for One-Day Passes at the Base Visitor Control Office to access an installation.
1.2.1.2.1 Registration for DBIDS
Registration for DBIDS is available at https://www.cnic.navy.mil/om/dbids.html . Procedure includes:
a. Present a letter or official award document (i.e. DD Form 1155 or SF 1442) from the Contracting Officer, that provides the purpose for access, to the base Visitor Control Center representative.
SECTION 01 14 00 Page 1
b. Present valid identification, such as a passport or Real ID Act-compliant state driver's license.
c. Provide completed SECNAV FORM 5512/1 to the base Visitor Control Center representative to obtain a background check. This form is available for download at https://www.cnic.navy.mil/om/dbids.html .
d. Upon successful completion of the background check, the Government will complete the DBIDS enrollment process, which includes Contractor employee photo, fingerprints, base restriction and several other assessments.
e. Upon successful completion of the enrollment process, the Contractor employee will be issued a DBIDS credential, and will be allowed to proceed to worksite.
1.2.1.2.2 DBIDS Eligibility Requirements
Throughout the length of the contract, the Contractor employee must continue to meet background screen standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.
An adjudication process may be initiated when a background screen failure results in disqualification from participation in the DBIDS, and Contractor employee does not agree with the reason for disqualification.
The Government is the final authority.
1.2.1.2.3 DBIDS Notification Requirements
a. Immediately report instances of lost or stolen badges to the Contracting Officer.
b. Immediately collect DBIDS credentials and notify the Contracting Officer in writing under the following circumstances:
(1) An employee has departed the company without having properly returned or surrendered their DBIDS credentials.
(2) There is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the Installation or anyone therein.
1.2.1.2.4 One-Day Passes
Personnel applying for One-Day passes at the Base Visitor Control Office are subject to daily mandatory vehicle inspection, and will have limited access to the installation. The Government is not responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the DBIDS.
1.2.1.3 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under
SECTION 01 14 00 Page 2 renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.2.2 Working Hours
Regular working hours will consist of a 10 hour period between 7 a.m. and 5:30 p.m., Monday through Friday, excluding Government holidays.
1.2.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.
1.2.4 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, telecommunication systems, and any others are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS.
d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.
Sanitary sewer and water connection permits are required to be obtained through the Base PWB Utilities Section.
e. Connection to Existing Sanitary Sewer Line: Provide positive verification that the existing line conveys sanitary sewer; verify line is not incorrectly connected to a storm drain.
1.3 SECURITY REQUIREMENTS
1.3.1 Marine Corps Base Quantico (MCBQ), Quantico, VA
All Contractor and its employees performing services on Marine Corps Base, Quantico (MCBQ) requiring physical access to the installation must be properly screened. Screening consists of identity proofing and vetting in accordance with the standards set forth in Marine Corps Base Order 4200.3 (28 JUL 10). The Contractor must request a copy of this policy from the
SECTION 01 14 00 Page 3
Contracting Officer.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 14 00 Page 4
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES
11/ 20, CHG 1: 02/ 21
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EP 1110-1-8 (2016) Construction Equipment Ownership and Operating Expense Schedule
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Earned Value Report ; G
1.3 EARNED VALUE REPORT
1.3.1 Data Required
This Contract requires the use of a cost-loaded Network Analysis Schedule (NAS). Schedule of Prices must not be used with cost-loaded Network Analysis Schedule (NAS). Use Earned Value Report derived from cost-loaded NAS. Provide a detailed breakdown of the Contract price, giving quantities for each of the various kinds of work, unit prices and extended prices.
Contractor overhead and profit including salaries for field office personnel, if applicable, must be proportionately spread over all pay items and not included as individual pay items.
1.3.1.1 Additional Facility Price Data
For all projects over $500K, the Contractor shall electronically submit Additional Facility Price Data to the Contracting Officer as a formal submittal within 15 days of Contract award. The cost break out will be in first or second level WBS format that will include:
a. Each individual facility to the five foot line.
b. The total site work/utilities from the five foot line outward.
