This document package includes technical drawings and specifications for renovations to four schools in Montenegro. The projects involve replacing exterior joinery, roofing materials, ceilings and other interior renovations. Drawings show existing conditions and proposed renovations to building facades, interiors and structural elements. Specifications include material types for new windows, doors, roofing and interior finishes. Renovations are planned in multiple phases to allow continued school operations. The work will be performed at schools in the municipalities of Andrijevica, Golubovci, Niksic and Zabljak, Montenegro.

View the file

Other files

File Type Posted
N3319120R4019 Amend 5 (1).pdf PDF
N3319120R4019 Amendment 0004.pdf PDF
N3319120R4019 Amendment 0003.pdf PDF
N3319120R4019 Amendment 0002.pdf PDF
N3319120R4019 PTS Annex 2-Part2of4 (Total 2 of 9).pdf PDF
N3319120R4019 PTS Annex 4- Part2of2 (Total 8 of 9).pdf PDF
N3319120R4019 Montenegro Schools Attach 1 - PTS Updated.pdf PDF
N3319120R4019 Solicitation Amendment 0001.pdf PDF
N3319120R4019 PTS Annex 4- Part1of2 (Total 7 of 9).pdf PDF
N3319120R4019 PTS Annex 2-Part3of4 (Total 3 of 9).pdf PDF
N3319120R4019 PTS Annex 5-Part1of1 (Total 9 of 9).pdf PDF
N3319120R4019 PTS Annex 2-Part1of4 (Total 1 of 9).pdf PDF
N3319120R4019 PTS Annex 3-Part1of2 (Total 5 of 9).pdf PDF
N3319120R4019 PTS Annex 2-Part4of4 (Total 4 of 9).pdf PDF
N3319120R4019 PTS Annex 3-Part2of2 (Total 6 of 9).pdf PDF
N3319120R4019 Montenegro Schools Attach 1 - PTS.pdf PDF
N3319120R4019 Montenegro Schools Attach 4 - Data Sheet.docx DOCX document
N3319120R4019 Montenegro Schools Attach 2 - PPI.docx DOCX document
N3319120R4019 Montenegro Schools Attach 5 - Safety Checklist.docx DOCX document
N3319120R4019 Montenegro Schools Solicitation.pdf PDF
N3319120R4019 Montenegro Schools Attach 3 - Price Schedule.doc DOC document
N3319120R4019 Montenegro Schools Attach 6 - PPQ.docx DOCX document
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

L E G E N D A / N O T E

+ 12.04

+ 12.22

B C A STARI OBJEKAT / OLD BUILDING

B NOVO KRILO ŠKOLE / NEW SCHOOL WING

D C FISKULTURNA SALA SA ANEKSOM / GYM WITH ANNEX

D KOTLARNICA / BOILER ROOM

A

+ 7.76

FAZE / PHASES :

BOJA_JUB 1443

+ 3.60

BOJA_JUB 1443

FAZA 1. / PHASE 1.

-ZAMJENA FASADNE STOLARIJE NA DIJELU ŠKOLE ''A''; /

-REPLACING OLD JOINERY FROM OLD SHOOL BUILDING - PART ''A'';

-ZAMJENA VERTIKALNIH OLUKA NA DIJELU ŠKOLE ''A''; /

-REPLACING OLD DOWNPIPES FROM OLD SHOOL BUILDING - PART ''A'';

± 0.00

- 0.85

O25

O24

O23

O30

O31

O22

O21 O20

- 0.89

-FASADERSKI RADOVI - DEKORATIVNI FASADNI MALTER NA SVIM

DJELOVMA ŠKOLE - ''A'', ''B'', ''C'', ''D''; /

-PLACING NEW FACADE FINAL LAYER ON ALL SCHOOL PARTS -

''A'', ''B'', ''C'', ''D'';

FAZA 2. / PHASE 2.

-SANIRANJE KROVNE KONSTRUKCIJE;

-ZAMJENA DIJELA KROVNE KONSTRUKCIJE;

-ZAMJENA CJELOKUPNE TAVANSKE KONSTRUKCIJE I PLAFONA;

NA DIJELU ŠKOLE ''C'';

A B C D E F G H I J

JUŽNA FASADA / SOUTH FACADE

-REPAIRING ROOF CONSTRUCTION;

-REPLACING A PART OF ROOF CONSTRUCTION;

-REPLACING ALL OF CEILING CONSTRUCTION AND CEILING;

SCHOOL GYM - PART ''C'';

FAZA 3. / PHASE 3.

