Revised Work Item 0110 A COMPOSITE EXTERIOR HULL VENT REPLACEMENT (TALT-425)3-29-21.docx

DOCX document 26 KB Posted

Attached to
USNS WILLIAM MCLEAN ROH/DD Federal contract opportunity
Solicitation number
N3220521R4014
Issued by
Department of the Navy Military Sealift Command

About this file

This work item describes replacing exterior hull vents on the USNS William McLean, a T-AKE class ship, with non-metallic or stainless steel construction. Thirty-eight composite exterior hull vent assemblies are required to replace existing vents on frames 44 through 69 portside and starboard along the main deck. The contractor must consult general technical requirements and comply with applicable standards. Peerless Manufacturing is identified as the only known manufacturer that can meet USCG and ABS fire integrity requirements for the composite vent material. The statement of work involves removing existing vents, fabricating and installing steel support plates, applying sealant, preparing drawings, and conducting inspections and final installation prior to painting.

The related federal contract opportunity is a solicitation for hull and structural work on the USNS William McLean issued by the Department of the Navy's Military Sealift Command. The solicitation number and vessel information are provided.

View the file

Other files for this federal contract opportunity

Other files attached to USNS WILLIAM MCLEAN ROH/DD, newest first.
File Type Posted
Amendment 0012 USNS MCLEAN N3220521R4014.docx DOCX document
WI 0451 A TAKE-CCSI ANNUAL RADAR SERVICE - Revised 5-24-21.doc DOC document
Revised J-2 MCLEAN N3220521R4014 5-24-21 (4).xls XLS spreadsheet
Revised J - 3 Category B Items MCLEAN.xls XLS spreadsheet
WI 0090 A LEVEL I DAILY COVID-19 PREVENTION AND CONTROL SERVICES REV CV 03-23-21.docx DOCX document
Amendment 0009 MCLEAN N3220521R4014.docx DOCX document
REVISED WI INDEX USNS MCLEAN FY21 ROH-DD - REV MAR 29 2021.doc DOC document
Amendment 0011 USNS MCLEAN ROH DD N3220521R4014.docx DOCX document
Amendment 0010 USNS MCLEAN N3220521R4014.docx DOCX document
Amendment 0007 USNS MCLEAN N3220521R4014.docx DOCX document
Amendment 0006 USNS MCLEAN N3220521R4014.docx DOCX document
Amendment 00005 MCLEAN N3220521R4014.docx DOCX document
Amendment 0004 J 2 MCLEAN 21R4014.xls XLS spreadsheet
N3220521R4014 Amendment 0004.docx DOCX document
N3220521R4014 Amend 0002.docx DOCX document
J 2 MCLEAN 21R4014.xls XLS spreadsheet
N3220521R4014 Amendment 0003.docx DOCX document
N3220521R4014 Amendment 0002.docx DOCX document
N3220521R4014 Amendment 0001.docx DOCX document
J - 2 Category A Items MCLEAN 21R4014.xls XLS spreadsheet
J-Attachments.zip ZIP file
N3220521R4014.docx DOCX document
Show all 22

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USNS McLean

( TAKE 12 )

HULL AND STRUCTURAL
CONTRACT NO. N32205-21-R-4014
ITEM NO. 0110
CATEGORY "A"
2021-03-29
COMPOSITE EXTERIOR HULL VENT REPLACEMENT (TALT-425)
Escobar, Daniel

1.0 ABSTRACT:

1.1 This Work Item describes replacing the existing Exterior Hull Vents with Non-Metallic construction approved by ABS and the US Coast Guard and conforming to MSC Guidelines on HVAC Construction and Weather Louvers. Although primarily addressing Non-Metallic construction replacement, this Work Item additionally approves Hull Vent replacement with Stainless Steel (SS316).

2.0 REFERENCES/ENCLOSURES:

2.1 References:

2.1.1 MSC DWG 512-8496620 Rev -, Exterior Hull Vent Material Replacement Design and Installation (T-AKE 1 – 14)

2.2 Enclosures:

2.2.1 Peerless Manufacturing Fiberglass Reinforced Plastic (FRP) material property characteristics sheet

3.0 ITEM LOCATION/DESCRIPTION:

3.1 Location/Quantity

3.1.1 Location: Frames 44 – 69 Portside and Starboard along Main Deck. Externally accessible along Hull, internally accessible in Main Deck Cargo Hold Space.

