P114_SET_2_AMENDMENT_0003.pdf
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
SOLICITATION N40080-15-R-5342 DBB, P-114 SET #2, MEDICAL CENTER ADDITION/ALTERATION (MCAA), WALTER REED NATIONAL
MILITARY MEDICAL CENTER (WRNMMC), NAVAL SUPPORT ACTIVITY BETHESDA, BETHESDA, MD
PLEASE SEE SECTION SF 30 - BLOCK 14 CONTINUATION PAGE FOR DETAILS OF AMENDMENT.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 14
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 13-Jun-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N40080-15-R-5342
X 9B. DATED (SEE ITEM 11)
08-May-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
13-Jun-2018
CODE
NAVAL FACILITIES ENG COMMAND WASHINGTON
1314 HARWOOD ST
WASHINGTON DC 20374
N40080 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N40080-15-R-5342
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0003
The purpose of this amendmnet is to incorporate the following:
1. Provide Site Visit 2 Information
2. Amendment 0002 Attachment Clarification
3. Attachments
4. Revised Wage Determination: MD180057 05/25/2018 MD57 located in Section 00800 -
Special Contract Requirements
All other terms and conditions remain unchanged.
1. PRE-PROPOSAL CONFERENCE AND SITE VISIT:
2. AMENDMENT 0002 ATTACHMENT CLARIFICATION
Second Government Scheduled Site Visit
DATE: THURSDAY, 28 JUNE 2018
TIME: 9:00 A.M. EST
LOCATION: Building 51, The National Intrepid Center of Excellecne (NICoE) Auditorium, NSA, Bethesda, MD
An organized site visit will be held on 28 June 2018, starting promptly at 9:00 am EST. The site visit will held in the National Intrepid Center of Excellecne (NICoE) Auditorium located in Building 51 on the NSA Bethesda Installation.
The day of the site visit: ALL PERSONNELL shall muster outside of Gate 1 (North Gate) located at 8901 Rockville Pike on GPS at 9:00 AM. Each individual will be checked in by the Government representative and then be escorted through the Gate to the auditorium.
If you do not have a U.S. Government DoD Common Access Card (CAC) identification card and require base access, you must complete the attached Base Access Form "SECNAVF Form 5512" and submit to Lindsay Brown at Lindsay.naill@navy.mil NLT noon on 20 June 2018. By providing your information as instructed above, the Government will register each individual who does not have base access prior to the site visit.
Please refer to the P114 Set #2 Site Visit Map uploaded as an attachment. Installation parking will not be provided. There is a public parking area as shown on the map, south of the NIH Complex. In addition, there is Metro stop, Medical Center Metro/Naval Med CTR &NIH, located within walking distance from the installation.
If there are specific areas Contractors want to see, please submit a request NLT COB 20 June 2018. The Government cannot guarantee access to all areas, but will accommodate as best as we can.
2. AMENDMENT 0002 ATTACHMENT CLARIFICATION
Amendment 0002 included four attachments to be uploaded:
- 2.2 Specs_Appx_Set #2_EBS Submission_Vol 1 of 2_(A)
- 2.2 Specs_Appx_Set #2_EBS Submission_Vol 2 of 2_(C-M)
- 2.3 Specs_Submittal Register_Set #2_EBS Submission
- 3. Supporting Project Documents
Due to the file sizes exceeding the NECO upload size limitations, 2.2 Specs_Appx_Set #2_EBS Submission_Vol 1 of 2_(A), 2.2 Specs_Appx_Set #2_EBS Submission_Vol 2 of 2_(C-M), and 3.
Supporting Project Documents have not been uploaded. The Governemnt is currently breaking these into smaller files and will upload in a future amendment.
3. ATTACHMENTS
The following documents will be uploaded:.
- P114 Set 2 Price Schedule Revised 13 June 18
- P114 June 5 Site Visit Attendance Log
SECTION 00010 - SOLICITATION CONTRACT FORM
CLIN 0005
The CLIN description has changed from DEDUCT: (8) Electric Traction Elevators to BIM As-Built Files.