-ZAMJENA CJELOKUPNOG KROVNOG POKRIVAČA I

HORIZONTALNIH OLUKA;

-SANIRANJE KROVNE KONSTRUKCIJE;

-ZAMJENA DIJELA KROVNE KONSTRUKCIJE;

-ZAMJENA CJELOKUPNE TAVANSKE KONSTRUKCIJE I PLAFONA;

NA STAROM DIJELU DIJELU SKOLE - ''A'';

-REPLACING OLD ROOF TILES AND OLD HORIZONTAL GUTTERS;

-REPAIRING ROOF CONSTRUCTION;

-REPLACING A PART OF ROOF CONSTRUCTION;

OLD SCHOOL BUILDING - PART ''A'';

O20 O12

+ 5.01

X NOVA FASADNA STOLARIJA /

A Y NEW JOINERY

KROVNA OBLOGA (TRAPEZASTI LIM) /

TRAPEZOIDAL METAL SHEET

OBJEKAT ''C'' - FAZA 2 / PART ''C'' - PHASE 2

O17

+ 2.57

NOVI ELMENTI (LIMENI OPŠAVI,

HORIZONTALNI OLUCI ITD.) /

NEW ELEMENTS (METAL SHEET FLASHINGS,

GUTTERS ETC.)

NOVA KROVNA OBLOGA (CRIJEP) /

NEW ROOF TILES

OBJEKAT ''A'' - FAZA 3 / PART ''A'' - PHASE 3

- 0.87

O18

O16

O11

O9

O10

O1 O29

- 0.90

NAPOMENA / REMARK:

- Grafički prilozi su preuzeti iz projekta ''Glavni projekat adaptacije Osnovne škole ''Milan Vukotić'', Golubovci - Program energetske efikasnosti u javnim objektima u Crnoj Gori - faza 2'' - projektant: ''KOPRING PMC d.o.o., Podgorica'' ; /

- Graphical documentation is taken from project '' Final Adaptation Design of the Centre for Primary School ''Milan Vukotić'', Golubovci, Energy Efficiancy Programme in Public Buildings - Phase II (EEPPB II) - designer: ''KOPRING PMC d.o.o., Podgorica'' ;

PROJEKTANT / DESIGNER:

Arhitektonika d .o .o . Nikšić Bulevar " 13 jul " br . 96 , 81400 Nikšić

Te l/ fax : + 3 8 2 ( 0 ) 40 2 5 1 867 Mo b : + 382 ( 0 ) 69 347 395

+ 382 ( 0 ) 69 309 590

INVESTITOR / CLIENT:

JU OŠ " MILAN VUKOTIĆ",

Opština Podgorica

J I H

G F E D C L

Objekat / Building: JU OŠ " Milan Vukotić", Golubovci, Opština Podgorica /

K School ''Milan Vukotić'', Golubovci, Montenegro Glavni inženjer / Leading designer:

Nikola Bulajić, d. i. a.

Odgovorni inženjer / Authorized designer:

Lokacija / Location: K.P. 12964, K.O. GOLUBOVCI, OPŠTINA U OKVIRU GLAVNOG GRADA GOLUBOVCI

Vrsta tehničke dokumentacije / Design phase:

Glavni projekat adaptacije / Main design of adaptation

Nikola Bulajić, d. i. a. Dio tehničke dokumentacije / Design discipline: faza - ARHITEKTURA RAZMJERA / SCALE:

Saradnici / Assistant designers: phase - ARCHITECTURE R=1:100 SJEVERNA FASADA / NORTH FACADE Jelena Međedović, spec.sci.arh

Prilog / Page title:

Br. priloga /

Br. strane /

Nemanja Jokić, b.sc.arh

Boris Radunović, spec.sci.arh

Datum izrade i M.P. / Date and stamp

Južna i sjeverna fasada (planirano stanje) Document no.: Page no.:

South and north facade (designed situation) 12 Datum revizije i M.P. / Revision date and stamp

DECEMBAR / DECEMBER 2019 . god.

L E G E N D A / N O T E

B C A STARI OBJEKAT / OLD BUILDING

+ 7.02

-ZAMJENA FASADNE STOLARIJE NA DIJELU ŠKOLE ''A''; /

-REPLACING OLD JOINERY FROM OLD SHOOL BUILDING - PART ''A'';

+ 3.60 -FASADERSKI RADOVI - DEKORATIVNI FASADNI MALTER NA SVIM

- 0.92

O21

O20

O19

O18

-ZAMJENA DIJELA KROVNE KONSTRUKCIJE;

1 2 3 4 9 10

ISTOČNA FASADA / EAST FACADE

-REPAIRING ROOF CONSTRUCTION;

-REPLACING A PART OF ROOF CONSTRUCTION;

HORIZONTALNIH OLUKA;

-SANIRANJE KROVNE KONSTRUKCIJE;

-ZAMJENA DIJELA KROVNE KONSTRUKCIJE;

-ZAMJENA CJELOKUPNE TAVANSKE KONSTRUKCIJE I PLAFONA;

