AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

SOLICITATION N40080-15-R-5342 DBB, P-114 SET #2, MEDICAL CENTER ADDITION/ALTERATION (MCAA), WALTER REED NATIONAL

MILITARY MEDICAL CENTER (WRNMMC), NAVAL SUPPORT ACTIVITY BETHESDA, BETHESDA, MD

PLEASE SEE SECTION SF 30 - BLOCK 14 CONTINUATION PAGE FOR DETAILS OF AMENDMENT

1. CONTRACT ID CODE PAGE OF PAGES

J 1 22

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 06-Aug-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N40080-15-R-5342

X 9B. DATED (SEE ITEM 11)

08-May-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

06-Aug-2018

CODE

NAVAL FACILITIES ENG COMMAND WASHINGTON

1314 HARWOOD ST

WASHINGTON DC 20374

N40080 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N40080-15-R-5342

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 0008

The purpose of this amendmnet is to incorporate the following:

1. As-Built Drawings are available for Information Only. In order to obtain these documents, please send a written request to the Contracting Officer, Lindsay Brown, at Lindsay.naill@navy.mil with the names and email addresses of those individuals who require a copy.

2. Provide RFI Responses

3. Revised Wage Determination: MD180057 08/03/2018 MD57 located in Section 00800 –

Special Contract Requirements

4. The proposal due date has been extended to 21 September 2018 by 2:00 PM EST.

5. Attachments uploaded under the additional documents link in NECO.

All other terms and conditions remain unchanged.

1. RFI RESPONSES

1. Specification Section 23 09 23.13 20 states the work in this section shall be accomplished by a first tier subcontractor. Section 2.1 - p states, "The existing Johnson Controls system in building 14 shall be extended to include the new building automation equipment under the scope of work for this project. [...] Only a qualified Johnson Controls Technician shall incorporate the new system into the existing server."

Section 2.1 - r lists Johnson, Siemens, Automated Logic, Honeywell, and Schneider as acceptable controls manufacturers for the Project. Please confirm the listed controls contractors are all acceptable to perform the work. Please confirm a qualified Johnson Controls technician is not required to make the tie-in to the existing system. Drawing Reference 23 09 23.13 20

GOVERNMENT RESPONSE: The manufacturers listed in spec section 2.1 are acceptable for the new BAS system. It is also required that a Johnson Controls technician shall make the tie-in to the Johnson Controls existing system.

2. Please provide the specification appendices as listed on the table of contents. Reference TOC

GOVERNMENT RESPONSE: All of the section 2.2 specification appendices (A, C, D, E, F, G, H1, H2, H3, J, K, L, and M) have been provided as part of Amendment 4.

3. Please provide drawing volume 2.04. Reference Vol 2.04

GOVERNMENT RESPONSE: Refer to Set #2 / Package 2 – Building C, Phase 2 Vol 2.04 General Cover sheet, Indices, Package, Phasing and Fire Protection drawings FA-041 through FX-105-N.

These drawings documents include drawing numbers 13087101 through 13087206.

4. The structural steel specification requires AISC certification per section 05 12 00-1.3. The main structural of the building is Cast-In-Place concrete. Typically for Concrete structures, the Miscellaneous Metal subcontractor perform the structural steel scope of work. The number of subcontractors that hold

AISC certification will limit the number of potential bidders. Please confirm that AISC certification may be waived for this project. Reference 051200-1.3.

GOVERNMENT RESPONSE: AISC certification is required for all work governed by specification 05 12 00. There exists major structural steel work in this project (e.g. auditorium structure).

5. The steel deck specification requires AWS certification welders per 05 30 00-1.3.3. Decking manufacturers typically follow SJI and SDI and their welders are not AWS certified. Please confirm this is acceptable. Reference 053000-1.3.3

GOVERNMENT RESPONSE: Deck manufacturer welders shall be AWS certified as required by 05 30 00 section 1.3.3.

6. The title block of sheet A-882 in Package 4 indicates the plans on the sheet are for floors 5, 6, and 7 slab infills and penetrations, but the plans only indicates floors 5 & 6. Is there any work for the 7th floor slab? Please clarify. Reference A-882

GOVERNMENT RESPONSE: Work at or around level 7 floor slab is indicated in notes and details on A-882. Reference callouts for A3-AI-505D, and new slab penetration shown at GL XDD5/X7.2, for example.

7. M-834, Detail A1 & C1 shows an Automated Chilled Water System Panel by Artichill or equivalent.

This panel is not scheduled on the drawings. Please confirm it is furnished with the MRI? Reference M-

GOVERNMENT RESPONSE: The panel in question is a bypass switchover from chilled water to domestic water. Panel is not furnished by MRI manufacturer (reference M-834) but must interface with MRI manufacturer’s systems.

8. The finish schedule on sheet I-622 in Package 5 Volume 5.05 shows porcelain wall tile (PWT-1) in Vestibule 1K05, however there are no drawings that correspond to this location. Please provide elevations to show the extent of this tile. Reference AI-101G and I-622

GOVERNMENT RESPONSE: Vestibule 1K05 and ATM Alcove 1K17 should receive PWT-1 from floor to ceiling on all walls. Reference I-622, revised 06/14/2018.

