This document provides a contractor price breakdown for Category "A" items for the regular overhaul and dry-docking of the USNS PATUXENT (T-AO 201) under solicitation N3220520R4003 issued by the Military Sealift Command. The contractor price breakdown lists over 1,000 line items covering major ship systems and components, such as hull structures, machinery, electrical systems, auxiliary machinery, communications and navigation aids, outfitting and habitability, HVAC, drydocking, and UNREP equipment. Pricing is provided for labor and materials for prime contractor and subcontractor work. The solicitation seeks bids from contractors for the overhaul and maintenance work to be performed from FY2020-FY2021 at a cost to be determined.
View the file
Other files
Show all 50
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Cat A Items
| CATEGORY “A” ITEMS | ||||||||||||
| GENERAL REQUIREMENT | PRIME Contractor | SUB Contractor | Govt Mandated Tech Rep/Sub | OTHER COSTS | TOTAL PRICE | |||||||
| ITEM NO. | TITLE CAT A ITEM | PRIME L/H | LABOR PRICE | MATERIAL PRICE | SUB L/H | LABOR PRICE | MATERIAL PRICE | PRICE | TOTAL LABOR HOURS | TOTAL MATERIAL | ||
| CATEGORY "A" | ||||||||||||
| 000 | GENERAL REQUIREMENTS | |||||||||||
| 001 | INTENT, SCOPE, GENERAL REQUIREMENTS, AND DEFINITIONS | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP |
| 002 | TECHNICAL AND MANUFACTURER’S REPRESENTATIVES | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP |
| 003 | APPROACH, BERTH, AND MOORING REQUIREMENTS | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP |
| 004 | TESTING AND QUALITY ASSURANCE | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP |
| 005 | ELECTRICAL SAFETY PROCEDURES REQUIREMENTS | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP |
| 006 | HEAVY WEATHER PLAN | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP |
| 007 | COLD WEATHE PLAN | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP |
| 010 | FURNISH OFFICE FOR OVERHAUL MANAGEMENT TEAM | |||||||||||
| 011 | GENERAL SERVICES FOR SHIP (T-AO) | |||||||||||
| 012 | INFORMATION TECHNOLOGY SERVICES | |||||||||||
| 013 | PROJECT PLANNING AND PRODUCTION STAUS MONITORING REPORT | |||||||||||
| 014 | WEIGHT AND MOMENT REPORT | |||||||||||
| 015 | ILS GFM | |||||||||||
| 016 | FIRE PROTECTION AND SHIP'S SAFETY PROGRAM | |||||||||||
| 017 | HANDLING SHIP'S STORES | |||||||||||
| 018 | DELIVERY AND REDELIVERY OF VESSEL | |||||||||||
| 019 | SHIPBOARD ACCESS AND SECURITY | |||||||||||
| 020 | GAS FREE CERTIFICATES | |||||||||||
| 021 | CLEAN AND GAS FREE TANKS, VOIDS, COFFERDAMS AND SPACES | |||||||||||
| 022 | MACHINERY SPACE TURN-OVER, DOCK TRIALS AND SEA TRIALS | |||||||||||
| 023 | HAZARDOUS WASTE DISPOSAL AT A CONTRACTOR'S FACILITY | |||||||||||