The CLIN extended description has changed from:
Delete (3) electric traction passenger elevators (elevators P5, P6, P7) and (2) electric traction freight elevators (elevators S1 and H1) in Building C - Phase 1. Delete (3) Electric traction passenger elevators (elevators P4, P10, and P11) in Building C - Phase 2. Add new drywall closure to all elevator shafts.
To:
Price to provide the Record Model at closeout, refer to Specification 01 78 00 CLOSEOUT SUBMITTIALS.
CLIN 0006
The CLIN description has changed from DEDUCT: LANDSCAPING to DEDUCT: (8) Electric Traction Elevators.
The CLIN extended description has changed from:
Delete all non-grass and non-labyrinth area landscaping plantings, refer to Landscaping drawings Building C - Phase 1 and 2.
Delete (3) electric traction passenger elevators (elevators P5, P6, P7) and (2) electric traction freight elevators (elevators S1 and H1) in Building C - Phase 1. Delete (3) Electric traction passenger elevators (elevators P4, P10, and P11) in Building C - Phase 2. Add new drywall closure to all elevator shafts.
CLIN 0007
The CLIN description has changed from DEDUCT: Delete exterior entry canopy to DEDUCT:
LANDSCAPING.
The CLIN extended description has changed from:
Delete the exterior entry canopy. Provide pricing for: The removal of the exterior entry canopy as shown on drawing A-460. The remaining east building façade will remain as shown and detailed minus this exterior canopy
Delete all non-grass and non-labyrinth area landscaping plantings, refer to Landscaping drawings Building C - Phase 1 and 2.
CLIN 0008 is added as follows:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0008 Project OPTION DEDUCT: Delete exterior entry canopy
FFP
Delete the exterior entry canopy. Provide pricing for: The removal of the exterior entry canopy as shown on drawing A-460. The remaining east building façade will remain as shown and detailed minus this exterior canopy FOB: Destination
NET AMT
INSPECTION AND ACCEPTANCE
The following Acceptance/Inspection Schedule was added for CLIN 0008:
INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
N/A N/A N/A Government
SECTION 00700 - CONTRACT CLAUSES
The following have been modified:
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 15 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 2070 calendar days from Notice to Proceed. The time stated for completion shall include final cleanup of the premises.
(End of clause)
5252.228-9305 Notice of Bonding Requirements.
NOTICE OF BONDING REQUIREMENTS (DEC 2000)
(a) Within _15__ days after receipt of award, the bidder/offeror to whom the award is made shall furnish the following bond(s) each with satisfactory security:
_X__ A Performance Bond (Standard Form 25). The performance bond shall be in a penal sum equal to 100% percent of the contract price.
_X__ A Payment Bond (Standard Form 25A). The payment bond shall be in a penal sum equal to 100% of the contract price.
(b) Any surety company holding a certificate of authority from the Secretary of Treasury as an acceptable Surety on Federal bonds will be accepted. Individual sureties will be permitted as prescribed in FAR 28.203 and FAC 5252.228 9300. Alternative types of security in lieu of furnishing sureties on performance and/or payment bonds will be permitted as prescribed in FAR 28.204, and will be held for at least one year after the completion of the contract. Additional bond security may be required as prescribed in FAR 52.228-2. Bonds shall be accompanied by a document authenticating the agent’s authority to sign bonds for the surety company.
(c) The contract time for purposes of fixing the completion date, default, and liquidated damages shall begin to run 2070 days from Notice to Proceed, regardless of when performance and payment bonds or deposits in lieu of surety are executed. (End of clause)
ALTERNATE I – As prescribed in 28.102-3-100(b), for indefinite quantity solicitations, substitute "contract price" in the basic provision with "the price payable for the contract guaranteed minimum".