Finish schedule for Corridor BC 1E02 was also revised. Reference I-622 and IN- 101-E, revised 06/14/2018.

9. In order to completely establish the scope of work for the demolition a greater understanding of site conditions will be required. In addition to the site walk scheduled for June 28th can another one be arranged?

GOVERNMENT RESPONSE: The Government conducted 2 site visits one on Jun 05, 2018 and the second site visit on Jun 28, 2018. There is no intention to schedule another site visit.

10. Drawing Q-101-C1 calls out JSN A5180, but this is not listed on the equipment lists. Please indicate if this is to be Contractor Provided, and if so, provide information about the item. Reference Q-101-C1

GOVERNMENT RESPONSE: JSN A5180 has been added to sheet Q-600. Reference attached Q-600 revised 6/13/18.

11. Specification section 23 00 00, paragraph 2.16 Vibration Isolation specifies the types of mountings we are to furnish. The execution section does not indicate where or what conditions we are to apply/install the specified materials. Please provide a vibration isolation schedule indicating which mountings are to be applied to which systems throughout the project. Reference 23 00 00

GOVERNMENT RESPONSE: Refer to specification section 23 05 48.00 40, vibration and seismic controls for HVAC piping and equipment issued with amendment no. 6

12. Site Demolition Plan sheet CD-201 appears to have no work related to demolition but lacks the note "NO WORK THIS SHEET - FOR INFORMATION ONLY". Please confirm that there is no demolition scheduled to be completed on sheet CD-201. Reference CD-201

GOVERNMENT RESPONSE: Drawing Sheet CD-201 is part of the Phase 1 Plan Set, this CD (Civil Demolition) sheet covers the location of the Northwest Courtyard. This sheet should be marked "NO WORK THIS SHEET - FOR INFORMATION ONLY" as the Phase 1 portion of the work is focused on the southern portion of Building C. Corrected sheet will be provided in the forthcoming Amendment.

13. According to the Site Demolition Plan sheets CD-203, CD-204, and CD-301 through CD-304 call for the complete demolition of buildings 4, 6, 7, and 8, as well as portions of building 2. In order to completely establish the extent of the demolition please provide the as built drawings for the aforementioned buildings and their associated foundations. Reference CD-203 - CD204 and CD-301 - CD-304

GOVERNMENT RESPONSE: Due to strict file restrictions, the Government was unable to upload these documents to NECO. In order to obtain these documents, please send a written request to the Contracting Officer, Lindsay Brown, at Lindsay.naill@navy.mil with the names and email addresses of those individuals who require a copy.

14. According to the Site Demolition Plan sheets CD-203, CD-204, and CD-301 through CD-304 call for the complete demolition of buildings 4, 6, 7, and 8, as well as portions of building 2. In order to completely establish the extent of the demolition please clarify the extent of hazardous materials present in buildings 2, 4, 6, 7, and 8. Reference CD-203 - CD204 and CD-301 - CD-304

GOVERNMENT RESPONSE: Refer to Amendment 4, spec appendix F from EBS submission dated Feb 28, 2018, for description of hazardous materials in existing buildings to be demolished.

15. DIVISION 21 references UFC 3-600-01 from 2006 with Change 2 from 2013, Change 2 was released on March 25, 2018. Please confirm Change 2 dated from March 25, 2018 is now applicable. Please note this revision affects dry systems which now require nitrogen generators where it previously only affected preaction systems.

GOVERNMENT RESPONSE: UFC 3-600-01 Change 3, 1 March 2013 is the applicable edition

16. Aggregate pier soil reinforcement. Please provide locations and quantities required for aggregate soil reinforcement. Reference 31 66 13

GOVERNMENT RESPONSE: Response to this RFI will be provided in a later Amendment

17. SECTION 33 56 10 - 3.4. Please confirm the Owner is responsible for all diesel fuel for testing, commissioning, start-up, initial fill, and top off after testing/commissioning of the factory-fabricated fuel storage tanks. Reference 33 56 10

GOVERNMENT RESPONSE: The specifications are written instructions to the contractor. Accordingly, paragraph 3.4 Tank Fill Tests is directing the Contractor to fill the tanks.

18. SECTION 01 14 00 - 1.6 - f states, "The Government (EMCOR) will assist the Contractor by locating shut-off valves. The Contractor shall retain the services of EMCOR, at the Contractor's expense, to drain down and refill affected systems." This is vague and requires an ALLOWANCE determined by the Government. Please provide Contractor an ALLOWANCE to be carried in base bid and please clarify if this ALLOWANCE should be carried in CLIN0001 or CLIN0002. Reference 01 14 00

GOVERNMENT RESPONSE: An allowance is not necessary. The offeror/contractor shall coordinate through the contracting officer for government assistance in locating shut-off valves and to drain down and refill affected systems.

19. WRNMMC - Facility Management Department Utility Outage/Access for Work Permit Program states, "A NAVFAC representative/Liaison will notify Fire Protection Technician (SA Comunale), for the scheduling of Fire Alarm Tests and support for any kind of work done on the Fire Suppression systems."

Please confirm the Government will retain SA Comunale for this work and the Contractor will exclude this expense.