| 024 | PHYSICAL SECURITY AT PRIVATE CONTRACTOR'S FACILITY | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP | NSP |
| 100 | HULL STRUCTURES | |||||||||||
| 101 | NDT KINGPOST AREAS (ABS & USCG) | |||||||||||
| 106 | FOREPEAK TANK STRUCTURAL REPAIRS REV-A | |||||||||||
| 107 | BALLAST TANK STRUCTURAL REPAIRS REV-A | |||||||||||
| 108 | CONTAM TANKS DECK REPLACEMENT REV-A | |||||||||||
| 109 | CARGO TIE DOWN REPLACEMENT REV-A | |||||||||||
| 111 | PREP & PAINT VARIOUS DECK AREAS | |||||||||||
| 113 | MISCELLANEOUS STEEL REPAIRS REV-A | |||||||||||
| 115 | MISCELLANEOUS TANK REPAIRS | |||||||||||
| 116 | CONTAINMENT ENCLOSURE PIPE & STEEL REPLACEMENT | |||||||||||
| 117 | ALLIED DAVIT PRESERVATION REV-A | |||||||||||
| 119 | CARGO AND BALLAST TANK SWING LID PRESERVATION REV-A | |||||||||||
| 122 | FAS & RAS STATION PRESERVATION | |||||||||||
| 123 | FAS STATION MAINTENANCE PLATFORM REPAIRS REV-A | |||||||||||
| 124 | RAM TENSIONER & PLATFORM PRESERVATION REV-A | |||||||||||
| 127 | RAS & FAS KINGPOST SUPPORT BRACKETS (TALT 0819) REV-A | |||||||||||
| 128 | STABILITY TEST | |||||||||||
| 155 | INSPECTION OF PV VALVES | |||||||||||
| 158 | TANK PRESERVATION REV-A | |||||||||||
| 159 | DECKHOUSE PRESERVATION | |||||||||||
| 160 | WATERTIGHT CLOSURE REPAIR | |||||||||||
| 162 | WATERTIGHT CLOSURE INSPECTION | |||||||||||
| 196 | ER SIDE SHELL REPLACEMENT | |||||||||||
| 197 | CENTRAL FRESH WATER ROOM STEEL RENEWAL REV-A | |||||||||||
| 198 | JACKET WATER ROOM STEEL RENEWAL REV-A | |||||||||||
| 199 | ENGINE ROOM DECK PLATE REPLACEMENT REV-A | |||||||||||
| 200 | MACHINERY, PROPULSION | |||||||||||
| 201 | ME INDUSTRUAL ASSISTANCE AND SERVICE | |||||||||||
| 208 | PROPULSION SHAFT BRAKE OVERHAUL | |||||||||||
| 252 | MAIN REDUCTION GEAR INSPECTION (5 YR) | |||||||||||
| 254 | THRUST & LINESHAFT BEARING INSPECTION (5 YR) | |||||||||||
| 300 | ELECTRICAL | |||||||||||
| 304 | ANNUAL GENERATOR INSPECTION | |||||||||||
| 305 | ANNUAL PTO CONTROLS GROOM | |||||||||||
| 306 | BULKHEAD CABLE COLLAR MAGNAROCK REPLACEMENT REV-A | |||||||||||
| 311 | THERMOCOUPLE & WIRE REPLACEMENT ON SSDG | |||||||||||
| 351 | SWITCHBOARD CLEANING | |||||||||||
| 352 | MOTOR CONTROL CENTER CLEANING | |||||||||||
| 353 | THERMOGRAPHIC SURVEY | |||||||||||
| 400 | COMMUNICATION & NAV AIDS | |||||||||||
| 402 | TVDTS SYSTEM AND DISTRIBUTION GROOM REV-A | |||||||||||
| 405 | UHF SATCOM AND LOS TRANSCEIVER GROOM | |||||||||||
| 406 | URT-23(D) URR-2368A HF SET GROOM | |||||||||||
| 409 | DOPPLER SPEED LOG PREVENTATIVE MAINTENANCE | |||||||||||
| 411 | AVAYA TELEPHONE SYSTEM GROOM | |||||||||||
| 414 | ANNUAL SERVICE AND ADJUST MAGNETIC COMPASS | |||||||||||
| 415 | OVERHAUL ENGINE ORDER TELEGRAPH SYSTEM | |||||||||||
| 451 | ANNUAL RADAR SERVICE | |||||||||||
| 452 | ANNUAL ECDIS SERVICE | |||||||||||
| 453 | ANNUAL GYRO SYSTEM PM | |||||||||||