3.1.2 Quantity: Thirty-Eight (38 ea) FRP Composite Exterior Hull Vent Louver Assemblies required per T-AKE ship.

3.2 Item Description/Manufacturer's Data:

3.2.1 Bill of Materials:

Bill of Material (Contractor Furnished Material)

Item #
Description
Quantity
Specifications
Source
1
Bolt Hex Head, 3/8”-UNC-2A

Various Lengths

2000
Carbon Steel
Commercial
2
Hex Nut, 3/8”-11UNC-2A
2000
Carbon Steel
Commercial
3
Washer 5/16 USS Size
2000
Carbon Steel
Commercial
4
Steel Support Plate, ½” x 3” x L
152
Steel
Commercial
5
Marine Adhesive Sealant 5200
1 Gallon
Polyurethane
M3

4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES:

COMPOSITE LOUVER 24"X36" QTY 7
COMPOSITE LOUVER 24"X42" QTY 3
COMPOSITE LOUVER 32"X72X QTY 1
COMPOSITE LOUVER 36"X36" QTY 12
COMPOSITE LOUVER 36"X72" QTY 4
COMPOSITE LOUVER 48"X36" QTY 1
COMPOSITE LOUVER 72"X72" QTY 1
COMPOSITE LOUVER 72"X108" QTY 5
COMPOSITE LOUVER 24"X30" QTY 1
COMPOSITE LOUVER 36"X60" QTY 2
COMPOSITE LOUVER 48"X32" QTY 1

5.0 NOTES:

5.1 The contractor and all subcontractors, regardless of tier, must consult the General Technical Requirements (GTR) to determine applicability to this work item. In performance of this work item, the contractor and all subcontractors regardless of tier must comply with the requirements of all applicable GTRs.

5.2 The contractor and all subcontractors regardless of tier are advised to review the other work items under this contract to determine their effect on the work required under this work item.

5.3 THIS SHIP CONTAINS HIGH VOLTAGE (HV) ELECTRICAL SYSTEMS. OBEY ALL POSTED AND VERBAL INSTRUCTIONS REGARDING SAFETY AND EXCLUSION FROM HIGH VOLTAGE AREAS. AT NO TIME APPROACH, WORK ON, OR ENTER A HIGH VOLTAGE AREA WITHOUT PROPER AUTHORIZATION.

5.4 THE T-AKE CLASS ELECTRICAL COLOR CODING DOES NOT FOLLOW CONSISTENT COLOR SCHEME. THE SHIP IS KNOWN TO HAVE CURRENT CARRYING CONDUCTORS COLORED GREEN, BLUE, BLACK, AND WHITE. ASSUME ALL ELECTRICAL CABLES ARE ENERGIZED UNTIL TESTED AND PROVEN OTHERWISE. TEST ALL ELECTICAL CABLES TO ENSURE THEY ARE DE-ENERGIZED PRIOR TO WORKING ON THE ITEM.

6.0 QUALITY ASSURANCE REQUIREMENTS:

6.1 Materials and ABS approved applications requiring Level 2 (L2) fire integrity are required by the USCG PFM 2-98. This vendor is only known manufacturer to meet these requirements:

Peerless Manufacturing 14651 North Dallas Parkway Suite 500 Dallas, TX 75254 Marine Product Manager C. Chavez Office: 972-559-6303

Note: Stainless Steel (SS316) is allowed as a metallic option for Hull Vent Material Replacement. SS316 Replacement can be performed with Section 2.1 Reference Drawings as guidance or using steel fabrication common to shipyard practices.

7.0 STATEMENT OF WORK REQUIRED:

7.1 Preparation:

7.1.1 Tag-Out all required systems and equipment. Drain and dispose of any liquid in accordance with all federal, state, and local regulations.

7.2 Removals

7.2.1 Remove existing Exterior Hull Vents to include weather louvers and coaming from bulkhead structure in the fan rooms portside and starboard along Main Deck using as reference MSC DWG 512- 8496620 Rev –, Exterior Hull Vent Material Replacement Design and Installation. Removals can be performed along exterior of Hull or internal to ship from within the Main Deck’s Cargo Hold Space.

7.3 Installations:

7.3.1 Clean all bulkhead openings of debris generated by this work item to include metal shavings, rusted spots, and remove the existing steel lugs. Wipe down applicable surfaces prior to installation and sealing of Hull Vents.

7.3.2 Fabricate and install four (4 ea) steel support plates, one on each side of bulkhead opening. Ensure final bulkhead openings match the widths, heights, and radial dimensions of various Hull Vent louvers. Refer to Table 2 of MSC DWG 512-8496620 Rev -, Exterior Hull Vent Material Replacement Design and Installation.

7.3.3 Apply suitable Marine caulking (flexible caulking) to seal contact between bulkhead structure and the Hull Vent’s FRP material.

7.4 Preparation of Drawings: Peerless Manufacturing will supply Hull Vent drawings generated at their factory site during the manufacturing of FRP material Hull Vents

7.5 Inspection/Test:

7.5.1 Fit up (ABS and MSCREP to attend)

7.5.2 Final installation prior to paint (ABS and MSCREP to attend)

7.6 Paint/Lagging:

7.6.1 Renew lagging where old lagging was removed. Paint all new and disturbed surfaces to match surrounding surfaces.

8.0 GENERAL REQUIREMENTS:

0110 - 4

File details come from the government source that posted it. Updated .