GOVERNMENT RESPONSE: The government retains a separate contractor to perform support services for Fire Alarm and Fire Suppression at NSA Bethesda. The offeror/contractor shall coordinate through the contracting officer for government assistance when performing work in this regard.

20. Building C Phase 1 Drawing MP-10B-G4 near Column G-13, there are (2) new 14" CHW lines connecting to (2) existing 14"CHW butterfly valves outside of the footprint of the building. Please clarify if these existing 14" lines and valves are buried underground or if they are located in an existing crawl space shown on Building C Phase 1 Drawing MD-10C-F.

GOVERNMENT RESPONSE: Existing 14” CHW lines are located within existing crawl space as shown on MD-10C-F. 14” butterfly valves are added during demolition phase as shown on MD- 10C-F. Valves will be located in existing crawl space.

21. Building C Phase 1 Drawings MP-10B-J2.1, MP-10B-K1-1, & MP-10B-K2.1, Show a 10" HPS line and a 4" PCR line running outside the footprint of the Phase 1 Building. Please clarify if these lines are buried underground or if they are located in the existing crawl space shown on Building 2 Phase 2 Drawing MD- 10C-J.2

GOVERNMENT RESPONSE: Pipes are located in the existing crawl space. Pipes will be protected during construction of phase 2 until new connections for steam and pumped condensate are complete as shown on MP-10B-K4, MP-10B-K2.2.

22. SECTION 23 09 23.13 20 - 2.1 - r does not list Delta Controls by Envise as an acceptable DDC controls manufacturer. Please confirm Delta Controls native BACnet solution by Envise is an acceptable DDC manufacturer for this Project.

GOVERNMENT RESPONSE: Delta Controls by Enviste is an acceptable DDC manufacturer.

23. SECTION 23 00 00 - 1.7 states, "Verify seismic restraint vendor's calculations by a registered professional engineer." DIVISION 21 does not make any references to seismic. Please confirm DIVISION 21 work does not require seismic.

GOVERNMENT RESPONSE: Division 21 work does not require seismic bracing.

24. Following Building C completion the "WRNMMC P114 Phasing Nodal Diagram - Set #2" calls for the demolition of project P125, while Note 1 of G-022A states that the P125 project is contractually separate from the P114 project. Please clarify if the P125 project is to be demolished under the P114 contract. If it is, please provide the location and as built drawings of project P125. Reference WRNMMC P114 Phasing Nodal Diagram - Set #2 and G-022A

GOVERNMENT RESPONSE: The P125 project shall be demolished under the P114 scope of work, as indicated in note 7 on G-022A. Demolition of P125 temporary facilities and repaving of P125 parking lot is included in Building C – Phase 2B.

NAVFAC will provide P125 as-built drawings in the forthcoming Amendment.

25. Amendment 2 stated that missing specification appendices would be provided in a later addendum.

The appendices were not provided in Amendment 3. Please provide these appendices. Reference Spec Appendices

GOVERNMENT RESPONSE: The specification appendices have been provided as part of Amendment 4.

26. Please provide the as built drawings for Building 100 and it's foundations. Reference AD-111.2A

GOVERNMENT RESPONSE: Due to strict file restrictions, the Government was unable to upload these documents to NECO. In order to obtain these documents, please send a written request to the Contracting Officer, Lindsay Brown, at Lindsay.naill@navy.mil with the names and email addresses of those individuals who require a copy.

27. Please provide a differentiation document for all work described in specification section 011100.1.2.1 to clarify what work is to be done by the contractor and what work will be done by others. Reference 01 11 00

GOVERNMENT RESPONSE: Reference specification 01 14 00 WORK RESTRICTIONS, which clarifies what work is done by contractor and what work is done by others.

28. The auditorium roofing system is described as a flat seam architectural roof system. Please confirm that an FSMR-1 system will be used in this location. Reference C1/A-538

GOVERNMENT RESPONSE: Auditorium roofing system is FSMR-1. Reference revised sheet A- 346, issued in Amendment 0006 dated June 28, 2018.

29. Detail referenced calls for an architectural louver system and a mechanical louver system. Please confirm there is only one louver or two facing each other. Reference B1/A-325

GOVERNMENT RESPONSE: Louver shown at B1/A-325 shall be in accordance with 07 42 13.01 section 1.2.3. Provide an architectural louver over vertical mechanical louver specified in 08 91 00.

30. Sheet note one calls for insulated blank off panels but they are not called out for in the section details.

Please clarify which louvers contain blankoff panels. Reference Sheet Note 1/ A-224

GOVERNMENT RESPONSE: Reference 08 91 00 section 2.2.4. Blankoff panels shall be provided at all inactive areas of louvers. Inactive areas shall be determined based on mechanical drawings and requirements.

31. Please confirm grooved piping, valves, fittings, and couplings are acceptable for use in steel hydronic piping systems.

GOVERNMENT RESPONSE: Grooved piping, valves, fittings and couplings are not acceptable for use in steel hydronic piping systems. Provide piping, valves, fittings, and couplings that conform to specifications.

32. Please confirm grooved piping, valves, fittings, and couplings are acceptable for use in copper plumbing piping systems

GOVERNMENT RESPONSE: Grooved piping, valves, fittings and couplings are not acceptable for use in copper plumbing systems. Provide as specified.