NA STAROM DIJELU DIJELU SKOLE - ''A'';

-REPLACING OLD ROOF TILES AND OLD HORIZONTAL GUTTERS;

-REPAIRING ROOF CONSTRUCTION;

-REPLACING A PART OF ROOF CONSTRUCTION;

Y NEW JOINERY

O29

O28

O27

O26

O25

O24

- Grafički prilozi su preuzeti iz projekta ''Glavni projekat adaptacije Osnovne škole ''Milan Vukotić'', Golubovci - Program energetske efikasnosti u javnim objektima u Crnoj Gori - faza 2'' - projektant: ''KOPRING PMC d.o.o., Podgorica'' ; /

- Graphical documentation is taken from project '' Final Adaptation Design of the Centre for Primary School ''Milan Vukotić'', Golubovci, Energy Efficiancy Programme in Public Buildings - Phase II (EEPPB II) - designer: ''KOPRING PMC d.o.o., Podgorica'' ;

PROJEKTANT / DESIGNER:

Te l/ f a x : + 3 8 2 ( 0 ) 4 0 2 5 1 8 6 7 Mob : + 382 ( 0 ) 69 347 395

INVESTITOR / CLIENT:

8 7 6

5 4 3 2 1

Opština Podgorica /

School ''Milan Vukotić'', Golubovci, Montenegro Glavni inženjer / Leading designer:

Nikola Bulajić, d. i. a.

Odgovorni inženjer / Authorized designer:

Nikola Bulajić, d. i. a.

Lokacija / Location:

K.P. 12964, K.O. GOLUBOVCI,

OPŠTINA U OKVIRU GLAVNOG GRADA GOLUBOVCI

Vrsta tehničke dokumentacije / Design phase:

Glavni projekat adaptacije / Main design of adaptation

Dio tehničke dokumentacije / RAZMJERA / SCALE: Design discipline: faza - ARHITEKTURA Saradnici / Assistant designers: phase - ARCHITECTURE R=1:100

ZAPADNA FASADA / WEST FACADE Jelena Međedović, spec.sci.arh

Boris Radunović, spec.sci.arh

Datum izrade i M.P. / Date and stamp

Istočna i zapadna fasada (planirano stanje) Document no.: Page no.:

East and west facade (designed situation) 13 Datum revizije i M.P. /

-ZAMJENA FASADNE STOLARIJE NA DIJELU ŠKOLE ''A''; /

-REPLACING OLD JOINERY FROM OLD SHOOL BUILDING - PART ''A'';

+ 4.02

DJELOVMA ŠKOLE - ''A'', ''B'', ''C'', ''D''; /

+ 2.24

O17

- 0.64 O16 O15

O14

O13

O12

- 0.90

-SANIRANJE KROVNE KONSTRUKCIJE;

-ZAMJENA DIJELA KROVNE KONSTRUKCIJE;

10 9

4 3 2 1

-REPAIRING ROOF CONSTRUCTION;

-REPLACING A PART OF ROOF CONSTRUCTION;

-REPLACING ALL OF CEILING CONSTRUCTION AND CEILING;

UNUTRAŠNJA FASADA 1 / INNER YARD FACADE 1

HORIZONTALNIH OLUKA;

-SANIRANJE KROVNE KONSTRUKCIJE;

-ZAMJENA DIJELA KROVNE KONSTRUKCIJE;

-ZAMJENA CJELOKUPNE TAVANSKE KONSTRUKCIJE I PLAFONA;

NA STAROM DIJELU DIJELU SKOLE - ''A'';

-REPLACING OLD ROOF TILES AND OLD HORIZONTAL GUTTERS;

-REPAIRING ROOF CONSTRUCTION;

-REPLACING A PART OF ROOF CONSTRUCTION;

- Grafički prilozi su preuzeti iz projekta ''Glavni projekat adaptacije Osnovne škole ''Milan Vukotić'', Golubovci - Program energetske efikasnosti u javnim objektima u Crnoj Gori - faza 2'' - projektant: ''KOPRING PMC d.o.o., Podgorica'' ; /

- Graphical documentation is taken from project '' Final Adaptation Design of the Centre for Primary School ''Milan Vukotić'', Golubovci, Energy Efficiancy Programme in Public Buildings - Phase II (EEPPB II) - designer: ''KOPRING PMC d.o.o., Podgorica'' ;

PROJEKTANT / DESIGNER: INVESTITOR / CLIENT:

- 0.88

± 0.00 O5 O4 O3

O2 O1

School ''Milan Vukotić'', Golubovci, Montenegro Glavni inženjer / Leading designer:

Nikola Bulajić, d. i. a.