| 454 | ANNUAL VDR RECERTIFICATION | |||||||||||
| 455 | ANNAUL RADIO COMMUNICATION EQUIPMENT RECERTIFICATION | |||||||||||
| 457 | EPIRB SERVICE (5 YR) | |||||||||||
| 459 | ECHO SOUNDER SERVICE | |||||||||||
| 500 | AUXILIARY MACHINERY | |||||||||||
| 504 | NO.3 SSDG 60,000 HOUR OVERHAUL (STD) | |||||||||||
| 507 | VACUUM SEWAGE COLLECTION SYSTEM PIPING ACID CLEANING | |||||||||||
| 508 | MISCELLANEOUS PIPE REPAIRS REV-A | |||||||||||
| 510 | AUXILIARY BOILER VALVES MAINTENANCE & TESTING | |||||||||||
| 514 | PUMP OVERHAUL -PTX | |||||||||||
| 515 | REFRIGERATION & AC SYSTEM PREVENTATIVE MAINTENANCE | |||||||||||
| 517 | ANNUAL INCINERATOR SERVICE | |||||||||||
| 518 | STBD ANCHOR WINDLASS CAPSTAN REPAIR REV-A | |||||||||||
| 520 | OVERHAUL BALANCED FAIRLEADS | |||||||||||
| 521 | PURIFIER MAINTENANCE, FO (WESTFALIA) REV-A | |||||||||||
| 522 | PURIFIER MAINTENANCE, LO (WESTFALIA) | |||||||||||
| 524 | ER OWS & CARGO OCM GROOM | |||||||||||
| 527 | HIGH PRESSURE AIR COMPRESSOR (HPAC) OVERHAULS | |||||||||||
| 528 | STEERING GEAR MAINTENANCE (5 YR) | |||||||||||
| 535 | ABS AUXILLARY BOILER SURVEY AND HYDRO | |||||||||||
| 537 | CONSTANT TENSION WINCHES No.5 and No.6 | |||||||||||
| 538 | GAYLORD BOOSTER HEATER REPLACEMENT (T-ALT 06-34) REV-A | |||||||||||
| 550 | OVERHAUL JW PLATE COOLERS REV-A | |||||||||||
| 551 | OVERHAUL CFW PLATE COOLERS REV-A | |||||||||||
| 552 | HOSE REPLACEMENT (5 YR) | |||||||||||
| 553 | PRESSURE VESSELS & RELIEF VALVES (5 YR) REV-A | |||||||||||
| 555 | INSPECT, TEST, & CERTIFY MACHINERY SPACE CRANES & HOISTS (5 YR) | |||||||||||
| 560 | PERSONNEL ELEVATOR INSPECTION & TEST (5 YR) | |||||||||||
| 561 | GAUGE CALIBRATION REV-A | |||||||||||
| 562 | SCBA ANNUAL INSPECTION REV-A | |||||||||||
| 563 | SCBA AIR COMPRESSOR & FILL STATION INSPECTIONS (1 YR) | |||||||||||
| 565 | FIXED GAS FIREFIGHTING SYSTEM INSPECTION & TEST (1 YR) REV-A | |||||||||||
| 567 | FIXED FOAM FIREFIGHTING SYSTEM INSPECTION & TEST | |||||||||||
| 569 | FIRE & SMOKE DETECTION & ALARM SERVICE | |||||||||||
| 570 | PORTABLE FIRE EXTINGUISHER SERVICE REV-A | |||||||||||
| 571 | FIRE AND SMOKE DAMPER SERVICE | |||||||||||
| 572 | DEEP FAT FRYER & RANGE HOOD FIRE EXTINGUISHING SYSTEM REV-A | |||||||||||
| 573 | FIRE HOSES | |||||||||||
| 574 | FIRE DOORS & SHUTTERS (I YR) | |||||||||||
| 575 | FIRE DETECTION SYSTEM REPLACEMENT (T-ALT 872) | |||||||||||
| 576 | THERMOSTATIC SWITCH REACTION TIME TEST | |||||||||||
| 600 | OUTFIT, FURNISHING & HABITABILITY | |||||||||||
| 602 | NEW LIFEBOAT INSTALLATION | |||||||||||
| 605 | RESCUE BOAT DAVIT REPAIRS REV-A | |||||||||||
| 611 | STATEROOM HEAD FLOOR COVERING RENEWAL | |||||||||||
| 615 | SHOWER STALL BULKHEAD PANEL RENEWALS | |||||||||||
| 619 | WINDOW REGASKETING AND STEEL REPAIR | |||||||||||
| 652 | LIFEBOAT & DAVIT SERVICE (5 YR) REV-A | |||||||||||