33. Please confirm pressed type valves and fittings, i.e. Propress, are acceptable for use in copper hydronic and plumbing piping systems

GOVERNMENT RESPONSE: Propress valves and fittings are not acceptable for use in copper hydronic and plumbing piping systems. Provide valves and fittings that conform to specifications.

34. DIV 23, Please confirm flexible piping connections to terminal equipment are allowed.

GOVERNMENT RESPONSE: Flexible piping connection is only allowed downstream of valve package for final connection to terminal equipment.

35. Please confirm Pre-Configured coil piping packages are acceptable for use as hydronic connections to terminal equipment and coils.

GOVERNMENT RESPONSE: Pre-configured coil packages are acceptable.

36. Please confirm system specific design, pressed type valves and fittings are acceptable for use in steel and/or copper gas systems

GOVERNMENT RESPONSE: Valves and fittings for said systems shall be as specified.

37. Please confirm Charlotte Chem-Drain products are acceptable products for the chemical waste systems

GOVERNMENT RESPONSE: 22 00 70 is performance specification, individual piping manufacturers are not indicated, therefore the Contractor shall submit product that meets the specification.

38. The Expansion Joints spec calls for two types of expansion joint covers EJ-5 and EJ-6 however both types are the same. Please clarify the difference. Reference Spec 07 93 13

GOVERNMENT RESPONSE: Product requirements are similar for EJ-5 and EJ-6 but installation varies. Reference A1/A-505E: EJ-5 is shown in deck-to-wall expansion joint and EJ-6 is shown in deck-to-deck expansion joint detail.

39. Please confirm that the floor to floor interior expansion joints are typical and that their widths are to scale in the details on this page. Reference AI-505-E

GOVERNMENT RESPONSE: Typical details on AI-505-E indicate interface of expansion joint and cover with other materials. Expansion joint width shall not be scaled, as it varies as indicated on these details, and shall be coordinated in field with as-built and existing conditions. Slab and wall dimensions needed to size expansion joints are shown on structural and architectural drawings.

40. Building C Phase 2 Drawing MP-10B-K4, Shows (1) 18" CHWS line running through the wall of the tunnel and connecting to an existing pipe outside of the tunnel. Please confirm this line outside of the tunnel is direct buried underground.

GOVERNMENT RESPONSE: The connection point between the existing pipe and the 18" CHWS line is located within a crawlspace.

41. Drawings MH-106-F2, MH-106-G4 show stacked AHU-14A and AHU-14B, stacked AHU-16A and AHU-16B. There isn't any support steel shown for this on the structural or the mechanical drawings.

Please confirm the steel frames needed to stack one AHU on top of another AHU will be designed by a structural engineer and revised on the structural drawings.

GOVERNMENT RESPONSE: Support for the stacked unit shall be internal to the unit and provided by AHU manufacturer. Mechanical drawings will be updated with this clarification in forthcoming amendment.

42. Drawing M-846 Steam Riser Diagram-Phase 2 Bldg C shows the steam condensate from HX-3.1, HX3.2, USG-2A, USG-2B, and the Water Heater gravity feeding to (2) different pressured powered pumps. These (2) pumps are not shown on MP-105-K3 Piping Plan or scheduled on M-628. The steam condensate from all five of these pieces of equipment should not be pumped up to the condensate main in the ceiling as shown on MP-105-K3. Please advise.

GOVERNMENT RESPONSE: Pressure power pumps will be added to drawing MP-105-K3 and scheduled on M-628. In review with manufacturers, it is acceptable to pump condensate back to the gravity line. Flow diagram M-846 will be revised to add a pressure power pump for each piece of equipment (HX-3.1, HX3.2, USG-2A, USG-2B and the Water Heater).

Drawings will be forthcoming with a later Amendment.

43. Please confirm that an unoccupied crawl space should be shown on A-311. Reference A-311 and A3/A-558

GOVERNMENT RESPONSE: Crawl space should be shown on A-311. See revised A-311 issued 7/20/18 in Amendment 0008.

44. Please confirm that the 1" precast reveals with 3/4" backer rod and sealant are typical of all reveals in precast panels. Reference A4/A-610

GOVERNMENT RESPONSE: Detail A4/A-610 applies to all conditions which are not otherwise depicted in the details. Reference A-500 series for precast panel details.

45. Note 3 in the general architectural demolition notes states "the contracting officer shall have the first right of refusal on all items removed". Please clarify if this mean items will be removed by others or the contractor is to remove and deliver to a storage area? Reference AD-001.1

GOVERNMENT RESPONSE: All equipment and material, unless otherwise noted on the drawings, will be claimed and moved "by others" before the P114, Set 2 Contractor is cleared for demolition.

Anything left in the building will be available for the contractor to either demo/dispose or salvage for his own use.

46. Please confirm if ceiling is to be demolished and replaced for temporary protection to from slab to slab. Reference AD-101B.1

GOVERNMENT RESPONSE: Reference note 47 on AD-001.1. Ceiling shall be removed and replaced as required for installation of temporary protection.

47. Please confirm where salvaged material is to be stored. Reference AD-001.1

GOVERNMENT RESPONSE: The contractor shall store all salvaged material (that to be reused as per the contract drawings) with in the laydown area or other areas within the limit of disturbance.