Odgovorni inženjer / Authorized designer:

Lokacija / Location:

K.P. 12964, K.O. GOLUBOVCI,

OPŠTINA U OKVIRU GLAVNOG GRADA GOLUBOVCI

Vrsta tehničke dokumentacije / Design phase:

Glavni projekat adaptacije / Main design of adaptation

Nikola Bulajić, d. i. a. Dio tehničke dokumentacije / Design discipline: faza - ARHITEKTURA RAZMJERA / SCALE:

UNUTRAŠNJA FASADA 2 / INNER YARD FACADE 2 Saradnici / Assistant designers: phase - ARCHITECTURE R=1:100 Jelena Međedović, spec.sci.arh

Boris Radunović, spec.sci.arh

Datum izrade i M.P. / Date and stamp

Unutrašnje fasade (planirano stanje) Document no.: Page no.:

Inner yard facade (designed situation) 14 Datum revizije i M.P. /

+ 7.76 FAZE / PHASES :

-ZAMJENA FASADNE STOLARIJE NA DIJELU ŠKOLE ''A''; /

-REPLACING OLD JOINERY FROM OLD SHOOL BUILDING - PART ''A'';

- 0.88 - 0.85

-ZAMJENA DIJELA KROVNE KONSTRUKCIJE;

1 2 3 4 5 6 7 8

UNUTRAŠNJA FASADA 3 / INNER YARD FACADE 3

-REPAIRING ROOF CONSTRUCTION;

-REPLACING A PART OF ROOF CONSTRUCTION;

HORIZONTALNIH OLUKA;

-SANIRANJE KROVNE KONSTRUKCIJE;

-ZAMJENA DIJELA KROVNE KONSTRUKCIJE;

-ZAMJENA CJELOKUPNE TAVANSKE KONSTRUKCIJE I PLAFONA;

NA STAROM DIJELU DIJELU SKOLE - ''A'';

-REPLACING OLD ROOF TILES AND OLD HORIZONTAL GUTTERS;

-REPAIRING ROOF CONSTRUCTION;

-REPLACING A PART OF ROOF CONSTRUCTION;

+ 1.82

+ 3.55

+ 3.55

- Grafički prilozi su preuzeti iz projekta ''Glavni projekat adaptacije Osnovne škole ''Milan Vukotić'', Golubovci - Program energetske efikasnosti u javnim objektima u Crnoj Gori - faza 2'' - projektant: ''KOPRING PMC d.o.o., Podgorica'' ; /

- Graphical documentation is taken from project '' Final Adaptation Design of the Centre for Primary School ''Milan Vukotić'', Golubovci, Energy Efficiancy Programme in Public Buildings - Phase II (EEPPB II) - designer: ''KOPRING PMC d.o.o., Podgorica'' ;

PROJEKTANT / DESIGNER: INVESTITOR / CLIENT:

± 0.00 ± 0.00 O6

- 0.64

- 0.92

+ 382 ( 0 ) 69 309 590 Opština Podgorica

School ''Milan Vukotić'', Golubovci, Montenegro Glavni inženjer / Leading designer:

Nikola Bulajić, d. i. a.

Odgovorni inženjer / Authorized designer:

Lokacija / Location:

K.P. 12964, K.O. GOLUBOVCI,

OPŠTINA U OKVIRU GLAVNOG GRADA GOLUBOVCI

Vrsta tehničke dokumentacije / Design phase:

Glavni projekat adaptacije / Main design of adaptation

Nikola Bulajić, d. i. a. Dio tehničke dokumentacije / Design discipline: faza - ARHITEKTURA RAZMJERA / SCALE:

Saradnici / Assistant designers: phase - ARCHITECTURE R=1:100 Jelena Međedović, spec.sci.arh

Boris Radunović, spec.sci.arh

Unutrašnje fasade (planirano stanje) Document no.: Page no.:

Inner yard facade (designed situation) 15 10 9 4 3 2 1 Datum izrade i M.P. / Datum revizije i M.P. /

Date and stamp Revision date and stamp

UNUTRAŠNJA FASADA 4 / INNER YARD FACADE 4

B ul evar " 13 jul " br . 96 , 81400 N i kši ć

JU OŠ ''MILAN VUKOTIĆ'', GOLUBOVCI

Tel/ f a x : + 3 8 2 ( 0 ) 4 0 2 5 1 8 6 7 M ob : + 382 ( 0 ) 69 347 395

+ 382 ( 0 ) 69 309 590 šema fasadne PVC stolarije schemes of external PVC joinery

JU OŠ ''MILAN VUKOTIĆ''

