N3319120R4019 Solicitation Amendment 0001.pdf
PDF 275 KB Posted
- Solicitation number
- N3319120R4019
About this file
This document is a solicitation amendment for the renovation of four schools in Montenegro. The Navy is seeking proposals to renovate schools in the cities of Andrijevica, Golubovci, Niksic, and Zabljak. The amendment extends the proposal due date to June 16, 2020 and provides responses to pre-proposal inquiries. It clarifies that detailed bills of quantities or technical specifications for each school are not provided, as contractors are required to perform their own measurements and assessments. The amendment also contains annexes with details for the scope of work at each school location. The period of performance has been increased from 400 to 720 calendar days from contract award.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ACQR5777862
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
N33191120R4019 D-B Renovate Four Schools, Andrijevica, Golubovci, Niksic, and Zabljak, Montenegro
This solicitation amendment continues on page 2.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 15-Apr-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N3319120R4019
X 9B. DATED (SEE ITEM 11)
02-Apr-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
15-Apr-2020
CODE
NAVFAC EUROPE AFRICA CENTRAL
VIALE PORTO CAPODICHINO
NAPOLI 80144
N33191 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N3319120R4019
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
Amendment 0001
The purpose of this solicitation amendment is to:
1) respond to Pre-Proposal Inquiries, and
2) extend the proposal due date to 16 June 2020 by 2:00p.m. Central European Summer Time
(CEST).
Pre-Proposal Inquiry 1:
Could you please let us know how to acquire detailed Bill of quantities / technical project (specification) for each school that should be provided (purchase request number ACQR5777862)?
N43319120R4019+Montenegro+Schools+Solicitation (1).pdf - Pages 3 to 7 of 40.
Pre-Proposal Inquiry 1 Response:
Bill of quantities is not provided for any of the 4 schools. As stated in paragraph 2.7 of the PTS: “This contract complies with the US Contracting Regulations, and as such, all measurements and quantities of materials provided shall be verified and measured on site by the contractor. The contractor needs to visit the job site in order to perform the necessary measurements and to observe the existing field conditions in order to prepare their cost proposal”
Pre-Proposal Inquiry 2:
It is mentioned in tender documentation that Attachment 1 should contain Annex #2-5(technical projects) prepared by beneficiary (Ministry of Education).
N43319120R4019+Montenegro+Schools+Attach+1+-+PTS (1).pdf - Page 3 of 95 and Page 9 of 95, paragraph 5
Pre-Proposal Inquiry 2 Response:
Yes, there are four (4) annexes with each annex corresponding to a school. Due to the size of the files, the four (4) annexes are broken down into a total of nine (9) files and are provided as part of this amendment.
Pre-Proposal Inquiry 3:
According to paragraph 2.5. General Project Description (Base-Bid and Contract Options) resume chart (page 11 of 95) CLIN0002 of base bid includes the works to be performed in GOLUBOVCI-PDGORICA (see attached 01).
In the deta this SOW
Contracto
Pre-Prop
The sectio “N331912 includes t
Pre-Prop
Reference be perform according
These an
Please cla
Pre-Prop
Please se ailed scope o is called CLI or understand osal Inquiry on title on pag 20R4019 Mon he correct se osal Inquiry e to Annexes med in detail g to the table b nexes are no arify.
osal Inquiry ee Pre-Propos of works 4. CL N0004 instea s this is a typ
3 Response ge 20 is a typ ntenegro Scho ction/CLIN tit
4:
2 to 5 is cont for each of th below.
t available for
4 Response sal Inquiry 2 R
LIN0004 - GE
ad of CLIN000 ping issue. Ple e:
pographical er ools Attach 1 tle.
tinuously don he locations a r review.
e:
Response.
NERAL SCO
02. (see attac ease clarify.
rror in the orig
– PTS Updat e in PTS prov nd expands t
OPE OF WOR
ched 02).
ginal PTS. Th ted.pdf” provi vided. These the informatio
RK OF BASE-
he attachment ded with this
Annexes inc on for each of
N3319120R
Page
-BID GOLUBO
t amendment ludes the SO f the CLINs
R4019
OVCI,
W to
N3319120R4019
Pre-Proposal Inquiry 5:
Paragraph 11.7. Construction/Design Schedule and Contractual Milestones states: (see attached #01)
Perform all work within 200 calendar days after contract award. Provide a bar chart with a minimum of 20 activities. Indicate planned start and completion dates for design and construction.
In addition to the contractual requirement to complete all construction works within the 200 calendar days after award of the contract, the contractor shall comply with the following required milestones. Failure to comply with these milestones will be objective basis for invoice retention or further contractual action by the Contracting Officer.
Paragraph 11.8. Construction Schedule (bar chart is authorized) states: (see attached #01) Perform all work within 400 calendar days after contract award. Within 45 days after contract award, the contractor shall provide a construction schedule including a minimum of 40 activities, and clearly defining the different phases.
The contractor would need to know the established duration of the contract to schedule work and costs.
Please clarify.
Pre-Proposal Inquiry 5 Response:
In accordance with Sections 11.7 and 11.8 of the updated PTS provided as an attachment with this amendment (“N3319120R4019 Montenegro Schools Attach 1 – PTS Updated.pdf”), all work shall be completed within 720 calendar days after contract award. The SF1442 has also been updated to reflect this.
SECTION 00010 - SOLICITATION CONTRACT FORM
The contractor period of performance end date has increased by 320 days from 400 days to 720 days.
(End of Summary of Changes)