Use CLIN 0001AA, AB, AC, and AD from UFGS 00 22 13.00 20 SUPPLEMENTARY INSTRUCTIONS TO OFFERORS, as an example on how to prepare the cost breakout structure. Contact the NAVFAC Washington Cost Engineer for additional information and guidance on the development of the cost breakout.
SECTION 01 20 00 Page 1
1.3.2 Payment Schedule Instructions
Payments will not be made until the Earned Value Report from the cost-loaded NAS has been submitted to and accepted by the Contracting Officer.
Additionally, the Earned Value Report must be separated as follows:
a. Primary Facilities Cost Breakdown:
Defined as work on the primary facilities out to the 5 foot line.
Work out to the 5 foot line includes construction encompassed within a theoretical line 5 foot from the face of exterior walls and includes attendant construction, such as pad mounted HVAC cooling equipment, cooling towers, and transformers placed beyond the 5 foot line.
b. Supporting Facilities Cost Breakdown:
Defined as site work, including incidental work, outside the 5 foot line.
1.3.3 Schedule Requirements for HVAC TAB
The field work requirements in Section 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC must be broken down in the Earned Value Report from the cost-loaded NAS by separate line items which reflect measurable deliverables. The value for each pay item listed below will be established on a case by case basis for each Contract. The line items are as follows:
a. Approval of Design Review Report: The TABS Agency is required to conduct a review of the project plans and specifications to identify any feature, or the lack thereof, that would preclude successful testing and balancing of the project HVAC systems. Submit the resulting findings to the Government to allow correction of the design. The progress payment will not be issued until the report is reviewed and approved.
b. Approval of the pre-field engineering report: The TABS Agency submits a report which outlines the scope of field work. The report must contain details of what systems will be tested, procedures to be used, sample report forms for reporting test results and a quality control checklist of work items that must be completed before TABS field work commences.
c. Season I field work: Incremental payments are issued as the TABS field work progresses. The TABS Agency mobilizes to the project site and executes the field work as outlined in the pre-field engineering report. The HVAC water and air systems are balanced and operational data must be collected for one seasonal condition (either summer or winter depending on project timing).
d. Approval of Season I report: On completion of the Season I field work, the data is compiled into a report and submitted to the Government. The report is reviewed, and approved, after ensuring compliance with the pre-field engineering report scope of work.
e. Completion of Season I field QA check: Contract QC and Government representatives meet the TABS Agency at the jobsite to retest portions
SECTION 01 20 00 Page 2 of the systems reported in the Season I report. The purpose of these tests are to validate the accuracy and completeness of the previously submitted Season I report.
f. Approval of Season II report: The TABS Agency completes all Season II field work, which is normally comprised mainly of taking heat transfer temperature readings, in the season opposite of that under which Season I performance data was compiled. Compile this data into a report and submit to the Government. On completion of submittal review to ensure compliance with the pre-field engineering report scope, progress payment is issued. Progress payment is less than that issued for the Season I report since most of the water and air balancing work effort is completed under Season I.
1.4 CONTRACT MODIFICATIONS
In conjunction with the Contract Clause DFARS 252.236-7000 Modification Proposals-Price Breakdown, and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, base equipment use rates upon the applicable provisions of the
EP 1110-1-8 .