The contractor should determine and fund transportation and storage of salvaged material for which they take personal possession.

48. Please confirm if temporary partitions can be prefabricated in lieu of 5/8" drywall with fire rated plywood. This would allow temporary partitions to be reused. Reference AD-001.1

GOVERNMENT RESPONSE: This is acceptable provided that the prefabricated partition meets all requirements of the temporary partition.

49. Please provide details for expansion joints at temporary wall locations. Reference AD-104.1

GOVERNMENT RESPONSE: Temporary walls shown on AD-104.1 do not interact with expansion joint referenced by keynote 2.

50. Please confirm what finish is to be used at round columns in the atrium area. Reference A-102-B and A2/A-502

GOVERNMENT RESPONSE: Reference AI-520 series for interior column finish details.

51. The notes states "Inspect windows. If functional, patch, repair, and seal. If damaged, replace." Please confirm if we can provide alternate pricing for this activity. Reference B1/AD-207-2

GOVERNMENT RESPONSE: The Hospital is the process of replacing all the windows in bldgs. 9 and 10 except for the 3 windows that is obscured by bldg. 100. These 3 windows will need to be replaced to match existing windows as part of P-114 project.

52. The notes states "Patch and repair existing building surfaces and provide parging as needed to maintain a weathertight exterior." Please confirm if we can provide alternate pricing for this activity.

Reference A5/AD-301.3

GOVERNMENT RESPONSE: Response to this RFI will be provided in later Amendment

53. Please clarify what a "wall-mounted tieback" is. Reference B4/A-244

GOVERNMENT RESPONSE: Wall-mounted tiebacks are tie-offs for façade maintenance.

Reference A3/A-534 for an example.

54. Please provide details for wall-mounted safety tieback anchors. Reference C2/A-321

GOVERNMENT RESPONSE: Detail reference is given on A1/A-321. Detail is C3/A-521.

55. Will manufacturers other than Pevco be permitted for the Pneumatic Tube System? If so, please provide additional information about the existing system so that pricing can be determined for a complete operational system. Reference 14 92 01

GOVERNMENT RESPONSE: The pneumatic tube system shall be provided by Pevco in order to ensure total compatibility with the existing system as required by 14 92 01 section 1.2.

56. M702 (controls network riser) states, "To Siemens Building Automation System Site Server BACnet over Ethernet Protocol Located in Building #14. To Building 55." Please confirm WRNMMC Campus has a Siemens BACnet DDC server located in Building #14. Please confirm the work in Buildings 9, 10 and C can be tied into the Siemens BACnet DDC server located in Building 14. Reference M702

GOVERNMENT RESPONSE: All BAS documented work on the drawings and specifications shall be interfaced to the Johnson Controls Site Server located in Building 14.

57. Detail 7 on Drawing P-501 shows drain pipe routed in the utility space schematically. The pipe is run below and through the mat foundation, which varies in thickness from 48 to 60 inches, turning and running horizontally in the utility space on concrete curbs shown on the structural drawings below the metal deck and turning up through the metal deck with a sleeve. (a) Are sleeves required where the plumbing piping penetrates the concrete curb? If yes, please provide a detail. (b) Where the piping is installed parallel to the concrete curb shown typical on S-10B-E, what is intended method of support for the piping in the utility space? Please provide a detail/sketch. (c) Are the penetrations through the mat foundation and metal deck floor to be water tight? If yes, please provide a detail/sketch. (d) Are pipe supports or hangers required below the mat foundation? If yes please provide a detail/sketch. Reference P-501

GOVERNMENT RESPONSE: 57 (a) - Refer to P-502 revised 7/20/18 in Amendment 0008 for detail of pipe sleeve through the basement floor above utility space and for pipe penetration through mat foundation. This detail provided for Contractor’s use is similar to pipe penetration through below-grade wall detail already provided, on drawing P-502. No water shall be permitted in utility space. Matt foundation penetrations shall be water tight.

Items (b) through (d) are Contractor’s Means and Methods in accordance with project documents.

58. Paragraph 1.5 states that the shielding design specified is for generic guidance only, but then Part 2 of the specification goes on to give some very specific materials and methods. Please confirm that the shielding design can vary from the construction in Part 2 of the specifications, as long as it meets the requirements stated in paragraph 1.5. Reference 13 49 20

GOVERNMENT RESPONSE: Shielding design shall not vary from Part 2 in preference to minimal requirements of section 1.5. Report all conflicts between the two sections to the Contracting Officer. Refer to 13 49 20, section 1.5, revised 7/20/18 in Amendment 0008.

59. Spec section 08 44 00 calls for a unitized curtain wall system design. The blast requirements mandated for glazing systems on this project are not able to be tested for most unitized systems. Please confirm if the curtain wall can be stick or ladder built in lieu of unitized. Reference Section 08 44 00

GOVERNMENT RESPONSE: Curtain wall system must meet all blast requirements indicated in 08 44 00 issued 2/28/18. Substitution requests made in accordance with specification 01 33 00 will be considered where advantageous to Government.

60. Please provide a specification section for Spray Foam Insulation.

GOVERNMENT RESPONSE: Spray foam insulation shall not be used in the project. Drawing A-534 has been revised 7/20/18 in Amendment 0008 to remove reference to spray foam.