| 654 | RHIB/RESCUE BOAT/ FAST RESCUE BOAT & DAVIT SERVICE 95 YR) | |||||||||||
| 655 | IMMERSION SUIT SERVICE (3 YR) | |||||||||||
| 656 | ANNUAL LIFERAFT CERTIFICATION (ABS) | |||||||||||
| 657 | ACCOMMODATION LADDER INSPECTION (1 YR) | |||||||||||
| 659 | PILOT BOARDING EQPT & EMBARKATION LADDERS (5 YR) | |||||||||||
| 660 | DECK TILE REPLACEMENT | |||||||||||
| 661 | CARPET REPLACEMENT | |||||||||||
| 662 | DEEP FAT FRYER INSPECTION | |||||||||||
| 800 | HVAC | |||||||||||
| 801 | VENT DUCT REPAIR & PRESERVATION | |||||||||||
| 803 | MISC. LAGGING AND INSULATION RENEWALS | |||||||||||
| 851 | ANNUAL GALLEY VENTILATION AND GAYLORD HOOD | |||||||||||
| 852 | ANNUAL LAUNDRY VENT CLEANING | |||||||||||
| 853 | ACCOMMODATION VENT SYSTEM CLEANING | |||||||||||
| 900 | DRYDOCKING | |||||||||||
| 901 | DRY-DOCKING AND UNDOCKING VESSEL | |||||||||||
| 903 | INSPECTION OF BILGE KEELS, BOW VOID & SKEGS | |||||||||||
| 905 | PROPELLER SHAFT WEARDOWN READINGS | |||||||||||
| 911 | PROPELLER SYSTEM MAINTENANCE (30 MONTHS) | |||||||||||
| 912 | STERN TUBE SEAL MAINTENANCE | |||||||||||
| 913 | SPURS LINE AND NET CUTTER MAINTENANCE | |||||||||||
| 915 | ROPE GUARD ZINC ANODE REPLACEMENT | |||||||||||
| 953 | ANCHORS, CHAINS, & LOCKERS (5 YR) | |||||||||||
| 954 | RUDDER AND STERN FRAME EXAMINATION (5 YR) | |||||||||||
| 956 | OVERHAULING SEA VALVES (5 YR) | |||||||||||
| 960 | UNDERWATER HULL CLEANING & PAINTING - SPOT BLAST REV-A | |||||||||||
| 961 | FREEBOARD PRESERVATION REV-A | |||||||||||
| 962 | CATHODIC PROTECTION SYSTEM REV-A | |||||||||||
| 963 | SEA CHEST MARINE GROWTH PREVENTION SYSTEM (2.5 YR) | |||||||||||
| 966 | SHAFT ALIGNMENT & BEARING REACTION CHECKS (2.5 YR) | |||||||||||
| 1000 | UNREP EQUIPMENT | |||||||||||
| 1001 | SPANWIRE WINCH CONTROLLEX CABLE AND HANGERS REV-A | |||||||||||
| 1002 | ASD COOLING FAN MOTOR OVERHUAL AND SHROUD FABRICATION | |||||||||||
| 1003 | TRANSM REPLEN PUMP ELECTRIC MOTOR BEARING REFURBISHMENT | |||||||||||
| 1004 | HYDRUALIC TRANSMISSION HEAT EXCHANGERS FRAME | |||||||||||
| 1005 | SADDLE WINCH GEARBOX REPAIR AND SHAFT REPLACEMENT- REPAIR | |||||||||||
| 1006 | ASD FRAME AND FOUNDATION REFURBISHMENT REV-A | |||||||||||
| 1007 | LEAD ANGLE COMPENSATOR REPAIRS REV-A | |||||||||||
| 1008 | REFURB OF RAM ARC UNIT INCLUDING BRACKETS AND MOUNTS REV-A | |||||||||||
| 1010 | CARGO GEAR QUADRENNIAL RECERTIFICATION | |||||||||||
| 1016 | UNREP STRUCTURAL STEEL REPLACEMENT | |||||||||||
| 1025 | REFURB HAULING WINCH ASSEMBLY & RECONDITION MACHINERY | |||||||||||
| TOTAL |
| &"Times New Roman,Regular"USNS PATUXENT (T-AO 201) | &"Times New Roman,Regular"CONTRACTOR PRICE BREAKDOWN |
| &"Times New Roman,Bold"CATEGORY "A" ITEMS REV-A | &"Times New Roman,Regular"N3220520R4003 |
ATTACHMENT J-2
File details come from the government source that posted it. Updated .