1.5 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.5.1 Content of Invoice
Requests for payment will be processed in accordance with the Contract Clause FAR 52.232-27 Prompt Payment for Construction Contracts and FAR 52.232-5 Payments Under Fixed-Price Construction Contracts. Invoices not completed in accordance with contract requirements will be returned to the Contractor for correction of the deficiencies. The requests for payment shall include the documents listed below.
a. The Contractor's invoice, on NAVFAC Form 7300/30 furnished by the Government, showing in summary form, the basis for arriving at the amount of the invoice. Form 7300/30 must include certification by Quality Control (QC) Manager as required by the Contract.
b. The Earned Value Report from the cost-loaded NAS.
c. Contractor's Monthly Estimate for Voucher and Contractors Certification (NAVFAC Form 4330) with Subcontractor and supplier payment certification. Other documents, including but not limited to, that need to be received prior to processing payment include the following submittals as required. These items are still required monthly even when a pay voucher is not submitted.
d. Monthly Work-hour report.
e. Updated Construction Progress Schedule and tabular reports required by the contract.
f. Contractor Safety Self Evaluation Checklist.
g. Updated submittal register.
h. Solid Waste Disposal Report.
i. Certified payrolls.
SECTION 01 20 00 Page 3
j. Updated testing logs.
k. Other supporting documents as requested.
1.5.2 Submission of Invoices
If DFARS Clause 252.232-7006 Wide Area WorkFlow Payment Instructions is included in the Contract, provide the documents listed in above paragraph CONTENT OF INVOICE in their entirety as attachments in Wide Area Work Flow (WAWF) for each invoice submitted. The maximum size of each WAWF attachment is two megabytes, but there are no limits on the number of attachments. If a document cannot be attached in WAWF due to system or size restriction, provide it as instructed by the Contracting Officer.
Monthly invoices and supporting forms for work performed through the anniversary award date of the Contract must be submitted to the Contracting Officer within 5 calendar days of the date of invoice. For example, if Contract award date is the 7th of the month, the date of each monthly invoice must be the 7th and the invoice must be submitted by the 12th of the month.
1.5.3 Final Invoice
a. A final invoice must be accompanied by the certification required by DFARS 252.247.7023 Transportation of Supplies by Sea, and the Contractor's Final Release. If the Contractor is incorporated, the Final Release must contain the corporate seal. An officer of the corporation must sign and the corporate secretary must certify the Final Release.
b. For final invoices being submitted via WAWF, the original Contractor's Final Release Form and required certification of Transportation of Supplies by Sea must be provided directly to the respective Contracting Officer prior to submission of the final invoice. Once receipt of the original Final Release Form and required certification of Transportation of Supplies by Sea has been confirmed by the Contracting Officer, the Contractor must then submit final invoice and attach a copy of the Final Release Form and required certification of Transportation of Supplies by Sea in WAWF.
c. Final invoices not accompanied by the Contractor's Final Release and required certification of Transportation of Supplies by Sea will be considered incomplete and will be returned to the Contractor.
1.6 PAYMENTS TO THE CONTRACTOR
Payments will be made on submission of itemized requests by the Contractor which comply with the requirements of this section, and will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.
1.6.1 Obligation of Government Payments
The obligation of the Government to make payments required under the provisions of this Contract will, at the discretion of the Contracting Officer, be subject to reductions and suspensions permitted under the FAR and agency regulations including the following in accordance with FAR FAR
32.103 Progress Payments Under Construction Contracts:
SECTION 01 20 00 Page 4
a. Reasonable deductions due to defects in material or workmanship;
b. Claims which the Government may have against the Contractor under or in connection with this Contract;
c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor; and
d. Failure to maintain accurate "as-built" or record drawings in accordance with FAR 52.236.21.
1.6.2 Payment for Onsite and Offsite Materials
Progress payments may be made to the Contractor for materials delivered on the site, for materials stored off construction sites, or materials that are in transit to the construction sites under the following conditions:
a. FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts.
b. Materials delivered on the site but not installed, including completed preparatory work, and off-site materials to be considered for progress payment must be major high cost, long lead, special order, or specialty items, not susceptible to deterioration or physical damage in storage or in transit to the construction site. Examples of materials acceptable for payment consideration include, but are not limited to, structural steel, non-magnetic steel, non-magnetic aggregate, equipment, machinery, large pipe and fittings, precast/prestressed concrete products, plastic lumber (e.g., fender piles/curbs), and high-voltage electrical cable. Materials not acceptable for payment include consumable materials such as nails, fasteners, conduits, gypsum board, glass, insulation, and wall coverings.
c. Materials to be considered for progress payment prior to installation must be specifically and separately identified in the Contractor's estimates of work submitted for the Contracting Officer's approval in accordance with Earned Value Report requirement of this Contract.