61. Details on A-572 show a sloped reinforced structural concrete slab creating a minimum 4" void on top of the roof slab on metal deck. This structural slab is not shown in the structural drawings. Details B3 and D3 on S-341 only show architectural topping slabs. Please provide structural details for these additional roof slabs. Reference A-572 and B3,D3/S-341

GOVERNMENT RESPONSE: Refer to details B1 and B2 on sheet S-317 issued 2/28/18 for structural reinforcement of topping slab details.

62. Building 10 M-582, Detail C1 says to run the steam vent from the steam condensate pump CP-5-1 to the outside. Drawing M-105-AA4 shows CP-5-1 is located on the 5th floor. The steam vent is not shown on the drawing. Please provide the steam vent size and routing. Reference M-582

GOVERNMENT RESPONSE: Response to this RFI will be provided in a later Amendment

63. Building 10 Isolation Rooms have hard ceilings in them. There are (2) CV boxes that will require access doors in the ceiling in each of these rooms. There are also (3) manual dampers in the ductwork in each of the Isolation rooms. Please clarify if these CV boxes and/or manual dampers will require access doors in the ceiling.

GOVERNMENT RESPONSE: Response to this RFI will be provided in a later Amendment

64. Please confirm that the air barriers in these two details are the same and were called out twice.

Reference A3/AD-301.2 ; A2/AD-521.1 and A2/A-335; B2/A-530

GOVERNMENT RESPONSE: Air barriers shown in these details are not the same. The air barrier shown on the temporary partition in A2/AD-521.1 issued 2/28/18 is applied to Building 2. The air barrier shown in B2/A-530 issued 2/28/18 is applied to Building C.

65. Spec section 08 32 12 (Aluminum Sliding Glass Doors) is listed in the project table of contents, but has not been provided. Please confirm if this scope of work exists and provide a spec section if it does.

Reference Spec 08 32 12

GOVERNMENT RESPONSE: Section 08 32 12 is not used and has been deleted from spec table of contents. Reference revised table of contents issued 7/20/18 in Amendment 0008.

66. Please confirm if there will be an expansion joint in this detail. Reference C1/AI-523-A.

GOVERNMENT RESPONSE: Expansion joint shall be provided at this condition. Reference revised C1/AI-523-A issued 7/20/18 in Amendment 0008.

67. PL-106CC was issued as a duplicate of PG-106CC. Please reissue PL-106CC.Reference PL-106CC

GOVERNMENT RESPONSE: Corrected PL-106CC is issued 7/20/18 in Amendment 0008.

68. Please provide a detail for roofing system PMRS-3

GOVERNMENT RESPONSE: Reference A3/A-527 issued 2/28/18 as referenced on A1/A-345 issued 2/28/18.

69. Typical detail A-555 shows waterproofing applied under typical slab on grade. Please confirm if this waterproofing is required under mat slab foundations. Reference A-555 and A3/A-558

GOVERNMENT RESPONSE: Waterproofing shall extend under mat slab foundation. Reference A3/A-558 revised 7/20/18 in Amendment 0008.

70. Typical detail A-555 shows waterproofing applied under typical slab on grade. Please confirm if this waterproofing is required under slab on grade at unoccupied space. Reference A-555 and A3/A-558

GOVERNMENT RESPONSE: Vapor barrier shall be provided under slab on grade at unoccupied space per A3/A-558 issued 2/28/18. Waterproofing is not required at this condition under slab on grade.