Golubovci, Podgorica

KONVENCIJA SMJERA OTVARANJA VRATA I PROZORA

DOORS AND WINDOWS OPENING CONVENTION

DESNA / RIGHT

LIJEVA / LEFT

Investitor: JU OŠ ''Milan Vukotić'', Podgor6ic2 a

Arhitektonika d . o . o . Nikšić Bulevar " 13 jul" br . 96 , 81400 Nikšić

T e l / f ax : + 3 8 2 ( 0 ) 40 2 5 1 8 6 7 M o b : + 3 8 2 ( 0 ) 69 3 4 7 3 9 5

+ 382 ( 0 ) 69 309 590

JU OŠ ''MILAN VUKOTIĆ'', GOLUBOVCI

Str. 1 / Page no. 1 šeme fasadne PVC stolarije scheme of external PVC joinery

POS 1

IZGLED SA FASADE /

FACADE VIEW

PRESJEK 1-1 /

SECTION 1-1

poluga / lever stool nova

PVC klupica new internal

PVC

Al okapnica/ Al sill

OSNOVA

p:90cm

NAPOMENA / NOTE:

iznad h=220 cm, a otvara se jedino na "ventus", koristi se mehanizam sa plugom. /

Window handle shall be mounted as low as possible so it could be reachable from the ground. For opening of window leaf which opens only on "ventus" and its handle is mounted on a height that exceeds 2.20m, mechanism with lever shall be used.

kom: 42 L - D -

Opis pozicije / Position description

- Grafički prilozi su preuzeti iz projekta ''Glavni projekat adaptacije Osnovne škole ''Milan Vukotić'', Golubovci - Program energetske efikasnosti u javnim objektima u Crnoj Gori - faza 2'' - projektant: ''KOPRING PMC d.o.o., Podgorica'' ; /

- Graphical documentation is taken from project '' Final Adaptation Design of the Centre for Primary School ''Milan Vukotić'', Golubovci, Energy Efficiancy Programme in Public Buildings - Phase II (EEPPB II) - designer: ''KOPRING PMC d.o.o., Podgorica'' ;

Napomena: Sve mjere provjeriti na licu mjesta Note: All measurements must be taken before, at building site zidarska mjera / built in measure 191 x 23163

Bulevar " 13 jul" br . 96 , 81400 Nikšić

T e l / f ax : + 3 8 2 ( 0 ) 40 2 5 1 8 6 7 M o b : + 3 8 2 ( 0 ) 69 3 4 7 3 9 5

+ 382 ( 0 ) 69 309 590

JU OŠ ''MILAN VUKOTIĆ'', GOLUBOVCI

Str. 2 / Page no. 2

POS 2 1

IZGLED SA FASADE /

FACADE VIEW

140 1 p:100cm iznad h=220 cm, a otvara se jedino na "ventus", koristi se mehanizam sa plugom. /

Window handle shall be mounted as low as possible so it could be reachable from the ground. For opening of window leaf which opens only on "ventus" and its handle is mounted on a height that exceeds 2.20m, mechanism with lever shall be used.

kom: 22 L - D -

- Grafički prilozi su preuzeti iz projekta ''Glavni projekat adaptacije Osnovne škole ''Milan Vukotić'', Golubovci - Program energetske efikasnosti u javnim objektima u Crnoj Gori - faza 2'' - projektant: ''KOPRING PMC d.o.o., Podgorica'' ; /

- Graphical documentation is taken from project '' Final Adaptation Design of the Centre for Primary School ''Milan Vukotić'', Golubovci, Energy Efficiancy Programme in Public Buildings - Phase II (EEPPB II) - designer: ''KOPRING PMC d.o.o., Podgorica'' ;

Napomena: Sve mjere provjeriti na licu mjesta Note: All measurements must be taken before, at building site zidarska mjera / built in measure 141 x 22164

T e l / f ax : + 3 8 2 ( 0 ) 40 2 5 1 8 6 7 M o b : + 3 8 2 ( 0 ) 69 3 4 7 3 9 5

+ 382 ( 0 ) 69 309 590

JU OŠ ''MILAN VUKOTIĆ'', GOLUBOVCI

Str. 3 / Page no. 3

POS 5

FACADE VIEW

p:180cm dohvatiti sa zemlje. / Window handle shall be mounted as low as possible so it could be reachable from the ground.

kom: 2 L - D -

- Grafički prilozi su preuzeti iz projekta ''Glavni projekat adaptacije Osnovne škole ''Milan Vukotić'', Golubovci - Program energetske efikasnosti u javnim objektima u Crnoj Gori - faza 2'' - projektant: ''KOPRING PMC d.o.o., Podgorica'' ; /

- Graphical documentation is taken from project '' Final Adaptation Design of the Centre for Primary School ''Milan Vukotić'', Golubovci, Energy Efficiancy Programme in Public Buildings - Phase II (EEPPB II) - designer: ''KOPRING PMC d.o.o., Podgorica'' ;