Requests for progress payment consideration for such items must be supported by documents establishing their value and that the title requirements of the clause at FAR 52.232-5 Payments Under Fixed-Price Construction Contracts have been met.
d. Materials are adequately insured and protected from theft and exposure.
e. Provide a written consent from the surety company with each payment request for offsite materials.
f. Materials to be considered for progress payments prior to installation must be stored in a safe place in the Continental United States as approved by the Contracting Officer and where he or she can oversee the materials or products . Other locations are subject to written approval by the Contracting Officer.
g. Materials in transit to the job site or storage site are not acceptable for payment.
SECTION 01 20 00 Page 5
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 20 00 Page 6
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
11/20
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
View Location Map
Progress and Completion Pictures
1.3 VIEW LOCATION MAP
Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.
1.4 PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten different viewpoints selected by the Contractor unless otherwise directed by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures.
Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file.
Include a date designator in file names. Photographs provided are for unrestricted use by the Government. Note: Photographs must not be taken of aircraft, military equipment, hangars, or restricted areas.
SECTION 01 30 00 Page 1
1.5 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by State law.
1.6 SUPERVISION
1.6.1 Superintendent Qualifications
Provide project superintendent with a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
1.6.2 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work.In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.
1.6.3 Duties
The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend Red Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.6.4 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.
Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
1.7 PRECONSTRUCTION MEETING
Immediately after award , prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction Meeting . The meeting must take place within 35 calendar days after award of the contract, but prior to commencement of any work at the site. The purpose of this meeting is to discuss and develop a mutual understanding of the administrative requirements of the Contract including
SECTION 01 30 00 Page 2 but not limited to: daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out. Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.
1.7.1 Attendees
Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.
1.8 FACILITY TURNOVER PLANNING MEETINGS (Red Zone Meetings)
Meet with the Government to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client. Start planning the turnover process at the Pre-Construction Conference meeting with a discussion of the Red Zone process and convene at regularly scheduled NRZ Meetings beginning at approximately 75 percent of project completion.
Include the following in the facility Turnover effort:
1.8.1 Red Zone Checklist
a. Contracting Officer's Technical Representative (COTR) will provide the Contractor a copy of the Red Zone Checklist template.
b. Prior to 75 percent completion, modify the Red Zone Checklist template by adding or deleting critical activities applicable to the project and assign planned completion dates for each activity. Submit the modified Red Zone Checklist to the Contracting Officer. The Contracting Officer may request additional activities be added to the Red Zone Checklist at any time as necessary.
1.8.2 Meetings
a. Conduct regular Red Zone Meetings beginning at approximately 75 percent project completion, or three to six months prior to Beneficial Occupancy Date (BOD), whichever comes first.
b. The Contracting Officer will establish the frequency of the meetings, which is expected to increase as the project completion draws nearer.
At the beginning, Red Zone meetings may be every two weeks then increase to weekly towards the final month of the project.
c. Using the Red Zone Checklist as a Plan of Action and Milestones (POAM) and basis for discussion, review upcoming critical activities and strategies to ensure work is completed on time.
d. During the Red Zone Meetings discuss with the COTR any upcoming activities that require Government involvement.
e. Maintain the Red Zone Checklist by documenting the actual completion dates as work is completed and update the Red Zone Checklist with revised planned completion dates as necessary to match progress.
Distribute copies of the current Red Zone Checklist to attendees at each Red Zone Meeting.