2. ATTACHMENTS

- 180720_Set #2 Amendment 0008 narrative

- 01_A-311 - SECTIONS – BUILDING

- 02_A-534 - EXTERIOR DETAILS – SECTION

- 03_A-558 - INSULATION OVER UNOCCUPIED SPACE

- 04_AI-506C - BASE DETAILS

- 05_AI-523A - INTERIOR PLAN DETAILS - THIRD FLOOR - PHASE 1

- 06_PL-106CC - PLUMBING-GRAVITY PIPING PLAN-SIXTH FLOOR-AREA CC

- 07_P-502 - PLUMBING DETAILS - BLDG C

- 08_MH-106-E2 - MECHANICAL - SIXTH FLOOR HVAC PLAN - AREA E2 - PHASE 1

- 09_M-702 - BAS - SYSTEM ARCHITECTURE DRAWING - BLDG C

- 10_M10_M-703 - BAS - AHU CONTROL DIAGRAM - BLDG C

- 11_M-704 - BAS - MANIFOLDED AHU CONTROL DIAGRAM - BLDG C

- 12_M-705 - BAS - EXHAUST FANS CONTROL DIAGRAM - BLDG C

- 13_M-705A - BAS - EXHAUST SYSTEMS SEQUENCE OF OPERATIONS - BLDG C

- 14_M-720 - BAS - ROOM CONTROLS DIAGRAMS SHEET 1 - BLDG C

- 15_M-721 - BAS - ROOM CONTROLS DIAGRAMS SHEET 2 - BLDG C

- 16_M-730 - BAS-MISCELLANEOUS CONTROL DIAGRAMS SHEET 1-BLDG C

- 17_M-731 - BAS-MISCELLANEOUS CONTROL DIAGRAMS SHEET 2-BLDG C

- Revised 00 00 00_TOC

- Revised Section 01 78 00 CLOSEOUT SUBMITTALS

- Revised Section 01 78 30.00 23 CADD DATA FOR GIS DELIVERABLES

- Revised Section 13 49 20 ELECTROMAGNETIC (EM) SHIELDING

- Revised Section 23 09 23.13 20 BACnet DIRECT DIGITAL CONTROL SYSTEMS FOR HVAC

- Revised Section 26 20 00 INTERIOR DISTRIBUTION SYSTEM

- Revised Section 26 23 00 LOW-VOLTAGE SWITCHGEAR

- Revised Section 26 23 13.00 23 PARALLELING LOW VOLTAGE SWITCHGEAR

- Revised Section 26 24 13 SWITCHBOARDS

- Revised Section 26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION

- Revised Section 26 33 53.00 23 STATIC UNINTERRUPTIBLE POWER SUPPLY (UPS)

SECTION 00010 - SOLICITATION CONTRACT FORM

The required response date/time has changed from 21-Aug-2018 02:00 PM to 21-Sep-2018 02:00 PM.

SECTION 00700 - CONTRACT CLAUSES

5252.211-9301 Phased Construction Schedule.

PHASED CONSTRUCTION SCHEDULE (SEP 1996)

Within the overall project schedule, commence and complete the work in phases. Complete each phase of the work within the number of calendar days stated in the following schedule:

a. Schedule start day: The day designated as the beginning of a particular phase; the number listed is the number of calendar days from the award of contract.

b. Completion day: The day designated as the end of a given phase and the day the work in that phase must be completed; the number listed is the number of calendar days from the award of the contract.

c. Schedule:

Phase Description Schedule Start Day Completion Day

A Building C, Phase 1 Cannot Start untl NTP is received 1219 calendar days after NTP

B Building C, Phase 2 Cannot Start untl NTP is received 851 calendar days after completion and occupancy of Phase 1 and NTP is issued

C Building 9, Phase 3 Cannot Start untl NTP is received 365 calendar days after completion and occupancy of Phase 1 and NTP is issued

D Building 10, Phase 3 Cannot Start untl NTP is received 730 calendar days after completion and occupancy of Phase 1 and NTP is issued

d. If the work of a particular phase is complete and accepted before the scheduled completion day, immediately begin work on the subsequent phase unless otherwise restricted.

(End of clause)

The following have been modified:

52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government for each calendar day of delay until the work is completed or accepted for each of the following phases as follows:

(1) BUILDING C, PHASE 1: $70,000.00 – 1219 calendar days after NTP;

(2) BUILDING C, PHASE 2: $70,000.00 – 851 calendar days after completion and occupancy of Phase 1 and NTP is issued for this Phase;

(3) BUILDING 9, PHASE 3: $3,450.00 – 365 calendar days after completion and occupancy of Phase 1 and NTP is issued for this Phase; and

(4) BUILDING 10, PHASE 3: $24,450 – 730 calendar days after completion and occupancy of Phase 1and NTP is issued for this Phase.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

(End of clause)

SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS

WD 8/3/18

General Decision Number: MD180057 08/03/2018 MD57

Superseded General Decision Number: MD20170057

State: Maryland

Construction Type: Building

County: Montgomery County in Maryland.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.35 for calendar year 2018 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.35 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2018. The EO minimum wage rate will be adjusted annually.

Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/05/2018 1 01/12/2018 2 02/09/2018 3 02/23/2018 4 03/23/2018 5 04/20/2018 6 05/11/2018

7 05/25/2018 8 06/15/2018 9 06/29/2018 10 07/06/2018 11 07/13/2018 12 08/03/2018

ASBE0024-007 10/01/2017

Rates Fringes

ASBESTOS WORKER/HEAT & FROST

INSULATOR........................$ 35.13 16.22

Includes the application of all insulating materials, protective coverings, coatings and finishes to all types of mechanical systems

ASBE0024-010 10/01/2017

Rates Fringes

ASBESTOS WORKER: HAZARDOUS

MATERIAL HANDLER (Removal of hazardous material from ceilings, floors, mechanical systems, and walls)..............$ 22.81 7.34

BRMD0001-006 04/29/2018

Rates Fringes

TILE SETTER......................$ 28.20 11.67

BRMD0001-009 04/29/2018

Rates Fringes

TILE FINISHER....................$ 23.28 10.72

BRMD0001-011 04/29/2018

Rates Fringes

BRICKLAYER (Excluding Pointing, Caulking and Cleaning)........................$ 31.36 10.78

BRMD0001-012 04/29/2018

Rates Fringes

MASON - STONE....................$ 37.91 17.08

CARP0197-001 05/01/2018

Rates Fringes

CARPENTER (Including Acoustical Ceiling Installation, Drywall Hanging, Metal Stud Installation and Form Work)......$ 28.71 12.08

CARP0219-001 05/01/2018

Rates Fringes

MILLWRIGHT.......................$ 34.24 11.23

ELEC0026-021 09/11/2017

Rates Fringes

ELECTRICIAN (Communication and Sound Equipment).............$ 27.80 10.55

ELEC0026-022 11/06/2017

Rates Fringes

ELECTRICIAN (Including low voltage wiring for and installation of alarms, HVAC controls)........................$ 45.15 17.15+a a.PAID HOLIDAYS: New Year's Day, Inauguration Day, Martin Luther King Jr.'s Birthday, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day, the day after Thanksgiving Day and Christmas Day.