ALTERNATE II – As prescribed in 28.102-3-100(c), for combination firm fixed-price/indefinite quantity solicitations where the firm fixed-price portion constitutes the guaranteed minimum, replace "contract price" in the basic provision with "the price payable for the firm fixed-price portion". Where the firm fixed-price portion and a percentage of the indefinite quantity portion will constitute the guaranteed minimum, substitute “contract price” in the basic provision with "the price payable for the firm fixed-price portion and the guaranteed minimum amount of the IQ portion".
ALTERNATE III - As prescribed in 28.102-3-100(d), for requirements solicitations, substitute "contract price" in the basic provision with "the price payable for the estimated quantity".
SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS
The following have been added by full text:
WD 5/25/18
General Decision Number: MD180057 05/25/2018 MD57
Superseded General Decision Number: MD20170057
State: Maryland
Construction Type: Building
County: Montgomery County in Maryland.
BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.35 for calendar year 2018 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.35 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2018. The EO minimum wage rate will be adjusted annually.
Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/05/2018 1 01/12/2018 2 02/09/2018 3 02/23/2018 4 03/23/2018 5 04/20/2018 6 05/11/2018 7 05/25/2018
ASBE0024-007 10/01/2017
Rates Fringes
ASBESTOS WORKER/HEAT & FROST
INSULATOR........................$ 35.13 16.22
Includes the application of all insulating materials, protective coverings, coatings and finishes to all types of mechanical systems
ASBE0024-010 10/01/2017
Rates Fringes
ASBESTOS WORKER: HAZARDOUS
MATERIAL HANDLER (Removal of hazardous material from ceilings, floors, mechanical systems, and walls)..............$ 22.81 7.34
BRMD0001-006 04/30/2017
Rates Fringes
TILE SETTER......................$ 27.44 11.44
BRMD0001-009 04/30/2017
Rates Fringes
TILE FINISHER....................$ 22.51 10.50
BRMD0001-011 04/30/2017
Rates Fringes
BRICKLAYER (Excluding Pointing, Caulking and Cleaning)........................$ 30.91 10.24
BRMD0001-012 04/30/2017
Rates Fringes
MASON - STONE....................$ 36.91 16.55
CARP0177-011 01/01/2018
Rates Fringes
CARPENTER (Including Acoustical Ceiling Installation, Drywall Hanging, Metal Stud Installation and Form Work)......$ 28.46 11.53
CARP0219-001 05/01/2017
Rates Fringes
MILLWRIGHT.......................$ 32.49 11.23
* ELEC0026-021 09/11/2017
Rates Fringes
ELECTRICIAN (Communication and Sound Equipment).............$ 27.80 10.55
ELEC0026-022 11/06/2017
Rates Fringes
ELECTRICIAN (Including low voltage wiring for and installation of alarms, HVAC controls)........................$ 45.15 17.15+a a.PAID HOLIDAYS: New Year's Day, Inauguration Day, Martin Luther King Jr.'s Birthday, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day, the day after Thanksgiving Day and Christmas Day.
ELEV0010-001 01/01/2018
Rates Fringes
ELEVATOR MECHANIC................$ 44.12 32.645+a+b
a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day, Christmas Day and the Friday after Thanksgiving.
b. VACATIONS: Employer contributes 8% of basic hourly rate for 5 years or more of service; 6% of basic hourly rate for 6 months to 5 years of service as vacation pay credit.
ENGI0077-018 05/01/2017
Rates Fringes
OPERATOR: Bulldozer.............$ 30.56 8.95+a OPERATOR: Loader Front End Loaders 3 1/2 cubic yards and above.......$ 30.56 8.95+a Front End Loaders Below 3 1/2 cubic yards.............$ 30.56 8.95+a a.PAID HOLIDAYS: New Year's Day, Inaugural Day, Decoration Day, Independence Day, Labor Day, Martin Luther King's Birthday, Veterans' Day, Thanksgiving Day, Friday after Thanksgiving and Christmas Day.