SECTION 01 30 00 Page 3
1.9 PARTNERING
To most effectively accomplish this Contract, the Contractor and Government must form a cohesive partnership with the common goal of drawing on the strength of each organization in an effort to achieve a successful project without safety mishaps, conforming to the Contract, within budget and on schedule. The partnering team must consist of personnel from both the Government and Contractor including project level and corporate level leadership positions. Key Personnel from the supported command, end user, NAVFAC, PWD, FEAD/ROICC, Contractor, key subcontractors and the Designer of Record are required to participate in the Partnering process.
1.9.1 Facilitated (Formal) Partnering
a. Within 35 calendar days after award and prior to the start of work, host a Formal Partnering session with key personnel from the project team including both Contractor and Government personnel. All costs associated with the Partnering session including the third-party independent Facilitator Consultant, meeting room and other incidental items are the responsibility of the Contractor.
b. Before the Facilitated (Formal) Partnering session, coordinate with the Facilitator all requirements for incidental items (such as audio-visual equipment, easels, flipchart paper, colored markers, note pads, pens/pencils, colored flash cards) and have these items available at the Partnering session. Provide copies of any documents required for distribution to all attendees. Participants will bear their own costs for meals, lodging and transportation associated with Partnering .
c. The Initial Partnering Session must be a duration of one day and be held at a location off base as agreed to by the Contracting Officer.
Partnering session may take place concurrently with the Pre-Construction Meeting.
d. Facilitator must be experienced in conducting corporate Partnering sessions and must be a third-party independent facilitating consultant
- not an employee of the Contractor. The Facilitator is responsible for leading all aspects of the Partnering session necessary to achieve the Partnering goal.
e. An outcome of the Partnering session must be an escalation matrix agreed upon by both the Government and Contractor, which identifies key Government and Contractor decision makers by name and anticipated decision durations.
f. Host follow-on Partnering Sessions at three- to six-month intervals or more frequently if needed and lasting generally a half day or less.
Attendees need only be those required to resolve current issues. The same Facilitator used in the Initial Partnering session must lead the follow-on sessions unless an alternative is permitted by the Contractor Officer. All costs associated with follow-on Partnering sessions are the responsibility of the Contractor.
SECTION 01 30 00 Page 4
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 30 00 Page 5
SECTION 01 30 00 Page 6 s
SECTION 01 30 01.00 23
DESIGN, PROCUREMENT, AND INSTALLATION OF FURNITURE, FIXTURES, AND EQUIPMENT
09/15
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
UNIFIED FACILITIES CRITERIA (UFC)
UFC 3-120-10 (16 May 2018) Interior Design
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING.
The following must be submitted in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Preliminary (Pre-Final) FF&E Package ; G, ID NAVFAC Interior Design
Final FF&E Package ; G, ID NAVFAC Interior Design
Best Value Determinations ; G, ID NAVFAC Interior Design
SD-07 Certificates
Contractor's Interior Designer's Qualifications ; G, ID NAVFAC Interior Design
1.3 GENERAL REQUIREMENTS
The Furnishings, Fixtures, and Equipment (FF&E) Packages may include, but are not limited to; systems and modular furniture, workstations, seating, storage, filing, visual display items, accessories, artwork, command graphics, training and conference furniture, soft window treatments (draperies, valances, and cornices), shop equipment, fitness equipment, Child Development Center furniture/furnishings, appliances, portable weapons cabinets and dorm and quarters furnishings and other miscellaneous items to support facility functions. The FF&E Package must be fully integrated with the building systems and finishes. FF&E may also include specialty items for which the customer activity is be responsible for specifying.
The Interior Design for the design and specification of the FF&E Package must be included in the Construction Base Bid Construction Line Item
SECTION 01 30 01.00 23 Page 1
Number (CLIN). This project contract/task order Contract Pricing Schedule contains separate CLINs for the Construction Base Bid and FF&E Planned Modification CLIN(s). The purchase and installation of the FF&E Package will be funded separately as the FF&E Planned Modification CLIN . The Government FF&E Package budget identified on the Contract Pricing Schedule does NOT include the Contractor's Handling and Administration Rate (HAR).
