Attachment 2 - Submital Table.docx

DOCX document 18 KB Posted

Attached to
Dismantle, Transport, and Disposal of a Submarine Support Facility (SSF)
Solicitation number
N3904020R0288
Issued by

About this file

This solicitation seeks proposals for the dismantlement, transportation, and disposal of a Submarine Support Facility at the Portsmouth Naval Shipyard. The facility is radiologically controlled, and the contractor will be expected to maintain accountability for all materials at the worksite during demolition. The Navy contemplates using a "Rip and Ship" demolition and bulk disposal method for approximately 1,600,000 pounds of waste. The Portsmouth Naval Shipyard will perform waste stream characterizations and radiological surveys. Offerors must hold all necessary qualifications, certifications, and licenses for this work, including transportation and disposal at an approved offsite facility. Potential offerors must tour the Submarine Support Facility in order to submit a proposal that will be considered for award of a contract.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT D: Submittal Summary NOTE: See Attachment A for additional required submittals Specification - Required Submittals

Title
Specification Paragraph
Contractor's Due Date
Government Review Time (Business Days)
Copies
List of Contact Personnel; G
1
Prior to work
Personnel List; G
Att. A Section 1
Prior to Mobilization
Vehicle List; G
Att. A Section 1
Prior to Mobilization
Demolition Plan ; G
Att. A Section 7
Prior to Mobilization

Environmental Management Plan; G

Att. A Section 7
Prior to work

Accident Prevention Plan (APP); G

Att. A Section 9
Prior to work

Activity Hazard Analysis (AHA); G

Att. A Section 9
Prior to work
Crane Critical Lift Plan; G
Att. A Section 9
10 DAYS PRIOR TO EQUIPMENT ARRIVAL

Crane Operators qualification; G

Att. A Section 9
10 DAYS PRIOR TO EQUIPMENT ARRIVAL
Accident Reports; G
Att. A Section 9
Within 48 hours
Crane Reports; G
Att. A Section 9
weekly
Hot work permit; G
Att. A Section 9
Prior to work
Contractor Safety Self-Evaluation Checklist; G
Att. A Section 9
Prior to work

Accident Notification; G

Att. A Section 9
Within 24 hours

Environmental Management Plan; G

Att. A Section 13
Prework

Dirt and Dust Control Plan; G

Att. A Section 13
Prework

Contractor Hazardous Material Inventory Log; G

Att. A Section 13
Prework

Contractor 40 CFR Employee Training Records; G

Att. A Section 13
Closeout Submittals
Contractor Hazardous Material Inventory Log; G
Att. A Section 13
Closeout Submittals