Napomena: Sve mjere provjeriti na licu mjesta Note: All measurements must be taken before, at building site zidarska mjera / built in measure 141 x 15165

T e l / f ax : + 3 8 2 ( 0 ) 40 2 5 1 8 6 7 M o b : + 3 8 2 ( 0 ) 69 3 4 7 3 9 5

+ 382 ( 0 ) 69 309 590

JU OŠ ''MILAN VUKOTIĆ'', GOLUBOVCI

Str. 4 / Page no. 4

POS 6 1

FACADE VIEW

kom: 4 L - D -

- Grafički prilozi su preuzeti iz projekta ''Glavni projekat adaptacije Osnovne škole ''Milan Vukotić'', Golubovci - Program energetske efikasnosti u javnim objektima u Crnoj Gori - faza 2'' - projektant: ''KOPRING PMC d.o.o., Podgorica'' ; /

- Graphical documentation is taken from project '' Final Adaptation Design of the Centre for Primary School ''Milan Vukotić'', Golubovci, Energy Efficiancy Programme in Public Buildings - Phase II (EEPPB II) - designer: ''KOPRING PMC d.o.o., Podgorica'' ;

Napomena: Sve mjere provjeriti na licu mjesta Note: All measurements must be taken before, at building site zidarska mjera / built in measure 136 x 25666

5 78

T e l / f ax : + 3 8 2 ( 0 ) 40 2 5 1 8 6 7 M o b : + 3 8 2 ( 0 ) 69 3 4 7 3 9 5

+ 382 ( 0 ) 69 309 590

JU OŠ ''MILAN VUKOTIĆ'', GOLUBOVCI

Str. 5 / Page no. 5

POS 7 1

FACADE VIEW

kom: 2 L - D -

- Grafički prilozi su preuzeti iz projekta ''Glavni projekat adaptacije Osnovne škole ''Milan Vukotić'', Golubovci - Program energetske efikasnosti u javnim objektima u Crnoj Gori - faza 2'' - projektant: ''KOPRING PMC d.o.o., Podgorica'' ; /

- Graphical documentation is taken from project '' Final Adaptation Design of the Centre for Primary School ''Milan Vukotić'', Golubovci, Energy Efficiancy Programme in Public Buildings - Phase II (EEPPB II) - designer: ''KOPRING PMC d.o.o., Podgorica'' ;

Napomena: Sve mjere provjeriti na licu mjesta Note: All measurements must be taken before, at building site zidarska mjera / built in measure 141 x 21167

Al sill

T e l / f ax : + 3 8 2 ( 0 ) 40 2 5 1 8 6 7 M o b : + 3 8 2 ( 0 ) 69 3 4 7 3 9 5

+ 382 ( 0 ) 69 309 590

JU OŠ ''MILAN VUKOTIĆ'', GOLUBOVCI

Str. 6 / Page no. 6

FACADE VIEW

L -

- Grafički prilozi su preuzeti iz projekta ''Glavni projekat adaptacije Osnovne škole ''Milan Vukotić'', Golubovci - Program energetske efikasnosti u javnim objektima u Crnoj Gori - faza 2'' - projektant: ''KOPRING PMC d.o.o., Podgorica'' ; /

- Graphical documentation is taken from project '' Final Adaptation Design of the Centre for Primary School ''Milan Vukotić'', Golubovci, Energy Efficiancy Programme in Public Buildings - Phase II (EEPPB II) - designer: ''KOPRING PMC d.o.o., Podgorica'' ;

Napomena: Sve mjere provjeriti na licu mjesta Note: All measurements must be taken before, at building site p:100cm

D - kom: 2

POS 8

zidarska mjera / built in measure 71 x 211 68 kom: 2

Arhitektonika d . o . o . Nikšić Bulevar " 13 jul" br . 96 , 81400 Nikšić

T e l / f ax : + 3 8 2 ( 0 ) 40 2 5 1 8 6 7 M o b : + 3 8 2 ( 0 ) 69 3 4 7 3 9 5

+ 382 ( 0 ) 69 309 590

JU OŠ ''MILAN VUKOTIĆ'', GOLUBOVCI

Str. 7 / Page no. 7

140 1

POS 12

- Grafički prilozi su preuzeti iz projekta ''Glavni projekat adaptacije Osnovne škole ''Milan Vukotić'', Golubovci - Program energetske efikasnosti u javnim objektima u Crnoj Gori - faza 2'' - projektant: ''KOPRING PMC d.o.o., Podgorica'' ; /

- Graphical documentation is taken from project '' Final Adaptation Design of the Centre for Primary School ''Milan Vukotić'', Golubovci, Energy Efficiancy Programme in Public Buildings - Phase II (EEPPB II) - designer: ''KOPRING PMC d.o.o., Podgorica'' ;

