N40027-16-R-0016 _Amendment_0003.pdf

PDF 133 KB Posted

Attached to
Blasting and Preservation
Solicitation number
N40027-16-R-0016
Issued by

About this file

Amendment 0003

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

Submarine IDIQ Amendment 0003

The purpose of this amendment is to incorporate revised w ork item 631-13-010, revised J4 and specif ications clarif ications.

Receipt of proposals remain 1400 (SERMC Local Time) on 07 April 2016.

SEE PAGE TWO FOR SF30 BLOCK 14 CONTINUATION

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 04-Apr-2016

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N40027-16-R-0016

X 9B. DATED (SEE ITEM 11)

08-Mar-2016

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

04-Apr-2016

CODE

COMMANDER SOUTHEAST REGIONAL MAINTENANCE

CTR P.O. BOX 280057, MAYPORT NAVAL STATION

JACKSONVILLE FL 32228-0057

N40027 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N40027-16-R-0016

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 0003

Bidder’s Question #9:

J-4 Line EC requires preservation of Frames 52 to 62 for paragraph 1.2.6 of Item 631-13-010. Paragraph 1.2.6 specifics Frams 84 to 94. Please provide correct Frame reference.

Answer:

Work Item 631-13-010 Revised. See revised work item.

Bidder’s Question #10:

J-4 Line ED requires preservation of Frames 62 to 71 for paragraph 1.2.7 of Item 631-13-010. Paragraph 1.2.7 specifies Frames 94 to 105. Please provide correct Frame reference.

Work Item 631-13-010 Revised. See revised work item..

Bidder’s Question #11:

J-4 Line EE requires preservation of Frames 71 to 80 for paragraph 1.2.8 of Item 631-13-010. Paragraph 1.2.8 specifies Frames 105 to 113. Please provide correct Frame reference.

Bidder’s Question #12:

J-4 Line EF requires preservation of Frames 80 to 84 for paragraph 1.2.9 of Item 631-13-010. Paragraph 1.2.9 specifies Frames 113 to 118. Please provide correct Frame reference.

Bidder’s Question #13:

Attachment J-1, Work Package SUB IDIQ 2016, Item 631-13-010 does not have locations listed for Missile Bays 1 through 4 (Frames 52 to 62, 62 to 71, 71 to 80 and 80 to 84). Was it the government’s intent to exclude these areas from the Item?

No. Work Item 631-13-010 revised to add Missile Bays One through 4.

Bidder’s Question #14:

In reference to the response to bidder’s question #8, are Vol III – Para (3a), (3b), and (3c) Production

Manning/Manning Curves no longer required, as well as Para (18), Key Event and Milestone Schedule?”

Yes. No longer required for IDIQ contract bid. However, production manning/manning curves and key event and milestone schedules shall be provided for each subsequent delivery order invoked during the execution of the contract in accordance with Navsea Standard Items 009-60 or 009-111 as applicable based on length of each delivery order.

Bidder’s Question #15:

Based on the response to bidder's question #8, are there any other checked elements in VOL III that are not required to be included in the original proposal?

No.

SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

The following have been modified:

RMC J-2-0001 LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

(a) Any contract awarded as a result of this solicitation shall consist of the following sections of this solicitation, and the documents, exhibits, and attachments described below:

Part I The Schedule (Sections A through H)

Part II Contract Clauses (Section I)

Part III List of Documents, Exhibits and other Attachments (Section J)

Part IV Representations and Instructions (Sections K through M)

Part IV of the solicitation will not be physically incorporated into the resulting contract. However, Section K, “Representations, Certifications and Other Statements of Offerors” will be retained in the contract file and acceptance of a proposal under this solicitation incorporates Section K by reference into the resultant contract (FAR

15.204-1(b)).

(b) Documents, exhibits and other attachments that will form part of and constitute this contract are as follows:

J-1 Specification Work Package SUB IDIQ 2016, Revised WI 631-13-010

J-2 Request for Specification Clarification

J-3 SSBN/SSGN General Requirements

J-4 Cost Data Break Down, Excel Spreadsheet, five (5) tabs, (Revision 1)

J-5 TRIREFFAC KINGS BAY INST 5100.1D CH-3

J-6 TRIREFFAC KINGS BAY INSTRUCTION 5401.1F

J-7 SUBASE INSTR 5090.6

J-8 TRIREFFACINST 5090_1e

J-9 SUBASE INSTR 5090.3e

J-10 TRIREFFACINST 5090_2b

J-11 TRIREFFACINST 5090_3d

J-12 Exhibit “A” Contract Data Requirements List (CDRL) DD Form 1423

J-13 Past Performance Questionnaire

(End of Summary of Changes)

File details come from the government source that posted it. Updated .