The total estimated budget amount for FF&E has been identified, to provide offerors with the projected magnitude of effort for FF&E. The FF&E Budget Amount is only an estimated amount. The contractor shall determine the final budget amount for the FF&E, during the post-award phase of the FF&E.
The proposed HAR percentage will be incorporated into the contract/task order award and will not be adjusted regardless of fluctuations from the estimated budget amount for FF&E. The proposed HAR is a fixed rate. The dollar amount of the HAR will change based on the actual, final amount for the FF&E determined during the post-award design phase of the FF&E.
All FF&E items are subject to the Buy American Act.
1.4 INTERIOR DESIGN SERVICES
1.4.1 Qualifications and Affiliations
Per UFC 3-120-10 , The Interior Designer of Record, hereafter referred to as the Prime Contractor's Interior Designer, must have attained National Council for Interior Design Qualification (NCIDQ) certification or state licensure, certification or registration. The Prime Contractor's Interior Designer, Design Firm owners, and any Specialists must NOT have any affiliation with any furniture, fixture, or equipment products, any furniture dealership or any manufacturers in order to avoid any potential organizational conflict of interest. Provide documentation of the Prime Contractor's Interior Designer's qualifications and significant interior design experience on similar type projects to the Government. NAVFAC reserves the right to approve/disapprove the Prime Contractor's Interior Designer.
1.4.2 Concept FF&E Package
A Concept FF&E package, prepared by the NAVFAC Interior Designer, indicating the salient characteristics of all required FF&E items and CADD drawings, will be provided to the Prime Contractor. The Prime Contractor must provide the services of a Certified Interior Designer to function as Prime Contractor's Interior Designer, to prepare and provide the Final, Best Valued FF&E Package and procurement data based on the Concept FF&E package.
All fixed and movable furnishings selections must be closely coordinated with the final construction documents and interior finishes. The Prime Contractor's Interior Designer is required to validate all FF&E requirements with the Activity, make any necessary changes to the FF&E and interior building finishes. Per UFC 3-120-10 , the (FF&E) includes the design, selection, specification, color coordination, and procurement documentation of the required items necessary to meet the functional, operational, sustainability, and aesthetic needs of the facility. The FF&E package must be fully integrated with the design, construction, and schedule of all building finishes and all building systems (HVAC, Plumbing, Fire Protection, Communications, Electrical, Data, Architecture, etc. All outlets, switches, fire extinguishers, thermostats, etc. must be fully accessible. All sprinkler heads, ADA, etc. clearances must be accommodated.
SECTION 01 30 01.00 23 Page 2
The Prime Contractor's Interior Designer must also attend walk-throughs, coordinate mock-ups, and attend any and all required meetings to accomplish this task. The Contractor's Interior Designer and equipment specialists must be responsible for designing and providing specifications for procurement of all FF&E, to include delivery and installation, for the facilities built under this contract as directed by the NAVFAC Interior Designer. FF&E specifications must be based on Navy Blanket Purchase Agreements (BPA's), GSA schedules, and other Federal contracts and complying with priorities found in FAR Part 8.404. The utilization of the current Navy BPA list is required for BVD Analysis Request for Pricing.
The current Navy BPA list is available at:
http://www.wbdg.org/ffc/navy-navfac/collateral-equipment
1.5 FURNISHINGS, FIXTURES, AND EQUIPMENT (FF&E) SUBMITTALS FOR THE
INTERIOR DESIGN SERVICES
Develop design as described and in accordance with the Activity requirements. Include in the design all loose furnishings required to produce an optimum functional facility, consistent with quality commercial design. This project also includes the preparation of specific detailed information for each selected item.