Napomena: Sve mjere provjeriti na licu mjesta Note: All measurements must be taken before, at building site p:85cm

PRESJEK 1-1 /

Al sill new internal

PVC

D - zidarska mjera / built in measure 141 x 23169 kom: 5

Bulevar " 13 jul" br . 96 , 81400 Nikšić

T e l / f ax : + 3 8 2 ( 0 ) 40 2 5 1 8 6 7 M o b : + 3 8 2 ( 0 ) 69 3 4 7 3 9 5

+ 382 ( 0 ) 69 309 590

JU OŠ ''MILAN VUKOTIĆ'', GOLUBOVCI

Str. 8 / Page no. 8

- Grafički prilozi su preuzeti iz projekta ''Glavni projekat adaptacije Osnovne škole ''Milan Vukotić'', Golubovci - Program energetske efikasnosti u javnim objektima u Crnoj Gori - faza 2'' - projektant: ''KOPRING PMC d.o.o., Podgorica'' ; /

- Graphical documentation is taken from project '' Final Adaptation Design of the Centre for Primary School ''Milan Vukotić'', Golubovci, Energy Efficiancy Programme in Public Buildings - Phase II (EEPPB II) - designer: ''KOPRING PMC d.o.o., Podgorica'' ;

Napomena: Sve mjere provjeriti na licu mjesta Note: All measurements must be taken before, at building site p:90cm

PRESJEK 1-1 /

Al sill new internal

PVC

D -

POS 13

zidarska mjera / built in measure 131 x 22170 kom: 1

T e l / f ax : + 3 8 2 ( 0 ) 40 2 5 1 8 6 7 M o b : + 3 8 2 ( 0 ) 69 3 4 7 3 9 5

+ 382 ( 0 ) 69 309 590

JU OŠ ''MILAN VUKOTIĆ'', GOLUBOVCI

Str. 9 / Page no. 9

- pocinkovani plastificirani metalni lim d=0.7mm

Covering- plastic coated galvanized metal sheet d=0.7mm

POS 19

- Grafički prilozi su preuzeti iz projekta ''Glavni projekat adaptacije Osnovne škole ''Milan Vukotić'', Golubovci - Program energetske efikasnosti u javnim objektima u Crnoj Gori - faza 2'' - projektant: ''KOPRING PMC d.o.o., Podgorica'' ; /

- Graphical documentation is taken from project '' Final Adaptation Design of the Centre for Primary School ''Milan Vukotić'', Golubovci, Energy Efficiancy Programme in Public Buildings - Phase II (EEPPB II) - designer: ''KOPRING PMC d.o.o., Podgorica'' ;

Napomena: Sve mjere provjeriti na licu mjesta Note: All measurements must be taken before, at building site

D - zidarska mjera / built in measure 76 x 101 71 kom: 1

T e l / f ax : + 3 8 2 ( 0 ) 40 2 5 1 8 6 7 M o b : + 3 8 2 ( 0 ) 69 3 4 7 3 9 5

+ 382 ( 0 ) 69 309 590

JU OŠ ''MILAN VUKOTIĆ'', GOLUBOVCI

Str. 10 / Page no. 10

- pocinkovani plastificirani metalni lim d=0.7mm

Covering- plastic coated galvanized metal sheet d=0.7mm

POS 20

- Grafički prilozi su preuzeti iz projekta ''Glavni projekat adaptacije Osnovne škole ''Milan Vukotić'', Golubovci - Program energetske efikasnosti u javnim objektima u Crnoj Gori - faza 2'' - projektant: ''KOPRING PMC d.o.o., Podgorica'' ; /

- Graphical documentation is taken from project '' Final Adaptation Design of the Centre for Primary School ''Milan Vukotić'', Golubovci, Energy Efficiancy Programme in Public Buildings - Phase II (EEPPB II) - designer: ''KOPRING PMC d.o.o., Podgorica'' ;

Napomena: Sve mjere provjeriti na licu mjesta Note: All measurements must be taken before, at building site

D - zidarska mjera / built in measure 71 x 101 72

B ul evar " 13 jul " br . 96 , 81400 N i kši ć

JU OŠ ''MILAN VUKOTIĆ'', GOLUBOVCI

Tel/ f a x : + 3 8 2 ( 0 ) 4 0 2 5 1 8 6 7 M ob : + 382 ( 0 ) 69 347 395

+ 382 ( 0 ) 69 309 590 šema fasadne alu. stolarije schemes of external alu. joinery

JU OŠ ''MILAN VUKOTIĆ''

