This document is an attachment titled "Format Outline for Safety" that is part of a solicitation for the "DESIGN-BUILD ELECTRICAL SUBSTATION REPAIRS, NSA SOUDA BAY, CRETE, GREECE" federal contract opportunity. The solicitation is for a project to repair electrical distribution substations at NSA Souda Bay, Crete, Greece, including six substations and one medium voltage switchgear.
The attachment outlines the required safety information to be provided by the offeror, including details on the proposed Site Safety and Health Officer (SSHO) experience, the offeror's safety procedures management and implementation, and the monitoring of subcontractor safety procedures if subcontractors are used. Offerors must describe how they will properly manage and implement safety procedures for subcontractors, evaluate and measure subcontractor safety performance, and employ innovative methods to ensure and monitor safe work practices. The solicitation has an estimated construction value between $1,000,000 and $5,000,000.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION: ELECTRICAL SUBSTATION REPAIR, NSA SOUDA BAY
ATTACHMENT F – FORMAT OUTLINE FOR SAFETY
SAFETY FORMAT OUTLINE
1. NAME OF OFFEROR/JOINT VENTURE:
2. SSHO PROPOSED EXPERIENCE: Provide Total Years of Experience, Certification and Years of Safety Experience (include industry and total projects cost, where applicable):
Total Years of Experience: ______________
Safety Certification: ☐ OSHA ☐ EM 385-1-1 ☐ Other: ______________________________________________
| Safety Experience in the following Industry: |
| Years of Experience |
| Total Cost ($) |
Construction
General
Other (specify: ________________________________________)
3. DESCRIBE OFFEROR’S SAFETY PROCEDURES MANAGEMENT AND IMPLEMENTATION
4. MONITORING OF SUBCONTRACTOR’S SAFETY PROCEDURES
a. Are Subcontractors being used?
| ☐ Yes (proceed to b, c and d) |
| ☐ No (provide statement that no Subcontractors will be used) |
b. Describe how Offeror plans to properly manage and implement safety procedures for its Subcontractors. Explain how Subcontractor safety performance will be monitored.
c. Describe how Offeror plans to evaluate and measure safety performance of potential Subcontractors, as part of the selection process for all levels of Subcontractors.
d. Describe any innovative methods that will be employed to ensure and monitor safe work practices at all levels.