IRON0005-011 06/01/2017
IRONWORKER.......................$ 31.15 20.63
LABO0657-017 06/01/2015
Rates Fringes
LABORER: Mason Tender - Cement/Concrete..................$ 22.63 7.31 LABORER: Pipelayer..............$ 22.63 7.31
PAIN0051-014 06/01/2017
Rates Fringes
GLAZIER
Glazing Contracts $2 million and under...........$ 25.74 11.55 Glazing Contracts over $2 million.....................$ 29.87 11.55
PAIN0051-019 06/01/2017
Rates Fringes
PAINTER
Brush, Roller, Spray and Drywall Finisher/Taper......$ 25.06 9.66 Industrial..................$ 30.90 10.49
PLAS0891-005 07/01/2016
Rates Fringes
PLASTERER........................$ 28.83 6.05
PLAS0891-006 02/01/2018
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 28.15 10.58
PLAS0891-008 08/01/2016
Rates Fringes
PLASTERER (Fireproofing Including Sprayer, Mixer, and Handler) Handler.....................$ 16.50 4.89 Mixer/Pump..................$ 18.50 4.89 Sprayer.....................$ 23.00 4.89
PLUM0005-010 02/01/2018
PLUMBER..........................$ 41.67 17.60+a
a. PAID HOLIDAYS: Labor Day, Veterans' Day, Thanksgiving Day and the day after Thanksgiving, Christmas Day, New Year's Day, Martin Luther King's Birthday, Memorial Day and the Fourth of July.
PLUM0602-011 08/01/2017
Rates Fringes
PIPEFITTER (Including HVAC Pipe and System Installation)....$ 40.69 21.07+a
a. PAID HOLIDAYS: New Year's Day, Martin Luther King's Birthday, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day and the day after Thanksgiving and Christmas Day.
ROOF0030-016 05/01/2016
Rates Fringes
ROOFER...........................$ 28.75 11.74
SFMD0669-001 04/01/2017
Rates Fringes
SPRINKLER FITTER (Fire Sprinklers)......................$ 34.40 19.24
SHEE0100-015 03/01/2018
Rates Fringes
SHEET METAL WORKER (Including HVAC Duct Installation)..........$ 40.27 18.87+a
a. PAID HOLIDAYS: New Year's Day, Martin Luther King's Birthday, Memorial Day, Independence Day, Labor Day, Veterans Day, Thanksgiving Day and Christmas Day
SUMD2010-091 08/04/2010
Rates Fringes
LABORER
Common or General...........$ 14.15 2.30
Grade Checker...............$ 16.00 2.90 Landscape...................$ 9.23 Mason Tender - Brick........$ 13.00 0.00 Mason Tender - Stone........$ 14.03 0.00 Mason Tender for Pointing, Caulking and Cleaning.......$ 13.21 Mortar Mixer................$ 16.61 9.08
POINTER, CAULKER, CLEANER,
Includes pointing, caulking, cleaning of existing masonry, brick, stone and cement structures (restoration work); excludes pointing, caulking, cleaning of new or replacement masonry, brick, stone or cement...........................$ 19.19 0.00
POWER EQUIPMENT OPERATOR:
Asphalt Roller..............$ 21.35 5.38 Backhoe.....................$ 19.82 5.02 Bobcat/Skid Loader..........$ 18.05 8.78 Boom........................$ 21.44 8.29 Crane.......................$ 20.95 6.18 Excavator...................$ 20.00 0.00 Forklift....................$ 16.00 5.12 Gradall.....................$ 20.50 8.42 Grader/Blade................$ 14.50 5.18 Paver.......................$ 17.47 6.36 Roller excluding Asphalt....$ 17.60 3.88
TERRAZZO WORKER/SETTER...........$ 19.94 6.54
TRUCK DRIVER
Dump Truck..................$ 15.90 1.12 Tractor Haul Truck..........$ 17.87 9.98
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations
Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
(End of Summary of Changes)
File details come from the government source that posted it.