Golubovci, Podgorica

KONVENCIJA SMJERA OTVARANJA VRATA I PROZORA

DOORS AND WINDOWS OPENING CONVENTION

DESNA / RIGHT

LIJEVA / LEFT

Investitor: JU OŠ ''Milan Vukotić'', Podgor7ic3 a

POS A

Al "sandwich" panel

- Grafički prilozi su preuzeti iz projekta ''Glavni projekat adaptacije Osnovne škole ''Milan Vukotić'', Golubovci - Program energetske efikasnosti u javnim objektima u Crnoj Gori -faza 2'' - projektant: ''KOPRING PMC d.o.o., Podgorica'' ; /

- Graphical documentation is taken from project '' Final Adaptation Design of the Centre for Primary School ''Milan Vukotić'', Golubovci, Energy Efficiancy Programme in Public Buildings - Phase II (EEPPB II) - designer: ''KOPRING PMC d.o.o., Podgorica'' ;

Napomena: Sve mjere provjeriti na licu mjesta Note: All measurements must be taken before, at building site kom: 1 L - D - zidarska mjera / built in measure 191 x 23674

T e l / f ax : + 3 8 2 ( 0 ) 40 2 5 1 8 6 7 M o b : + 3 8 2 ( 0 ) 69 3 4 7 3 9 5

+ 382 ( 0 ) 69 309 590

JU OŠ ''MILAN VUKOTIĆ'', GOLUBOVCI

Str. 1 / Page no. 1 šeme fasadne alu. stolarije scheme of external alu. joinery

POS B

pod / The door sill shall be waterproof and sturdy fixed to the floor.

Contractor is obliged to reinforce the construction of the item.

- Grafički prilozi su preuzeti iz projekta ''Glavni projekat adaptacije Osnovne škole ''Milan Vukotić'', Golubovci - Program energetske efikasnosti u javnim objektima u Crnoj Gori -faza 2'' - projektant: ''KOPRING PMC d.o.o., Podgorica'' ; /

- Graphical documentation is taken from project '' Final Adaptation Design of the Centre for Primary School ''Milan Vukotić'', Golubovci, Energy Efficiancy Programme in Public kom: 1 L - D - zidarska mjera / built in measure 190 x 23575

T e l / f ax : + 3 8 2 ( 0 ) 40 2 5 1 8 6 7 M o b : + 3 8 2 ( 0 ) 69 3 4 7 3 9 5

+ 382 ( 0 ) 69 309 590

JU OŠ ''MILAN VUKOTIĆ'', GOLUBOVCI

Str. 2 / Page no. 2

POS C

130 175 135

- Grafički prilozi su preuzeti iz projekta ''Glavni projekat adaptacije Osnovne škole ''Milan Vukotić'', Golubovci - Program energetske efikasnosti u javnim objektima u Crnoj Gori -faza 2'' - projektant: ''KOPRING PMC d.o.o., Podgorica'' ; /

- Graphical documentation is taken from project '' Final Adaptation Design of the Centre for Primary School ''Milan Vukotić'', Golubovci, Energy Efficiancy Programme in Public kom: 1 L - D - zidarska mjera / built in measure 190 x 23576

T e l / f ax : + 3 8 2 ( 0 ) 40 2 5 1 8 6 7 M o b : + 3 8 2 ( 0 ) 69 3 4 7 3 9 5

+ 382 ( 0 ) 69 309 590

JU OŠ ''MILAN VUKOTIĆ'', GOLUBOVCI

Str. 3 / Page no. 3

OBRAZAC 1a
2. TEKSTUALNA I NUMERIČKA DOKUMENTACIJA
Arhitektonika d.o.o. adresa: Bulevar 13. jul br. 96, 81400 Nikšić
I INTRODUCTION
3.GRAFIČKA DOKUMENTACIJA
JUŽNA FASADA / SOUTH FACADE
SJEVERNA FASADA / NORTH FACADE
ZAPADNA FASADA / WEST FACADE
UNUTRAŠNJA FASADA 1 / INNER YARD FACADE 1
UNUTRAŠNJA FASADA 2 / INNER YARD FACADE 2
UNUTRAŠNJA FASADA 3 / INNER YARD FACADE 3
UNUTRAŠNJA FASADA 4 / INNER YARD FACADE 4
JUŽNA FASADA / SOUTH FACADE
SJEVERNA FASADA / NORTH FACADE
ISTOČNA FASADA / EAST FACADE
ZAPADNA FASADA / WEST FACADE
UNUTRAŠNJA FASADA 1 / INNER YARD FACADE 1
UNUTRAŠNJA FASADA 2 / INNER YARD FACADE 2
UNUTRAŠNJA FASADA 3 / INNER YARD FACADE 3
190
190
140 1
p:100cm
141
140
p:180cm
140
135
135
140
140
70
MIPR 39596_Andrijevica Quantities.pdf
Kindergarten
Primary Win-Doors
Heating

File details come from the government source that posted it. Updated .