ELEV0010-001 01/01/2018

Rates Fringes

ELEVATOR MECHANIC................$ 44.12 32.645+a+b

a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day, Christmas Day and the Friday after Thanksgiving.

b. VACATIONS: Employer contributes 8% of basic hourly rate for 5 years or more of service; 6% of basic hourly rate for 6 months to 5 years of service as vacation pay credit.

ENGI0077-018 05/01/2017

OPERATOR: Bulldozer.............$ 30.56 8.95+a OPERATOR: Loader Front End Loaders 3 1/2 cubic yards and above.......$ 30.56 8.95+a Front End Loaders Below 3 1/2 cubic yards.............$ 30.56 8.95+a a.PAID HOLIDAYS: New Year's Day, Inaugural Day, Decoration Day, Independence Day, Labor Day, Martin Luther King's Birthday, Veterans' Day, Thanksgiving Day, Friday after Thanksgiving and Christmas Day.

IRON0005-011 06/01/2017

Rates Fringes

IRONWORKER.......................$ 31.15 20.63

LABO0657-017 06/01/2015

Rates Fringes

LABORER: Mason Tender - Cement/Concrete..................$ 22.63 7.31 LABORER: Pipelayer..............$ 22.63 7.31

PAIN0051-014 06/01/2018

Rates Fringes

GLAZIER

Glazing Contracts $2 million and under...........$ 26.07 12.15 Glazing Contracts over $2 million.....................$ 30.31 12.15

PAIN0051-019 06/01/2017

Rates Fringes

PAINTER

Brush, Roller, Spray and Drywall Finisher/Taper......$ 25.06 9.66 Industrial..................$ 30.90 10.49

PLAS0891-005 07/01/2018

Rates Fringes

PLASTERER........................$ 29.53 6.80

PLAS0891-006 02/01/2018

CEMENT MASON/CONCRETE FINISHER...$ 28.15 10.58

PLAS0891-008 08/01/2016

Rates Fringes

PLASTERER (Fireproofing Including Sprayer, Mixer, and Handler) Handler.....................$ 16.50 4.89 Mixer/Pump..................$ 18.50 4.89 Sprayer.....................$ 23.00 4.89

PLUM0005-010 02/01/2018

Rates Fringes

PLUMBER..........................$ 41.67 17.60+a

a. PAID HOLIDAYS: Labor Day, Veterans' Day, Thanksgiving Day and the day after Thanksgiving, Christmas Day, New Year's Day, Martin Luther King's Birthday, Memorial Day and the Fourth of July.

* PLUM0602-011 08/01/2018

Rates Fringes

PIPEFITTER (Including HVAC Pipe and System Installation)....$ 41.64 21.57+a

a. PAID HOLIDAYS: New Year's Day, Martin Luther King's Birthday, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day and the day after Thanksgiving and Christmas Day.

ROOF0030-016 05/01/2016

Rates Fringes

ROOFER...........................$ 28.75 11.74

SFMD0669-001 04/01/2017

Rates Fringes

SPRINKLER FITTER (Fire Sprinklers)......................$ 34.40 19.24

SHEE0100-015 03/01/2018

SHEET METAL WORKER (Including

HVAC Duct Installation)..........$ 40.27 18.87+a

a. PAID HOLIDAYS: New Year's Day, Martin Luther King's Birthday, Memorial Day, Independence Day, Labor Day, Veterans Day, Thanksgiving Day and Christmas Day

SUMD2010-091 08/04/2010

Rates Fringes

LABORER

Common or General...........$ 14.15 2.30 Grade Checker...............$ 16.00 2.90 Landscape...................$ 9.23 Mason Tender - Brick........$ 13.00 0.00 Mason Tender - Stone........$ 14.03 0.00 Mason Tender for Pointing, Caulking and Cleaning.......$ 13.21 Mortar Mixer................$ 16.61 9.08

POINTER, CAULKER, CLEANER,

Includes pointing, caulking, cleaning of existing masonry, brick, stone and cement structures (restoration work); excludes pointing, caulking, cleaning of new or replacement masonry, brick, stone or cement...........................$ 19.19 0.00

POWER EQUIPMENT OPERATOR:

Asphalt Roller..............$ 21.35 5.38 Backhoe.....................$ 19.82 5.02 Bobcat/Skid Loader..........$ 18.05 8.78 Boom........................$ 21.44 8.29 Crane.......................$ 20.95 6.18 Excavator...................$ 20.00 0.00 Forklift....................$ 16.00 5.12 Gradall.....................$ 20.50 8.42 Grader/Blade................$ 14.50 5.18 Paver.......................$ 17.47 6.36 Roller excluding Asphalt....$ 17.60 3.88

TERRAZZO WORKER/SETTER...........$ 19.94 6.54

TRUCK DRIVER

Dump Truck..................$ 15.90 1.12 Tractor Haul Truck..........$ 17.87 9.98

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have…